Given Value, x 48
Expected Time to Complete the Project, μ 46
Standard Deviation of the Project, σ 1.095445
Probability of more than 48 weeks 0.03394
3 4 5 4 0.111111
1 2 3 2 0.111111
0.5 1 1.5 1 0.027778
1 2 9 3 1.777778
1 5.5 7 5 1
Immediat
Most
e Optimisti Pessimisti
Activity Likely Expected Variance
Predecess c Time, to c Time, tp
Time, tm
or/s
A --- 10 12 15 12.1667 0.6944
B A 6 10 14 10 1.7778
C A 10 15 20 15 2.7778
D A 9 9 18 10.5 2.25
E B 5 6 8 6.1667 0.25
F C, E 10 12 13 11.8333 0.25
G B 12 14 16 14 0.4444
H B, D 18 21 24 21 1
I B, D 10 15 20 15 2.7778
J F, G, H 8 10 14 10.3333 1
Immediat
Most
e Optimisti Pessimisti
Activity Predecess c Time, to Likely c Time, tp e v
Time, tm
or/s
A --- 15 20 25 20 2.777778
B --- 8 10 12 10 0.444444
C A 25 30 40 30.83333 6.25
D B 15 15 15 15 0
E B 22 25 27 24.83333 0.694444
F E 15 20 22 19.5 1.361111
G D 20 20 22 20.33333 0.111111