Concrete Pouring RAMS
Concrete Pouring RAMS
Method Statement Title:         Health & Safety Management System Method Statement
   Method Statement No:                                                                     Rev No:          Rev C
   Approval
    Revision                                     Approval                                     Approval                 Client                  Approval   Approval
                          Approved By                                 Approved By
      No                                           Date                                         Date               (If Required)                 Date      Status
   Contents
    1.         Project Details                                                        10.     Emergency Response Plan
    2.         Scope of Work / Activity Intended                                      11.     Other Safety / Method Statements, ITP’s, etc. Affected
    3.         Order / Priority of Operations                                         12.     Drawings / Sketches / Pictures
    4.         Personnel / Resources                                                  13.     Handover Notices and O&M Data
    5.         Reference / Requirement to Work                                        14.     Briefing Arrangements / Communication of Method Statement
    6.         Method of Work                                                                 Risk Assessment
    7.         Control Measures                                                       15.     Risk Assessment
    8.         Materials                                                              16.     Appendices
    9.         Plant / Equipment
   Distribution
   MAIN CONTRACTOR + CONTRACTOR Construction Ltd
   Notes
   1 – Holders of a controlled document are responsible for ensuring that any superseded Method Statement is removed and destroyed.
   2 – Please keep your Method Statement safe, and do not allow it to be copied. Contact your Line Manager if you require further copies.
4.2 Numbers:
    4.3    Personnel                 3 site operatives dependent on the work and all CSCS qualified
                                     All operatives are to hold as a minimum a CSCS card; Supervisor to be SMSTS or SSSTS as a minimum
           Training &
    4.3                              All operatives carrying out specialist work or activities must have appropriate training i.e Asbestos Awareness,
           Competence:
                                     Abrasive wheel training.
    4.4    Signing in/out            All operatives are to sign in and out each day as per Main Contractor arrangements.
5.3 Sole Possession: Main Contractor controlled site. No pedestrian access. Other contractors working on site.
           Traffic / Access          Access is through the main site entrance on Bluewater Parkway. Visitors are asked to comply with the requests of
   5.5     Management:               the gatemen.
           Pedestrian Access /       Please refer to the above, pedestrians are to access site via security, sign in and report to the site offices for
   5.6     Egress:                   further instruction.
                                     Via the Site entrance and security off Bluewater Parkway. The site Address is:
   5.7     Emergency Access:
                                     XXXX
               The days’ work is to be confirmed by MAIN CONTRACTOR site management to the Supervisor who will then
               conduct a daily site briefing in conjunction with these RAMS. Once the daily briefing is complete all site operatives
               are to sign the briefing sheet to confirm they understand. All works are to be supervised by a CONTRACTOR
               supervisor at all times.
General Considerations:
                        Prior to the commencement of the works the area will be surveyed with MAIN CONTRACTOR to
                         highlight the scope and any restrictions.
                        There are strict noise restrictions in place during shop opening times.
                        Site operatives are to ensure proper manual handling techniques are followed.
Method of work:
                        Before works can begin a permit to work will need to be gained from MAIN CONTRACTOR Site
                         management.
                        A new reinforced concrete slab is to be constructed as per the engineer’s drawings found in Appendix A.
                        To begin some enabling works will need to be completed which includes some scabbling back of the
                         existing concrete ramp using scabbling machine a small Hilti AVR kango’s with wide chisels.
                        Once the enabling works have been completed install the rebar and dowels as per the engineers
                         drawing found in Appendix A.
                        The rebars are H10 and fixed in place using Hilti RE-500 resin with 100mm of embedment.
                        H10 L-Bars need to be installed at the bottom of the existing ramp at 200 c/c with 100mm of
                         embedment and fixed in place with Hilti RE-500 resin.
                        Once the dowels are in place, secure some A393 mesh to the dowels with binding wire.
                        The shuttering will be cut using a skill saw, and the 4x2 timber using a handsaw. The shuttering will be
                         fixed together using screws and a battery drill.
                        Rubber gloves are to be worn during the mixing of the concrete.
                        Pour the concrete into the shuttering a level off ensuring the concrete is level with the SSL of +6.350m.
                        Allow the concrete to cure before removing the shuttering.
                        Clean and tidy the work area and remove and waste generated during the construction of the slab.
Drainage installation:
                        Prior to any works being undertaken all operatives will read the method statement and ensure they
                         understand its content.
                        There is an excavation to be formed in the road.
                        Prior to the commencement of works the area will be barriered off and signage in place to allow the
                         works to proceed.
                        A cat scan will be undertook to ensure that the presence of any live services is highlighted.
                        Digging is to be by hand as a precautionary measure.
                        The area is to be scanned every 300mm.
                        Whilst the excavation is being formed it will have barriers in place and also signage indicating there is an
                         excavation underway.
                        Suitable access to the excavation will be provided in the form of a tied down ladder.
                        At no time is the Excavation to be left uncovered.
                        A steel plate is to be used at all times to protect the hole.
                        Once the hole has been excavated a hole is to be drilled through the existing beam using a diamond
                         drilling rig.
                        The rig is to be operated by a competent operator.
                        The hole is to allow the drainage to be passed through the beam.
                        A hole will be broken in the slab by an operative on the other side of the beam to allow the rest bend to
                         be installed.
                                             This is to be as per the Engineers drawings and will be connected to a pipe that is passed through the
                                              beam.
                                             Once the rest bend has been installed the slab will be reinstated to the concrete specifications’ details.
Waste Removal:
                                    Transport the waste to the CONTRACTOR waste storage area to await loading into a skip. Waste removal is to be
                                    booked in with the waste removal company. Confirm times the day before with MAIN Contractor Site
                                    management who will then book in the arrival times with the XXXX Gatekeepers. Once skip truck arrives load the
                                    skip.
                                    Daily task briefings are required prior to works commencing each day to be handed in to MAIN CONTRACTOR
                                    management or works are ceased until complete.
                                    The worksites will be maintained clean, tidy and in good condition at all times. Materials and waste will be
                                    stacked tidily, with power leads and cables kept tidy to prevent trips.
                                    During the course of the work, site operatives will give full consideration to the Health & Safety of all 3 rd parties
                                    working on or adjacent to the work location. The work site will be kept in an orderly state to avoid endangering
                                    any such person.
                                    Where there are any variations in the work, amendments will need to be made and recorded on this document.
          Checked (Inspection &
   6.2                              Inspections must be carried out as detailed in line with the MAIN CONTRACTOR procedures.
          Test Plans)
          Documented (e.g.
   6.3                              All Inspection sheets to be completed as per the MAIN CONTRACTOR Quality procedures.
          Inspection Sheets)
8.0 Materials
           Certification (i.e.
   8.5                                N/A
           Timber):
           Protection
   8.6                                All material storage areas to be kept tidy and segregated.
           Requirements:
      Oxidising             Toxic           Gas Under     Corrosive       Harmful        Flammable       Dangerous to       Explosive        Long Term
                                             Pressure                                                    Environment                       Health Hazards
         No                  Yes                No            No            Yes              No               No               No               Yes
    Risk to Health
    Harmful by inhalation; contact with eyes; if swallowed; contact with broken skin.
    Control Measures
    Cover all cuts with waterproof plasters. Avoid inhalation of aerosol. Wash thoroughly before eating, smoking or drinking. Avoid
    contact with skin & eyes. Wear suitable protective clothing & gloves. If feeling unwell consult G.P. show this assessment if
    possible.
    Storage                                                   Disposal
    N/a                                                       N/a
    First Aid
    Eye Contact: Irrigate with plenty of water for at least   Inhalation: Remove to fresh air and rest.
    15 minutes.
    Skin Contact: Wash all cuts and abrasions thoroughly      Ingestion: Do not induce vomiting
    with clean water. Cover all cuts & broken skin with
    waterproof plaster immediately.
                                                     Training/Instruction Required
    Verbal Instruction                                                      Written Instruction                Yes
    Tool Box Talk                                                           Specialist Training
      Oxidising          Toxic      Gas Under     Corrosive     Harmful       Flammable    Dangerous to        Explosive        Long Term
                                     Pressure                                              Environment                            Health
                                                                                                                                 Hazards
          No             Yes             No          No             Yes          No               No              No               Yes
Risk to Health
    Can cause allergic dermatitis through contact with chromates. Can cause Burns/skin ulceration. Contact can cause irritant
    contact dermatitis. Irritating to eyes and respiratory system. Inhalation of respirable Quartz causes long term hazard.
    Control Measures
    Cover all cuts with waterproof plasters. Avoid inhalation. Wash thoroughly before eating, smoking or drinking. Avoid contact
    with skin & eyes. Wear suitable protective clothing & gloves. Use a FFP3 dust mask. Eye goggles. Cover skin. When using do not
    smoke, eat or drink. Wash after contact. Damp down then sweep up.
    Storage                                                            Disposal
    A specifically designated area made by MAIN                        Via the use of skips each day
    CONTRACTORon site
    First Aid
    Eye Contact: Irrigate with plenty of water for at least            Inhalation: Remove to fresh air and rest.
    15 minutes.
    Skin Contact: Wash all cuts and abrasions thoroughly               Ingestion: Do not induce vomiting
    with clean water. Cover all cuts & broken skin with
    waterproof plaster immediately.
                                                           Training/Instruction Required
    Verbal Instruction                                                                Written Instruction                   Yes
    Tool Box Talk                                                                     Specialist Training
                                   Plant to be kept within designated area, to avoid interference with other ongoing works. Small plant to be kept
   9.4     Storage Requirements:
                                   within locked stores when not in use.
           Protection
   9.5                             Site is under security provisions put in place by MAIN CONTRACTOR.
           Requirements:
9.7 Hand Tools: Crowbars, claw hammers, club hammer, masonry chisels, screwdrivers
           Contractor ( CONTRACTOR Supervisor): 07902 793867                               Mr J. Sweeney ( CONTRACTOR Pro. Manager): 07920
           573414
           Mr E. Hugh ( CONTRACTOR Ass. Project Manager): 07920 573417
           Emergency Procedures: All accidents however minor must be reported directly to the MAIN CONTRACTOR or CONTRACTOR Site Team. In
           the event of a fire a claxon will be sounded to alert site operatives of the danger who will leave the building as per the MAIN
           CONTRACTOR fire alarm procedures in an orderly fashion and muster opposite the job. The emergency services will be called.
General:
                     All site foremen for CONTRACTOR are trained to direct any injured person to the site office or wherever the first aider is
                      located.
                     All fire stations will be continually checked by our staff for safety tags and misuse, if signs of the above are affected the
                      offending item will be passed over to the site team.
                     At no time, will firefighting be undertaken unless it is deemed that the complete fire can be safely extinguished using the
                      provided equipment.
                     All services to be confirmed as being redundant prior to stripping out.
N/a
N/a
Handover certificates are to be completed by a member of CONTRACTOR and MAIN CONTRACTOR management.
           To access site, all operatives, and supervisors to check in with MAIN CONTRACTOR site supervisor to safely access the area to ensure no
           conflict with surrounding works.
 Supervisor in charge Site Check: To be carried out at work commencement by Site Supervisor in charge of work or their nominee.
 The operations covered by this risk assessment have been checked on site and given the following status:
        A                     Accepted for operations to continue.
        B                     Comments made and incorporated into the task briefings. Operations may proceed.
        C                     Revised MS / WPP required for acceptance. Operations to cease.
                                 Probability/likelihood                                               Description
                                 Likely/foreseeable                                Occurs repeatedly/event only to be expected.
                                 Probable                                  Not surprised. Will occur several times. Could occur sometimes.
                                 Possible                                                   Unlikely, though conceivable.
                                 Remote/Improbable                                   So unlikely that probability is close to zero.
 KEY                                                                                                                  Probability
 High                                                                                                                  High Risk
 High                                                                                                                  High Risk
 Medium                                                                                                              Medium Risk
 Low                                                                                                        Low acceptable risk - no action**
                                                                                                                                                Level of
 Element of the Work Process                               Level of                                                                                        Person Who Will Control
                                      Persons at Risk                   Control Measure/ Precaution                                             Residual
 and Hazard                                                Risk                                                                                            the Risk
                                                                                                                                                Risk
 Use of vibrating tools and                 Operatives       3x3= 9              Where practicable minimise exposure to operatives              3x1= 3
 equipment (Reciprocating                                                         by reducing usage time of vibrating equipment.
 Saws, SDS Drills, Skill Saws)
Page 11 of 19                                                   Method Statement No:                                    Rev: 1.0
Doc No: 001
                                                                         CONTRACTOR RISK ASSESSMENT
                                                                                                                                   Level of
 Element of the Work Process                       Level of                                                                                   Person Who Will Control
                                Persons at Risk                 Control Measure/ Precaution                                        Residual
 and Hazard                                        Risk                                                                                       the Risk
                                                                                                                                   Risk
 i.e. when breaking Concrete,                                            Where hand held, tools are to be used ensure that
 Masonry                                                                  the items of plant are vibration dampened / low in
                                                                          vibration.
                                                                         Only use effective, well maintained items of plant.
                                                                         Minimise exposure to operatives by rotating shift
                                                                          patterns.
                                                                         Ensure operatives wear gloves to help keep hands
                                                                          warm and aid circulation during operations.
                                                                         Where operatives use vibrating tools a record of
                                                                          ‘trigger’ time spent on ‘each’ piece of equipment
                                                                          used during the shift is to be logged to ensure that
                                                                          the exposure limit is not exceeded.
                                                                         Prior to starting works with any vibrating equipment
                                                                          operatives are to be briefed on and complete a HAVS
                                                                          health self-assessment.
                                                                         Supervisor to ensure vibration exposure limits
                                                                          information has been provided by the equipment
                                                                          supplier.
                                                                         Supervisor to ensure any compressor driven
                                                                          equipment has whip checks in place.
 Manual Handling, Injury by           Operatives    4x3= 12              Use mechanical lifting methods to move/locate             4x1= 4
 heavy lifting.                                                           materials as close to the installation location as
                                                                          possible to prevent double handling.
                                                                         Protective gloves suited to the task to be worn at all
                                                                          times.
                                                                         Operatives to be advised on correct positioning of
                                                                          hands and feet in relation to the movement of the
                                                                          load by tool box talks. All materials are to be
                                                                          delivered as close as possible to the storage area.
                                                                         All lifting and lowering areas are clear of tripping
                                                                          hazards, and likewise check the route over which any
                                                                          load is to be carried.
                                                                         Large heavy loads if at all possible to be broken down
                                                                          into smaller lighter and more manageable sizes.
                                                                         Weight of items to be assessed and advised to
Page 12 of 19                                           Method Statement No:                                 Rev: 1.0
Doc No: 001
                                                                          CONTRACTOR RISK ASSESSMENT
                                                                                                                                    Level of
 Element of the Work Process                        Level of                                                                                   Person Who Will Control
                                  Persons at Risk                Control Measure/ Precaution                                        Residual
 and Hazard                                         Risk                                                                                       the Risk
                                                                                                                                    Risk
                                                                           personnel on site.
                                                                          Use good lifting techniques at all times. Only lift or
                                                                           carry materials or equipment if you feel comfortable
                                                                           to do so, consider the use of mechanical means
                                                                           where possible. Rest and rotate as required during
                                                                           natural pauses in activity.
 Noise                                      All      5x3= 15              Where exposure is above 1st action level (80dba),         5x1 = 5
                                                                           information must be provided on the risk of damage
                                                                           to hearing and personnel made aware of the
                                                                           availability of hearing protection.
                                                                          Where exposure level is at or above the 2nd action
                                                                           level (85dba) the use of hearing protection is
                                                                           compulsory.
                                                                          For longer, continuous Periods of exposure the time is
                                                                           to be monitored and limited to shorter Periods.
                                                                          Equipment is to be properly maintained.
                                                                          All plant used will either be super silenced where
                                                                           possible.
                                                                          Adequate and suitable warning signs must be placed
                                                                           in the vicinity of the works location.
                                                                          Hearing protection to be readily available at first
                                                                           action level – 80dba.
                                                                          Hearing protection compulsory when 2nd action level
                                                                           reached. – 85dba.
 Leptospirosis (Weil’s Disease)             All      4x5= 20              Leptospirosis (Weils Disease) can be caught through       4x1= 4
                                                                           contact with foul water and contaminated ground /
                                                                           rubbish.
                                                                          No eating or drinking except in the site offices /
                                                                           canteen.
                                                                          Running water to obtained from an approved supply.
                                                                          Provide adequate welfare facilities.
                                                                          If operatives cut themselves the cut / abrasion is to
                                                                           be thoroughly washed using clean water. Broken skin
                                                                           is to be covered with a waterproof plaster
                                                                           immediately.
Page 13 of 19                                            Method Statement No:                                  Rev: 1.0
Doc No: 001
                                                                       CONTRACTOR RISK ASSESSMENT
                                                                                                                                   Level of
 Element of the Work Process                     Level of                                                                                     Person Who Will Control
                               Persons at Risk                Control Measure/ Precaution                                          Residual
 and Hazard                                      Risk                                                                                         the Risk
                                                                                                                                   Risk
                                                                       If they are feeling unwell they should consult their
                                                                        doctor. Any incident should be recorded in the site
                                                                        accident book.
                                                                       Refer to COSHH assessment for Leptospirosis which
                                                                        will be located in the Safety File.
 Slips, trips, and falls       Operatives          4x2= 8              All tools / equipment and materials are to be properly      4x1= 4
 (Housekeeping)                                                         stored immediately on delivery and after use.
                                                                       All unwanted packing materials to be correctly
                                                                        disposed of. Tripping obstructions to be cleared from
                                                                        work area and maintained.
                                                                       Appropriate task lighting to be available for all
                                                                        relevant works.
                                                                       Welfare facilities to be kept in a clean and tidy
                                                                        condition. Operatives to maintain good personal
                                                                        hygiene.
                                                                       Adequate waste skips to be provided – operatives to
                                                                        receive TBT on waste segregation.
                                                                       Materials and equipment to be stacked in a tidy
                                                                        fashion.
                                                                       Clear walkways to be maintained at all times.
                                                                       Properly considered access/egress points into
                                                                        excavations.
 Use of Power/Hand Tools       Operatives         5x4= 20              All hand tools will be inspected before use by the          5x1 = 5
                                                                        operative.
                                                                       Defective tools will be reported to the supervisor, will
                                                                        not be used and will be replaced.
                                                                       All electrical equipment is to be PAT tested and
                                                                        within 3month date if heavy use.
                                                                       All tools are to be inspected in line with the PUWER
                                                                        regs on no later than 7 days basis.
                                                                       All faulty tools are to be either replaced or repaired
                                                                        by the supplier / manufacturer of the equipment.
                                                                       All accessories i.e. blades and bits are to be checked
                                                                        regularly and replaced when worn.
                                                                                                                                  Level of
 Element of the Work Process                     Level of                                                                                    Person Who Will Control
                               Persons at Risk                Control Measure/ Precaution                                         Residual
 and Hazard                                      Risk                                                                                        the Risk
                                                                                                                                  Risk
 Use of abrasive wheels:       Operatives         4x3= 12              Operatives to wear the correct PPE at all times (i.e.      4x1 = 4
 Flying debris                                                          safety goggles/visor and dust mask if not in well
                                                                        ventilated area).
                                                                       Where no dust collection bag is fitted, dust mask is to
                                                                        be worn.
                                                                       Only competent trained operatives to use grinders.
                                                                       Ensure the correct retractable guard is fitted and in
                                                                        good working order.
                                                                       Operatives to be briefed on the contents of the risk
                                                                        assessment.
                                                                       Hot works permit to be given before works can begin
                                                                        with a grinder.
 Pollution                     Operatives          2x3= 6              Consideration needs to be given safe waste disposal        2x1 = 2
                                                                        and in accordance with MAIN CONTRACTOR Site
                                                                        Waste Management Plan.
                                                                       Waste material will not be poured down drains, sinks
                                                                        or toilets.
                                                                       Dust will be controlled as far as practicable possible
                                                                        with the use of mechanical extraction or the use of
                                                                        dustbags on power tools.
                                                                       Noise pollution will also be monitored by
                                                                        CONTRACTOR and MAIN CONTRACTOR Site
                                                                        Management as this is a noise sensitive environment
                                                                        and any restrictions put in place will be implemented.
 Asbestos                      Operatives         5x4= 20              All operatives are to be briefed on the Asbestos           5x1 = 5
                                                                        Survey / Register
                                                                       All operatives are to be Asbestos awareness trained.
                                                                       Operatives are to immediately stop work if they
                                                                        discover or perceive an item to be ACM’s and report
                                                                        it to a member of the MAIN CONTRACTOR
                                                                        Management team.
                                                                       Operatives are not to disturb any potentially
                                                                        suspected Asbestos.
 Working around Electrical     Operatives         5x4= 20              Before works commence electrics need to be                 5x1 = 5
                                                                                                                                     Level of
 Element of the Work Process                       Level of                                                                                     Person Who Will Control
                               Persons at Risk                  Control Measure/ Precaution                                          Residual
 and Hazard                                        Risk                                                                                         the Risk
                                                                                                                                     Risk
                                                                          isolated.
                                                                         Electric isolation needs to be confirmed in writing by
                                                                          MAIN CONTRACTORthat the area is safe.
                                                                         Whereby live Electrics isolated then they are to be
                                                                          clearly labelled and / or identified to CONTRACTOR
                                                                          operatives via a briefing sheet.
                                                                         Operatives are to ensure when drilling, breaking or
                                                                          cutting out ceilings or walls etc… that they carry out
                                                                          an initial exploratory hole with a smaller blade or bit
                                                                          to ensure they can identify the build up behind /
                                                                          underneath etc… and miss any services.
 3rd Party Protection          Members of Public    4x3= 12              Establish safe working area to prevent unauthorised         4x1 = 4   Contractor
                                                                          access.
                                                                         All works will be carried out under a permit to work
                                                                          system gained from the MAIN CONTRACTORsite
                                                                          team.
                                                                         Protection to the public will be in the form of barriers
                                                                          and adequate signage to notify of the danger. Site
                                                                          supervisors will also be on hand to ensure no third-
                                                                          party access.
 Concrete                      Operatives           4x3=12               Operatives to be briefed regarding the risk and safety       4x1=4    Contractor
                                                                          awareness. If practicable lay a board across kicker
                                                                          bars until immediately before pour.
                                                                         Inform site operatives of hazards associated with
                                                                          concreting and the control measures to be
                                                                          implemented. Wear appropriate PPE and monitor
                                                                          compliance. Welfare facilities are provided for
                                                                          operatives to remove any contaminated clothing and
                                                                          showers for washing and immediate first aid (eye
                                                                          irrigation) facilities.
                                                                         Ensure all moving parts (where there is a risk of
                                                                          entanglement are guarded, or other suitable
                                                                          measures are in place. Do not wear loose clothing
                                                                          that could be caught in rotating/ moving parts. Do not
                                                                          climb inside concrete drums. Do not reach into
Page 16 of 19                                           Method Statement No:                                  Rev: 1.0
Doc No: 001
                                                                         CONTRACTOR RISK ASSESSMENT
                                                                                                                                      Level of
 Element of the Work Process                       Level of                                                                                      Person Who Will Control
                               Persons at Risk                  Control Measure/ Precaution                                           Residual
 and Hazard                                        Risk                                                                                          the Risk
                                                                                                                                      Risk
                                                                          rotating drums with hand/ arm or shovel.
                                                                         Where practicable allow spills to set and then lift. If
                                                                          this is not an option, lift the wet product with suitable
                                                                          equipment (depending on spilt quantity) into a
                                                                          suitable receptacle for later disposal. Dispose of via
                                                                          authorised site or in accordance with the local
                                                                          authorities. Avoid spills into local watercourses due to
                                                                          alkalinity of the product.
 Working in an excavation      Operatives and       5x4=20               Ensure cat scan is taken                                       5x1     5
                               members of public                         Hand digging only
                                                                         Ensure weekly inspections of excavation
                                                                         Ensure suitable access
                                                                         No Lone working
                                                                         Ensure excavation is covered at all times.
 Weals disease                 Operatives                                Ensure operatives wear correct PPE.                            5x1     5
                                                                         Ensure operatives have access to washing facilitys
                                                                         Ensure operatives are educated as to the dangers of
                                                                          weals disease.
Appendix A: