NEC4 GCT 10-11-2021 Clean
NEC4 GCT 10-11-2021 Clean
LIBRARY OF
STANDARD GENERAL CONDITIONS OF TENDER
Important Notes:
(1) This set of General Conditions of Tender (“GCT”) is applicable to contracts using NEC4
ECC (June 2017, with amendments October 2020) form.
(2) Project officers should refer to the latest technical circulars/memos on DEVB’s website
and Works Group Intranet Portal during their preparation of tender documents.
(3) Project officers should use the library with caution and, if any anomalies are found,
please notify their departmental contract advisors for clarification and, if necessary,
please seek further clarification with the DEVB subject officer [AS(WP4)8, telephone
no. 3509 7308].
(4) Double check the correct references are inserted in the relevant spaces.
Clause Remarks/Guidelines
GCT 1 Definitions
(1) For the purpose of these General Conditions of DEVB memo ref. (02B6J-01-6) in
Tender and Special Conditions of Tender: DEVB(W)510/10/01 dated
24.3.2011.
(i) “Project Manager designate” means ____# # Full description of the “Project
Manager designate” (including
(ii) “unincorporated joint venture”,
full name or, as the case may be,
“participant”, “incorporated joint venture”
full description of the post and
and “shareholder” shall bear the same
name of the current holder of the
meanings as those given in paragraph 6 of
post, address, telephone number
the Environment, Transport and Works
and fax number) should be given
Bureau Technical Circular (Works) No.
in the definition.
50/2002 on Contractors’ Joint Venture.
Clause Remarks/Guidelines
Clause Remarks/Guidelines
activity schedule.
*(c) One set of drawings as listed in Appendix [insert Note: Where applicable, amend
appropriate reference] to the Particular this to (c)(i) and add other item(s)
Specification, such as “Site investigation
information” as (c)(ii), etc.
(d) One set of the Electronic Dissemination Package
(EDP) consisting of:
(i) Files containing the contents of the documents
stated in sub-clauses (a), (b) and (c) above,
Clause Remarks/Guidelines
Clause Remarks/Guidelines
Clause Remarks/Guidelines
* Delete/Modify as appropriate.
(c) The submissions that are required by the General
Conditions of Tender (GCT) and Special
Conditions of Tender (SCT).
Library of Standard GCT for NEC4 ECC (4.10.2021) Page GCT 4(V1) - 1 of 3
General Conditions of Tender
Clause Remarks/Guidelines
Library of Standard GCT for NEC4 ECC (4.10.2021) Page GCT 4(V1) - 2 of 3
General Conditions of Tender
Clause Remarks/Guidelines
Library of Standard GCT for NEC4 ECC (4.10.2021) Page GCT 4(V1) - 3 of 3
General Conditions of Tender
Clause Remarks/Guidelines
Library of Standard GCT for NEC4 ECC (10.11.2021) Page GCT 4(V2) - 1 of 4
General Conditions of Tender
Clause Remarks/Guidelines
subcontracted works/items stipulated in submission in electronic format
Appendix [insert appropriate reference] to the (Appendix 4 to ETWB TCW
additional conditions of contract under pre-bid No. 11/2005)
arrangement in either hard copy format or 6. Sub-clause (c)(iv) is only
electronic format (Clause SCT [18]) [See Note 3] applicable for works tenders of
(iv) The Estimates for Tender Price Index (ETPI) Group C contracts issued under
in either hard copy format or electronic format CEDD, HyD, WSD and DSD
fully priced as to each item, extended, cast and and adopting ECC Options A or
totaled as appropriate. (Clause SCT [20]) [See C, where the tender price
Note 6] information are required for
compilation of the CEWTPI.
(DEVB TC(W) No. 6/2017)
Library of Standard GCT for NEC4 ECC (10.11.2021) Page GCT 4(V2) - 2 of 4
General Conditions of Tender
Clause Remarks/Guidelines
requisite requirements for each proposed
Subcontractor/supplier in accordance with SCT
[18(2)(b), (c) and (d)]. [See Note 4]
Library of Standard GCT for NEC4 ECC (10.11.2021) Page GCT 4(V2) - 3 of 4
General Conditions of Tender
Clause Remarks/Guidelines
as a debt. The tenderer whose tender has been so
checked shall pay such cost if demanded by the
Client.
(5) Where a document may be submitted in hard
copy format or electronic format and if a tenderer
makes two submissions for the same document,
one in hard copy format and one in electronic
format, the submission in hard copy format shall
be discarded.
(6) All submission in electronic format shall comply
with the requirements set out in Appendix [insert
appropriate reference] to these General
Conditions of Tender [See Note 5].
Library of Standard GCT for NEC4 ECC (10.11.2021) Page GCT 4(V2) - 4 of 4
General Conditions of Tender
Clause Remarks/Guidelines
Clause Remarks/Guidelines
Clause Remarks/Guidelines
Clause Remarks/Guidelines
Clause Remarks/Guidelines
Clause Remarks/Guidelines
Clause Remarks/Guidelines
Without prejudice to other General Conditions of Tender # Please include the principles and
and Special Conditions of Tender, if errors and/or rules contained in ETWB TC(W)
omissions are found in a tender during tender examination, No. 41/2002 as an appendix to these
such errors and/or omissions shall be dealt with in General Conditions of Tender and
accordance with the principles and rules contained in insert appropriate reference.
Appendix [insert appropriate reference]# to these General
Conditions of Tender.
Clause Remarks/Guidelines
Unless otherwise provided, the tender shall be in Hong Note: Please refer to SPR 355 for
Kong dollars. tenders in foreign currencies.
Clause Remarks/Guidelines
Clause Remarks/Guidelines
(2) For the purposes of this Clause, “erratic pricing” * Delete as appropriate.
means the situation where an *item/*activity or
certain *items/*activities in *a/an *bill of
quantities/*activity schedule are priced or
structured in such a way as to suggest significant
and unjustified:-
Clause Remarks/Guidelines
Clause Remarks/Guidelines
Clause Remarks/Guidelines
(1) The Client will not consider any clarification or DEVB memo ref. DEVB(W)
information submitted by a tenderer after close of 510/20/01 dated 10.9.2012 and ref.
tender irrespective of whether or not the DEVB(W) 510/83/05 dated
clarification or information is submitted at the 9.11.2020.
invitation of the Client if such clarification or
information would alter the tender in substance or
give the tenderer an advantage over the other
tenderers.
Clause Remarks/Guidelines
Clause Remarks/Guidelines
Clause Remarks/Guidelines
(1) Site investigation information *as listed in Clause Please refer to the guidelines in
GCT 2(c) of these General Conditions of Tender is Section 11.5, Chapter 5 of the
issued with the tender documents/* as listed in Project Administration Handbook
Clause GCT 3(b) of these General Conditions of for issuing information to
Tender is available for inspection by appointment prospective contractors in the pre-
at the Project Manager designate’s office during contract stage.
normal office hours for the information of the
* Delete as appropriate.
tenderer. Any site investigation information, if
issued, is to be returned to the Project Manager
designate’s office after submission of the tender.
Clause Remarks/Guidelines
GCT 19 Copyright
(1) The documents, plans, drawings or other materials Ref: ETWB TCW No. 26/2004
forming part of the tender documents shall only be
(Based on the SCT clause in the
used by a tenderer or any person authorized or
obsolete ETWB TCW No. 39/2002.)
licensed by the tenderer for the purpose of
preparing its tender. All other rights in the aforesaid
materials are reserved by the relevant copyright
owners. The tenderer shall be liable to the Client
for breach of the foregoing by any such person as
if the breach were committed by the tenderer.
Clause Remarks/Guidelines
(1) The tenderer shall, upon written request by the Note: This is usually a non-
Project Manager designate issued in accordance essential submission.
with General Conditions of Tender Clause GCT However, if the submission
25, submit to the Project Manager designate an of a SMP is considered an
outline Subcontractor Management Plan (SMP) essential requirement
which shall contain information as required in the (which is rare), sub-clause
Guidelines on Scope and Contents of the (1) will need to be re-
Subcontractor Management Plan at Appendix worded to state that the
[insert appropriate reference] to the additional SMP shall be submitted
conditions of contract. The outline SMP submitted together with the
shall not form part of this contract. submission of the tender.
Clause Remarks/Guidelines
Without prejudice to other General Conditions of Tender or Ref: DEVB memo ref. (01YVQ-
Special Conditions of Tender providing for invalidating a 01-2) in DEVB(W) 546/17/01
tender submitted by a tenderer, the failure of a tenderer to dated 3.4.2009 and DEVB memo
submit with its tender any of the following on or before the ref. (03487-01-1) in DEVB(W)
original date set for the close of tender or, if this has been 510/83/05 dated 31.12.2019.
extended, the extended date shall render its tender invalid:
(i) the Form of Tender required under Clause GCT Note: The items (i) and (ii) must be
4(1)(a)(i) listed under this GCT. Please see
also the “remark” for SCT.
(ii) the *bill of quantities/*activity schedule required The items from (iii) to (ix) are used
under Clause GCT 4(1)(a)(iii) only in rare cases. Please refer to
the individual SCT Clause for
*(iii) the programme of works required under Clause
guidance. These items are to
[SCT 1]
be included as essential
*(iv) design required for part of the works not covered requirements if required to be
by the Client’s design required under Clause submitted by the tenderers. If
[SCT 3] these are not regarded as essential
*(v) Temporary Works design required under Clause requirements they should not be
[SCT 4] required to be submitted.
*(vi) Outline Safety Plan required under Clause [SCT * Delete as appropriate.
14]
*(x) where the tenderer is an unincorporated joint Items (x) and (xi) must be listed for
venture, nomination of a lead participant required tenders that allow joint ventures to
under SCT Clause [SCT 5]1 participate.
Clause Remarks/Guidelines
1 SCT 5(2)(a)
Clause Remarks/Guidelines
(1) If the tenderer or, if the tenderer is an Ref: ETWB TCW No. 10/2004 with
unincorporated or incorporated joint venture, any modifications in accordance with the
participant of the unincorporated joint venture or definition in GCT 1(b).
shareholder of the incorporated joint venture is
This clause is designed for inputting
under suspension from tendering for Buildings* /
one service category only. If a
Port Works* / Roads and Drainage* / Site
project requires invitation of more
Formation*/ Waterworks* category of the List of
than one service category in the List,
Approved Contractors for Public Works (see Note
DEVB and LAD(W) have to be
1), its tender will not be considered unless the
consulted on the non-standard
suspension is lifted by the relevant works
amendments.
department or the Development Bureau by the
date set for the close of tender, or if this has been For tenders adopting open tendering
extended, the extended date. procedures, project may require to
include more than one service
category in the List of Approved
Contractors for Public Works or the
List of Approved Suppliers of
Materials and Specialist Contractors
for Public Works, DEVB and
LAD(W) have to be consulted on the
non-standard amendments.
* Delete as appropriate.
Clause Remarks/Guidelines
Clause Remarks/Guidelines
Alternative tenders or designs for which no invitation has Ref.: DEVB TCW No. 3/2014.
been made shall not be considered.
Clause Remarks/Guidelines
The tenderer shall not and shall ensure that its agents and Ref: ETWB TCW No. 3/2004
employees shall not offer or give any advantage, gratuity, “Ethical Commitment by
bonus, discount, bribe or loan of any sort to any agent or Consultants and Contractors” is
employee of the Client or to the Project Manager designate relevant.
or to any member of the Project Manager designate’s staff.
Any breach of or non-compliance with this Clause by the
tenderer shall, without affecting the tenderer’s liability for
such breach or non-compliance, invalidate its tender.
Clause Remarks/Guidelines
The tenderer shall upon written request by the Project DEVB memo ref. (02B6J-01-6) in
Manager designate (which may be issued at any time after DEVB(W)510/10/01 dated
the tender closing date) submit to the Project Manager 24.3.2011.
designate within 7 days of the date of issue of the written
Note: Non submission will be
request or within reasonable time upon the written request the
regarded as withdrawal of
following documents:
tender.
1. GCT 5,
2. GCT 20(1),
3. GCT 27(2),
4. GCT 28(2),
6. SCT 5(5)(b),
8. SCT 7(1),
Clause Remarks/Guidelines
GCT 26 Anti-collusion
(1) (a) Subject to sub-clause (2) of this Clause, DEVB memo ref. (02B6J-01-6) in
the tenderer shall not communicate to any DEVB(W)510/10/01 dated
person other than the Client the amount of 24.3.2011.
the tender price or any part thereof until
the tenderer is notified by the Client of the
outcome of the tender exercise.
Clause Remarks/Guidelines
(3) The tenderer shall submit with its tender a duly + See below. It shall not be
signed and witnessed letter in the form set out in included as an essential
Appendix [insert appropriate reference]+ to these requirement under GCT 21.
General Conditions of Tender. The signatory to
the letter shall be a person authorized to sign
Government contracts on the tenderer’s behalf.
Appendix [ ]
Date: _____________________
Dear Sir/Madam,
Contract No.: [ ]
Title: [ ]
Clause Remarks/Guidelines
*[I/We], represent and warrant that in relation to the expanded to include the
tender for the above contract: respective names and addresses
of such persons or as the case
(i) *[I/We], other than the Excepted
may be companies.
Communications referred to in the last
paragraph of this letter, have not communicated 2 Where the tenderer comprises
and will not communicate to any person other two or more persons or
than the Government the amount of the tender companies acting in partnership,
price or any part thereof until *[I/we] have been joint venture or otherwise, all
notified by the Government of the outcome of such persons or as the case may
the tender exercise; be companies must sign. The
signatory for each of such
(ii) *[I/We] have not fixed and will not fix the
persons or companies shall be a
amount of the tender price or any part thereof
person authorized to sign
by arrangement with any person;
Government contracts on behalf
(iii) *[I/We] have not made and will not make any of that person or as the case may
arrangement with any person as to whether be company.
*[I/we] or that other person will or will not
submit a tender; and
Clause Remarks/Guidelines
Occupation: ________________________
Clause Remarks/Guidelines
(2) The tenderer shall submit, subject to General ** Delete as appropriate for
Conditions of Tender Clause GCT 25/with the Formula Approach / Marking
tender**, either a statement of all convictions Scheme tender evaluation.
under Sections 17I or 38A of the Immigration
Ordinance (Cap. 115) for employing illegal
workers or for having illegal workers for all sites
under its control (whether they are sites under
public or private contracts) during the 12-month^ ^ [or other period specified by the
period prior to the date set for the close of tender, Project Manager where
Clause Remarks/Guidelines
or if this has been extended, the extended date, the appropriate to cope with the
details of which shall include the legislation assessment period for tender
violated, dates of offences, dates of convictions evaluation using the Marking
and the associated fine imposed by the court, site Scheme.]
addresses, contract numbers and contract titles, or
a statement of “no conviction”. The statement
shall be certified by a person authorized to sign
Government contracts on the tenderer’s behalf #[, # For use in tenders which
or in case of EMSTF’s tender, a person authorized EMSTF is eligible to bid
to sign the Service Level Agreement.].
Clause Remarks/Guidelines
(1) A tender will not be considered if, during the 12- Ref. ETWB TCW No. 10/2004 and
month period prior to the date set for the close of Clause 5.7.1 of the Contractor
tender, or if this has been extended, the extended Management Handbook, with
date, the tenderer has had three or more modifications in accordance with the
convictions in respect of separate incidents under definition in GCT 1(b).
the Employment Ordinance (Cap. 57) on any site
under the tenderer’s control, whether or not it has
been formally suspended as a result of such
convictions. If the tenderer is an unincorporated
or incorporated joint venture, the tender will not be
considered if any participant of the unincorporated
joint venture or shareholder of the incorporated
joint venture has had three or more such
convictions during the 12-month period, whether
or not that participant or shareholder has been
formally suspended as a result of such convictions.
Clause Remarks/Guidelines
Clause Remarks/Guidelines
(2) (a) A holding company and all of its subsidiaries DEVB memo ref. DEVB(W)
shall be allowed to submit only one tender 510/10/01 dated 16.12.2014.
from any one of the companies in the group.
(2A) (a) For related parties, only one of them is DEVB memo ref. DEVB(W)
permitted to submit a tender for this contract. 510/83/05 dated 16.9.2020
Clause Remarks/Guidelines
tenderer or of a parent of the
tenderer.
Clause Remarks/Guidelines
directly or indirectly, including any director
(whether executive or otherwise) of that
tenderer/entity/parent.
(4) The tenderer shall submit with its tender a duly DEVB memo ref. DEVB(W)
signed and witnessed letter in the form set out in 510/83/05 dated 9.11.2020
Appendix [insert an appropriate reference]+ to
+
these General Conditions of Tender. The It shall not be included as an
signatory to the letter shall be a person authorized essential requirement under GCT
to sign Government contracts on the tenderer’s 21.
behalf.
Appendix [ ]
Date: _____________________
Dear Sir/Madam,
Contract No.: [ ]
Title: [ ]
Clause Remarks/Guidelines
Occupation: _____________________________
Clause Remarks/Guidelines
GCT 30 Admission, promotion and confirmation to the List of Approved Contractors for
Public Works / the List of Approved Suppliers of Materials and Specialist Contractors for
Public Works
A tender submitted by a contractor who has applied for DEVB memo ref. DEVB(W)
admission or promotion to the category, class and/or group 546/83/01 dated 10.8.2011
specified in the tender invitation or, in relation to a contract
for which tenders are invited from confirmed contractors
only, a tender submitted by a contractor who has applied
for confirmed status will not be considered unless its
application for admission or promotion or, as the case may
be, confirmation is approved by the date set for the close of
tender, or if this has been extended, the extended date.
Clause Remarks/Guidelines
GCT 31 Eligibility of probationary contractors to tender and for the award of contracts
(a) the number and/or value of contracts or This clause is not applicable for
works that it already holds (also counting tenders adopting open tendering
this contract and the corrected forecast total procedures.
of the Prices) exceeds the limits on number
and/or value of contracts or works in the
relevant category, class and group as
stipulated in the then current version of the
Contractor Management Handbook; or
Clause Remarks/Guidelines
set for close of tender or, if this has been
extended, the extended date; or
(3) In counting the number and/or value of contracts Refer to DEVB’s memo ref.
or works that a tenderer already holds under sub- DEVB(W) 510/83/05 dated
clauses (1)(a) and (2)(a) above, the joint venture 14.7.2020
contract(s) held by the tenderer of which it is
NOT the lead participant or major shareholder
will NOT be counted.
(4) Tenderers should note that where: Refer to DEVB’s memo ref.
DEVB(W) 510/83/05 dated
(a) a probationary contractor has submitted
14.7.2020
tenders (including a tender for this
contract) and attained the highest
combined scores for more than one
contract (including this contract) in the
Clause Remarks/Guidelines
same category, class and group; and
Clause Remarks/Guidelines
GCT 31A Eligibility to Tender and for the Award of Contracts Applicable to Confirmed
Group [B]Note 1 Contractors [Effective period from 2 October 2020 to 30 September 2022]
(1) Where a tender is submitted by a confirmed DEVB memo ref. DEVB(W)
Group [B]Note 1 contractor in the category(ies) 510/33/02 dated 31.8.2020.
and group(s) specified in the tender invitation:- Effective period from 2 October
2020 to 30 September 2022.
(a) The rules on the eligibility to tender and for
the award of contract for probationary Group
[C]Note 2 contractors and the limits on the
number and/or values of contract or works
that may be undertaken by probationary
Group [C]Note 2 contractors in the relevant
category, all as set out in the current version
of the Contractor Management Handbook,
shall apply to the confirmed Group [B]Note 1
contractor. The eligibility shall be checked
at the date set for the close of tender or, if
this has been extended, the extended date
and at the date when the tender report is
completed and signed for submission to the
relevant authority for determination of the
contract award in accordance with sub-
clauses (1)(b) and (1)(c).
Library of Standard GCT for NEC4 ECC (4.10.2021) Page GCT 31A - 1 of 6
General Conditions of Tender
Clause Remarks/Guidelines
[C]Note 2 contractors as stipulated in the
then current version of the Contractor
Management Handbook; or
Library of Standard GCT for NEC4 ECC (4.10.2021) Page GCT 31A - 2 of 6
General Conditions of Tender
Clause Remarks/Guidelines
close of tender or, if this has been
extended, the extended date,
Library of Standard GCT for NEC4 ECC (4.10.2021) Page GCT 31A - 3 of 6
General Conditions of Tender
Clause Remarks/Guidelines
(3) In counting the number and/or the value of
contracts or works that a tenderer already holds
under sub-clauses (1)(b) and (1)(c), the joint
venture contract(s) held by the tenderer of which
it is NOT the lead participant or major
shareholder will not be counted.
Library of Standard GCT for NEC4 ECC (4.10.2021) Page GCT 31A - 4 of 6
General Conditions of Tender
Clause Remarks/Guidelines
extended date,
Library of Standard GCT for NEC4 ECC (4.10.2021) Page GCT 31A - 5 of 6
General Conditions of Tender
Notes:
Contract Group
Works contract (other than term contract) with pre- Group A
tender estimate more than the Group A tender limit but
less than or equivalent to 110% of the Group A tender
limit
Works contract (other than term contract) with pre- Group B
tender estimate more than the Group B tender limit but
less than or equivalent to 110% of the Group B tender
limit
Contract Group
Works contract (other than term contract) with pre- Group B
tender estimate more than the Group A tender limit but
less than or equivalent to 110% of the Group A tender
limit
Works contract (other than term contract) with pre- Group C
tender estimate more than the Group B tender limit but
less than or equivalent to 110% of the Group B tender
limit
Note 3
SCT 5 (Contractors’ Joint Venture) in the Library of Standard Special Conditions
of Tender.
Library of Standard GCT for NEC4 ECC (4.10.2021) Page GCT 31A - 6 of 6
General Conditions of Tender
Clause Remarks/Guidelines
(1) The tenderer shall not, and shall procure that its
employees, agents and subcontractors shall not,
offer, solicit or accept an advantage as defined in
the Prevention of Bribery Ordinance, Cap. 201 in
connection with the tendering and execution of
this contract.
Clause Remarks/Guidelines
The Client shall not in any circumstances be liable for any Note : Originated from the funding
costs, expenses and damages incurred or suffered by the approval clause.
tenderers in connection with the preparation and submission
of their tenders, in the event that this tender exercise is
cancelled on any ground[, including on the ground that funds * Delete the words in square
are not available under Special Conditions of Tender Clause brackets if SCT 10 is not used.
SCT 10].*
Clause Remarks/Guidelines
(1) The tenderer shall submit with the tender a duly DEVB memo ref. DEVB(W)
signed letter in the form set out in Appendix 510/10/01 dated 3.12.2012.
[insert appropriate reference ] to these General
Conditions of Tender giving consent to the [ name
of the project office/procuring department ] to
obtain from all relevant government
departments/bureaux, authorizing such relevant
Note 1 : Project office/procuring
government departments/bureaux to release and
department should check the
make available to [ name of the project
ordinances / specific subsidiary
office/procuring department ] and giving further
legislation to be listed, taking into
consent to the [ name of the project
account the provisions of the tender
office/procuring department ] to furnish to the
documents as adopted for any
Project Manager designate, all information
particular project (including GCT
relating to its convictions, including the legislation
and SCT). On the basis of the
violated, dates of offences, dates of convictions
GCT and SCT promulgated by
and the associated fine imposed by the court, site
DEVB (via Technical Circulars and
addresses, contract numbers and contract titles, for
memos) as at 30 November 2012,
offences under the following ordinances
the ordinances/specific subsidiary
(including all subsidiary legislation made
legislation to be covered include:
thereunder) and specific subsidiary legislation (if
any):
(a) [Set out the ordinances/specific sub-
legislation quoted in relevant GCTs and
SCTs] [See Note 1];
(b) [Land (Miscellaneous Provisions)
Ordinance (Cap. 28) ][See Note 2]; and
(c) [Other ordinances / specific subsidiary
legislation to be specified by the project
office/procuring department if required for
tender assessment in accordance with the
provisions of the tender documents as
adopted for any particular project ]. [See
Note 1]
Clause Remarks/Guidelines
Clause Remarks/Guidelines
standard marking scheme set out in
Appendix C1 to DEVB TCW No.
4/2014 is adopted. Departments
should check with the Highways
Department for such conviction
records.
The letter shall be signed by a person authorized Note 3 : This is not to be inserted as
to sign Government contracts on the tenderer's an essential requirement pursuant to
behalf [See Note 3]. Clause GCT 21. However, contract
drafter shall ensure that the
submission of the duly signed letter
of consent and authorization is
covered by GCT 16 as amended in
accordance with DEVB’s memo ref.
DEVB(W) 510/10/01 dated 10
September 2012 and entitled Tender
Clarifications.
Appendix __
Dear Sir/Madam,
Contract No. [ ]
[ Contract title ]
Letter of Consent and Authorization
Clause Remarks/Guidelines
office/procuring department ] to obtain from all relevant
government departments/bureaux and authorize such
relevant government departments/bureaux to release and
make available to [ name of the project office/procuring
department ] information relating to our conviction
records (if any), including the legislation violated, dates
of offences, dates of convictions and the associated fine
imposed by the court, site addresses, contract numbers
and contract titles, for offences under the following
ordinances (including all sub-legislation made
thereunder) and specific sub-legislation (if any) for the * Where GCT 34(2) applies,
purposes of assessment of [our submission]* in this change to "the submission of
tendering exercise. [name of the tenderer]".
Clause Remarks/Guidelines
GCT 35 Contingency sums, provisional sums and forecast total of the Prices
(1) Notwithstanding the inclusion of contingency sums, * Delete where appropriate.
provisional sums and forecast total of the Prices in the
# Insert appropriate clause reference.
Grand Summary of the *bill of quantities/*activity
schedule, the contingency sums, provisional sums and
forecast total of the Prices shall not form part of this
contract.
(2) The contingency sums and provisional sums are
allowed as contingencies for the purpose of internal
administration of the Client under the Stores and
Procurement Regulations only. The forecast total of
the Prices is included for tender evaluation purpose
only and shall not affect the tendered total of the
Prices which shall remain contractually binding.
The tenderer shall not rely on any information
supplied to it on the contingency sums, provisional
sums or forecast total of the Prices as estimated
changes to the Prices due to the effect of compensation
events or other estimated payment which shall be
assessed in accordance with the relevant contract
terms if this contract is awarded to it.
(3) The attention of the tenderer is drawn to Clause [A7]#
of the additional conditions of contract.
Part A - Financial information required to be submitted in tender for public works contracts
(for tenderers already on the List of Approved Contractors for Public Works and/or the List
of Approved Suppliers of Materials and Specialist Contractors for Public Works)
(1) Tenderers shall provide the following documents if they have not already been submitted to
the Finance Section of Development Bureau before:
(a) management accounts covering the period between the latest set of audited financial
statements up to a date not earlier than three months before the date of submission;
(b) a statement listing current or outstanding contracts held in hand with the Client and the
private sector including but not limited to the Hospital Authority and the Housing Authority,
both as main contractor or subcontractor, with total and outstanding contract sums,
contract period and time required to complete the outstanding portion of the contract;
and
(c) bank letters or agreements on existing banking facilities such as term loans and overdraft.
Copies of all statements submitted under paragraphs (a) to (c) above shall be certified true and
correct by independent auditors or directors of the company. The sample statement format
for (b) above can be downloaded from the website of Development Bureau.
(3) The management accounts shall reflect the financial position of the company only (i.e. the
accounts must not be consolidated accounts).
(4) The management accounts include at a minimum statement of financial position (or balance
sheet) and statement of comprehensive income (or profit and loss accounts) and must be in
the same layout of the audited financial statements.
(5) In the case of a joint venture, financial and supplementary statements as mentioned under
paragraph (1) above for each participating company must be submitted.
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 5 - A1
General Conditions of Tender
Part B - Financial information required to be submitted in tender for public works contracts
(for tenderers NOT on the List of Approved Contractors for Public Works and the List of
Approved Suppliers of Materials and Specialist Contractors for Public Works)
(1) Tenderers shall provide the following documents if they have not already been submitted to
the Finance Section of Development Bureau before:
(a) the original or copies of annual financial statements for the last three accounting years
audited and certified by certified public accountants;
(b) management accounts covering the period between the latest set of audited financial
statements up to a date not earlier than three months before the date of submission;
(c) a statement of gains/(losses) arising from fair value adjustments for the latest audited
financial statements;
(d) a statement giving details of significant events which occurred after the year end date
of the latest audited financial statements which would affect the tenderer’s financial
position;
(e) a statement giving details of subsequent settlement of current assets after the year end
date of the latest audited financial statements;
(f) a statement giving details of any off-balance sheet liabilities, including contingent
liabilities, if not covered in the latest audited financial statements;
(g) a statement listing current or outstanding contracts held in hand with the Client and the
private sector including but not limited to the Hospital Authority and the Housing
Authority, both as main contractor or subcontractor, with total and outstanding contract
sums, contract period and time required to complete the outstanding portion of the
contract; and
(h) bank letters or agreements on existing banking facilities such as term loans and
overdraft.
Copies of audited financial statements submitted under paragraph (a) shall be certified true
by the directors of the company and all documents under paragraphs (b) to (h) above shall
be certified true and correct by independent auditors or directors of the company. The
sample statement format for (c), (d), (e) and (g) above can be downloaded from the website
of Development Bureau.
(2) All statements submitted should be prepared in English or Chinese.
(3) The financial statements and the management accounts shall reflect the financial position of
the company only (i.e. the accounts must not be consolidated accounts).
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 5 - A2
General Conditions of Tender
(4) Audited financial statements include auditor’s report, statement of financial position,
statement of comprehensive income, statement of changes in equity and statement of cash
flows, and notes comprising significant accounting policies and other explanatory
information.
(5) The latest audited financial statements must be for a period ending no more than 18 months
before the submission date.
(6) For the latest audited financial statements, if the auditor has issued a disclaimer or adverse
audit opinion in the auditor’s report, the company shall be deemed as failing to submit the
required financial statements.
(7) The management accounts include at a minimum statement of financial position (or balance
sheet) and statement of comprehensive income (or profit and loss accounts) and must be in
the same layout of the audited financial statements.
(8) In the case of a joint venture, financial and supplementary statements as mentioned under
paragraph (1) above for each participating company must be submitted.
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 5 - A3
APPENDIX [ ] TO THE GENERAL CONDITIONS OF TENDER
Section 1 – General
1.1 For errors which have been specifically addressed in the General or Special Conditions
of Tender, the errors shall be dealt with strictly in accordance with the relevant General
or Special Conditions of Tender. The following rules shall only apply where the errors
have not been specifically addressed in the General or Special Conditions of Tender.
1.2 Subject to paragraph 1.1 above, where a correction rule provided in Section 2 below is
applicable, the errors shall be corrected in accordance with that rule.
(i) where ambiguity as to the tenderer’s true intention exists, it shall be construed
by the tender examiner by reference to the best practice or his best judgment;
and
(ii) where errors relate to factual information and there is no room for manipulation
by a tenderer by virtue of subsequent correction; or where the correction of such
errors would not change the tender in substance or the quality of the tender which
would give the tenderer an advantage over the other tenderers, the concerned
tenderers may be permitted to correct the errors. In other cases, the tender shall
be assessed with the errors as submitted.
Notes: Four sets of similar but slightly different correction rules are set out in
Section 2. Their applications are shown in the table below: -
Set I II III IV
Option A
(May use for
(May use for
Option B & D Option B
NEC Option C in Option C
in building Option D
building
contracts)
contracts)
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 11 - A1
[Set I]
*Section 2 – Errors in pricing document [for use in contracts with activity schedule and
correction rules similar to those for conventional lump sum contracts]
2.1 The tendered total of the Prices stated in the Form of Tender shall remain unchanged
irrespective of any corrections made hereinafter. If there is a discrepancy between the
amount in “words” and in “figures” for the tendered total of the Prices in the Form of
Tender, the one that agrees with the figure stated in the Grand Summary of the activity
schedule shall be taken as the tendered total of the Prices. If neither one agrees with the
figure stated in the Grand Summary, the amount in “figures” shall be taken as the
tendered total of the Prices. Where either the amount in “words” or the amount in
“figures” is left blank or illegible, the remaining one shall be taken as the tendered total
of the Prices. If the amount in “words” and the amount in “figures” for the
tendered total of the Prices in the Form of Tender are both left blank or illegible,
the tender is invalid. Subject to the conditions abovementioned, the tendered total of
the Prices stated in the Form of Tender shall take precedence over the tendered total of
the Prices stated in the Contract Data Part two and the Grand Summary and the same
figure shall be correctly reinstated in the latter two documents for any discrepancy. If
the tenderer has not inserted the tendered total of the Prices in Contract Data Part two,
the tendered total of the Prices in Contract Data Part two shall be corrected to the
tendered total of the Prices stated in the Form of Tender.
2.2 If there are errors in the activity schedule, they shall be corrected as follows:
(i) Errors in the casting of cash columns in a schedule of the activity schedule shall
be corrected.
(ii) The extension may be amended to agree with the quantity and rate or (dependent
on the judgement of the tender examiner) the rate may be amended to agree with
the quantity and the extension in the cash column but in no case will the alteration
of both rate and cash extension be permitted for any re-measurement item
with provisional quantity. [Optional]
(iii) Indistinct rates shall be clarified to agree with the quantity and the extension in
the cash column for any re-measurement item with provisional quantity.
[Optional]
(iv) Where there is no price or an illegible price inserted against any activity in the
activity schedule, it shall be deemed that the price for the activity has been
allowed in prices entered elsewhere in the activity schedule and the price shall
therefore be marked as zero.
(v) If one or more pages of the activity schedule are found missing, subject to sub-
paragraph (vii) below, the prices for all activities in the missing page(s) shall be
marked as zero and the prices shall be deemed to have been allowed for in prices
entered elsewhere in the activity schedule.
(vi) Should there be a tender addendum introducing changes to the activity schedule
but the changes have not been incorporated into the activity schedule by a
tenderer, then the changes as required by the tender addendum shall be
incorporated into the tenderer’s activity schedule and the prices for those new
activities or modified activities shall be determined as follows:
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 11 - A2
Where new activity is Price for the new activity shall be marked
introduced as zero and the price of the activity shall be
deemed to have been allowed for in prices
entered elsewhere in the activity schedule,
unless it is an activity pre-priced by the
Client. For a pre-priced activity, the same
price in the addendum shall be used.
Where the activity description If a price has been entered against the
is changed original activity, the same price shall be
used.
Where the provisional quantity If a rate has been entered against the
for any re-measurement item original item, the same rate shall be used.
is changed [Optional]
Where the measurement unit is If a rate has been entered against the
modified for any re- original item, the rate shall be adjusted to
measurement item [Optional] fit in with the new unit.
(vii) Where the activity schedule contains any pre-priced activities and the tenderer
fails to include any of them correctly in its activity schedule, then such sum (or
sums) shall be correctly reinstated in the activity schedule.
(viii) Where the total of the prices of the additional activities in any schedule of
Schedule No. [XX]# to [XX]# of the activity schedule entered by the tenderer
exceeds [10%]^ of the total of the prices for that schedule, the total of the prices
of the additional activities in the respective schedule shall be corrected to the
equivalent value of [10%]^ of the total of prices for that schedule. The difference
between the corrected prices and the original prices entered by the tenderer for
that schedule shall then be distributed to all activities in that schedule in
proportion according to the original prices of those activities entered by the
tenderer. [Optional]
2.3 After correcting all the errors in accordance with paragraph 2.2 above, the difference
between:
(i) the tendered total of the Prices stated in the Form of Tender minus the total of
the prices for any pre-priced activities, and
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 11 - A3
(ii) the corrected total of all schedules of the activity schedule minus the total of the
prices for any pre-priced activities
shall be calculated as a plus percentage of the sum at 2.3(ii) if 2.3(i) is greater than
2.3(ii), or as a minus percentage of the sum at 2.3(ii) if 2.3(i) is less than 2.3(ii).
2.4 Subject to paragraph 2.3, the plus or minus percentage shall be applied to the tendered
prices including those corrected under paragraph 2.2 but excluding all pre-priced
activities.
2.5 After application of paragraphs 2.1 to 2.4 above, if the corrected total of the prices for
Schedule No. [XX]## of the activity schedule exceeds [YY%]^^ of the corrected total of
the prices for all schedules of the activity schedule, then the corrected total of the prices
for Schedule No. [XX]## shall be further adjusted to the equivalent value of [YY%]^^
of the corrected total of the prices for all schedules. The prices of the activities in
Schedule No. [XX]##, except for those pre-priced activities, shall be adjusted in
proportion according to the prices of those activities before application of this rule. The
difference between the adjusted prices and the prices before adjustment for Schedule No.
[XX]## shall then be distributed to other activities in all schedules of the activity schedule,
except for Schedule No. [XX]## and those pre-priced activities, in proportion according
to the prices of those activities before application of this rule. [Optional clause for
prevention of front loading scenario but satisfying the cash flow requirement if
applicable]
2.6 The tender examiner may adjust the corrected prices for any round-off error in order to
match with the tendered total of the Prices stated in the Form of Tender.
2.7 After correcting errors in accordance with the foregoing rules, the summary of all
schedules of the activity schedule shall be endorsed as follows:
“In accordance with the correction rules set out in Appendix [insert appropriate
reference] to the General Conditions of Tender as referred to in the General Conditions
of Tender Clause GCT 11, all the prices inserted by the tenderer in Schedules No. […]
and […] to […] of the activity schedule [except those pre-priced activities] shall be
corrected by …..% and …..% respectively for all purposes for which those prices may
be used under this contract.”
(i) If the fee percentage inserted by the tenderer in the Contract Data Part two
exceeds the cap of fee percentage as stated in the Contract Data Part two, it shall
be corrected to the cap of fee percentage. The Grand Summary including the
forecast total of the Prices shall be adjusted accordingly.
(ii) If the fee percentage inserted by the tenderer in the Contract Data Part two is a
negative percentage or lower than the minimum fee percentage, it shall be
corrected to the minimum fee percentage. The Grand Summary including the
forecast total of the Prices shall be adjusted accordingly.
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 11 - A4
(iii) If the tenderer has not inserted a fee percentage in the Contract Data Part two,
the fee percentage shall be corrected to the minimum fee percentage. The Grand
Summary including the forecast total of the Prices shall be adjusted accordingly.
(iv) If the fee percentage inserted by the tenderer in the Contract Data Part two is
illegible, the fee percentage shall be corrected to the minimum fee percentage.
The Grand Summary including the forecast total of the Prices shall be adjusted
accordingly.
2.9 Where the Grand Summary contains contingency sum for Defined Cost for
compensation events, *provisional sum for price adjustment for inflation under
secondary Option X1, *provisional sum for provision of Assistant Clerical Officer
(Labour Relations) and *provisional sum for performance-tied payment item under Pay
for Safety Performance Merit Scheme (PFSPMS) under secondary Option X20 or any
combination of them and the tenderer fails to include any or all of them correctly in the
Grand Summary, then such sum (or sums) shall be correctly reinstated in the Grand
Summary.
2.10 Where the Grand Summary contains contingency sum for Fee for compensation events,
and sub-total of all contingency sums and provisional sums or any combination of them
and arithmetical errors are found, then errors in calculation of such sum (or sums) shall
be corrected in the Grand Summary.
2.11 After correcting all the errors in the manner abovementioned, the forecast total of the
Prices shall be corrected to the sum of (i) the tendered total of the Prices in the Form of
Tender and (ii) the sub-total of all corrected contingency sums and corrected provisional
sums in the Grand Summary.
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 11 - A5
[Set II]
*Section 2 – Errors in pricing document [for use in contracts with bill of quantities and
correction rules similar to those for conventional lump sum contracts]
2.1 The tendered total of the Prices stated in the Form of Tender shall remain unchanged
irrespective of any corrections made hereinafter. If there is a discrepancy between the
amount in “words” and in “figures” for the tendered total of the Prices in the Form of
Tender, the one that agrees with the figure stated in the Grand Summary of the bill of
quantities shall be taken as the tendered total of the Prices. If neither one agrees with
the figure stated in the Grand Summary, the amount in “figures” shall be taken as the
tendered total of the Prices. Where either the amount in “words” or the amount in
“figures” is left blank or illegible, the remaining one shall be taken as the tendered total
of the Prices. If the amount in “words” and the amount in “figures” for the
tendered total of the Prices in the Form of Tender are both left blank or illegible,
the tender is invalid. Subject to the conditions abovementioned, the tendered total of
the Prices stated in the Form of Tender shall take precedence over the tendered total of
the Prices stated in the Contract Data Part two and the Grand Summary and the same
figure shall be correctly reinstated in the latter two documents for any discrepancy. If
the tenderer has not inserted the tendered total of the Prices in Contract Data Part two,
the tendered total of the Prices in Contract Data Part two shall be corrected to the
tendered total of the Prices stated in the Form of Tender.
2.2 If there are errors in the bill of quantities, they shall be corrected as follows:
(i) Errors in the casting of cash columns in a bill of the bill of quantities shall be
corrected.
(ii) The extension may be amended to agree with the quantity and rate or (dependent
on the judgement of the tender examiner) the rate may be amended to agree with
the quantity and the extension in the cash column but in no case will the alteration
of both rate and cash extension be permitted.
(iii) Indistinct rates shall be clarified to agree with the quantity and the extension in
the cash column.
(v) If one or more pages of the bill of quantities are found missing, subject to sub-
paragraph (vii) below, the rates for all items in the missing page(s) shall be
marked as zero and the prices shall be deemed to have been allowed for in rates
entered elsewhere in the bill of quantities.
(vi) Should there be a tender addendum introducing changes to the bill of quantities
but the changes have not been incorporated into the bill of quantities by a
tenderer, then the changes as required by the tender addendum shall be
incorporated into the tenderer’s bill of quantities and the rates for those new
items or modified items shall be determined as follows:
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 11 - A6
Where new item is introduced Rate for the new item shall be marked as
zero and the price of the item shall be
deemed to have been allowed for in rates
entered elsewhere in the bill of quantities,
unless it is an item pre-priced by the Client.
For a pre-priced item, the same rate in the
addendum shall be used.
Where the item description If a rate has been entered against the
and/or quantity is changed original item, the same rate shall be used.
Where the measurement unit is If a rate has been entered against the
modified original item, the rate shall be adjusted to
fit in with the new unit.
(vii) Where the bill of quantities contains any pre-priced items and the tenderer fails
to include any of them correctly in its bill of quantities, then such sum (or sums)
shall be correctly reinstated in the bill of quantities.
2.3 After correcting all the errors in accordance with paragraph 2.2 above, the difference
between:
(i) the tendered total of the Prices stated in the Form of Tender minus the total of
any pre-priced items, and
(ii) the corrected total of all items in all bills of the bill of quantities minus the total
of any pre-priced items
shall be calculated as a plus percentage of the sum at 2.3(ii) if 2.3(i) is greater than
2.3(ii), or as a minus percentage of the sum at 2.3(ii) if 2.3(i) is less than 2.3(ii).
2.4 Subject to paragraph 2.3, the plus or minus percentage shall be applied to the tendered
rates including those corrected under paragraph 2.2 but excluding all pre-priced items.
2.5 After application of paragraphs 2.1 to 2.4 above, if the corrected total of the prices for
Bill No. [XX]## of the bill of quantities exceeds [YY%]^^ of the corrected total of the
prices for all bills of the bill of quantities, then the corrected total of the prices for Bill
No. [XX]## shall be further adjusted to the equivalent value of [YY%]^^ of the corrected
total of the prices for all bills. The rates of the items in Bill No. [XX]##, except for those
pre-priced items, shall be adjusted in proportion according to the rates of those items
before application of this rule. The difference between the adjusted rates and the rates
before adjustment for Bill No. [XX]## shall then be distributed to other items in all bills
of the bill of quantities except for Bill No. [XX]## and those pre-priced items, in
proportion according to the rates of those items before application of this rule. [Optional
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 11 - A7
clause for prevention of front loading scenario but satisfying the cash flow requirement
if applicable]
2.6 The tender examiner may adjust the corrected rates for any round-off error in order to
match with the tendered total of the Prices stated in the Form of Tender.
2.7 After correcting errors in accordance with the foregoing rules, the summary of all bills
of the bill of quantities shall be endorsed as follows:
“In accordance with the correction rules set out in Appendix [insert appropriate
reference] to the General Conditions of Tender as referred to in the General Conditions
of Tender Clause GCT 11, all the rates and prices inserted by the tenderer in Bills No.
[…] and […] to […] of the bill of quantities [except those pre-priced items] shall be
corrected by …..% and …..% respectively for all purposes for which those rates and
prices may be used under this contract.”
(i) If the fee percentage inserted by the tenderer in the Contract Data Part two
exceeds the cap of fee percentage as stated in the Contract Data Part two, it shall
be corrected to the cap of fee percentage. The Grand Summary including the
forecast total of the Prices shall be adjusted accordingly.
(ii) If the fee percentage inserted by the tenderer in the Contract Data Part two is a
negative percentage or lower than the minimum fee percentage, it shall be
corrected to the minimum fee percentage. The Grand Summary including the
forecast total of the Prices shall be adjusted accordingly.
(iii) If the tenderer has not inserted a fee percentage in the Contract Data Part two,
the fee percentage shall be corrected to the minimum fee percentage. The Grand
Summary including the forecast total of the Prices shall be adjusted accordingly.
(iv) If the fee percentage inserted by the tenderer in the Contract Data Part two is
illegible, the fee percentage shall be corrected to the minimum fee percentage.
The Grand Summary including the forecast total of the Prices shall be adjusted
accordingly.
2.9 Where the Grand Summary contains contingency sum for Defined Cost for
compensation events, *provisional sum for price adjustment for inflation under
secondary Option X1, *provisional sum for provision of Assistant Clerical Officer
(Labour Relations) and *provisional sum for performance-tied payment item under Pay
for Safety Performance Merit Scheme (PFSPMS) under secondary Option X20 or any
combination of them and the tenderer fails to include any or all of them correctly in the
Grand Summary, then such sum (or sums) shall be correctly reinstated in the Grand
Summary.
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 11 - A8
2.10 Where the Grand Summary contains contingency sum for Fee for compensation events,
and sub-total of all contingency sums and provisional sums or any combination of them
and arithmetical errors are found, then errors in calculation of such sum (or sums) shall
be corrected in the Grand Summary.
2.11 After correcting all the errors in the manner abovementioned, the forecast total of the
Prices shall be corrected to the sum of (i) the tendered total of the Prices in the Form of
Tender and (ii) the sub-total of all corrected contingency sums and corrected provisional
sums in the Grand Summary.
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 11 - A9
[Set III]
*Section 2 – Errors in pricing document [for use in contract with activity schedule and
correction rules similar to those for conventional re-measurement contracts]
2.1 Under no circumstances can the tendered prices for activities be changed.
2.2 If errors are found in the activity schedule, they shall be corrected as follows:
(i) Errors in extensions and casting of page totals in a schedule of the activity
schedule shall be corrected and the rectified amounts carried to the Grand
Summary.
(ii) Where there is an extension amount but no rate or an illegible rate has been
inserted against any provisional quantity for any re-measurement item in the
activity schedule the rate is deemed to be the amount divided by the provisional
quantity as rounded off to the nearest cent. [Optional]
(iii) Subject to sub-clause (ii) above, where there is no price or an illegible price has
been inserted against any activity in the activity schedule, it shall be deemed that
the price for the activity has been allowed in prices entered elsewhere in the
activity schedule and the price shall therefore be marked as zero.
(iv) If one or more pages of the activity schedule are found missing, subject to sub-
paragraph (vi) below, the prices for all activities in the missing page(s) shall be
marked as zero and the prices shall be deemed to have been allowed for in prices
entered elsewhere in the activity schedule.
(v) Should there be a tender addendum introducing changes to the activity schedule
but the changes have not been incorporated into the activity schedule by a
tenderer, then the changes as required by the tender addendum shall be
incorporated into the tenderer’s activity schedule and the prices for those new
activities or modified activities shall be determined as follows:
Where new activity is Price for the new activity shall be marked
introduced as zero and the price of the activity shall be
deemed to have been allowed for in prices
entered elsewhere in the activity schedule,
unless it is an activity pre-priced by the
Client. For a pre-priced activity, the same
price in the addendum shall be used.
Where the activity description If a price has been entered against the
is changed original activity, the same price shall be
used.
Where the provisional quantity If a rate has been entered against the
for any re-measurement item original item, the same rate shall be used.
is changed [Optional]
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 11 - A10
Where the measurement unit is If a rate has been entered against the
modified for any re- original item, the rate shall be adjusted to
measurement item [Optional] fit in with the new unit.
(vi) Where the activity schedule contains any pre-priced activities and the tenderer
fails to include any of them correctly in its activity schedule, then such sum (or
sums) shall be correctly reinstated in the activity schedule.
2.3 After correcting all the errors in the manner abovementioned, the tendered total of the
Prices in the Grand Summary shall be corrected to the corrected total of all schedules of
the activity schedule. The tendered total of the Prices stated in the Form of Tender and
the Contract Data Part two shall be corrected accordingly.
2.3A If the activity schedule does not require any correction, and if the tendered total of the
Prices stated in the Grand Summary is different from that stated in the Form of Tender
or the Contract Data Part two, the Grand Summary shall prevail and the latter shall be
corrected accordingly.
2.3B If the tenderer has not inserted the tendered total of the Prices in Contract Data Part two,
the tendered total of the Prices in Contract Data Part two shall be corrected to the
tendered total of the Prices stated (or corrected, if applicable) in the Grand Summary.
(i) If the fee percentage inserted by the tenderer in the Contract Data Part two
exceeds the cap of fee percentage as stated in the Contract Data Part two, it shall
be corrected to the cap of fee percentage. The Grand Summary including the
forecast total of the Prices shall be adjusted accordingly.
(ii) If the fee percentage inserted by the tenderer in the Contract Data Part two is a
negative percentage or lower than the minimum fee percentage, it shall be
corrected to the minimum fee percentage. The Grand Summary including the
forecast total of the Prices shall be adjusted accordingly.
(iii) If the tenderer has not inserted a fee percentage in the Contract Data Part two,
the fee percentage shall be corrected to the minimum fee percentage. The Grand
Summary including the forecast total of the Prices shall be adjusted accordingly.
(iv) If the fee percentage inserted by the tenderer in the Contract Data Part two is
illegible, the fee percentage shall be corrected to the minimum fee percentage.
The Grand Summary including the forecast total of the Prices shall be adjusted
accordingly.
2.5 Where the Grand Summary contains contingency sum for Defined Cost for
compensation events, *provisional sum for price adjustment for inflation under
secondary Option X1, *provisional sum for provision of Assistant Clerical Officer
(Labour Relations) and *provisional sum for performance-tied payment item under Pay
for Safety Performance Merit Scheme (PFSPMS) under secondary Option X20 or any
combination of them and the tenderer fails to include any or all of them correctly in the
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 11 - A11
Grand Summary, then such sum (or sums) shall be correctly reinstated in the Grand
Summary.
2.6 Where the Grand Summary contains contingency sum for Fee for compensation events,
and sub-total of all contingency sums and provisional sums or any combination of them
and arithmetical errors are found, then errors in calculation of such sum (or sums) shall
be corrected in the Grand Summary.
2.7 After correcting all the errors in the manner abovementioned, the forecast total of the
Prices shall be corrected to the sum of (i) the corrected tendered total of the Prices and
(ii) the sub-total of all corrected contingency sums and corrected provisional sums in the
Grand Summary.
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 11 - A12
[Set IV]
*Section 2 – Errors in pricing document [for use in contracts with bill of quantities and
correction rules similar to those for conventional re-measurement contracts]
2.2 If errors are found in the bill of quantities, they shall be corrected as follows:
(i) Errors in extensions and casting of page totals in a bill of the bill of quantities
shall be corrected and the rectified amounts carried to the Grand Summary.
(ii) Where there is an extension amount but no rate or an illegible rate has been
inserted against any quantity in the bill of quantities the rate is deemed to be the
amount divided by the quantity as rounded off to the nearest cent.
(iv) If one or more pages of the bill of quantities are found missing, subject to sub-
paragraph (vi) below, the rates for all items in the missing page(s) shall be
marked as zero and the prices shall be deemed to have been allowed for in
rates entered elsewhere in the bill of quantities.
(v) Should there be a tender addendum introducing changes to the bill of quantities
but the changes have not been incorporated into the bill of quantities by a
tenderer, then the changes as required by the tender addendum shall be
incorporated into the tenderer’s bill of quantities and the rates for those new
items or modified items shall be determined as follows:
Where new item is introduced Rate for the new item shall be marked as
zero and the price of the item shall be
deemed to have been allowed for in rates
entered elsewhere in the bill of quantities,
unless it is an item pre-priced by the Client.
For a pre-priced item, the same rate in the
addendum shall be used.
Where the item description If a rate has been entered against the
and/or quantity is changed original item of work, the same rate shall
be used.
Where the measurement unit is If a rate has been entered against the
modified original item of work, the rate shall be
adjusted to fit in with the new unit.
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 11 - A13
(vi) Where the bill of quantities contains any pre-priced items and the tenderer fails
to include any of them correctly in its bill of quantities, then such sum (or sums)
shall be correctly reinstated in the bill of quantities.
2.3 After correcting all the errors in the manner abovementioned, the tendered total of the
Prices in the Grand Summary shall be corrected to the corrected total of all bills of the
bill of quantities. The tendered total of the Prices stated in the Form of Tender and the
Contract Data Part two shall be corrected accordingly.
2.3A If the bill of quantities does not require any correction, and if the tendered total of the
Prices stated in the Grand Summary is different from that stated in the Form of Tender
or the Contract Data Part two, the Grand Summary shall prevail and the latter shall be
corrected accordingly.
2.3B If the tenderer has not inserted the tendered total of the Prices in Contract Data Part two,
the tendered total of the Prices in Contract Data Part two shall be corrected to the
tendered total of the Prices stated (or corrected, if applicable) in the Grand Summary.
(i) If the fee percentage inserted by the tenderer in the Contract Data Part two
exceeds the cap of fee percentage as stated in the Contract Data Part two, it shall
be corrected to the cap of fee percentage. The Grand Summary including the
forecast total of the Prices shall be adjusted accordingly.
(ii) If the fee percentage inserted by the tenderer in the Contract Data Part two is a
negative percentage or lower than the minimum fee percentage, it shall be
corrected to the minimum fee percentage. The Grand Summary including the
forecast total of the Prices shall be adjusted accordingly.
(iii) If the tenderer has not inserted a fee percentage in the Contract Data Part two,
the fee percentage shall be corrected to the minimum fee percentage. The Grand
Summary including the forecast total of the Prices shall be adjusted accordingly.
(iv) If the fee percentage inserted by the tenderer in the Contract Data Part two is
illegible, the fee percentage shall be corrected to the minimum fee percentage.
The Grand Summary including the forecast total of the Prices shall be adjusted
accordingly.
2.5 Where the Grand Summary contains contingency sum for Defined Cost for
compensation events, *provisional sum for price adjustment for inflation under
secondary Option X1, *provisional sum for provision of Assistant Clerical Officer
(Labour Relations) and *provisional sum for performance-tied payment item under Pay
for Safety Performance Merit Scheme (PFSPMS) under secondary Option X20 or any
combination of them and the tenderer fails to include any or all of them correctly in the
Grand Summary, then such sum (or sums) shall be correctly reinstated in the Grand
Summary.
2.6 Where the Grand Summary contains contingency sum for Fee for compensation events,
and sub-total of all contingency sums and provisional sums or any combination of them
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 11 - A14
and arithmetical errors are found, then errors in calculation of such sum (or sums) shall
be corrected in the Grand Summary.
2.7 After correcting all the errors in the manner abovementioned, the forecast total of the
Prices shall be corrected to the sum of (i) the corrected tendered total of the Prices and
(ii) the sub-total of all corrected contingency sums and corrected provisional sums in the
Grand Summary.
Library of Standard GCT for NEC4 ECC (4.10.2021) Appendix Page GCT 11 - A15