SAP Material Training
SAP Material Training
Material Analyst
Material Level 1
Material Level 2
Material Level 3
Material Level 4
                                     When the component is a part within an assembly it is still required to create the
                                     material in SAP when the component needs to be defined and designed by Aker
                                     Solutions. Each material should carry the design documentation and description of how
                                     to manufacture and deliver the component independently.
                                     If the components within the assembly are designed by the supplier and delivered as
                                     part of the assembly ordered, it is not always necessary to create material for the detail
                                     components within the assembly.
                                     The design and delivery information can then be linked to the assembly ordered.
                                     Remember, that if ordering any of the internal components individually (e.g. later for
                                     spare parts) these components must also be set up in SAP.
Confidential © 2018 Aker Solutions
 REQUEST FOR NEW MATERIAL
•       Material description according to the agreed description for the component family or as per procedure
        10000008968.
Each box represents one step in the material creation workflow in SAP
                                      *If you have any similar material master already existing in SAP, you can copy that
                                      material using ‘copy’ button.
            2) Description = When the material is being created from CAD desktop (coming from Solidworks or
            AutoCAD) the system will automatically suggest using the DIR title as the material description.
            3) Base Unit = Base Unit of Measure (how the material is bought/manufactured, e.g. Valve => “ea” and
            Piping => “m”).
            Make sure this is filled correctly as it cannot be changed after the material has been taken into use.
            If Base Unit of Measure is set as e.g. “M” (meter), FT (feet), KG (kilogram) etc., it will not be possible to set
            the Serial number profile. Batch flag must be set if traceability is required.
                   4) Traceability code = Enter required Traceability Code (TC) (Global field) to define what serial or
                   batch numbering system is required for the current material.
                   5) Basic Material = Basic material is the physical material used. This is generally only specified
                   for single materials.
                   For assemblies having BoM set up by Aker Solutions use; “See BoM for materials”.
                   For assemblies (e.g. pumps, motors, valves, fittings) not having BoMs defined by Aker Solutions use:
                   – (hyphen)
                   For Parts, Material applied to part in SolidWorks is assigned to basic material field.
6) Lab / Office = Enter office (business area) being responsible for the material.
             8) Shelf life time = When the material is received at the warehouse, shelf life time will alert that the
             expiration date must be checked.
             Examples of materials that could have an expiration date; adhesive, chemicals and O-rings.
             In general it has been stipulated that shelf life controlled materials shall have 12 months of shelf life remaining
             upon receipt. 12 months will be default set in the material master when the “Shelf Life Time” = “Yes”.
             “Shelf Life Time” = “Yes” will also add the text “Delivery must be marked with expiry date” in the Basic data
             text field, as for instruction to the manufacturer.
             9) Classification = Product classification is used to structure the materials in Aker Solutions. The result is a
             searchable catalogue where Aker Solutions materials can be found and further assessed. The product
             classification is also important to avoid duplicate materials.
             Make sure to complete all levels and all attributes. If the classification is wrong, the material will be returned by
             the Material Analyst. The material analyst can be contacted for how to assign classification.
             When requesting material from the CAD desktop the classification is automatically inherited from the
             Document Info Record.
Example:
          10) (DMS Documents) Reference DIR = If material is being created from a document in CAD desktop
         this field will be automatically populated by the system. The reference DIR is the document in SAP
         representing the material, i.e. there will automatically be a link between this material and the DIR referenced.
         11) (Plant Data) Applicable Plant = Assign all applicable plants where the material will be handled,
         including for the aftermarket.
         e.g., 1800 = Subsea in OSLO
         13) Off Shelf Product? = Radio button to identify whether the material is a standard material that can be
         bought directly off shelf from description. Such materials will require less documentation.
         If there is only one supplier of this material, information should be given in Manufacturer field. Otherwise
         information should be given in Internal comment.
         14) Make / Buy = Radio button to define whether the material normally is manufactured by Aker Solutions
         (Make) or bought (Buy) by purchasing. This decision controls how the resource planning system will set up
         the order and send the request to the correct department.
          15) Basic Data & Internal Comment = “Basic data text” will appear on the Purchase Order and
         Material Master/BoM Report. Therefore it is important to write only material specific information (e.g.
         additional design information) in this field.
         Do not include preferred vendor or other supplier specific information in “Basic data text”. Such
         information can be entered in; Manufacturer.
         Alternatively, Internal comment is for information about the material for internal use. This text will only
         appear in the Material Master.
         Information about supplier and supplier’s product can be written in the “Internal comment” field (not
         “Basic data text” as this will turn up is all PO for the material).
         The field is also used for identifying the Master Inspection Characteristics (MIC) for the material. MICs
         are the inspection requirements for the material.
         16) (Workflow) Material Analyst = The material master attributes will be completed by the Material
         Analyst assigned.
         Several Material Analysts can be assigned. If assigning more than one Material Analyst the Material
         Analyst first opening the material workflow will process the work item.
         Highlight users to be assigned for the workflow before clicking OK. Only highlighted users will receive
         the workflow, even if there are more names in the list.
               17) Engineer = The originator/requestor name will be automatically copied here. Material Analyst
              can change this when the workflow reached to the Material Analyst work item.
              18) Approver = Select the approver for your product. This field also can be change by the material
              analyst . The name in this field will be automatically copied to the tech. reference field in material
              master after the material has been approved. (only if the tech. reference field is empty).
              19) Material Group = Material group should be selected according to the classification. Product
              responsible can be contacted in case of any issues.
              20) Material Subtype = Material subtype should be selected accordingly. In case of tender material
              select the material subtype TEND. The following matrix will help in selecting the material subtype.
                                     21) Comments = This is used for any other information following the workflow. The
                                     comments will be kept throughout the workflow process so that all involved user can
                                     see the history of the material creation.
                                     The comment field should not be used for information that is relevant for the entire
                                     material service life time. Such information should be entered in the “Basic data text” or
                                     the “Internal Comment” of the material master.
                                     The workflow comment is also available in the workflow log of the material.
Status of Material:
The input screen can be opened by clicking link in lower right screen of the work task.
                                     Material analyst will verify the changes & if changes are ok, he will send material back
                                     to you for completion.
                                     Once processing for all the linked documents is complete, material can be sent to
                                     approver.
                                     The material workflow will continue to the material planner according to lab / office and
                                     division set for material.
                                     The material workflow will continue to the material planner according to lab / office and
                                     division set for material.
                                     Finally when material master is ready for procurement, it will gain status Z9.
                                     If approver needs some changes in the material master, he will return the workflow with
                                     comments in the same way as material analyst.
                                     Requestor can do the changes and send the material workflow back to approver
                                     directly.
                                     If there are configurations in the assembly, a dialogue will pop up asking which of the
                                     configurations BOM should be based on. Select appropriate configuration, then
                                     accept.
                                     Click ‘continue action’ in create/change material BOM window.
                                     Note, use the default values:
                                     •Alternative BOM = 1 (Do not use alternative BOMs)
                                     •Plant = blank (Only global BOM is engineering responsibility)
                                     •Usage = 3 (Use only universal BOM)
Display BOM:
                                       00           01         02          Initiated / Issued
                                     Created      Started   In Work        Workflow specific
                                                                                 status
                                                                       99
                                                                  Change Owner                    44
                                                                                                Checked
                                                                       04
                                                                   Correction
                                                                        Workflow                   45
                                                                      specific status           Approved
        If any one of the above point is missing and the material is released (in Z9 status) then any changes to the material :
        Basic Material, TC, SDRL, Drg, Doc etc then the material has to go for ‘Engineering Change’
 2.           Enter the material number : assembly or sub-assembly (i.e. the material for which a BoM is to be created).
 3.           Leave “Plant” blank to create a Group BoM valid for all Aker Solutions
Important: Materials created by Engineering shall always be created as a Global BoM. Plant shall be left blank.
  Important:
                              3 – Universal” to be used unless otherwise instructed.
       9.        Fill in “L” (Stock) item in the ICt (Item Category) column for each material item (“L” to be used unless otherwise instructed)
                 Note: “L” means that the system will check stock for available material when running the MRP (Material Requirement Planning)
                 process.
       10.       The Item line numbers should be changed to match the item numbers in the position balloons of the drawing (SAP uses Item line
                 numbers in steps of 10 rather than 1)
                 Note: If BoM is created from the CAD application and the CAD interface the integration should take care of this automatically (ref. training course CAD51
                 and CAD 52)
Disclaimer
This Presentation includes and is based, inter alia, on forward-looking information and statements that are subject to risks and uncertainties
that could cause actual results to differ. These statements and this Presentation are based on current expectations, estimates and projections
about global economic conditions, the economic conditions of the regions and industries that are major markets for Aker Solutions ASA and
Aker Solutions ASA’s (including subsidiaries and affiliates) lines of business. These expectations, estimates and projections are generally
identifiable by statements containing words such as “expects”, “believes”, “estimates” or similar expressions. Important factors that could
cause actual results to differ materially from those expectations include, among others, economic and market conditions in the geographic
areas and industries that are or will be major markets for Aker Solutions’ businesses, oil prices, market acceptance of new products and
services, changes in governmental regulations, interest rates, fluctuations in currency exchange rates and such other factors as may be
discussed from time to time in the Presentation. Although Aker Solutions ASA believes that its expectations and the Presentation are based
upon reasonable assumptions, it can give no assurance that those expectations will be achieved or that the actual results will be as set out in
the Presentation. Aker Solutions ASA is making no representation or warranty, expressed or implied, as to the accuracy, reliability or
completeness of the Presentation, and neither Aker Solutions ASA nor any of its directors, officers or employees will have any liability to you
or any other persons resulting from your use.
Aker Solutions consists of many legally independent entities, constituting their own separate identities. Aker Solutions is used as the common
brand or trade mark for most of these entities. In this presentation we may sometimes use “Aker Solutions”, “we” or “us” when we refer to Aker
Solutions companies in general or where no useful purpose is served by identifying any particular Aker Solutions company.