Rate Analysis
Rate Analysis
0 Rate Analysis
Rate Analysis:
Method of determining the rate per unit of particular item of work considering the cost and
quantities of material, cost of labors (skilled and unskilled), hire of tools and plants,
contractor profit etc. is known as rate analysis.
        Rate of material usually takes as the rate delivered at the site of work and includes
the first cost (cost of origin), cost of transport, taxes, etc. If the material are to be carried
from a distant place, more than 8 km, the cost of transportation is also added. The rate of
materials and labors vary from place to place and therefore the rate of different item of
work also varies from place to place.
   1. The process of doing analysis gives clear picture of the various types of labors and
      materials required for completing the particular work.
   2. It can be used frequently to settle the disputes between contractor and client about
      the item not included in original estimate.
   3. It can be used for the compensation by insurance.
MATERIAL ESTIMATE:
Note:
   1. In concrete mix:
             To get dry mix (Cement+Sand+Aggregates) increase 50% to 55% of wet
               mix.
   2. In mortar mix:
             To get dry mix (Cement sand) increase 30% to 35% of wet mix.
   3. In plastering works:
             Firstly, increase 25% for filling in between joints and irregular surface. In
               case of ceiling and concrete surface (plain surface) only 10% - 15%
               increase of wet mix to get total wet mix.
             Then, to get dry mix (Cement sand) increase 30% to 35% of wet mix.
   4. In case stone works:
           To get required stone 15% - 20% increase of total works due to wastage and
             dressing.
           Volume of dry mortar mix = 30% to 40% of stone masonry.
   5. In RCC work
           To get reinforcement : 1% of volume of RCC
           Binding wire: 1Kg per quintal.
Calculate the quantities of materials requires for the following item of work.
        1.   Soln :
             Here, Volume of brick work = 48.5 m3
             Assume
             Brick Size =230mm x 110mm x 55 mm.
             Mortar thickness = 10mm
= 25908.11
= 25909 𝑁𝑜𝑠.
Add 5% wastage
Volume of wet mortar = Total brick work – Actual Vol. of brick (without mortar)
= 12.45 m3
= 4.05 x 28.8
= 116.57 bags
W/C = 0.8
Hence, Required
Bricks = 27205 no, Cement = 116.57 bag, Sand = 12.15 m3, Water = 4662.8 lit.
       2. Soln:
      Total quantities of work (PCC) = 42 x 0.95 x 0.15 = 5.99 m3
Required,
Water/Cement = 0.5
       3. Soln:
             PCC for RCC work = 25 x20 x 0.10 = 50 m3
Required,
= 1 % of 50 m3
= 0.01 x 50 = 0.5 m3
        4. Soln:………………………………………………………………………………………………………………………………………………………………….
        5. Soln:
        Here, Quantity of plastering work = 713 m²
        𝑇ℎ𝑒𝑟𝑒𝑓𝑜𝑟𝑒, Vol. of wet mortar = 713 x 0.0125 = 8.91 m3
            Firstly, increase 25% for filling in between joints and irregular surface to get
            total wet mix.            =1.25 x 8.91= 11.14 m3
Hence, Required,
W/C = 0.8
6. Soln: No mortar
= 7051.28
= 7052 𝑁𝑜𝑠.
Add 5% wastage
Volume of wet mortar = Total brick work – Actual Vol. of brick (without mortar)
= 2.287 m3
W/C = 0.8
7. Soln
Required,
= 0.4 x 10 = 4 m3
W/C = 0.6,
                                                               Wood(patch work)             12 kg
      ii) Over Base course                       10     Unskilled 0.20     Bitumen         9.7 kg
                                                 m²
                                                                            Kerosene         L.S     Boiler
                                                                                                              0.04
                                                                           Wood(Boiler)     4 kg      and
                                                                                                               hr
                                                              Wood(open mass)               16 kg   sprayer
                                                               Wood(patch work)             24 kg
10    Providing and laying single coat surface   10     Unskilled 0.80
      dressing including compaction              m²                        Bitumen          34kg
                                                                            Kerosene         L.S              0.04
                                                                                                    Roller
                                                                           Wood(Boiler)     8kg                hr
                                                              Wood(open mass)               32kg     Boiler
                                                                                                              0.04
                                                              Wood(patch work)              48kg      and
                                                                                                               hr
                                                               12mm Aggregate             0.15 m³   sprayer
 17                              Paint
      Whitewash                                                kg       22
      Distemper                                                lit      205
      Waterproof paint                                         lit      430
      Enamelpaint                                              lit      470
      Emulsion paint                                           lit      475
      Aluminium                                                lit      502
      Varnish                                                  lit      400
      Chapra polish                                            kg       850
      Sprit                                                    lit      115
      primer cement                                            kg       250
      wood primer                                              lit      350
      gum                                                      kg       246
 18   Hinge
      3"                                                      no        18
      4"                                                      no        35
      5"                                                      no        47
      6"                                                      no        62
 19   locking set
      300mm                                                   no        261
      225mm                                                   no        232
      150mm                                                   no        200
 20   Tower bolt
      3" ,4" ,6" ,8" ,10" ,12"                                no         25, 48, 71, 85, 101, 115
 21   Handle
      ordinary                                                no        45
      special                                                 no        75
 22   Hold fast (7 no /kg)                                     kg      132
      nail                                                     kg      125
 23   80/100 grade bitumen                                     kg      108
      CRMB-DIGO 55 Bitumen                                     kg      112
      wood                                                     kg       25
       white glazed porcelain clay 10 lit cistern
 24   complete set (internal part of cistern pvc fittings )   set    4150.00
                                                                     Rate(
S.N          Materials/ manpower/machine                      Unit             Remarks
                                                                     Nrs)
       white glazed porcelain clay 10 lit cistern
24    complete set (internal part of cistern pvc fittings )   set    4150.00
   1. Cost of material                                                        X
   2. Cost of labors                                                          Y
   3. Hire of tools and plants
       (@ 3% of Unskilled labor cost)                                         Z
                                        ......................................................................
Note: Extra cost such as scaffolding for super structure…..may provide as a L.S amount.
       1. Brick work in 1:3 cement mortar for first floor. Unit of analysis per m3
       2. 12.5 mm thick cement plaster (1:4) in wall. Unit of rate analysis 100 sqm.
       3. PCC (1:2:4). Unit of rate analysis 1 cum.
       4. 10 m3 of stone masonry in 1:6 mortar ratios.
       5. Saalwood for doors and windows frame per cum.
       6. Providing, laying & consolidation of 10 cm thick compacted gravel for sub grade
           per sqm.
       7. Providing, laying & consolidation of 15 cm thick compacted gravel for sub grade
           per sqm.
       8. Providing and laying 10 cm thick compacted semi grouting per 10 sq.m
       9. Providing and laying 15mm ɸ GI pipe per rm.
       10. Providing and fixing W.C commode with low level cistern per no.
       11. Providing and fixing W.C Pan with low level cistern per no.
       12. Providing and fixing Wash basin per no.
       13. Providing and fixing kitchen sink per no.
    1. Solution
       Here, unit of analysis per cum.
          Here, Volume of brick work = 1.0 m3
          Assume
          Brick Size =230mm x 110mm x 55 mm.
          Mortar thickness = 10mm
          » Brick size with mortar = 240mm x 120mm x 65mm
                                                   Vol. of Brick work
          Therefore, No. of Brick required =
                                             Vol.of one Brick with mortar
                                                      1.0
                                           =
                                             0.24 x 0.120 x 0.065
= 534.18
= 535 𝑁𝑜𝑠.
Add 5% wastage
Volume of wet mortar = Total brick work – Actual Vol. of brick (without mortar)
= 0.26 m3
= 0.0845 x 28.8
= 2.434 bags
W/C = 0.6
Hence, Required
Bricks = 562 no, Cement = 2.434 bag, Sand = 0.2535m3, Water = 73.02 lit.
      2. Solution
        Here unit of analysis per 100sqm.
                 Firstly, increase 25% for filling in between joints and irregular surface to get
                 total wet mix.                  =1.25 x 1.25= 1.5625 m3
Hence, Required,
W/C = 0.8
Hence, Required
Required,
Water/Cement = 0.55
Hence, Required
Cement = 6.16 bag, Sand = 0.428 m3, Agg. = 0.856 m3 Water = 169.94 lit.
      4. Solution
         Here unit of rate analysis per 10 m3
       Now to get of volume of stone – increase it by 15% to 20% due to wastage and
dressing during placing.
Again, Take volume of dry mortar 30% - 40% volume of stone masonry due to irregular
shape and size of stone available.
= 0.4 x 10 = 4 m3
W/C = 0.6,
6. Solution
                                       10
       Volume of gravel – subgrade =       x 1 = 0.1 m3
                                       100
       Add 30% - 40%, loose volume of gravel = 1.35 x 0.1 = 0.135 m3
          (A) Materials
                 i.      Well graded gravel = 0.135 m3 @Rs 1700 = Rs 229.50
          (B) Labors
                 i.      Unskilled          = 0.14 Nos. @Rs 475 = Rs 66.50
          (C) Equipment
                 i.      Road roller       = 0.028 hr. @Rs1000 = Rs 28.00
          (D) Hire of tools and plants = 3% of unskilled labor cost = Rs 2.00
Total = Rs 326.00
   8. Solution
          Volume = 0.1 x 10 = 1 m3
          Loose volume = 1.4 x 1 =1.40 m3
          Materials
             i.     Well graded Aggregates = 1.40 m3 @Rs 2100 = Rs 2940.00
             ii.    Bitumen                = 60 kg @ Rs 99.00 = Rs 5940.00
             iii.   Wood (only boiler)    = 20 kg @ Rs 17.00 = Rs 340.00
Labors
Equipment
Total = Rs 10310.00
   9. Solution
          Materials
            i.      15 mm dia. GI pipe = 1 m @Rs 250                   = Rs 250.00
            ii.     GI fittings (elbow, bend, tee etc.) = L.S (20-30%) = Rs 75.00
            iii.    Pipe tape, clamp, screws etc.      = L.S (5-7%)    = Rs 17.50
Labors
Total = Rs 537.78
10. Solution
   (A) MATERIALS
(i) White glazed ceramic clay W.C commode with P or S-trap= 1no. @Rs7854.00 = Rs 7854.00
(ii)White glazed ceramic clay 10 lit. capacity low level cistern with complete accessories
                                                           = 1 no. @Rs 3230        = Rs 3230.00
(iii) Commode cover with C.P hinge                         = 1 no. @Rs 2200        = Rs 2200.00
(iv) C.P angle valve (Blue star or equivalent)             = 1 no. @Rs 1098        = Rs 1098.00
(v) PVC pipe connector with coupling                       = 1 no. @Rs 290         = Rs 290.00
(vi) 32mm dia. PVC flushing pipe with coupling             = 1 no. @Rs 315         = Rs 315.00
(vii) Pipe tape, clamp, screws etc.                        L.S                     = Rs 600.00
                                                             Material cost         Rs 15587.00
  (B) LABORS.
     (i) Skilled:        3 no. @RS 650 = Rs 1950
     (ii) Unskilled:      3 no. @Rs 475 = Rs 1425
                                Labor cost Rs 3375
  (C) Hire of tools and plants @ 3% of unskilled labor cost = Rs 42.75
                                           Subtotal Rs 19004.75
  (D)Contractor overhead and profit @ 15% of subtotal = Rs 2850.71
                                                 Total Rs 21855.46 /no
      11. Solution
(A) MATERIALS
White glazed ceramic clay W.C Orisa pan with P or S-trap= 1no. @Rs3090.00 = Rs 3090.00
White glazed ceramic clay 10 lit. Capacity low level cistern with complete accessories
                                                       = 1 no. @Rs 3230       = Rs 3230.00
  C.P angle valve (Blue star or equivalent)           = 1 no. @Rs 1098        = Rs 1098.00
  PVC pipe connector with coupling                     = 1 no. @Rs 290         = Rs 290.00
  32mm dia. PVC flushing pipe with coupling            = 1 no. @Rs 315        = Rs 315.00
  Pipe tape, clamp, screws etc.                       L.S                     = Rs 600.00
                                                         Material cost         Rs 11998.00
(B) LABORS.
        Skilled:           3 no. @RS 650 = Rs 1950
        Unskilled:         3 no. @Rs 475 = Rs 1425
                              Labor cost Rs 3375
(C) Hire of tools and plants @ 3% of unskilled labor cost = Rs 42.75
                                         Subtotal Rs 15415.75
(D)Contractor overhead and profit @ 15% of subtotal = Rs 2312.36
                                               Total Rs 17758.11 /no
12. Solution
(A)MATERIALS
White glazed ceramic clay 500 x 400 size basin = 1no. @Rs.................. = Rs …………….
C.P angle valve (Blue star or equivalent) = 1 no. @Rs ………… = Rs ……………
32mm dia. Waste pipe with coupling = 1 no. @Rs ………… = Rs …………….
(B) LABORS.
Subtotal Rs ……………………