3 2.5m Thick Cement Concrete 1:1/1.5:3 Damp Proof Course (DPC)

1. The document provides a cost estimate for various construction items including earthwork, concrete work, masonry work, and flooring work. 2. The estimated costs for 122.8 cum of earthwork is Rs. 206,976, and for concrete work like PCC and DPC is Rs. 82901.76 and Rs. 7300.091 respectively. 3. Masonry work for 76.39 cum is estimated at Rs. 100,246.59, and flooring work like mosaic and terrazo for 187 sqm is estimated at Rs. 258,527.5. RCC work for 28.75 cum is estimated at Rs. 47,878.52.

Uploaded by

NATIONAL XEROX
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
623 views7 pages

3 2.5m Thick Cement Concrete 1:1/1.5:3 Damp Proof Course (DPC)

1. The document provides a cost estimate for various construction items including earthwork, concrete work, masonry work, and flooring work. 2. The estimated costs for 122.8 cum of earthwork is Rs. 206,976, and for concrete work like PCC and DPC is Rs. 82901.76 and Rs. 7300.091 respectively. 3. Masonry work for 76.39 cum is estimated at Rs. 100,246.59, and flooring work like mosaic and terrazo for 187 sqm is estimated at Rs. 258,527.5. RCC work for 28.75 cum is estimated at Rs. 47,878.52.

Uploaded by

NATIONAL XEROX
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

3 2.5m thick cement concrete 1:1/1.

5:3 Damp proof course (DPC)


PARTICULAR QUANTITY RATE COST
Stone ballast 12mm
gauge 2.25cum 3011.21 6775.00
Sand (coarse) 1.13cum 2748/cum 3145.00
Cement 22bags 0.75cum 9632/cum 7224.00
Cem- (1bag) 22.50kg 60 per kg 1350.00
Total 18494.00
Mistri 1/3 nos. 600 200
Mason 8nos. 400 3200
Mazdoor 8nos. 350 2800
Bhishti 1nos. 200 200
From inside Lump-sum 200 200
Senturate% T &P Lumsp-sum 100 100
Total 6400.00
Total M&L 24894.00
Add 1.5% of water
charge 373.41
Add 10% contractor
profit 2489.4
Grand total 27756.81
Rate per m 27756.81/100
=277.57 Rs
4 RCC work in beams, slabs etc.
PARTICULAR QUANTITY RATES COST
MATERIALS:
Stone ballast 20mm 8.80cum 3312.32/cum 29148.41
gauge
Sand(coarse) 4.40cum 2704/cum 12249.6
Cement(66bags) 2.20cum 9632/cum 21190.4
Steel, mild steel, bars
@ 1%=5cum@
78.59g/cum=7.859 7.85g 7000/g 54950
Binding wires 1.50kg 200/kg 300
Total 1,17838
LABOUR:
Mistri(Head) 1/2 nos. 600 300
Mason 3 nos. 500 1500
Mazdoor(Beldaar) 12 nos. 350 4200
Bpy or women coolie 20 nos. 300 6000
Bhisti 6 nos. 250 1500
Total 13,640

Bending, crackiing
+bending steel bars
in position
Black smith(II class) 8nos. 450 3600
Mazdoor (beldar) 8nos. 350 2800
T&P Lump-sum 140 140
Total 6540
Centering &
shuttering (both
erection and
dismantling)
Timber plank & Lump-sum 15006.6 1500
ballies
Carpenter(IIclas) 10 nos. 600 6000
Mazdoor (beldar) 10 nos. 350 3500
Nails Lump-sum 200l.s. 200
T&P Lump-sum 140 l.s. 740
Total 11,340
GRAND TOTAL 149358
1/1.5%add water
charges 2240.37
10% for contractor
profit 14935.8
GRAND TOTAL 166534.17

rates per cum =166534.17/10 = Rs.16653.417


5 Ist class brick work in superstructure
PARTICULAR QUANTITY RATES COST
MATERIAL:
Brick Ist class
(500brick/cum) 5000nos. 7/bricks 35000
Cement(13.5bags) 0.28 cum 9632 per cum 2696.96
Sand(local) 2.7 cum 1505 per cum 4063
Total 41759.96
LABOUR:
Mistri(head mason) 1/2 nos, 600 300
Mason 10 nos. 500 5000
Mazdoor 7 nos. 350 2450
Boy or women coolie 10 nos. 300 3000
Bhishti 2 nos. 250 500
Scaffolding Lump-sum 380 380
Sundries T&P Lump-sum 140L.s. 140
Total 11770
1/1.5% add water
charge 176.55
10% add contractor
profit 1177
GRAND TOTAL 13123.55

Rates /cum =13123.55/10=Rs. 1312.355


6 Mosaic in terrazo tile floor take 100sq.m
PARTICULAR QUANTITY RATES COST
MATERIAL:
Mosaic tiles
20cm*20cm
Nominal size 100 sq.m 540/sq.m 54000
2500nos.
20mm lime mortar 1cum 1200/cum 1200
white lime(slaked)
Surkhi 2cum 750/cum 1500
Cement for neat
cement paste o grout 0.2cum 9632/cum 1926.4
for laying tiles and
for joints
6buy
TOTAL 58626.4
LABOUR:
Mistri(head mason) 1 nos 600 600
Mason(speacilist) 15nos. 500 9000
Mazdoor(beldar) 15nos. 350 5250
Bhisti 1/1.5 250 375
Polishers 120 nos. 400 48000
Polishing stone L.s. 1500 l.s. 1500
Oxalic acid powder L.s. 500 l.s. 500
Sundries T&P L.s. 140 l.s. 140
Total 65,365
Grand total 123991.4
1/1.5% water
charges 1859.87
10% contractor profit 12399.14
Grand total 138250.41
7 7.5 cm thick lime concrete in floor PPC 100sqm
PARTICULAR QUANTITY RATES COST
MATERIAL:
Brick ballast Iclass
40mm gauge 7.50 cum 975/cum 7312.5
White lime slaked 1.20cum 1200/cum 1440
Surkhi (or sand) 2.40cum 1050/cum 2520
Total 11275.5
LABOURS:
Mistri(head mason) 1.5nos 600 300
Mason 1nos. 500 500
Mazdoor(beldar) 10nos. 350 3500
Boy or women coolie 10nos. 300 3000
Bhisti 1nos. 250 250
Sundries T&P Lump-sum Lump-140 140
Total 7690
Grand total 18965.5
1/1.5% water charge 284.48
10% add for
contractor profit 1896.55
Grand Total 21146.53

for 1 cum= 21146.53/100 = Rs.211.46


8 12 mm plastering 1:6unit 1sqm take 100sqm
PARTICULAR QUANTITY RATES COST
MATERIAL:
Cement (9bag) 0.30cum 9632/cum 2889.6
Sand(local) 1.80cum 2784/cum 5122.56
Total 8012.16
LABOUR:
Mistri(head mistri) 1/3nos. 600 200
Mason 10nos. 500 5000
Mazdoor 15nos. 350 5250
Including ranking
joints
Bhisti including 3/4 nos. 250 187.5
(curing)
Scaffolding sundries Lump-sum 400 400
T&P Total 10637.5

Grand Total 18649.66


1/1.5% add water
charges 279.74
10% contractor profit 1864.96
Grand Total 20794.36

for 1sqm rates=20794.36/100=Rs. 207.94


COSTING
S.No. ITEM QUANTITY RATE COST
01 Earthwork:
Earthwork In
Excavation In
Foundation
(1.5m Lift
30m Lead)
23cm Wall
11.5cm Wall 122.8 1617 206,976
02 Concrete
Work: PCC in
foundation
(1:6:12) 36.98 2241.8 82901.76
DPC at plinth
(1:2:4) with 2 26.3 277.57 7300.091
Coat bitumen
03 Masonary
work:
Masonry work
in 1312.3 100,246.59
76.39
superstructure
04 Flooring
Work: mosac
and terrazo
187.0 1382.5 258527.5

05 RCC work in
beams, slabs
etc. 1665.34
28.75 47878.52