Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
How to turn geological uncertainty into manageable risk?
T. Dickmann and D. Krueger
Amberg Technologies AG, Regensdorf, Switzerland.
ABSTRACT: Risk management became an integral part of most underground construction projects
during the last decade. Still, there are parties, who may not plan for insubstantial unknown
uncertainties of ground conditions because they are so unpredictable and out of scope of normal
planning as they think. Finally, many of them end up as the most catastrophic events. Even known
geological uncertainty is a risk that certainly exists without knowing how it will affect the work.
Further, human biases form part of the way prior knowledge is being used to interpret data in a way
it’s anchored in one’s mind or in a way that is just available. If no naive assessment of the uncertain
situation is carelessly considered, risk becomes manageable if one know, detect and quantify the risk.
A reasonable and cost-effective way to tread is the application of 3D-Tunnel Seismic Prediction on a
regular base. Knowing what’s ahead (in a case study) results in manageable risk.
1 INTRODUCTION                                                      et al., 2004). Further, the insurance industry
                                                                    issued the joint code of practice for risk
The very nature of tunnel projects implies that                     management of tunnel works in 2006 that is
any potential tunnel owner will be facing                           now being used worldwide and effective in risk
considerable risks when developing such a                           sharing and encouraging best practice of risk
project. Due to the inherent uncertainties,                         management procedure in tunneling (Adeyemo,
including ground and groundwater conditions,                        2011). Eventually, this encouraging progress
there might be significant cost overrun and                         may lead to some tunnel builders’ opinion that
delay risks as well as environmental risks. Also,                   bearing the risk of loss and saving money by
as demonstrated by spectacular tunnel collapses                     being uninsured might be a charming option.
and other disasters in the recent past, there is a                     Very well then; the overall term “risk
potential for large scale accidents during                          management” is widespread and in everyone’s
tunneling work. Between 1994 and 2004, about                        lips in many fields of activity and expertise.
600 million US$ had been lost in 20 major                           Though, do we really sufficiently know about
projects where collapses had occurred. In 2006,                     manageable risk?
tunneling projects became uninsurable due to a                         In fact, manage risk stands for identify,
tremendous increase of loss ratio of 500%. It                       assess, analyze, eliminate, mitigate and control
could give the impression that insurance had                        risk, and it’s a fallacy to believe that risk
been the cheapest risk management tool. As a                        management could end before finishing the
result, risk management became an integral part                     tunnel. In particular, it’s the unknown
of most underground construction projects                           uncertainty that comes as a geological hazard
during the late 1990s. Since April 2003,                            zone. There are still owners or contractors, who
international guidelines on tunneling risk                          may not plan for these insubstantial events
management had been established showing how                         because they are so unpredictable and out of
risk management may be utilized throughout the                      scope of normal planning as they think. Finally,
project’s phases of design, tendering and                           many of them end up as the most catastrophic
contract negotiation and construction (Eskesen                      events.
                                                                1
                   Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
2 RELEVANT UNCERTAINTIES                                            processing procedures with their options of
                                                                    parameters. An interpretation should therefore
An owner’s or contractor’s ability to identify                      be not merely a section of mapped seismic
risk is limited by the certainty or uncertainty of                  events, but also a description of the variability
risk. A simplified grouping of risk could be                        tolerated within the data. Quantifying the
made like this: known certainties, known                            ambiguity in the prediction is the concept of
uncertainties, and unknown uncertainties.                           measurement uncertainty (Leahy and Skorstad,
Actually, common understanding of risk is so                        2013).
closely associated to uncertainty that almost                          This measurement uncertainty is clearly
nobody would consider known certainties to be                       different from the “conceptual uncertainty” in
risks at all. If we know something is coming, we                    geologic interpretation, which derives from a
think of it simply as a circumstance to be                          range of concepts that geoscientists could apply
addressed. Known uncertainties is a risk we                         to a single data set.
know exists, but we do not know how it will
affect us. The unknown uncertainties are
                                                                    2.2 Constraints by conceptual uncertainty
unlikely to be addressed during project
planning. However, even in the project planning                     Interpretations of seismic images are used to
they need to be addressed at least in order to                      analyze subsurface geology and form the basis
budget for measures such as geophysical or                          for many exploration and extraction decisions,
more specifically seismic measurements                              but the uncertainty that arises from human bias
necessary to identify the unknown uncertainties                     in seismic data interpretation has not previously
during the prospective construction phase. At                       been quantified.
the end of the day, there is always the one                             It follows that geoscientists use their prior
question: has the geology in the tunnel area                        knowledge to apply or generate a new concept
been adequately explored and analyzed before                        to data in order to construct an interpretation
and during tunneling?                                               and geological model. The initial geological
                                                                    model might be a fundamental source of
                                                                    uncertainty because it is dependent on the
2.1 Constraints by measurement uncertainty
                                                                    tectonic paradigm or concept used in its
In subsurface investigation, geophysicists                          construction. Bond et al. (2007) argue that
typically measure, process and interpret the data                   conceptual uncertainty can be more important
and hand over the interpretation result to the                      than the uncertainty inherent in the positioning
geologist or geomodeller. She or he then                            of boundaries or fault planes in a geological
integrates this result with other geologic data                     model (Figure 1). Human biases form part of
and compiles a geologic model. This                                 the way prior knowledge is being used to
conventional workflow fails to meet the                             interpret data. There are three relevant bias
challenges because it is not attuned to quantify                    types in the context of geo-data interpretation,
uncertainty that is associated with every piece of                  which are known from cognitive psychology.
geologic data due to resolution, sensitivity and                    The Availability bias occurs taking the model or
noise.                                                              interpretation that is most dominant in one’s
   In consequence, the workflow need to be                          mind. Anchoring bias is the failure to adjust
changed where “measurement uncertainty”                             from experts’ beliefs, dominant approaches, or
associated with seismic and geologic                                initial ideas. Interpreters expect to see a
interpretation is quantified. With uncertainty                      particular type of structure in a given setting
collected at the early design and planning stages                   such as a geographical location. Confirmation
of an underground construction project, the                         bias involves actively seeking out opinions and
interpretation becomes not a single geologic                        facts that support one’s own beliefs or
model but an ensemble of models that can be                         hypotheses.
used to risk and improve decision making
(Leahy and Skorstad, 2013).
   The seismic image is impacted by the survey
acquisition parameters of sources, receivers and
geometry, the material response such as                              Figure 1. The conventional subsurface analysis workflow
                                                                      produces a single deterministic structural model of the
inelasticity,   anisotropy and attenuation,                                                  ground.
environmental or electronic noise and signal
                                                                2
                      Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
   Conceptual uncertainty is likely to be a major                      whereas a management decision to limit the
risk factor for disciplines in which decision                          extent of a site investigation to save money will
making is based on prior knowledge and hence                           pose another type of hazard. Although
concepts of interpretation of data sets containing                     geological assessment constraints exist, hazards
limited information.                                                   induced by saving money don’t have to be taken
                                                                       into account unless a naive assessment of the
                                                                       situation is carelessly considered.
2.3 Implication to tunneling
                                                                          Non-destructive          geophysical        site
In tunneling, uncertainty could lead to fatalities                     investigations while tunneling have developed
and doesn’t need to be accepted. Once a                                and improved significantly over recent times. In
preliminary model or hypothesis has been                               particular, when site investigations from the
generated, the real geological conditions in a                         surface are limited given the topography, tunnel
tunnel project could be generally verified by                          seismic imaging can detect lithological
collecting further data from pre-investigations                        heterogeneities within distances up to hundreds
from the surface or from geological mapping in                         of meters ahead of the face, many times more
the tunnel during the construction phase. Here, a                      that of probe drilling alone. It is the most
continuous reconciliation of forecasted and                            effective prediction method because of its large
observed data can be obtained resulting in a                           prediction range, high resolution and ease of
workflow where a geologically consistent                               application on a tunnel construction site
structural model is updated. This process                              (Dickmann and Krueger, 2013).
therefore becomes a constructive process rather                           The Tunnel Seismic Prediction (TSP) method
than a simple mapping process that Leahy and                           detects changes in rock mass such as irregular
Skorstad (2013) call a concept of model-driven                         bodies, discontinuities, fault and fracture zones
interpretation (Figure 2).                                             ahead of the tunnel face (Dickmann and Sander,
                                                                       1996). Employed as a predictive method during
                                                                       excavation process for both drill & blast and
                                                                       TBM headings, no access to the face is required
                                                                       to perform measurements, which are taken in
                                                                       tunneling production breaks of around 60
                                                                       minutes. Acoustic signals are produced by a
                                                                       series of 24 shots of usually 50 to 100 grams of
                                                                       detonation cord aligned along one tunnel wall
                                                                       side and having an additional shot line along the
                                                                       opposite tunnel wall side in cases of more
                                                                       complex geology.           Four sensor probes,
                                                                       consisting of highly sensitive tri-axial receivers,
                                                                       are contained in protection tubes whose tips are
                                                                       firmly cemented into boreholes of 45-50 mm in
                                                                       both side-walls. The 3-component receivers
  Figure 2. Model-driven interpretation workflow where                 pick up the seismic signals which were being
 measurement uncertainty allows for the generation of a
 geologically plausible model (after Leahy and Skorstad,
                         2013).
3 FROM GEOLOGICAL UNCERTAINTY
  TO MANAGEABLE RISK
The geotechnical risks that can affect projects
result from a range of hazards associated with
geological conditions, but also from hazards
associated with the geo-engineering process.                                   Figure 3.Measurement layout of the 3D Tunnel
                                                                            Seismic Prediction method consisting of usually 4
For example, active faults identified during pre-                                 receivers (RCV) and 24 shot points.
feasibility studies will pose one type of hazard,
                                                                   3
                      Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
reflected from any kind of discontinuity in the                        cause 3 days downtime at its best, not
rock mass ahead. A highly sophisticated                                infrequently one month. Figure 4 illustrates the
processing & evaluation software has been                              TSP expenses in time-related site costs. For
devised for ease of operation. The capability of                       TBM operation, a minimum heading length of 3
the system to record the full wave field of                            km is assumed. Here, a reduction of only three
compressional and shear waves in conjunction                           to five days of downtime pays off TSP
with the intelligent analysis software enables a                       operations on a regular base. In conclusion also
determination of rock mechanical properties                            from an economic point, does it really make
such as Poisson ratio and Young’s Modulus                              sense to even think about limit site
within the prediction area. The final 2D- and                          investigations to save money? The answer is
3D-summary results produced by the system                              clear with regard to ITA’s guidelines for
software present as well detected events and                           tunneling risk management: any implementation
boundary planes crossing the tunnel axis                               of measures to eliminate or mitigate risks where
coordinates ahead of the face.                                         economically feasible or required according to
   The owner and contractor can make know                              the specific risk objectives or health and safety
their risk, because they can detect and quantify                       legislation is to be ensured (Eskesen et al.,
the geological hazard. Unknown uncertainties                           2004).
should belong to the past and they become                                  By way of example, the next chapter
known uncertainties and in some cases even                             illustrates how these operations contribute to
certainties. Once a geological risk zone is                            measures economically mitigate risk.
identified, the contactor in agreement with the
Engineer is able to decide, what measures are to
be taken.                                                              4 CASE STUDY
   With a regular tunnel seismic operation, you
identify your geological risk detecting hazards                        The objective of this case study is a geological
and quantifying their impact to your tunneling                         prediction of minimum 100 m ahead of the
job. By this means, the tunnel builder can                             tunnel face and in addition, the verification of
understand the risk as chance or thread and even                       the results of an existing probe drill. Since
very economical. Depending on the heading                              geology is known from an extrapolation
length and type of the project, the investment in                      approach from a parallel tunnel, TSP was
knowing the risk by a regular TSP operation is                         requested     verify the       appearance    and
just between 0.7 % and 1.8 % of the time-                              characteristics of fault and fracture zones and
related site costs such as labor costs, provision                      their crossing to the planned tunnel axis.
of installations and energy expenses. In other
words, all investments in this technology are
                                                                       4.1 Site Location
already paid after saving 3 to 7 days of
downtime. How easily may happen one                                    The geology encountered within the seismic
unforeseen incident of water ingress that would                        layout between receiver reference location and
                                                                       face location at meter 57 is dominated by
                                                                       weathered volcanic breccia. The geomechanical
                                                                       classification is class III-IV according to RMR
                                                                       rock mass rating. The rock behavior at the tun-
                                                                       nel face is seen as instable. With on-going exca-
                                                                       vation following rock behavior is assumed:
                                                                       meter 60 to meter 75 - Fault zone or heavily
                                                                       fractured, Class IV, instable face,
                                                                       meter 75 to meter 161 - Volcanic breccia, Class
                                                                       III, stable face,
      Figure 4. TSP expenses when applied on a regular
                                                                       meter 161 to meter 168 - Fracture zone, Class
base dependent on heading length and excavation method.                IV, short-term stable face,
Expenses are based on time-related site costs. Numbers in              from meter 168 onwards - Volcanic breccia,
  bars give TSP expenses in percentage of total heading                Class II-III, stable face.
                         days.
                                                                   4
                   Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
4.2 Probe drill result & geological forecast                            Figure 5 illustrates the SH-wave velocity
                                                                    distribution in a cropped display of a computed
Figure 7a summarizes the geological forecast
                                                                    data cuboid of 200 x 50 x 50 metres in
based on the 30 m probe drill result between
                                                                    tunnelling direction and in each vertical and
tunnel face at meter 57 and end of drill at meter
                                                                    horizontal direction, respectively. The tunnel
87. The on-going geological forecast represents
                                                                    alignment is centred in the cuboid. The copping
the extrapolation of the encountered geology of
                                                                    reduces the display to velocities smaller than
the parallel tunnel until meter 182. The already
                                                                    2,050 m/s. Around the tunnel, SH-wave
excavated tunnel and the first 3 m of the probe
                                                                    velocities of more than 2050 m/s exist and
drill is placed in a weathered Volcanic breccia
                                                                    represent rock mass of weathered volcanic
where the geomechanical rock conditions shows
                                                                    breccia. Just few meters in front of the tunnel
fair to poor rock mass quality (RMR
                                                                    face, a low velocity zone up-dipping and left
classification III- IV). Between meter 60 and
                                                                    striking and an extension of approx. 20m is
meter 75 a Fault zone with decreased and poor
                                                                    indicated where highly fractured rock mass
rock mass quality (RMR classification III- IV)
                                                                    occurs. Behind this zone, the velocity increases
is embedded. At meter 75 the rock mass
                                                                    and returns to values of good rock mass
improves significantly and a change to good
                                                                    conditions. About 100 meters ahead of the
quality (RMR classification III- II) was found,
                                                                    tunnel face the velocity drops down again and a
although with a fractured contact zone of 4 m
                                                                    second low velocity zone becomes visible,
length until meter 79. The remaining section of
                                                                    almost cross-cut striking the prospective tunnel
the probe drill to meter 87 revealed Volcanic
                                                                    axis from approx. meter 160 to 170. Further
Breccia. The further geological forecast, based
                                                                    ahead, intact rock mass returns to good
on information of the parallel tunnel, doesn’t
                                                                    conditions and retains till the end of the forecast
indicate any other tunneling relevant or
                                                                    range at meter 200.
significant rock mass change, except a smaller 7
                                                                        With the combined velocity information of
m long fracture zone included between meter
                                                                    both P- and S-waves, further rock mechanical
161 and meter 168.
                                                                    parameters of interest such as Young’s modulus,
   The geo-hydrological conditions can’t be
                                                                    Poisson’s ratio, shear modulus etc. can be
considered critical. However, dripping water
                                                                    calculated using empirical relationships
with low permeability of 1.25 l/s was present in
                                                                    depending on the rock group or user-defined
the weathered volcanic breccia and fault zone
                                                                    formulae for the density (Figure 7).
between meter 45 and meter 75 and extends into
                                                                        Figure 7b) shows five graphs, which describe
the fractured contact zone up to meter 79.
                                                                    the predicted curve progression of the P-wave
   The subsequent volcanic breccia doesn’t
show any presence of water and is considered to                     velocity, S-wave velocity, Vp/Vs ratio, Poisson
                                                                    ratio, Density and Dyn. Young’s Modulus along
be dry to the area of the forecasted embedded
                                                                    the tunnel axis. The graphs are also colour
fracture zone, where a low permeability might
                                                                    shaded below their respective chart line. Figure
become possible again.
                                                                    7c) represents the longitudinal model view of
                                                                    the 3D-TSP result with reflectors and boundary
4.3 3D investigation                                                shading according to Young’s modulus values.
                                                                    A colour change takes place at a reflector
The measurement was carried out with the latest
                                                                    element extension from its location and
TSP 303 technology. This novel system
integrates 3D data acquisition and processing
software containing routines for optimal seismic
imaging with respect to tunnelling requirements.
It exploits the information in the seismic wave
field by separate compression (P) and shear (S)
wave analysis and the 3D-Velocity based
Migration & Reflector Extraction technology
(3D-VMR). The 3D-VMR technology provides
an adequate and detailed 3D image of the                                  Figure 5. Full space perspective view of the cropped 3D
ground leading to a more reliable interpretation                      velocity distribution (SH-wave) revealing fault and fracture
compared to conventional 2D approaches                                                               zone.
(Dickmann and Krueger, 2013).
                                                                5
                       Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
                                                                        start and end point of interrelated reflectors
                                                                        within same rock mass characteristics derived
                                                                        from the rock properties.
                                                                        Conclusively, it is shown that the seismic
                                                                        prognosis is in very good agreement with the
                                                                        geological findings of the probe drill and the
                                                                        further geological forecast. The result points out
                                                                        the fault zone and fracture zone as rock mass
                                                                        change critical for the tunnelling. In contrast to
                                                                        the probe drill, TSP found a widened fractured
                                                                        rock mass in the contact area between the fault
                                                                        zone and stable volcanic breccia. In addition,
                                                                        the result confirms the stable rock conditions
  Figure 6. 3D-TSP geological model highlighting fault and              after the excavation will have passed the fault
   fracture zones in their environment of volcanic breccia.             zone and before entering the fracture zone.
orientation in space and its intersection point
with the tunnel axis.                                                   5 CONCLUSION
    The measured reference velocity of the direct
P-wave in the area of the measurement layout                            It is well proved that a sound knowledge on
was 3,540 m/s (S-wave 2,050 m/s, Vp/Vs 1.73),                           measurement uncertainties and the consistent
corresponding to the fair to poor rock mass of                          way of a model-driven interpretation won’t pose
the weathered volcanic rock.                                            hazards caused by a wrong understanding of
    Beyond the tunnel face location at meter 60,                        cost savings. Generating and updating
the values of the mentioned parameters begin to                         geological plausible models with means of
decline. P-wave velocity (2,840 m/s) declines                           continuous cost effective 3D-Tunnel Seismic
more than S-wave velocity (1,800 m/s) and both                          Prediction applications during tunneling is the
considerably show the fault zone extension until                        right way to turn geological uncertainty into
meter 75. Its relative low Vp/Vs ratio (1.60-                           manageable risk.
1.58) represents a zone of mostly
unconsolidated breccia in a higher stress regime
where water presence does not influence the                             REFERENCES
shear wave, significantly.
    A contact zone between meter 75 and 90                              Adeymo, A. 2011. Risk Management of Tunnelling
                                                                           projects. IRM Construction SIG Meeting, 26th July
indicates a strong fractured not weathered                                 2011.
volcanic breccia. Within this transition zone, the                      Bond, C.E. ; Gibb, A.D.; Shipton, Z.K. and Jones, S.
situation (Dyn. Young’s Modulus) slowly                                    2007. What do you think this is? "Conceptual
changes to better and good condition until meter                           uncertainty” in geoscience interpretation. GSA Today,
90, according to the decreasing fracturing that                            v.17, no.11, p.4-11.
was being found. This better rock mass                                  Dickmann, T. and Krueger, D. 2013. Is geological
                                                                           uncertainty ahead of the face controllable? World
condition persist for about 70 m.                                          Tunnel Congress 2013 Geneva, Underground – the
    About 100m ahead of the tunnel face, at                                way to the future! G. Anagnostou & H. Ehrbar (eds),
meter 161, the P-wave velocity drops again                                 CRC Press
slightly (from 3,760 m/s to 3,630 m/s), while the                       Dickmann, T. and Sander, B.K. 1996. Drivage concurrent
S-wave velocity drops stronger (from 2,150 m/s                             Tunnel Seismic Prediction (TSP). Felsbau. v. 14, no.
to 1,940 m/s) indicating a fracture zone                                   6, p.406-411
forecasted for this area. This zone extends over                        Eskesen, S.D.; Tengborg, P.; Kampmann, J. and Holst
                                                                           Veicherts, T. 2004. Guidelines for tunnelling risk
about 5m where the higher increasing Vp/Vs                                 management: International Tunnelling Association,
ratio (from 1.75 to 1.87) also indicates possible                          Working Group No. 2. Tunnelling and Underground
water bearing.                                                             Space Technology, 19, p.217–237
    As a last step of interpretation, the seismic                       Leahy, G.M. and Skorstad, A. 2013. Uncertainty in
geological model is presented in Figure 7d) as                             subsurface interpretation: a new workflow. First
the plan view of the rock mass changes along                               Break, v.31, no.9, p.87-93.
the tunnel axis. The geological borders are the
                                                                    6
                  Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
Figure 7. a) Geological forecast with 30 m long probe drilling from tunnel face b) Rock property charts derived from
 TSP measurements c) TSP result with reflectors and boundary shading according to Young’s modulus values in
                           longitudinal view d) Seismic geological model in plan view.