Geo Technical
Geo Technical
Danute SLIZYTE1
Natalija LEPKOVA2
Rimantas MACKEVICIUS3
ABSTRACT
Analysis of the scientific literature has demonstrated that the risk of collapse or deformations
of flexible retaining walls has not been the object of in-depth examination so far. The article
presents an analysis of the main geotechnical risks, focusing on the installation of flexible
retaining walls according to analysis by construction participants and their experiences. A
case study was conducted to identify the risks of flexible retaining walls. In order to
determine the risks of installation of flexible retaining walls, the authors of the article
employed a face-to-face interview approach. Investigation of the data obtained during the
face-to-face interview was based on brainstorming and the cause and effect diagram: five
professionals who had monitored most of the risks were selected with the help of the face-
to-face interview. The results of the investigation showed, that for specific and complicated
projects the team of professionals should be composed of specialists from different fields of
construction. Additionally, the respondents agreed with the opinion that the greatest loss in
the given situation would be caused by a breakdown in the pressure pipe and pollution of the
natural environment by wastewater. The novelty of the article on investigating the
possibilities for identifying the risk of installation of flexible retaining walls and on
suggesting risk identification steps.
Keywords: Flexible retaining wall, technical risk, cause and effect diagram.
Note:
- This paper has been received on September 12, 2018 and accepted for publication by the Editorial
Board on April 24, 2019.
- Discussions on this paper will be accepted by September 30, 2020.
https://dx.doi.org/10.18400/tekderg.459316
1 Department of Reinforced Concrete Structures and Geotechnics, Vilnius Gediminas Technical University,
Vilnius, Lithuania -danute.slizyte@vgtu.lt- https://orcid.org/0000-0002-1220-7485
2 Department of Construction Management and Real Estate, Vilnius Gediminas Technical University,
Vilnius, Lithuania - natalija.lepkova@vgtu.lt - https://orcid.org/0000-0002-9760-1747
3 Department of Reinforced Concrete Structures and Geotechnics, Vilnius Gediminas Technical University,
Vilnius, Lithuania - rimantas.mackevicius@vgtu.lt -https://orcid.org/0000-0002-5643-1147
Geotechnical Risk Identification: Case Study of Flexible Retaining Walls Installation
1. INTRODUCTION
The article analyzes risk identification when installing flexible retaining walls. The article
considers this problem, taking into account that not all risks are always assessed within the
process of installing flexible retaining walls, which may result in collapse or deformations.
To determine and analyze risk, the concept has to be defined. Risk considers the probability
of an event occurring and the consequences of the event, should it occur [1]. Emerging risk
can be defined as the likelihood of loss, that is, the probability that a certain consequence will
occur in a specific time and space under specified or insufficiently specified conditions [2].
This article adopts the definition of risk as the ‘effect of uncertainties on objectives’ given
by ISO 31000:2009 [3]. The definition provides that uncertainties include events (that may
or may not happen) and are caused by ambiguity or lack of information. It also includes both
negative and positive impacts on objectives [3]. The article reports only negative effects.
Geotechnical risk has been analyzed in a number of scientific articles. Duncan [4]
investigated safety and reliability in geotechnical engineering. Special attention was paid to
uncertainty about the factors involved in safety against sliding. As an example, the stability
of a cantilever retaining wall with silty sand backfill was analysed. Gibson [5] explored and
compared four probabilistic methods for slope analysis and design. Brown [6] reviewed risk
assessment and management practice in underground rock engineering. Swannell et al. [7]
analysed the geotechnical risk management approach to boring machines tunnelling under
squeezing ground conditions. Lacasse [1] showed how the concepts of hazard, risk, and
reliability could help with making more secure decisions. The article shows examples of
calculation taken from a wide range of geotechnical problems, including the hazard and risk
of collapse related to railway traffic, mine slopes, and soil exploration. Mishra et al. [8]
analysed tools for geotechnical real-time risk assessment and management and proposed a
geotechnical risk management workflow diagram of intelligent deep mines. Xia et al. [9]
focused on the issue of model uncertainty and differences in risk consciousness with different
decision-makers in tunnel and underground engineering and proposed a risk decision model
based on sensitivity analysis and tolerance cost, which can improve decision-making
efficiency. Haddad et al. [10] performed a study based on the failure and stability of gravity
retaining walls, which can be categorized into three different modes of failure in sliding,
overturning, and foundation-bearing capacity. They introduced a relatively simple method of
probabilistic analysis of the dimensions of gravity retaining walls which might lead to a more
accurate understanding of failure. Risk management in the architecture, engineering, and
construction industries remains a global issue. Lack of adequate risk management may cause
difficulties in implementing the objectives of a project and negatively affect spatial planning
and urban spatial design in the future. Yang et al. [11] analysed risk management in the field
of health and safety using Building Information Modelling (BIM) and other BIM-related
technologies. Li et al. [12] analysed site selection for underground petroleum storage. To
reduce construction risk and cost during the construction of underground petroleum storage,
they proposed a new site selection model for large underground petroleum storage based on
the analytic hierarchy process (AHP) method and ideal point theory. Xue at al. [13] analysed
rockburst hazard, which is an important issue affecting safe production at coal mines in
China. They paid attention to the influence of the backfilling roadway driving sequence on
coal pillar stability. Ahmasi et al. [14] presented a comprehensive framework to manage the
main risk events of highway construction projects within three stages: (1) identification of
10086
Danute SLIZYTE, Natalija LEPKOVA, Rimantas MACKEVICIUS
potential risks; (2) assessment and prioritization of identified risks based on fuzzy FMEA;
(3) identification of appropriate response. Authors suggested the new expert system for
identifying an appropriate risk response strategy for a risk event based on risk factor, control
number and risk allocation. The proposed methodology is demonstrated for management of
risk events in a construction project of Bijar-Zanjan highway in Iran. Valipour et al. [15]
applied hybrid SWARA (Step-wise Weight Assessment Ratio Analysis) -COPRAS
(COmplexPRoportionalASsessment) method for risk assessment in deep foundation
excavation project through introducing new criteria for risk assessment. A case study of deep
foundation excavation in Shiraz (Iran) was presented. The results have shown that the risks
involving construction safety, unfavourable geological conditions, shortage of managerial
experience, incomplete emergency plan and subsidence of ground are the most significant
risks excavation projects in Shiraz.
To sum up, the risk of collapse or deformations of flexible retaining walls has not been widely
examined.
This paper aims to identify the most common risks of installing flexible retaining walls. The
analysis performed involves the face-to-face interview approach, brainstorming, and a cause
and effect diagram. The article discusses a specific case of installing flexible retaining walls.
This case study has been selected with reference to the results of the face-to-face interviews,
showing that the parties involved in construction most frequently fail to assess the risk of
installing the flexible retaining wall, which causes some problems in geotechnical
applications in Lithuania. Identification of risks is important for risk analysis in order to
reduce the number of emergencies. The face-to-face interview approach and the
brainstorming method were chosen for analysis, as the knowledge and experience of experts
in the field of installing flexible retaining walls allow a more thorough identification of
possible risks. The major finding of the face-to-face interview approach was that the greatest
loss is caused by breakdown in the pressure pipe. When analysing the case of installing the
flexible retaining wall using the cause and effect diagram, all possible risks leading to the
breakdown in the pipe are shown graphically.
The novelty of this article is investigating the identification of possible risks when installing
flexible retaining walls and suggests risk identification steps in the risk management flow of
the flexible retaining wall installation process.
The structure of the article is built as follows. Section 2 analyses geotechnical risks. The
authors of the article present the case study and risk identification by applying the face-to-
face interview approach in Section 3. Having analysed the data obtained during the face-to-
face interview and clarifying the possible causes of breakdown in the pipe, brainstorming and
the cause and effect diagram were used. Section 4 deals with risk identification in the risk
management flow of the flexible retaining wall.
10087
Geotechnical Risk Identification: Case Study of Flexible Retaining Walls Installation
To identify risk, the Swedish Geotechnical Society (SGF) [16] recommends employing
methods for detecting hazards and considering possibilities. When opting for techniques and
organizing a risk management team, one has to adhere to the following principles:
Risk identification is considered to be an engineering task:
anyone who may be of benefit to the work should be engaged in it;
the goals of the project have to be considered first;
a unified approach should prevail, and therefore all aspects of the project have to be
studied;
necessary information should be collected;
both hazards and consequences have to be investigated and distinguished from each other;
risk should be analysed without emotions;
there should be concentration on risk rather than on solving related problems.
The result should be documented so that it can be used for the entire project.
The geotechnical risk of the project is a part of the risk of a construction project and is
frequently one of the most controversial parts of the technical risks. ‘Geotechnical risk – is
the risk to buildings and construction work created by the site ground conditions’ [17].
However, this is only one of many risks that are specific to geotechnical projects. Table 1
presents the specific risks and hazards of geotechnical projects. In general understanding, a
hazard is something that can cause harm, e.g. electricity, chemicals, working up a ladder,
noise, stress, etc. A risk is the chance, high or low, that any hazard will actually cause
somebody harm. The geotechnical hazard can be named as building collapse, landslides and
etc.
Table 1 - Specific risks and hazards of geotechnical projects (adapted by authors from
Baynes’ [18]).
Type of geotechnical risk Hazard
Project management Poor management of the entire geotechnical process
Poor management of site investigation and contractor
Contractual
documentation
Unreasonable analytical model selected
Nonconformity of the structural scheme with design drawings
Analytical
Nonconformity of the structural scheme with construction stages;
technological effects are not assessed
Technical Properties Unreasonable design values selected
Inherently hazardous ground conditions
Geological
Unforeseen ground conditions
Invalid construction type selected
Construction
Invalid technology selected
10088
Danute SLIZYTE, Natalija LEPKOVA, Rimantas MACKEVICIUS
Based on the experience gained in the field of designing and constructing geotechnical
objects, the authors of the article propose five categories for analysing geotechnical risks, as
depicted in Figure 1: water, soil, seismology, surrounding buildings and structures, and
technological processes used during construction.
The first three types of risks are natural and most uncertain.
The risk of breakdown of the structure(Figure 1) took into account geotechnical research,
design, and Eurocodes and standards for specific geotechnical works.
The analysis of water level and its variations in terms of time shows that the groundwater
level is not constant in nature and is subject to various factors such as seasonal changes,
floods, tides, and so on. Frequently, the maximum possible rise in groundwater is calculated
according to standardized diagrams that may not meet local conditions.
External
geotechnical risks
10089
Geotechnical Risk Identification: Case Study of Flexible Retaining Walls Installation
only at separate points of the soil matter. Hence, it is important that attention is paid to the
selection of representative specimens when describing the characteristics of a single layer.
Variations in the characteristics of soil exposed to the effects of cold or mechanical or
dynamic factors are accepted as one of the soil properties. Therefore, soil properties described
-in the geotechnical report can only be applied on the condition that the structure of the soil
will not be destroyed during construction and afterwards.
Soil characteristics appear to be one of the greatest sources of risk (see Table 2). Information
on the layout of soil layers during engineering geological explorations and the preparation of
a geotechnical report is limited. The placement of layers is directly investigated in separate
places in the construction site by drilling, and information can be indirectly obtained through
the Cone Penetration Test (CPT), Standard Penetration Test (SPT), or other methods. Only
at tested points are the soil boundaries and type known. Between the tested points, only
assumptions can be made. Therefore, only at the time of construction, when excavating the
foundation pit, is it possible to verify whether the soil and the depth of the soil conform to
the geotechnical report.
The seismic effect on the specific construction site cannot be measured. This is the most
uncertain geotechnical external effect. Designing seismic districts is one of the greatest risks,
and the assessment of these risks may lead to fundamental changes in geotechnical solutions.
This effect is strictly regulated by separate normative standards.
For the rest of the risks related to the environment, the size of uncertainties greatly depends
on the ability to collect information about the surrounding buildings and structures. Those
opportunities will certainly be better if the builder's relations with neighbours are good and
if the builder convinces them that the risk to their property will be reduced during
construction by the provision of such information. In this case, there is a need for effective
communication with neighbours in order to avoid frightening them about possible risks. Lack
of communication is due to the fact that everyone treats risk differently [19].
10090
Danute SLIZYTE, Natalija LEPKOVA, Rimantas MACKEVICIUS
The selected technological processes of construction can determine the level of risks. From
a geotechnical point of view, efficient technological processes can increase risks on the
construction site. For example, hammering or vibrating a sheet pile wall results in producing
dynamic effects that will lead to the occurrence of thixotropic processes, the soil will
dissolve, and the surrounding structures may lose their foundations in silty sand saturated
with water. Therefore, at the engineering feasibility stage, one of the essential tasks is to
select the most appropriate technological processes taking into account the risks involved.
The risks of the construction project have to be assessed at all stages of its development. Each
of these stages addresses different problems of risk manageability [20]. Figure 2 shows a
diagram describing the risks under consideration during the stages of developing a
geotechnical project. Risk identification and analysis is a continuous process, because each
of the steps may result in additional data that will reveal new risks. The earlier the risk is
identified, the easier its management will be.
To solve geotechnical problems, as the first step, the designer has to collect as much
information as possible about the site itself and about the immediate environment that can
affect the building being designed. This will allow potential risks to be assessed at the initial
stages of the project (planning stage and engineering feasibility stage). Based on the analysis
of the initial information, the project manager will also be able to decide on the extent of the
required geotechnical exploration for the planned facility.
Stage Content
Construction
Dynamic risk management during construction
Stage
Operation
Risk management in operating environment
Stage
Figure 2 - Scheme for lifetime risk assessment by Huang and Zhang [20].
In different Member States of the European Union, investigation volumes are subject to the
geotechnical category assigned to the object. This can be done using the process shown in
Figure 3.
Subject to the category, the investigation volume and methods are regulated. A few
geotechnical categories may form the object, which will depend on conditions for variations
in the site and design constructions. It should also be considered that the situation must be
monitored to determine whether there is a need to adjust the established geotechnical
category during the whole construction process [22].
10091
Geotechnical Risk Identification: Case Study of Flexible Retaining Walls Installation
n
o
y
e
s
I
s
t
hr
ee
s
t
r
ui
c
t
u
r
es
sm
mp
a
l
l?
a
n
d
I
s
t
h
e
s
t
r
u
c
t
u
r
e
vn
e
r
y
l
a
r
g
e
o
r
u
n
u
s
u
a
l
?
l
ay
t
ve
e
l
y
i
l
e
y
e
s
s
D
o
e
s
i
t
i
n
v
o
vn
l
eo
a
b
n
o
r
m
a
l
r
i
s
k
s
?
Anl
r
ewac
g
r
o xy
ur
nmes
d r
c nieoo
oo
nme
d
i
ia
t
o
na
sl
k u
o
nl
f
op n
c
pth
r
b
e ry ?
y
e
s
I
s
t
h
e
r
e
u
n
u
s
u
a
l gn
o
rr
eu
xn
cd
e?
p
t
i
o
n
a
l
l
y
d
i
f
f
i
c
u
l
t
of
c
e
i
e
cghu
of
bwmi
e
n
o
oo
st d
ia
f
er
i
n
t
lida
t
r
a
to
od
r
a
d
hbe
tes
ou
u
t
ef
mr
t
s
a
y
e
s
A
r
e
t
h
e
r
e
u
n
u
sc
u on
a
ln
o
ri
ei
xn
cs
e?
p
t
i
o
n
a
l
l
o
a
d
i
n
g
s ny
e
od
f
ns
dr
at
t
o
n
do
t
o
i
g
ne
c
n
t
u
c
i
o
n
y
e
s
s
I
s
t
h
e
s
t
r
u
c
t
u
r
e
i
nn
ao
h
i
g
h
l
y
s
e
i
s
m
i
c
a
r
e
a
?
I
fwdx
ea
xe
crsr
a c n ey
vt
a
t
ol
i
ni
bs
e
l
ov
wo
t
he
ed
y
e
s
tee
aocs
bmet
epi
ibcf
n
l
v
, i?
sn
I
t
ha
eb
sl
t
r
uo
c
t
up
r
ee
i
ns
ae
nn
a
eg
r
au
o
fn
p
r
om
bo
av
b
l
em
s
i
et
t
n
o
opi
a
rih
a
l
et
l
o
ch
a
l
i
s
t
i
i
t
y
r
r
s
in
to
t
r
o
d
e
e
n
s
?
e
i
e
ni
d
ao
er
ta
ar
t
t
w
l
l
b
r
a
g
t
w
d
e
.
go
:nc
.
e
s
Category 2
Sf
p
ru
e
ad
da
f
oo
un
n,sn
dwo
a
t
il
o
nsr
s
,nabafe
rde
a
f
to
f
oh
ur
nsc
dtvstrh
au
t
i o
s
,e,ako
p
i
lri
e
ou
np
t
i
s
a
l
a
temot
exet
raai
tndb
u
r
sbr
edwsbm
t
a
ieo
n
ii
n
ge
o
r
:r
se
I
hm
t
e
eo
r
no
ev
g
l
i
gl
bse
i
l
et
r
i
s
ki
i
no
n
o
Category 3
sag
pau
o
r
t
i
nm
g c
lt
i
o
wmsnt
tanrs
r
,
a
t
in c
s
rt
g e
pk
r
s
S
t
r
uu
c
t
u
r
e
ssi
owh
r
pchca
ahehn
t
sd
o
f
t
r
sr
fu
e
r
a
lv
ae
b
i
l
t
y?
r
nr
don
b
u
tnnw
ehat
sa
,
e
ndas
k
n
t
e
h
rme
s
,,
s
t
ro
c
t
u
rwo
e
hte
i
o i
g
o
ny
de
ms
o
m
n
t
s
ne
d
a
o
rr
g
e
hr
e
r
e
anq
c
s
y
tje
st
ni
tm
f
a
l
l
t
i
n
t
us
ne
li
s
i
h
d
,
n
o
c
ur
et
d
o
ke
t
se
u
cs
e
d
t
o
lC
ia
t
se
fo
Gi
es
o
t1
nd
c2
a
l
p
c
a
l
a
e
r
t
i
g
h
n
o
o
e
r
r
u
i
r
n
t
.
t
g
r
e
Category 1
Figure 3 - The general decision tree for selecting a geotechnical category by Simpson and
Driscoll [21].
However, even following recommendations can reveal some uncertainties. As a rule, for the
objects of the second and third geotechnical categories, the mechanical properties of the soil
are determined by laboratory tests. For example, in determining the indicators of the shear
strength of the soil, their magnitude is subject to available comparable experience (see Table
3), according to EN 1997-2 [23]. Yet documents do not provide information on the type of
comparable experience.
Table 3 - Direct shear test. The recommended minimum number of tests for one soil stratum
[23].
Recommended number of testsa
Variability in strength envelope Comparable experience
Coefficient of correlation on regression curve None Medium Extensive
Coefficient of correlation < 0.95 4 3 2
0.95 ≤ coefficient of correlation < 0.98 3 2 2
Coefficient of correlation ≥ 0.98 2 2 1b
a One recommended test means a set of three individual specimens tested at different normal
stresses.
b A single test and classification tests to verify compatibility with comparable experience. If the
test results do not agree with the existing data, additional tests should be run.
To identify geotechnical risk, specific geotechnical issues that are not always successfully
solved by referring to regulatory documents about this particular field of construction need
10092
Danute SLIZYTE, Natalija LEPKOVA, Rimantas MACKEVICIUS
10093
Geotechnical Risk Identification: Case Study of Flexible Retaining Walls Installation
The interviewees were asked to list the types of geotechnical structures they designed based
on the frequency and level of contribution of their experience.
In response to this enquiry, the top three types of geotechnical structures designed were
revealed to be pile foundations (30%), retaining walls (26%), and shallow foundations (23%).
The distribution of the geotechnical structures designed by the respondents is as depicted in
Figure 4.
6; 8%
5; 6%
1; 23%
4; 7%
3; 26%
2; 30%
As can be seen from Figure 4, the most commonly used structure is pile foundations and the
second choice is retaining walls.
The most commonly encountered problems identified by the respondents were related to
retaining walls, loose soil, and water. However, very often, respondents related these
problems to insufficient geological exploration, limited information about surrounding
structures and engineering infrastructure, and their assessment at all stages of construction.
10094
Danute SLIZYTE, Natalija LEPKOVA, Rimantas MACKEVICIUS
It is worth noting that underground barriers were mentioned as problems only by geotechnical
engineers. The frequency of problems encountered in geotechnical structures as reported by
the respondents is given in Figure 5.
4; 11% 5; 9% 6; 5%
7; 4%
8; 4%
3; 15%
Other; 10% 9; 2%
10; 2%
2; 22%
11; 2%
1; 24%
When answering the questions about quality mismatches specific to geotechnical structures
and the usual reasons for their occurrence, 10 out of 14 respondents identified quality
mismatch as a deviation inherent in geotechnical structures. Others mentioned sediment,
insecure reinforcement in the project, insufficient depth, inadequate waterproofing, and
concrete works.
The most significant reason for the appearance of poor-quality geotechnical structures,
according to the respondents, was the geological conditions and their poor assessment or
insufficient geological explorations. Workplace culture on the construction site and errors in
design took second position. Errors in design were often (two times out of four) related to the
inadequacies of technological processes with computational schemes. Also, tight work
deadlines, incorrectly applied technology, misunderstandings, and corruption were also
pointed out. The reasons for poor quality of the finished work and their respective weights
are shown in Figure 6.
Insufficiency of geological and engineering investigations was cited as the most common
cause of poor-quality work. Therefore, an additional enquiry was carried out with the aim of
determining the causes of and reasons for complementary investigations in the design and
construction stages. Only 11 of 14 interviewees responded to this line of enquiry: three
respondents carried out the exploration when the properties of the soil at the site at the time
of construction did not match the data provided in the report; six respondents did so when
they lacked data in the design stage (insufficient depth of exploration, unspecified mechanical
properties of the soil, filtration coefficient, etc.); two of them commissioned additional
studies to clarify the characteristics of the loose soil for a reliable and cost effective design
(Figure 7).
10095
Geotechnical Risk Identification: Case Study of Flexible Retaining Walls Installation
7
6
Number of responses
5
4
3
2
1
0
1 2 3 4 5 6 7
The main reasons
7
Number of responses
6
5
4
3
2
1
0
Non-compliance Lack of data in Spread of a loose
with natural soil the project soil
9
8
Number of responses
7
6
5
4
3
2
1
0
5 4 3 2 1 Others
Assessment
Related companies Non-related companies
10096
Danute SLIZYTE, Natalija LEPKOVA, Rimantas MACKEVICIUS
10097
Geotechnical Risk Identification: Case Study of Flexible Retaining Walls Installation
3.2.1. Interviews for the geotechnical risk of the steps in the installation of the flexible
retaining wall
The respondents were asked to assess the compliance of the calculation scheme with the
technological one and to identify the relevance of the aforementioned risks, consequences,
and likely conditions to be observed at each stage and to recommend preventive measures to
be undertaken to mitigate the risks.
Analysis of the calculation schemes showed that only two respondents underlined that
pressure tubes sometimes formed intermediate cast-in-place that should affect the
calculations of flexible retaining walls. Therefore, it was necessary to assess whether the load
from the pipe could affect the retaining wall at all stages. As for the other stages, half of the
respondents pointed out the following:
in Stages 2 and 4, the calculated depth of the excavation has to be taken into account when
estimating the possible inaccuracies of the excavation rather than accepting a standard
size;
in Stage 5, cast-in-place formation opposite the wall destroys the foundation of the
retaining wall and therefore it is necessary to estimate this in the calculation scheme
(Figure 9).
The tables below (Tables 5–9) show the summarized answers to the questions about risks
arising and their consequences and conditions for the emergence of hazards occurring in each
stage. The numbers in brackets next to the risks and conditions for risks indicate the number
of respondents who named them.
The smallest number of risks were identified in Stages 6 and 7 (Table 5).
The most frequent ones involve the following:
too-deep excavation (Stages 2 and 4, Tables 8 and 9);
deviations from designed anchors and beam anchors or insufficient bearing capacity
(Stage 3, Table 6);
foundation weakening caused by anchor installation (Stage 5, Table 7);
H-beam deepening and related risks (Stages 1 to 3, Tables 6 and 8).
10098
Danute SLIZYTE, Natalija LEPKOVA, Rimantas MACKEVICIUS
Table 5 - The analysis of risks, consequences, and conditions in the case study. Stages 6
and 7.
Stage 6 – Installing the 1st overlay
Scheme / risk of the Calculation scheme / Description / conditions
technological process consequence
Concrete is poured on the grate,
wall and overlay above formed
cast-in-place
In 28 days after laying concrete,
Question
The overlay will not accept Collapse or deformations of Poor contact between the
Responses
horizontal loads (3) the retaining wall crack overlay (2) and retaining wall
in the pipe Overlay design did not consider
horizontal loads (1)
*The brackets next to risks and conditions for risks indicate the number of the respondents who named
them.
10099
Geotechnical Risk Identification: Case Study of Flexible Retaining Walls Installation
The most common opinion about potential risk was obtained by analysing Stage 4;
foundation weakening within the process of forming cast-in-place pile was identified as a
risk (Table 9).
Table 6 - The analysis of risks, consequences, and conditions in the case study. Stage 3.
Stage 3 – Installing an anchor
Scheme / risk of the technological Calculation scheme / Description / conditions
process consequence
Beam anchors connecting two
neighboring H-beams are
installed.
A A
A Anchors the roots of which
make ~ 20 cm in diameter are
installed
In 28 days, the anchors are
pressed in up to the force
provided in the project
Section A-A
Anchor
Question
View A
10100
Danute SLIZYTE, Natalija LEPKOVA, Rimantas MACKEVICIUS
Table 7 - The analysis of risks, consequences, and conditions in the case study. Stage 5.
Stage 5 – Installing piles next to the wall
Scheme / risk of the technological Calculation scheme / Description / conditions
process consequence
Calculations of the retention Formed cast-in-place bearing
walls of stage 4 are used vertical loads of the retention
wall are erected
B B
Question
Bored pile
Section B-B
Bored pile
10101
Geotechnical Risk Identification: Case Study of Flexible Retaining Walls Installation
Table 8 - The analysis of risks, consequences, and conditions in the case study. Stages 1
and 2.
Stage 1 - H-beam deepening into the designed position
Scheme / risk of the Calculation scheme / consequence Description / conditions
technological process
The site is enclosed
Construction site inserting H-beams into
enclosed by the fence
the designed situation
City street
Question
High pressure
sewage networks
D=400 mm
H-beam profile
between
them1,00 m
Designed deepening is not Collapse of the retaining wall or Clogged soil (1),
achieved (2)* deformations crack in the pipe inappropriate types of soil
(strong clay, rubble) (1)
H-beam inserted into the crack in the pipe
pipe (1)
Deviations of H-beams Project correction increase in
Responses
10102
Danute SLIZYTE, Natalija LEPKOVA, Rimantas MACKEVICIUS
Hd
H
embedded between H-
beams
Question
Cavities form between Soil moves behind the retaining Crumbly, dry soil,
planks and soil matter form wall deformations of pipe recommendations are
(2) foundations crack in the pipe neglected when work is
done’ (3)
Larger load than that Collapse or deformations of the The project does not
expected in the road zone retaining wall crack in the pipe provide the possibility of
(1) carrying heavy loads,
transport weight is not
limited (1)
Separate H-beams can enter Collapse or deformations of the H-beams are not
the layer of the unexpected retaining wall crack in the pipe interconnected,
Responses
10103
Geotechnical Risk Identification: Case Study of Flexible Retaining Walls Installation
Table 9 - The analysis of risks, consequences, and conditions in the case study. Stage 4.
Stage 4 – Excavation up to the designed position
Scheme / risk of the Calculation scheme / Description / conditions
technological process consequence
Excavated up to the altitude
of the designed foundation
pit
Hd
H
Hd=1.1H
but not exceeding
Hd=H+0.5m
Excavation is deeper than that Collapse or deformations of the Improper control during
provided in the computation retaining wall crack in the construction (5)
scheme (5) pipe Misunderstandings between
the parties of construction
(2)
Loss of overall stability (2) Collapse or deformations of the Too short anchors (1)
retaining wall crack in the Anchors are installed at a
pipe sharper angle of inclination
than that provided in
calculations (1)
Overall stability is not
verified (1)
10104
Danute SLIZYTE, Natalija LEPKOVA, Rimantas MACKEVICIUS
Stage 2 covers control of the depth of the excavation and the careful installation of planks to
minimize soil crumbling.
Stage 3 involves the process of making a continuous beam anchor that integrates H-beams
and anchors into the common system; all anchors must be tightened and tested in accordance
with the requirements for normative documents, the depth of the pipelines must be adjusted,
a sufficient distance from the borehole for the anchor to the bottom of the pipeline must be
maintained, the drilling angle must be monitored, and the designed injection area must be as
far as possible beyond the pipelines.
Stage 4 keeps control of the excavation.
Stage 5 embraces the selection of cast-in-place formation technology that should minimally
damage the foundations of H-beams and form cast-in-place as far from the H-beams as
possible. The stage also points to forming cast-in-place with pauses to reduce temporarily
weakened areas.
The interview was informal and had no time limit. Although the face-to-face interview
approach was used and assisted in clarifying the situation, there was no respondent who
should focus on all the risks listed in the table.
One of the respondent designers (Structural Project Manager) described situations and
calculation schemes as logical and thoughtful and therefore did not face any risks in the
process of installing flexible retaining walls. The surveyed architect, project manager (PM)
distinguished only deviations from the design situation as risks that could affect architectural
decisions.
The respondents agreed with the opinion that the greatest loss in the given situation would
be caused by a breakdown in the pressure pipe and pollution of the natural environment by
wastewater. Also, breakdown in the pressure pipe was mainly mentioned when assessing the
final consequences of the risk.
10105
Geotechnical Risk Identification: Case Study of Flexible Retaining Walls Installation
pit excavation (information included in the project, match with the calculation
scheme, control over altitudes);
initial information and the project (geological and engineering investigations, the
place of the pipes in space, project finalization and application of technology used,
the accuracy of calculation schemes, the amount and accuracy of all information).
Environmental causes
accuracy and content of geological and engineering investigations;
information on the surrounding buildings and structures;
loads and impacts (e.g. transport, seismic, technological).
Technological causes
technologies used in the construction of structures and their negative effects on the
structures or their members.
Managerial causes
poor organization;
frequent changes in projects;
excessive workloads;
insufficient experience of installing BIM systems.
Time-related causes
busy work schedules that disregard technologies.
Staff-related reasons:
poor communication between stakeholders;
lack of staff;
errors in taking control of the project;
errors in developing the geotechnical project.
Brainstorming disclosed that answers to the question of ‘why it might happen’ were based
on:
experience gained in the individual’s and company's projects or acquired by analysing
past failures in other projects;
theoretical knowledge obtained during studies or on training courses;
directions provided by regulatory documentation describing investigation, design, and
installation.
Although the aim of the participants was to identify the risks of installing retaining walls and
determining their causes while placing major focus on the retention wall as a geotechnical
structure, other causes of risks related to technology, time, management, environment, and
human resources were identified too. The selected team has to ensure the representation of
all stakeholders and participants of construction- the composition of the team needs to be
adjusted according to the intended goals. In this way, the project can be analysed in more
detail.
Based on these observations, one can conclude that the proper selection of brainstorming
participants can lead to good results when analysing geotechnical structures with respect to
risks.
10106
e
Pu ven
rs o p
F
ui po
ng s
an ull
sy
Deviations from the Inaccurate information on
di ing
A ste aly ap ffe g
o
project
ut m to
p sis pro the position of the pipes
ho in th ren als a os
of val
rit th t, compa
b ers ar e D es si
th wi iff am som Th nch ma H-bea cted soil
Th y an on ian co
e p th er e To mu e or ll m vib un
ro no
ou in m mp en si eti ration der the pi
m
F
o ltan dis and
s t pe
gh flu
t e
an an po c u t a tua e C
result
sa rit
La ag y te ma eou ance the s in th s
ck se n
x em ls ica
D nde sses tion s fr au un or i In chn ll d sly e
m l
tia if rs s be pip
of pr l en Im
co om ses d e n st co ol i
ad
pipe is
es t r t all
e C ns th dis
po fere tan men
ectl
co rre og stan wea twe e sh
he in e o
so
m se st nt din t
d sin
p o ct y ce ke
Incorr logy
g fo aus truc e ot sati pi g a
ly
S
pe Te ruc p
s b ne n th e is
te ch tur ex os g ri f
iti sk llo es tio he sfa pe nc se et d a e
y sele
wi di n r p ct th oil
nc ce D roje le
s a ho E
we r
e on
i o pr
no e a
C ss ng str act art ion
ev ct cte
re rs
to lo re o en eas
so ia d
re pr ust ors ies o nco nv se op
cted
f
ct
e
d lc hn
os th S eak e
ac p
technology is selected
lat l i co ire
m pr epe cle tere gat ned es d
i
techno il under th ed
io
al e
ul o m n fr
a
on gic ts
o rin ot
or n p ct er th
a t g a ev nd
So ted su th te d ct
g m
e si b
anchor length is not reached
tio
co ro s o ed
Insufficient competence of the
il pr ibra
sc l p ffi e
n
Ex
iv f
bi
control
control
ec ct g
and devices are selected
hn be lar ce
In
ce
no
Lo rme nsta la lit
e d fix re i epth
hn ly y
ic tw ge Th
S
rm a
ssi
ss di lla
Ex eote
is too weak
in cor ic sel l ee ef in nst
Poor communication with geotechnical ea
Ex yer
ve re n
ve
ce ch
of ate tio
Poor quality
Poor quality
ati
al ec
o r g t al
sti ct ca te
ve In ss ni d ce of de oil p nc m he led
and technological design promoters ov su n c
de
ga ly te d
su i v ca s s fo fin ro ho
ati a
E er pp au Th
fo
ed pe ri
r
go
Ex eep iv un
e
eu lc on nc at a
tio sel A al r
ffi
g rro
el d
n ec ry
ci nc on ca
l s orts ses du tie an st at hor n
fo mat
oo
The prestressed load
oa ati
m te p lim eo rs ta
en
da
va th
A rin s d ch
er dit
m w
ds on e
bi g o o
ta io
eth d
tc tio
provided in the project
un ion
ob arti ite tech in d r
ns
in n nc n lit ag ea
on s
y
da o
om
od so no
tio f
ta cul d i
s
ho th
Li in ar kn nica esig il t m b Calculations of the anchor do not
pe rs st
in
of o
ro
te In o
et
The level of
su
Increased dissatisfaction
correspond to the scheme
with work
responsibility decreases
op
du ld le
nc
sig e en
is too small
io is
n ul la ab
ho e t sio ed
t tru n
the beam.
at tio n h op ast-
pa
da ri ot
io n ou ct ot po in
id n
The excavated pit is too deep
t
ns he pr e p
Designers are not competent ur
Th ma
sc e sit -pl
oc ip
as pro
tal p
e e Th
member is selected
Structural e v ge
s l a ip
an su gr enough
ss e H ac
t
ib to
m am
tio e
dir e pi
D -b e fo
es
Anomalies
ra t n
pt s
io d
tin he ha
ire ec pe ea un
Poor communication with the Th tly is A
ha
technological project
Errors in developing a
ns oe
g pi ve
ct n m da
d
o sc
hit s a ti
geotechnical design promoter ef vib e pi
H pe
sn -b au
ee ex
Weakened foundations on the side
ot fe ra t p e i p c fte on
Ch f co ea se
and technical maintenance ct r d is
m d ion s a (e ava
o f
ca ted
ge in ca
s i ate u us th d c te v gi rm
in n s es ep rac d b at pit ng ed
Sp e
th U nde
ip ks y io is ap
e ns t
Inappropriately selected profile of
In the
it
es nd re
defined during soil investigation
ac p
Soil properties do not meet those
ys er sti
ManagementI I a oo
cific
Busy work schedules are
cu la gr m
ra n te
m ou ate nd
ground test
Small-amount
accepted as a priority
te
II)
c on
lo nd d
project
In
brainstorming.
Lack of knowledge e
ca pa
ac
ditio
tio rts
cu n
In ra
ar
e
ac te
are ns on
cu
ra lo L
the soil
te ca va oad
not the
ess
tio
lo n lu s e
ed
ca in es x
ass site
tio th fo cee
n
Poor quality control
ep r t di
in lan
hi ng
sp t Are
th Are
structural materials
es ar he unk
tic no not now
ec In n
Installing the BIM system
lacks use experience
ul rm c on
tio te cor sid
Inappropriate allocation of
the schemes for the technological
n ar a
Calculations do not correspond to
structures
no ct ob tiv d
construction participants
risk as
gi se t y
short
Technological breaks are too
Fails to assess variations in the
Fails to assess the properties of
ca s s
heights
schemes
Rush leads to inaccurate
technological processes
ll m Time
oa en
properties of structural materials in
ds t o
f
The project does not provide a possible
calculation-based altitude of excavation
conditions
Geological
Properties of the soil Soil layers
retaining wall.
Vibrations have a
negative effect on Possible deviations
foundations. from the project.
Anomalies
Installation technology for the
Anchor installation technology
Figure 10 - The cause and effect diagram according to the information collected during
foundations.
weakens the base on the side of passive pressure
Unrepresentative investigation
samples are taken
been broken
A high-pressure
waste pipe has
Misinterpretation of results
Inappropriate testing
The sample is damaged at the
preparation stage.
Danute SLIZYTE, Natalija LEPKOVA, Rimantas MACKEVICIUS
10107
Geotechnical Risk Identification: Case Study of Flexible Retaining Walls Installation
4. DISCUSSION
Based on the analysis carried out, the authors of the paper proposed risk identification of
flexible retaining walls using a risk management flow based on Mishra et al. [8] and ISO/IEC
31010:2009 [24]. In the future, this chart (Figure 11) can be verified by analysing other
geotechnical structures. For the effective application of risk identification in flexible
retaining wall risk management flow, a well-prepared team representing all interested parties
should be created.
Data collected on the investigated structure. A detailed project, including calculation
schemes, descriptions of technology, and the work order, is developed, and all information
on adjacent buildings and structures and data of geological engineering exploration are
obtained.
The collected information assists in establishing the content, thus allowing the risk
management objectives, criteria, and assessment programme to be identified and coordinated.
If the required information is missing, data are added before proceeding to the next stage.
The purpose of risk assessment is to help make decisions based on the results of risk analysis,
define the risks to be reduced, and set risk reduction priorities. Risk assessment includes one
or a few options for changing risk and implementing these options.
First, the risks are identified, which involves all pre-selected construction participants and
interested persons, for example, by applying the face-to-face interview approach.
Brainstorming is used to identify risks. To facilitate risk management, the installation of the
flexible retaining wall should be divided into technological stages.
Risk identification
Risk assessment
Risk analysis
Risk reduction
YES
Risk acceptable
NO
Treat the risk and analyse reliability
Figure 11 - Risk identification in flexible retaining wall risk management flow according to
ISO/IEC 31010:2009 [24] and Mishra et al. [8]
10108
Danute SLIZYTE, Natalija LEPKOVA, Rimantas MACKEVICIUS
At the stage of risk analysis, the probability of occurrence of the appropriate type of risk is
estimated. The consequences established at the risk identification stage are also assessed; that
is, their impact on the project and its related activities is evaluated.
The stage of selecting preventive measures, reducing risk, and analysing the reduced risk
completes the risk assessment. Thus, the question of ‘whether the risk is acceptable’ arises.
The authors of the article propose that if the risk is not acceptable, the data collection stage
should be performed again to acquire new data. It may involve material for additional
geological engineering exploration or any other bonus information that may affect the risk of
installing the retaining wall. Then, everything is repeated again. At the risk assessment stage,
the processes of risk identification, analysis, and reduction are very closely interrelated and
therefore have to complement one other.
The participants must be involved in information exchange, tutorials, risk monitoring, and
review within the whole process. In order to identify risk, first of all, the selection of all
construction participants involved has to be made. They may analyse geotechnical risks and
related problems. The proposal is based on the analysis carried out in this article and on the
observation that not all construction participants having experience in the field of
construction - are able to identify geotechnical risk (see Section 3).
5. CONCLUSIONS
Analysis of the scientific literature with reference to the topic of the article shows that the
risk of collapse or deformations of flexible retaining walls has not been widely analysed.
In order to determine the risk of installing flexible retaining walls, the authors of the article
used the face-to-face interview approach, brainstorming, and a cause and effect diagram. A
specific case study is presented.
The examination of the specific case (interviewing) demonstrated that the respondents
identified risks and proposed additional preventive measures. The respondents expressed the
same opinion about the given situation and agreed that the greatest loss would be caused by
breakdown of the pressure pipe and pollution of the natural environment with wastewater.
Also, breakdown in the pressure pipe was the most frequently mentioned option when
assessing the final consequences of risks.
Investigation of the data obtained during the face-to-face interview was based on
brainstorming and the cause and effect diagram: five professionals who had monitored most
of the risks were selected with the help of the face-to-face interview. The thoughts expressed
during brainstorming were used as the basis for drawing the cause and effect diagram.
The study found that the face-to-face interview approach could only be applied to risk
identification in simple cases and was suitable for preliminary screening of the respondents
involved in brainstorming. Thus, the face-to-face interview approach should provide an
identical or similar situation in order to independently assess the competence of would-be
respondents considering a particular issue.
10109
Geotechnical Risk Identification: Case Study of Flexible Retaining Walls Installation
Geotechnical experts are more trusted than other construction participants when expressing
their positions on objects not related to it or the company that employs them. Cooperation is
also smoother if reasoned statements are made.
Acknowledgements
We express our sincere gratitude to our colleagues who have been willing to discuss the ideas
and who made comments at the early stage of development of this paper.
Conflicts of Interest
The authors declare no conflict of interest.
References
[1] Lacasse, S. Hazard, Reliability and risk assessment – research and practice for
increased safety. NGM 2016 Reykjavik Proceedings. Paper presented at the 17th Nordic
Geotechnical Meeting. Challenges in Nordic Geotechnics, 25–28 May 2016.
[2] Flage, R., Aven, T. Emerging risk – Conceptual definition and relation to black swan
type of events. Reliab. Eng. Syst. Safe., 144, 61–67, 2015.
[3] ISO 31000:2009(E). Risk management – Principles and guidelines.
[4] Duncan, J.M. Factors of safety and reliability in geotechnical engineering. J. Geotech.
Geoenviron., 126(4), 307–316, 2000.
[5] Gibson, W. Probabilistic methods for slope analysis and design. Aust. Geomech. J.,
46(3), 1–12, 2011.
[6] Brown, E.T. Risk assessment and management in underground rock engineering—an
overview. J. Rock Mech. Geotech. Eng, 4(3), 193–204, 2012.
[7] Swannell, N., Palmer, M., Barla, G., Barla, M. Geotechnical risk management approach
for TBM tunnelling in squeezing ground conditions. Tunn. Undergr. Sp. Tech., 57,
201–210, 2016.
[8] Mishra, R.K., Janiszewski, M., Uotinen, L.K.T., Szydlowska, M., Siren, T., Rinne, M.
Geotechnical Risk Management Concept for Intelligent Deep Mines, Procedia Eng,
191, 361–368, 2017.
[9] Xia, Y., Xiong Z., Dong, X., Lu, H. Risk assessment and decision-making under
uncertainty in tunnel and underground engineering. Entropy, 19(10), 549, 2017.
[10] Haddad, A., Eidgahee, D.R., Naderpour, H. A probabilistic study on the geometrical
design of gravity retaining walls. World J. Eng., 14(5), 414–422, 2017.
[11] Zou, Y., Kiviniemi, A., Jones, S.W. A review of risk management through BIM and
BIM-related technologies. Safety Sci., 97, 88–98, 2017.
10110
Danute SLIZYTE, Natalija LEPKOVA, Rimantas MACKEVICIUS
[12] Li, Z., Xue, Y., Qiu, D., Xu, Z., Zhang, X., Zhou, B., Wang, X. AHP-ideal point model
for large underground petroleum storage site selection: an engineering application.
Sustainability, 9(12), 2343, 2017.
[13] Xue, Y., Cao, Z., Du, F., Zhu, L. The influence of the backfilling roadway driving
sequence on the rockburst risk of a coal pillar based on an energy density criterion.
Sustainability, 10(8), 2609, 2018.
[14] Ahmadi, M.; Behzadian, K.; Ardeshir, A.; Kapelan, Z. Comprehensive Risk
Management Using Fuzzy FMEA and MCDA Techniques in Highway Construction
Projects. Journal of Civil Engineering and Management 2017, 23 (2), 300-310, DOI:
10.3846/13923730.2015.1068847.
[15] Valipour, A.; Yahaya, N.; Md Noor, N.; Antuchevičienė, J.; Tamošaitienė, J. Hybrid
SWARA-COPRAS Method for Risk Assessment in Deep Foundation Excavation Project:
An Iranian Case Study. Journal of Civil Engineering and Management2017, 23(4), 524–532,
DOI: https://doi.org/10.3846/13923730.2017.1281842
[16] SGF (Swedish Geotechnical Society). Risk Management in Geotechnical Engineering
Projects – Requirements: Methodology. Report 1:2014E. 2nd ed. Linköping: Swedish
Geotechnical Society. 2017. Available online:
http://www.sgf.net/web/page.aspx?refid=4567 (accessed on 5 March 2018).
[17] Clayton, C.R.I. (ed.) Managing Geotechnical Risk - Improving Productivity in the
United Kingdom, 2001.
[18] Baynes, F.J. Sources of geotechnical risk. Q. J. Eng. Geol. Hydrog., 43, 321–331, 2010.
[19] Sartain, N., Mian, J., Free, M. Presenting uncertainty clearly: challenges in
communicating geotechnical risk. Geotechnical Safety and Risk V, 739–751, 2015.
[20] Huang, H., Zhang, D. Quantitative geotechnical risk management for tunneling projects
in China. Geotechnical Safety and Risk V, 61–75, 2015.
[21] Simpson B & Driscoll R, Eurocode 7: A Commentary. CRC Ltd, Watford. 179 p, 1998.
[22] EN-1997-1 Eurocode 7: Geotechnical Design – Part 1: General Rules. 168 p.
[23] EN-1997-2 Eurocode 7 – Geotechnical Design – Part 2: Ground Investigation and
Testing. 196 p.
[24] ISO/IEC 31010:2009. Risk Management – Risk Assessment Techniques. International
Organization for Standardization, Geneva.
[25] Dikčius, V. Marketing Research. Theory and Practice. Vilnius, Lithuania, 187 p, 2003
[in Lithuanian].
10111
Geotechnical Risk Identification: Case Study of Flexible Retaining Walls Installation
10112