                                 PETRONAS GAS BERHAD
                            INSPECTION TEST RECORD (ITR) - C
   VENDOR’S PACKAGE EQUIPMENT (SKID)                                    M36-C
Project No.
Project Title
                                     GENERAL INFORMATION
Tag no.                                           System no. /Sub-system No.
 1 COMPLETE PACKAGE                               Location
     Make & Model
     Serial No
     Capacity
     Unit Test Ref/Date
 2 DRIVER
     Make & Model
     Serial No.
     Capacity
     HP (KW)
     Rated Speed
     Voltage/Current
     V-belt spec/Coupling
 3 DRIVEN
     Make & Model
     Serial No
     Capacity
     HP (KW)
 4 INTERMEDIATE
     Make & Model
     Serial No
     Gear Ratio
     HP (KW)
                              RELIABILITY TEST                                OK   N/A P/L No
     Documents required:
          f. Signed off Pre-commissioning Check-sheet
          g. Accepted Punchlist
 1
          h. FAT report
          i. Relevant test report
          j. Commissioning and Start-up procedure (No.)
 2 Ensure availability of critical commissioning and start-up spares
     Perform final line walk to ensure system is safe and ready to run with
 3
     manual valves lined-up per P&ID
     Check the entire equipment skid and ensure all connections are
 4
     secured and intact
 5 Start-up equipment skid per manufacturer’s instruction or in
                                                                                      Page 1 of 2
                                                                                   CSP-20 rev 01
                                                                                  Appendix III-VI
                                  PETRONAS GAS BERHAD
                             INSPECTION TEST RECORD (ITR) - C
   VENDOR’S PACKAGE EQUIPMENT (SKID)                                   M36-C
Project No.
Project Title
     accordance with operating manual
     Observe and record any abnormalities such as high pitch/roaring noise
 6
     and excessive vibration; stop the unit when necessary
 7 Carry out 72-hour continuous test run
     Record all operating parameters at regular interval during the entire
 8
     endurance test
 9 Confirm results are in accordance with vendor’s specification
10 Attach vendor’s check-sheets used during the 72-hr test run, if any
COMMENT(S) AND ADDITIONAL INFORMATION:
                        COMPLETED BY                  VERIFIED BY              ACCEPTED BY
Designation
Company
Name
Signature
Date
                                                                                     Page 2 of 2