100% found this document useful (1 vote)
66 views3 pages

Holiday Test

Uploaded by

SHAMMASH
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
66 views3 pages

Holiday Test

Uploaded by

SHAMMASH
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 3

Kuwait International Industrial Laboratory

& Inspection Services (KIL)

Quality Control Procedure

HOLIDAY TESTING

KIL/QCP -22 Rev.0

1 For Review & Comments Prasanth.S

Rev Comments Prepared By Checked By Approved By


Kuwait Industrial Laboratory & Inspection Radiation
Services Co. (KIL)
HOLIDAY TESTING
QCP/KIL-21 Rev. 0

Index

1. Scope

2. Purpose

3. References

4. Procedure

5. Attachments

QCP/KIL-21 Rev.0 Holiday Testing Page 2 of 3


Kuwait Industrial Laboratory & Inspection Radiation
Services Co. (KIL)
HOLIDAY TESTING
QCP/KIL-21 Rev. 0

1. SCOPE

This procedure covers the requirement of Holiday Testing Inspection on internal surface of the
Fusion bond epoxy coated pipes.

2. PURPOSE

The purpose of this Quality Control Procedure is to address clause 4.9 “Process Control” of ISO
9001: 2008 and covers the requirement of holiday testing inspection

3. REFERENCES

This Procedure is based on the following codes:

NACE- RP - 490

4. PROCEDURE

4.1 Inspection

4.1.1 Visual Inspection shall be done to ensure that the protective layer have been applied in
quality workmanship.

4.1.2 A calibrated Low voltage holiday detector shall be used to check for any damage and pin
holes in the coating.

4.1.3 Voltage setting for total coating system shall be 67.5 V

4.1.4 The testing will be in accordance with NACE RP0490. Calibration of the holiday detector
shall be done. The holiday acceptance rates will be zero.
4.2 Personnel Qualifications

All personnel performing Holiday Test shall be qualified and certified according to
BGAS/NACE or Mechanical Engineering Diploma holder

Repairs.

When there is pin holes detected the area shall be repaired as per approved procedure and
conduct re holiday testing.

5 ATTACHMENTS

Holiday Testing Inspection Report Form

QCP/KIL-21 Rev.0 Holiday Testing Page 3 of 3