Concrete Log Book

The document contains details of concrete foundation coating activities for the MIP PKG-17 RAS TANURA AREA PIPELINE project. It provides information on surface preparation and moisture testing inspection dates, final coat inspection numbers and dates for various pipeline sections and foundation types from December 2022 to January 2023. A total of 111 foundations across 8 sections are documented to have undergone coating work over this period.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
102 views6 pages

Concrete Log Book

The document contains details of concrete foundation coating activities for the MIP PKG-17 RAS TANURA AREA PIPELINE project. It provides information on surface preparation and moisture testing inspection dates, final coat inspection numbers and dates for various pipeline sections and foundation types from December 2022 to January 2023. A total of 111 foundations across 8 sections are documented to have undergone coating work over this period.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6

MIP PKG-17 RAS TANURA AREA PIPELINE

CONCRETE FOUNDATIONS COATING ACTIVITY RFI LOG


Foundation Details
Suraface
No of Preparation & Suraface Preparation & Final Coat Final Coat
SL Description Type Number foundatio moisture test moisture test Inspection(RFI Inspection
No
ns inspection(RFI inspection(DATE) NO) (DATE)
NO )

NA SL-131 1 2886 12/13/2022 2929 14-Dec-22

NA SL-132 1 2886 12/13/2022 2929 14-Dec-22


TNJ-1,30"MLV-2 PRECAST
1 FOUNDATION @ KM 124.9
NA SL-133 1 2886 12/13/2022 2929 14-Dec-22

NA SL-134 1 2886 12/13/2022 2929 14-Dec-22

FOOTING VS -131 F1 1 2928 14-Dec-22

2 platform 104 s-131 2 Surface preparation & moiture test done by another QC 2928 14-Dec-22

platform 104 s-133 1 2928 14-Dec-22

TNJ-1,30"MLV-2 @KM
124.9 platform 104 s-134 1 2928 14-Dec-22

platform 105 s-135 1 2928 14-Dec-22


3
platform 105 s-132 2 2928 14-Dec-22

platform 105 s-136 1 2928 14-Dec-22

Total 11
MIP PKG-17 RAS TANURA AREA PIPELINE

CONCRETE FOUNDATIONS COATING ACTIVITY RFI LOG


Foundation Details
Suraface
No of Preparation & Suraface Preparation & Final Coat Final Coat
SL Description Type Number foundatio moisture test moisture test Inspection(RFI Inspection
No
ns inspection(RFI inspection(DATE) NO) (DATE)
NO )

PLATE 201 F1 7 2950 12/18/2022 3024 24-Dec-22

PLATE 201 F2 5 2950 12/18/2022 3024 24-Dec-22

TNJ-1,30"MLV-2 PRECAST
1 FOUNDATION @ KM 0 PLATE 203 F8 1 2950 12/18/2022 3024 24-Dec-22

NA S-209 1 2950 12/18/2022 3024 24-Dec-22

NA S-207 1 2950 12/18/2022 3024 24-Dec-22

Total 15
MIP PKG-17 RAS TANURA AREA PIPELINE

CONCRETE FOUNDATIONS COATING ACTIVITY RFI LOG


Foundation Details
Suraface
No of Preparation & Suraface Preparation & Final Coat Final Coat
SL Description Type Number foundatio moisture test moisture test Inspection(RFI Inspection
No
ns inspection(RFI inspection(DATE) NO) (DATE)
NO )

TNJ-1,30"MLV-1 PRECAST
FOUNDATION @ KM
1 67+900 LIFTING HOOK & NA VS-121 1 3058 12/27/2022 3137 3-Jan-23
FOUNDATION

Total 1
MIP PKG-17 RAS TANURA AREA PIPELINE

CONCRETE FOUNDATIONS COATING ACTIVITY RFI LOG


Foundation Details
Suraface
No of Preparation & Suraface Preparation & Final Coat Final Coat
SL Description Type Number foundatio moisture test moisture test Inspection(RFI Inspection
No
ns inspection(RFI inspection(DATE) NO) (DATE)
NO )

1 S-283 to S-314 32 3120 1/1/2023


TNRTNG-1,12 INCH
1 SCARPER RECEIVER
1 S-318 to S-360 43 3120 1/1/2023

Total 75
MIP PKG-17 RAS TANURA AREA PIPELINE

CONCRETE FOUNDATIONS COATING ACTIVITY RFI LOG


Foundation Details
Suraface
No of Preparation & Suraface Preparation & Final Coat Final Coat
SL Description Type Number foundatio moisture test moisture test Inspection(RFI Inspection
No
ns inspection(RFI inspection(DATE) NO) (DATE)
NO )

NA S-241 1 3263 1/19/2023 3295 24-Jan-23

NA S-242 1 3263 1/19/2023 3295 24-Jan-23


TNRTNG-1,12"MLV-3
1 PRECAST FOUNDATION @
KM 178
NA S-243 1 3263 1/19/2023 3295 24-Jan-23

NA S-244 1 3263 1/19/2023 3295 24-Jan-23

NA SL-151 1 3264 1/28/2023

NA SL-152 1 3264 1/28/2023


TNJ-1,30"MLV-3 @KM 178
2
NA SL-153 1 3264 1/28/2023

NA SL-154 1 3264 1/28/2023

Total 8
REMARKS " RFI CLOED ERALY AND INPECTION DONE 28-01-2023