Project: KG-1 SHEET NO : 1
Element: Sedimentation wall DESIGNER : Nalin
DATE : 15/02/2005
ref Calculation Results
1 Concrete Lateral pressure Calculation.
[
Pmax =D [ C1 √ R ]+ D C2 K ( √ H−C 1 √ R ) ] OR Pmax DH
Whichever is the smaller.
a. Formwork vertical height , H= 2.21 m
b. Average rate of concreting , R= 1 m/Hr
c. Temperature of concreting at the time of placing, t= 24 centi.
d. Type of cement C2,= 0.3
e. Density of concrete, D= 25 KN/m3
f. Coefficient of formwork of wall, C1 = 1
Pmax = 31.6825 KN/m2 OR Pmax =Dh = 55.25 KN/m2
( )
2
36
Where, K= 0.81 K=
t+16
The maximum concrete lateral Pressure= 31.68 KN/m2
2 Concret Lateral pressure Distribution
3 Tie Rod Calclation
Load Calculation
F=( P max × A×F s 1 + F c ×F s2 )
Fs1 = 1.5
Where Fs1, Fs2- Safety factors Fs2 = 1.4
Fc- Compaction Load, Cosider 6KN
PROJECT : SHEET NO :
ELEMENT : DATE :
reference Calculation
T18, Tie Rod diameter 14.93mm and Net Area, A = 174 mm2
Use G 43 Steek, Ps = 215 N/mm2
Let Tie Rod Spacings @ 600mm at 450mm height P1 = 31.7 KN/m2
F1 = 23.4 KN Spacing = 0.6 m
Tie Rod Spacings @ 600mm at 1050mm height P2 = 29.3 KN/m2
F2 = 24.2 KN Spacing = 0.6 m
Tie Rod Spacings @ 1200mm at 1650mm height P3 = 15.9 KN/m2
F3 = 25.6 KN Spacing = 1.2 m
Tie Rod Spacings @ 1200mm at 2250mm height P3 = 2.5 KN/m2
F3 = 10.0 KN Spacing = 1.2 m
Fallowable = Ps* A = 37.41 KN > F1,F2,F3,F4
It is OK.