.Section-1 General
.Section-1 General
TABLE OF CONTENT
1/1.2 Site offices for the Engineer and the Contractor shall be erected on a site
proposed by the contractor and approved by Roads & Transport Authority
and as shown in the Drawings. No Contractor’s plant and workshops will
be permitted within this compound.
1/1.3 The Contractor shall construct suitable entry and exit roads to and within
the compound and provide a covered parking area as specified in
Appendix-C. The Contractor shall take all necessary precautions to avoid
storm water flooding within the compound and accesses.
1/1.4 The Engineer’s office shall be erected and fully equipped to the
satisfaction of the Engineer.
1/1.5 Within one month after the Completion of the Whole of the Works and in
accordance with the provisions of Clause 1/2.1 the whole area of the
compound shall be reinstated to its original condition and all rubbish and
refuse removed.
1/1.6 The Contractor’s proposed access routes to and within the site shall be
provided and maintained as agreed with the Engineer. The Engineer may
at any time withdraw his approval for the use of any route and may order
such widening, strengthening or repair work as he considers necessary.
1/1.7 The Contractor shall employ at his own cost watchmen for the security of
the site establishment.
1/2.2 The Contractor shall retain on site for the exclusive use of the Engineer all
codes and standards referred to in the Specification which shall remain in
the custody of the Engineer for his exclusive use until completion of the
whole of the works but shall remain the property of the Contractor.
1/2.3 All Keys for the Engineer’s site offices shall be held by the Engineer until
such offices are removed.
1/2.4 The Contractor shall, at his own cost, provide the Engineer and his staff
with daily cleaning attendance and two full time for serving refreshments,
car cleaning etc.
1/3.2 The Contractor shall be responsible for the security of the site and the
safety of public and adjoining property and shall be liable for any claims
arising from loss or damage suffered. He shall employ watchmen for this
purpose.
1/3.4 The Contractor shall confine his apparatus, the storage of materials and
the operations of his workmen to the limits indicated by law, ordinances,
permits or direction of the Engineer. The Contractor shall erect temporary
fences as required by the Engineer. The site boundary lines shall be to the
approval of the Engineer.
1/3.5 The Contractor shall provide and maintain water, electricity and power
required for the works including that required by the Sub-Contractors. Pay
all charges and bear all costs for the necessary temporary installation
including pipework, pumps, water tankers, storage tanks, generating
equipment, etc. and remove on completion and make good all work
disturbed.
1/5.4 The Contractor shall also provide all assistance as required by the
Engineer for the measurement of the works for monthly valuation, Monthly
Laboratory Report and for the final payment certificate and also for
recording the progress of the works.
1/5.5 The Contractor shall be responsible for all follow up and co-ordination with
all service authorities (Electricity, Water, Drainage, Street Lighting,
Telephone, Horticulture, etc.).
1/5.6 The Contractor shall provide subject to the approval of the Engineer,
qualified and sufficient number of the Engineers, Quantity Surveyors,
Supervisors, Employees and skilled and non-skilled workmen for his
supervision of the works and site administration.
1/5.7 The Contractor shall provide all unskilled labour and all necessary tools as
directed by the Engineer.
1/5.8 If at any time before the commencement or during the progress of the
work, the Engineer decides that for the proper execution of a specified part
of the works, shop drawings are necessary, these drawings shall be
prepared by the Contractor and submitted to the Engineer for approval
according to sub-section 1/21. Such drawings must be provided at least
14 days prior to the commencement of the relevant work on site.
The Contractor shall not proceed with the above mentioned work until
these shop drawings are approved by the Engineer. The Contractor shall
not be entitled to any extra payment or extension of time for the
preparation of the shop drawings.
1/7.2 The Contractor shall provide the Engineer with all referenced ASTM, BS
Standards or any other standard indicated or referred to within the testing
requirements of the Contract Specifications.
1/7.3 At least 24 hours notice shall be given to DCL before any tests are to be
carried out.
1/7.4 The contractor must make due allowance for the time required for any
testing within his planning and program.
1/8.2 The Contractor shall in accordance with the Conditions of Contract, submit
a comprehensive plant schedule which shall include the proposed dates of
arrival or establishment on site for each major item. Plant shall not be
brought to or removed from site without prior approval of the Engineer.
1/8.3 In addition to the Critical Path Programme, the Contractor shall if required
by the Engineer provide a detailed bar chart schedule to be used by the
Engineer for monitoring the progress of works.
1/8.4 Furthermore, the contractor shall submit to the Engineer a daily work
Programme showing the activities to be undertaken for the day including
laboratory tests and survey checks at least 1 day in advance.
1/8.5 A monthly progress and material testing reports shall be submitted to RTA
1/8.6 The Contractor has to submit to the Engineer an updated weekly or bi-
weekly progress report based on the approved Clause 14 Programme
using the actual dates and estimated % age completed for each activity.
1/8.7 The contractor is not allowed to give priority in the program for the areas
that have physical obstructions and he has to start the construction for the
open areas.
1/8.8 If the Contractor failed, due to lack or poor details, to get the approval of
the Engineer and RTA on the submitted programme within a period of 90
days from the commencement date of the project, the Contractor's Monthly
Payments may be reduced or completely stopped.
1/9.2 The Contractor is responsible for all the setting out of line and levels of the
Works and shall employ adequate qualified staff to carry this out.
1/9.3 Before the commencement of the Works, the Contractor will be supplied
with the information necessary to establish the lines and levels of the
Works. The engineer has to show on the drawings all the survey markers
established but can give no warranty for their existence at the start of the
Contract nor will accept responsibility for replacing any survey markers
found to be missing. Where survey markers have been established by the
Engineer, the Contractor shall check the accuracy of their position and
level and shall immediately notify the Engineer of any discrepancies.
However, it is the Contractor’s sole responsibility to coordinate with Dubai
Municipality Planning & Survey Department and follow their regulations to
get the values (E, N & levels) for sufficient numbers of survey stations
within or near the work site.
1/9.4 All setting out throughout the Works must be related to the Dubai
Municipality Datum Levels. Any Temporary Bench Mark (T.B.M.) to be
fixed on the site shall be tied into the Dubai Municipality Datum.
1/9.5 The Contractor shall, as soon as practicable, supply the Engineer with
records in approved form relating to all reference pegs and bench marks
and shall keep such records up to date by formal notice to the Engineer.
1/9.6 All survey reference pegs shall be carefully preserved except where
construction requires their removal, and before such removal, the approval
1/9.7 Before commencing work on any section of the Works, the Contractor shall
survey and level the original ground surface and shall prepare plans and
cross-sections accordingly. These shall, when finally agreed, be signed by
the Engineer and Contractor as truly representing the configuration of the
areas in question before the commencement of the Work. The preparation
of the cross-section drawings shall comply with Clause 1/21.
1/9.8 All setting out shall be approved in writing by the Engineer before work
may commence. The centerlines are to be checked by the Dubai
Municipality Survey Section and approved by the Engineer.
1/9.9 When necessary the Contractor shall provide at his expense sufficient and
approved templates for the purpose of controlling the finished shape of
certain work. The templates will be in accordance with the specifications
and drawings where such are provided. All templates must be approved
and shall be maintained in good order to provide the section required for
the entire works. Templates may be checked from time and any
deficiencies noted shall be rectified immediately. The Contractor shall also
supply straight edges and lines when required to control the work.
1/9.10 The Engineer will, if he deems it necessary, revise the line or grade and
will require the Contractor to adjust the stake-out accordingly.
1/9.11 Where directed by the Engineer, the Contractor shall take such levels and
dimensions as may be required for the purpose of measurement prior to
disturbance of the ground. These shall be agreed between the Contractor
and the Engineer before any surface is disturbed or covered up.
1/9.12 Any change of the ground elevation resulting from compaction or other
works provided for in the Contract Documents shall be deemed included in
such works and paid for within the tender prices listed in the Bill of
Quantities. The Contractor shall consequently in no way be entitled to any
additional payment or claim whatsoever.
1/10.2 Project Sign Boards shall be signwritten by a skilled signwriter or any other
methods approved by the Engineer and RTA to show the details described
in the Contract plus any other relevant details to the approval of the Roads
& Transport Authority and the Engineer.
1/10.3 Within one month of completion of the (Whole of the) Works, and after the
works are handed over to the client and respective services authorities.
The Project Sign Boards shall be dismantled and removed by the
Contractor.
1/11.2 The Contractor shall provide the Engineer with one set of the monthly
progress photographs of digital format with dates marked / imprinted on it.
1/11.4 The Copyright of all photographs shall be vested in the Employer and the
negatives and prints shall be delivered to the Engineer within 4 days of
exposure. The photographs shall not be used for any other purpose
whatsoever without the Employer’s approval.
1/12.2 All materials and equipment specified in the contract documents which are
to be incorporated in the works must be obtained from or through a Dubai
Emirate supplier and or manufacturer who must be registered and licensed
by the Dubai Municipality. If such specified materials or equipment is not
available from the Dubai Emirate market then any other source is
acceptable subjected to the conditions set in the subsections below.
1/12.3 Materials delivered to the Site for the purpose of the Works, shall be
accompanied by a ‘Certificate of Guarantee” signed by the authorised
representative of the manufacturer. Such Certificate shall state that the
materials specifications and test results are in compliance with the
specified requirement of the pertinent designations of the most recent
edition of ASTM or any other approved equivalent National Standard
unless otherwise directed. Falsification of such Certificates, Materials,
Specifications or Test Results shall be just cause for the rejection of the
materials.
1/12.4 The borrow pit location if not designated in the Contract Documents shall
be approved by the Roads & Transport Authority. The Contractor shall
exercise a continuous quality control upon the extracted material to confirm
its suitability for use.
1/12.5 The Contractor shall select rock quarries and shall submit laboratory tested
and accepted samples, within two months before their use, in order for the
Engineer to determine their conformity with the related specifications. The
Contractor shall exercise a continuous quality control upon the extracted
1/12.6 The Engineer’s acceptance of the materials does not relieve the Contractor
of his total responsibility to carry on with additional investigations in order
to obtain and supply during the progress of the works uniform material
conforming to the Specifications.
1/12.7 The Contractor shall be responsible for payment of royalties, if any, arising
due to obtaining of materials for use in the Works. No separate payment
will be made by the Employer as a royalty for materials for use in the
Works.
The Contractor shall provide for the exclusive use of the Engineer copies
of each and any codes of practice, international standards, test methods
etc. relevant to the works. In addition the Contractor shall retain on site for
the use of the Engineer all manufacturers literature relating to all the
products to be used in the works, current BSI Handbook No. 3 and the
Manufacturers installations instructions for all relevant products, materials
components and installations.
1/12.10 The Contractor will be required to produce documentary evidence that all
materials which are not available in the local market and which have to be
imported have been ordered sufficiently in advance to ensure that no delay
to the works occur. As soon as orders have been placed, copies of such
orders shall be submitted to the Engineer. The Contractor shall be
responsible for delays as a consequence of late ordering.
1/12.11 Should the Engineer discover in the Works any materials other than those
approved, he may order their removal from the site and replacement with
approved materials at no cost to the Employer and in compliance with
Standard Specifications.
1/12.12 All specified materials incorporated in the Works shall be fixed or applied
strictly in accordance with the manufacturer’s printed instructions.
1/12.13 The Bills of Quantities shall NOT be used as a basis for ordering materials
and the Contractor is entirely responsible for assessing the quantities of
materials to be ordered.
1/12.15 The Contractor shall erect and maintain ample temporary and weather
proof sheds for proper storage and protection of his own and sub-
contractor’s materials. Cement and other perishable material shall have
floors raised 150mm off the ground. The Contractor shall clear away on
completion and make good all areas disturbed.
1/12.17 If judged necessary by the Engineer, the samples shall be tested for
compliance at DCL in accordance with Appendix A1 or in a laboratory
accredited in accordance with Appendix A2 of this Specification and Dubai
Municipality Administrative Decision No. 160:2000.
1/12.18 All materials and equipment specified in the Contract Documents which
are to be incorporated into the Works must be obtained from or through a
Dubai Emirate Supplier and or Manufacturer who must be registered and
licensed by the Dubai Municipality. If such specified materials or
equipment is not available from the Dubai Emirate then any source is
acceptable subject to approval from the Engineer and RTA.
1/12.19 Approval of a source does not mean that all the materials in the source is
approved. No source of supply shall be changed without Engineer's prior
approval. Approved samples shall be retained on site for comparison with
products and materials used in the works and shall be removed when no
longer required by the Engineer.
1/12.20 Any material requiring certification as per RTA regulations shall not be
used unless certified by DM-Dubai Central Laboratory or by an accredited
certification body approved by DMDCL.
1/13.2 The Contractor shall give the Engineer details of the source of materials to
be incorporated into the Works. Reasonable notice must be given by the
Contractor to allow the Engineer to carry out such tests and enquiries as
may be appropriate before giving approval.
1/13.4 Where the approval of the Engineer is required under this specification,
such approval shall not in anyway relieve the Contractor of his duties or
responsibilities under the Contract.
1/14.2 The Contractor shall take into account the current laws and Latest
recommended measures regarding the safety of service lines, together
with any amendment or additions thereto. The Contractor shall include in
his tender for anything in these laws considered to have a monetary value.
1/14.3 The cost of locating or verifying the location of existing services, liaison
with the various Service Authorities and complying with the above shall be
borne by the Contractor unless provided for elsewhere in the Contract.
1/14.4 Before opening the ground for any purpose, the Contractor must notify all
1/14.5 Notice of Intent” shall be circulated to all concerned parties including the
following: Roads & Transport Authority Roads Department Dubai Electricity
and Water Authority Emirates Telecommunication Corporation. Roads &
Transport Authority Street Lighting Section Dubai Municipality Drainage
and Irrigation Department Roads & Transport Authority Horticulture
Section Consultants for Water, Electricity and Drainage Departments.
1/14.6 Drawings and notices shall be sent in duplicate one of which shall be
retained by the addressee and the other returned to the sender duly
marked to show underground services. “Notice of Intent” will be given 14
(fourteen) days in advance of the proposed Works. In the event that the
work is not started within 8 (eight) weeks of the date of the “Notice of
Intent”, it will be deemed to have lapsed. A further Notice of Intent will then
be submitted.
1/14.7 The Contractor shall furnish copies of the above Notices of Intent to the
Engineer. The Contractor shall acquaint himself with the position of all
existing services and must obtain clearance from the relevant authority
before commencing any work in a particular area. Written evidence of such
clearance shall be provided to the Engineer by the Contractor. If any
underground service is encountered unexpectedly, excavation shall cease,
and the Engineer’s Representative shall be notified immediately.
Emergency work, as necessary, shall be put in hand without delay and
without prejudice to the indemnity of the Employer.
1/14.8 The Contractor shall prepare records and CAD drawings showing position,
levels and types of each existing service including manholes, joint boxes
and inspection chambers etc. All record drawings shall be prepared using
a Computer Aided Drafting program approved by the Engineer.
1/14.9 The Contractor shall take any and all measures reasonably required by
any public or concerned Authority for the support and full protection of all
mains, pipes, cables and other apparatus during the progress of the
Works, and shall construct and provide to the satisfaction of the Authority
concerned, all works necessary for the prevention of damage or
interruption of services.
1/14.10 The Contractor shall familiarize himself and all his employees with the
dangers of working in or near live sewers and at sewage treatment works;
in particular the risks of physical injury from the exposure to poisonous
gases, of bacterial infection from contact with sewage and of exposure to
poisonous gases, which may be given off by the sewage. Hydrogen
sulphide and methane are prevalent in the sewers in Dubai, and can exist
in excavations where septic sewage from collection tanks is allowed to
seep into groundwater. In the context of this clause the term sewer
includes irrigation mains and drains carrying ground water and/or storm
water.
1/14.11 The Contractor shall, at all times during the progress of the Works, afford
facilities to properly accredited agents of any Public or Utility Authority for
access to all or any of their apparatus situated in or under the site, as may
be necessary for inspecting, reporting, maintaining, removing, renewing or
altering such apparatus in connection with the construction of the Works or
any other purpose whatsoever.
1/14.12 The Contractor will be fully responsible for ensuring observance of the
above regulations of his sub-contractors.
1/14.13 Where any utility or service works are to be constructed under a separate
contract by the Employer within the Site and concurrent with the execution
of the Works, the Contractor shall cooperate with the other Contractor and
shall coordinate his construction operations to avoid interference with the
other Contractor’s operations.
1/14.14The Contractor shall prepare and furnish all necessary shop drawings of
the works required to complete the adjustment of apparatus to finished
grade or specified level. The drawings must be approved by the concerned
Utility Authorities and the Engineer prior to commencement of any work at
the site. Measurement shall be for each utility facility adjusted to finish
grade or level approved by the Engineer.
The Contractor must allow in his rates for services installations for the
production of combined service drawings covering the whole of the
Contract area. The drawings must show both existing services located by
trial pits and coordinated by survey and all proposed new services. The
drawings are to identify interface problems prior to production of working
drawings.
1/14.15 The Contractor shall prepare CADD shop drawings for utility protection
work and obtain the approval of the appropriate Authority and Engineer
before commencing with construction.
1/14.16 The Contractor shall relocate certain utilities to service reservation areas
as specified in the Contract. This work may only include the construction of
necessary protective housing (e.g. box culverts, slabs, concrete encased
sleeves etc.) in the service reservation areas for utility lines to be
relocated, or this work may include necessary protective housing as
described above and, in addition the relocation of specific utility lines to the
service reservation areas. In both cases the Contractor shall complete the
necessary survey to establish the lines and levels, prepare shop drawings
and submit them to the Engineer for his review and approval. The
Contractor shall obtain approval from the concerned Authority before
commencing this work.
1/14.17 Any public or private service for water, electricity, drainage, etc. affected
by the Works shall not be interrupted without the written permission of the
Engineer. Such permission will be withheld until suitable approved
permanent or temporary alternative service has been provided by the
Contractor or by the owner of the utility or his agents.
1/14.18 For temporary traffic diversions as may be required for the construction of
road crossings, full liaison with the Roads & Transport Authority and Dubai
Police shall be required and the requirements of Clause 1/16 and 1/17
complied with.
1/14.19 Due allowance (s) must be given by the Contractor when preparing the
Programme of Works to comply with this Clause 1/14.
1/14.20 The contractor shall comply with the latest specifications set by various
services authorities for the provision of new services and/or locating,
relocating, protecting, diverting of the existing services.
1/14.21 The contractor shall survey of all the existing services corridors in the
vicinity of the project limits and submit it to the Engineer for approval, in
particular, the gas pipelines reservation which may run along the boundary
of the project if any. No temporary road works are to be undertaken over
the gas pipelines or below DEWA overhead power lines without obtaining
an NOC from the proper service authority. The use of heavy equipment
shall be limited to where no impact can be caused to the gas pipeline or
other services.
1/15.2 The responsibility lies with the Contractor for the repair and return to the
previous condition of items to which the Contractor’s works have caused
damage. Also, also, it is the responsibility of the contractor to tie-in the new
footpath if any, to the existing footpath, smoothly and neatly and to the
satisfaction of the Engineer.
1/15.3 The Contractor shall not be permitted to use earth works of already
executed roads. Also, the contractor shall extend all ducts out of the
asphalt works wherever required and to the satisfaction of the Engineer.
1/15.6 The Contractor shall furnish and place fresh or brackish water at his own
expense for dust control when and where construction operations require it
and at locations where specifically directed by the Engineer due to
conditions created by the Contractor or his construction operations.
1/15.7 Existing roads, accesses to houses, buildings, etc., and any new roads,
whether part of the Works or not, which are being used by the Contractor’s
constructional traffic shall be kept clean and clear of all dirt, mud and
material dropped from vehicles or from tyres and any damage caused shall
be repaired at the Contractor’s expense. The Contractor shall provide,
maintain and use as directed by the Engineer, suitable equipment
including mechanical road sweepers solely for this purpose throughout the
course of the works.
1/16.2 The Contractor shall, after consultation with Engineer and all concerned
departments in RTA, prepare a scheme of traffic management for carrying
out the works. Such proposals shall be submitted to the Engineer for his
written approval not less than 30 days before the planned implementation
of each proposal. Prior to commencing any individual diversion or traffic
control the Contractor shall provide to the Engineer details of his overall
scheme of traffic control or diversions for the entire project giving his
programme of diversions etc. All diversions must be approved by the
Traffic Police and Roads & Transport Authority Roads Department prior to
implementation.
1/16.3 The Contractor shall not commence any work which affects the public
highway until all approved traffic safety measures conforming to RTA
Standards are fully operational to the satisfaction of the Engineer.
1/16.6 The Contractor shall be entirely responsible for complying with the
requirements of and coordinating with the Dubai Police Traffic Department
and Roads & Transport Authority Roads Department in relation to the
above.
1/16.7 Traffic diversion is a lump sum item and will be paid as per the Contract
BOQ without any possibility for any claims whosoever due to change of the
scope. The Contractor has to consider this work and any expected
requirements as part of the Contractor's risks.
1/17.3 The contractor is fully responsible for diversions maintenance and he shall
undertake whatever is necessary to maintain all diversions fully operational
i.e. 24 hours a day and over the entire period of the project.
1/18.3 The Contractor shall make arrangements for periodic inspection by the
local fire authority and shall co-operate with said authority to promptly carry
out their recommendations at his own expense.
The Contract documents are complementary and represent one unit and
any requirements mentioned in any part of the documents are considered
as mentioned in all other parts. If there is any discrepancy between the
different parts of the Contractor documents, the Engineer is the sole party
who has the authority to interpret and clarify the action to be taken and this
will not, at any case, entitle the Contractor for any additional cost or time
extension or whatsoever.
1/21.1 For any work or part thereof as requested, the Contractor shall supply four
(4) copies of shop/working drawings for approval by the Engineer. All
working drawings shall be A1 size folded to A4 size. An extra digital copy
of the working drawings should be submitted on a CD for easy future
reference or for further extra copy production.
1/21.2 For all above mentioned drawings, the Engineer shall return to the
Contractor one (1) copy with any necessary corrections for resubmittal or
marked with approval.
1/21.3 At the end of the project, the Contractor shall submit to the engineer 2 sets
of printed copies and one digital copy on a CD for all the approved shop
drawings.
1/21.4 In additions, the Contractor shall provide the Engineer with all information,
scale drawings and every assistance so that the Engineer can prepare
drawings of work as executed to form a complete record of the finished
work.
1/21.5 The Contractor shall record the exact location of all services apparatus
excavated during the works and shall submit drawings to the Engineer
showing such information for incorporation by the Engineer into the Record
Drawings.
1/21.6 The cost related to the production of the drawings, either during
construction or at the time of delivery of the final account (for which 1
negative + 3 copies of all attachments are necessary), shall be borne
directly by the Contractor, and no separate payment shall be in anyway
considered.
1/21.7 Within sixty (60) days of the date of field staking, the Contractor shall
submit to the Engineer for his approval the plotting of the original and final
earthwork cross-sections, together with the area and volumetric earthwork
computations.
1/21.8 The Contractor’s cross-section shall be on transparent cross-section
sheets for print reproduction. CD’s containing the drawings data are to be
supplied to the Engineer in the approved digital format.
The exact locations with dimensions of existing and new service ducts,
cables, pipes, etc shall be clearly shown on the drawings. All negatives of
record drawings prepared by the Engineer shall be dated and signed by
the Contractor and the Engineer as being a true record of the Works ‘as-
built”. The contractor shall also provide to the engineer all data and
drawings on CD’s in the approved digital format.
The final payment certificate will not be issued to the contractor until all the
above have been received by the Engineer.
1/24 PUBLICITY
1/24.1 The Contractor or any agents or servants in his employ shall not give any
information concerning Works for publication in the press or on radio,
television or cinema screen or elsewhere without the written approval of
the Engineer.
1/24.2 No advertisements shall be erected within the Site by the Contractor or any
subcontractor without written approval of the Employer. Should any
advertisement be erected within the site without such prior approval the
Engineer may instruct the Contractor to remove it forthwith. Should such
1/24.3 All advertisement within the site shall be removed within one month of the
date of Certificate of Substantial Completion of the Works, unless the
Employer agrees in writing for any advertisement to remain for a further period.
1/25.2 On completion the entire site within the Right of Way are to be cleared of
all construction materials and temporary buildings, etc. to the satisfaction
of the Engineer.
1/29.1 GENERAL
equipment necessary for the construction of each phase of the work and it
must be on the site, inspected and approved by the Engineer prior to the
commencement of the particular phase of work. Any plant or equipment of
portion thereof, which becomes worn or defective shall be immediately
repaired or replaced to the satisfaction of the Engineer.
Pull-type steel rollers shall have not less than one and two-tenths
(1.2) meter effective width of roller and shall be designed and
constructed so that the weight per linear centimeter of roller can be
varied from thirty five and seven-tenths (35.7) kilograms to at least
fifty-three and six-tenths (53.6) kilograms.
Two-axle tandem steel rollers shall weigh not less than eight (8)
tones or more than twelve (12) tones and shall have a weight per
centimeter width of roll between 35 Kg and 70 Kg.
Three axle tandem steel rollers shall weigh not less than eleven
(11) tons. Three axle tandem roller shall be so constructed that the
roller, when locked in position for all treads to be in one plane, are
held with a rigidity which will satisfy the following test under full
load; with the weight of the roller supported on the central roller, the
tread of the central roller shall not be more than three (3)
millimeters above the plane tangent to the tread of the end roller.
With the weight of the roller supported on the end rollers, the tread
of the central roller shall not be more than six (6) millimeters below
the plane tangent to the treads of the end roller.
i) Hauling Equipment:
Hauling equipment for aggregate shall consist of vehicles having dump
bodies suitable for dumping materials in a windrow or in spreader boxes.
The bodies shall be so constructed that their volume measurement can be
accurately determined. They shall be so constructed and maintained to
prevent loss of materials during hauling operations.
The equipment shall be provided with dump controls that can be operated
from the driver’s seat. The bodies of hauling equipment using public roads
shall be fitted with tarpaulins to prevent the nuisance of spillage.
approved means.
The heating device shall be constructed so that it will prevent the direct
flame from a burner from striking the surface of the coils, pipes or jackets
through which the bituminous material is circulated. The heating device shall
not be operated in a manner that will injure the bituminous material.
Tankers or trucks received on the work which have defective coils, or from
which the coils have been removed, will be rejected by the Engineer unless
some satisfactory auxiliary means can be provided by the Contractor for the
heating of the bituminous material without the introduction or moisture. The
use of any equipment for the agitation of bituminous material to aid in
heating will be prohibited if it injures or in any way changes the
characteristics of the bituminous material or introduces free steam or
moisture into the tank containing the bituminous material.
The power unit and pump distribution systems shall have a capacity of not
less than nine hundred fifty (950) litres per minute, shall be equipped with a
by-pass into the supply tank and shall be capable of distributing a uniform
and constant flow of bituminous material through all nozzles at a pressure
between one and one quarter (1.25) and three and one-half (3.5) kilograms
per square centimeter.
All distributors shall be calibrated and checked before being used on the
work. The calibration of the tank will be done by the Contractor in the
presence of the Engineer by the method prescribed by the manufacturer
and/or directed by the Engineer.
The operation of the distributor will be checked by the Engineer the first time
it is used and as often as he deems it necessary thereafter, and when the
operation is found to be satisfactory, a new certificate will be issued.
The proportioning devices for the bituminous materials and aggregates shall
be so synchronized that proper proportioning will be obtained at all times.
All equipment shall meet the approval of the Engineer, shall be kept in good
working condition, shall meet the requirements herein specified and shall be
of sufficient capacity to produce and process not less than eighty (80) tons of
mixed material per hour. All plants used by the Contractor for the preparation
of bituminous mixes and (Plant Mix) prepared mixes shall conform to all the
requirements of these Specifications except that scale requirements shall
apply only where weight proportioning is used, and in addition batch mixing
plants and continuous plants shall conform to the special requirements of
these specifications.
Uniformity:
Scale:
Scales for any weight box or hopper may be of either the beam or springless
dial type and shall be of a standard make and design, accurate to one (1)
percent of the maximum load that may be required.
When scales are of the beam type, there shall be a separate beam for each
size of aggregate. There shall be provided a “Tell-tale Dial” that will start to
function when the load being applied is within fifty (50) kilograms of that
desired. Sufficient vertical movement shall be provided for the beams to
permit the telltale dial to function properly. Each beam shall have a
locking device so designed and located that the beam can easily be
suspended or thrown into action.
Dial scales shall be springless, of a standard make, and of such size that the
numeral on the dial can be read at a distance of at least (8) metres. The dial
shall be of a compounding type having full complement of index. Pointers so
placed as to give excessive parallax errors shall not be used. The scales
shall be substantially constructed, and those that easily get out of
adjustment shall be replaced with other makes when so ordered. All dials
shall be so located as to be plainly visible to the operator at all times.
on hand not less than ten (10), twenty-five (25) kilograms weights for testing
the scales.
Provision shall be made for measuring and sampling storage tanks. Storage
tanks shall have sufficient capacity to provide for continuous operation. The
storage tanks shall be calibrated and equipped with a device whereby the
Engineer may determine the amount of asphalt on hand at any time.
Feeder for Drier: The plant shall be provided with accurate mechanical
means for uniformly feeding the aggregate into the drier so that uniform
production and uniform temperature will be obtained. A separate mechanical
feeder equipped with an adjustable gate opening shall be provided for each
individual aggregate being combined to produce the total aggregate. The
feeders and gate shall be so constructed and equipped that a continuous
and uniform flow of each material will be ensured. They shall also be
installed in such a manner as to be readily accessible for calibrating at all
times.
Drier: The plant shall include a drier or driers which continuously agitate the
aggregate during the heating and drying process. The drier shall be capable
of drying and heating the mineral aggregate to specification requirements.
The burners shall be of such capacity, and they shall be so constructed and
operated that complete combustion of the fuel is obtained.
Screens: Plant screens, capable of screening all aggregates to the specified
sizes and proportions and having normal capacities in excess of the full
capacity of the mixer, shall be provided.
Bins: The plant shall include storage bins (cold & hot) of sufficient capacity to
supply the mixer when it is operating at full capacity. Bins shall be arranged
to ensure separate and adequate storage of appropriate fractions of the
mineral aggregates. Separate dry storage shall be provided for Portland
Cement, hydrated lime, or other similar material when used and the plant
shall be equipped to feed such material into the mixer.
Each bin shall be provided with overflow pipes, of such size and at such
location as to prevent backing up of material into other compartments or
bins. Each compartment shall be provided with its individual outlet gate,
constructed so that when closed there shall be no leakage. The gate shall
cut off quickly and completely. Bins shall be so constructed that samples can
be readily obtained. Bins shall be equipped with adequate tell-tale devices to
indicate the position of the aggregates in the bins at the lower quarter point.
The minimum number of bins shall include at least one bin for each different
stockpile of material being used. Intermixing of material from different
stockpiles in one bin or on the ground shall not be permitted.
The plant shall also be equipped with either an approved dial-scale mercury-
actuated thermometer, an electric pyrometer, or other approved
thermometric instrument so placed at the discharge chute of the drier as to
register automatically or indicate the temperature of the heated aggregates.
All plants whether continuous or batch type shall be equipped with two
recording thermometers. These instruments shall be provided with dust-
proof cases, long leads, and automatic recording mechanism capable of
recording the desired temperature for a period of twenty-four (24) hours on a
chart not less than twenty (20) centimeters in diameter, or on a continuous
sheet. The chart for either type shall be graduated in hours, minutes, and
degrees of temperature. The maximum time graduation shall be fifteen (15)
minutes and the maximum temperature graduation shall be five (5) degrees
centigrade. Hours on the chart shall be designated as a.m or p.m.
They shall be located in a manner to provide easy access to the case and
chart. The bulb of one instrument shall be installed in the hot asphalt line as
close as is practicable to the spray bar discharge, the bulb of the second
recording thermometer shall be installed in the hot aggregate bin which
contains the fine aggregate. The bulb shall be located where the hot
materials will flow over it during the proportioning operation and shall not be
located near the corners of the bin or at locations where the material will
collect or pack around it.
The Engineer reserves the right to pass judgment upon the efficiency of
thermometric instruments.
Control of Mixing Time: The plant shall be equipped with positive means to
govern the time of mixing and to maintain a constant time unless changed by
order of the Engineer.
All gears, pulleys, chains, sprockets, and other dangerous moving parts shall
be thoroughly guarded and protected. Ample and unobstructed space shall
be provided on the mixing platform. A clear and unobstructed passage shall
be maintained at all times in and around the truck loading area. The area
shall be kept free from dropping from the mixing platform.
The equipment shall include a means for accurately weighing each size of
aggregate in a weigh box or hopper suspended on scales and of ample size
to hold a full batch without hand raking or running over. The gate shall close
tightly so that no material is allowed to leak into the mixer while batch is
being weighed. Asphalt plants shall meet requirements in accordance with
ASTMD995 & ASTMD290.
The bituminous material bucket, its discharge valve or valves and spray bar
shall be adequately heated. Steam jackets, if used, shall be efficiently
drained and all connections shall be so constructed that they will not
interfere with the efficient operation of the bituminous scales.
The capacity of the bituminous material bucket shall be at least fifteen (15)
percent in excess of the weight of bituminous material required in any batch.
The plant shall have an adequately heated quick-acting, nondrip, charging
valve located directly over the bituminous material bucket.
The indicator dial shall have a capacity of at least fifteen (15) percent in
excess of the quantity of bituminous material used in a batch.
The dial shall be in full view of the mixer operator. The flow of bituminous
material shall be automatically controlled so that it will begin when the dry
mixing period is over and all of the bituminous material required for one
batch will be discharged in not more than fifteen (15) seconds after the flow
has started.
The section of the bituminous line between the charging valve and the spray
bar shall be provided with a valve and outlet for checking the metering
device.
The clearance of blades from all fixed and moving parts shall not exceed two
and one-half (2.5) centimeters unless the maximum diameter of the
aggregate in the mix exceeds three (3) centimeters, in which case the
clearance shall not exceed three and eight-tenths (3.8) centimeters.
Control of Mixing Time: The mixer shall be equipped with an accurate time
lock to control the operations of a complete mixing cycle. It shall lock the
weigh box gate after the charging of the mixer until the closing of the mixer
at the completion of the cycle. It shall lock the bituminous material bucket
throughout the dry mixing period and shall lock the mixer gate throughout
the dry and wet mixing periods.
The dry mixing period is defined as the interval of the time between the
opening of the weigh box gate and the start of introduction of bituminous
material. The wet mixing period is the interval of time between the start of
introduction of bituminous material and the opening of the mixer gate.
The control of the timing shall be flexible and capable of being set at
intervals as necessary for mixing time throughout the total mixing cycle. A
mechanical batch counter shall be installed as a part of the timing device
and shall be so designed as to register only completely mixed batches.
Weight Calibration of Aggregate Feed: The plant shall include means for
calibration of gate opening by weighing test samples. Provisions shall be
made so that materials fed out of individual orifices may be bypassed to
individual test boxes.
The paddles shall be adjustable for angular position on the shaft and
reversible to retard the flow of the mix. The mixer shall have a
manufacturer’s plate giving the net volumetric contents of the mixer at the
several heights inscribed on a permanent gauge. Charts shall be provided
showing the rate of feed of the aggregate per minute for the aggregate being
used.
The paver shall be equipped with a distribution system to place the mixer
uniformly in front of the screed.
The automatic controls for the paver shall be automatic linkage arrangement
so that through the process of automatically adjusting the screed, the
thickness of asphaltic mixtures can be placed and finished to predetermined
grade and a uniform crown or cross-section.
The paver shall be equipped with automatic screed controls with sensors
capable of sensing grade from an outside reference line, sensing the
transverse slope of the screed, and providing the automatic signals that
operate the screed to maintain grade and transverse slope.
Manually controlled bituminous-mix pavers may be used only with the written
consent of the Engineer.
The climate of Dubai is relatively mild from November to April, and hot from May
The prevailing wind directions are from the North and West. Strong winds are
common with maximum velocities exceeding 160 Km/hr. and sand storms and
dust storms occur in the summer months.
TABLE OF CONTENT
2/1.1 This work shall consist of the removal, wholly or in part, and satisfactory
disposal of all buildings, fences, structures, abandoned pipelines, and any
other obstruction which are not designated or permitted to remain within
the clearing project limits designated on the plans. It shall also include the
salvaging of designated materials and backfilling the resulting trenches,
holes and pits.
2/2.1 Prior to starting the site clearance, the Contractor shall carry out a
thorough survey of buildings, structures, fences, trees, etc. that are to be
removed. The Engineer shall be fully informed of the results of this survey
and the amount and extent of the demolition and site clearance shall then
be agreed with the Engineer.
2/3.1 The Contractor shall in a careful manner, raze, remove and dispose of all
buildings and foundation structures, fences and other obstructions or any
portions of which are within the Right-of-Way, except utilities and those
for which other provisions have been made for removal. All
designated salvageable material shall be removed, without unnecessary
damage, in sections or pieces which may be readily transported, and shall
be stored by the Contractor at specified places within the project limits or
at designated storage areas as directed by the Engineer. All such
salvageable material shall be deemed the property of the Employer.
2/3.4 Where directed by the Engineer, the Contractor shall excavate in trench
and break out redundant pipe ducts and surrounds. Every precaution
should be taken to avoid breaking or damaging the pipes that are to be
removed and either salvaged or reused. The pipes shall be stored when
necessary so that there will be no loss or damage before relaying.
2/3.5 Trenches and pits resulting from demolition and site clearance below
ground level shall be properly cleaned out (including pumping) and filled
with suitable material and compacted in accordance with the relevant
2/3.7 Where shown on the drawings or otherwise directed by the Engineer, all
fences, walls or boundary structures to be erected or reinstated shall be
done in the same kind and form as the one it is intended to replace. The
wall, fence or boundary structure shall be made to match the remaining
existing portions. All materials and workmanship shall be in accordance
with the relevant standards and specifications contained herein.
2/4.1 Before commencing any excavation or fill, the area located within the
clearing project limits designated on the plans and drawings, shall be
cleared of all trees, stumps, roots, bushes, vegetation, debris, materials or
other obstructions.
2/4.2 Before removal of any trees or shrubs the Contractor shall obtain written
consent from Dubai Municipality Horticultural Section at least two weeks in
advance of the planned removal.
2/4.3 The Engineer's approval of any removal of trees and undergrowth must be
obtained before commencement of work. Where directed all bushes,
undergrowth, etc. shall be grubbed up and burnt or otherwise disposed of
in tips off site (Sub section 2/8). Holes left by stumps or roots shall, within
one week, be filled with suitable material, and compacted to the Engineer's
satisfaction in accordance with Specification Clause 2/17.
2/4.4.1 Ghaf Trees are a protected species in the United Arab Emirates they are
to be pruned or moved under the complete supervision and written
approval of Dubai Municipality Horticulture Section.
2/4.4.2 Trees may only be moved if they represent an absolute obstruction to the
works and no diversion of services or the road alignment is possible.
i) Mobile crane of sufficient capacity with slings etc. to enable the lifting of
the particular trees in question.
ii) Excavator to carry out excavation prior to tree removal.
iii)Low Bed trailer and tractor or similar to transport the removed
tree/trees to either Mushrif Park or the Dubai terminal of the
Dubai to Al Ain Road, whichever is the nearer to the site.
2/4.4.4 The above plant will be required at both the original and new tree sites.
The Horticulture Department may also require the provision of a supply of
potable water for irrigation of the tree prior to its removal.
2/5.1 Attention is directed to the Contractor's obligations under law and under
this Contract with regard to damage, particularly with regard to protection
of property, plants and landscape and to responsibility for damage claims.
2/5.3 The form of protection for vegetation within the site shall be of a type and
standard approved by the Dubai Municipality Horticultural Section.
2/6.1 All existing road signs, street name plates, gantry cantilever and like
effected by the works are to be recorded (size, dimension, condition.etc)
and carefully taken down and stored on site for reuse as directed by the
Engineer. Signs to be re-erected shall be cleaned, provided with new
fixings where necessary and the posts re-painted in accordance with the
Specifications. Redundant signs shall be transported to the stores or
depots of relevant Authorities. Any sign, street name plate or the like
damaged by the Contractor during his operation shall be repaired or
replaced at the Contractor's cost.
2/7.1 Where specified, certain materials arising from the site clearance and
excavation are to remain the property of the Employer. All fossils,
antiquities and other objects of interest or value which may be found or
uncovered on the site shall remain or become the property of the
Employer and upon discovery of such an object the Contractor shall
forthwith:
2/7.2 The Engineer will issue instructions on the procedure to be adopted which
may include conditions to permit the examination, excavation or removal
of the object by a third party.
2/8.1 Subject to the provision of Clause 27.1 of the Conditions of Contract Part I
and of the Specification, all materials arising from site clearance which are
surplus to or unsuitable (Section 2/13.3) for use in the Works shall become
the property of the Contractor and shall be disposed of by him either off the
Site to an approved tip or if directed or otherwise agreed by the Engineer
on the Site in an approved manner.
2/8.3 The Contractor has to prepare and submit to the Engineer Earth Work
Cross Section and calculate the total quantity of cut material and total
quantity of filled material.
If the filled material found more than cut material then the Engineer in
coordination with RTA will arrange to provide fill material to the project from
any of RTA running project if available. If not available, then the Contractor
can use the item of imported material.
If the cut material found more than the fill material, then the surplus material
if suitable has to be disposed to one of RTA running project as directed by
RTA. If not available the Contractor can dispose the surplus material at an
approved dumping area.
2/9.1 This work shall consist of excavating the roadway and borrow pits,
removing and satisfactorily disposing of all materials taken from within the
limits of the Work. It shall include all dewatering, excavation, shaping and
sloping as necessary for the construction, preparation and completion of all
embankments, cuttings, subgrade, shoulders, slopes, gutters, intersections,
approaches and private entrances, as directed, and in conformity to the
alignment, grades, and cross-sections shown on the plans or established
by the Engineer.
- Roadway Excavation.
- Borrow Excavation.
2/10.3 Authority to identify and define the physical characteristics which determine
the classification as "Common Excavation" and "Rock Excavation" in
accordance with the intent of the following provisions shall be vested in the
Engineer.
2/10.5 Rock Excavation - shall consist of the excavation and satisfactory disposal
(subject to Clause 2/15.3) of all unaltered and unweathered firm and rigid
igneous, metamorphic and sedimentary solid rock and boulders exceeding one
cubic metre in volume that in the opinion of the Engineer are impracticable to
remove by heavy mechanical excavating equipment (e.g. Cat.D8) or by heavy
duty hydraulic ripper, or by approved pneumatic tools.
2/10.6 Borrow Excavation - If the demand for fill material exceeds the quantity of
suitable material obtained from the necessary roadway excavation then
suitable material shall be imported to the worksite from an approved borrow pit.
The excavation, haulage and discharge of material in its final place from a
borrow pit shall be classified as Borrow Excavation.
2/11.1 All materials removed from an excavation shall be used in the formation of
the embankment, shoulders and at such other places as directed, unless it
is declared unsuitable and ordered to be sent to the disposal site by the
Engineer. No excavated material shall be wasted without written
permission from the Engineer, and when such material is to be wasted, it
shall be hauled to the approved disposal site (Clause 2/8) or as otherwise
directed by the Engineer.
Material suitable for top soil, base material, mineral aggregate or other
specified purpose, encountered in excavation, shall be reserved in
stockpile, if so directed, until it can be placed in its proper position in the
roadway during construction. When specified or designated, top soil shall
Volume 2, Part 1, General Specifications-Road Works March 2017 Page 6
7 SECTION 2 SITE CLEARANCE AND EARTHWORKS
2/11.3 During the construction of the roadway, the prepared formation shall be
maintained in such condition that it will be well drained at all times.
2/11.4 Rock, shale and other unsuitable material encountered in cuts shall be
excavated to the lateral limits and depth indicated on the plans or as
otherwise directed. Any excess breakage below the depth shown on the
plans or as otherwise directed will not be paid for. Backfill of the excess
breakage shall be approved suitable material and shall have the same
density requirements as specified by the Contract and shall be at the
expense of the Contractor. If the backfill of the excess breakage area
designated by the Engineer is to be a crushed aggregate concrete or other
special aggregate the entire cost of the backfill of the excess breakage
shall be at the expense of the Contractor. Undrained pockets shall not be
left in the surface of the rock, but they shall be treated as directed by the
Engineer.
2/11.5 All slopes, except in solid rock or other material which, in the judgment of
the Engineer, require a modified slope, shall be trimmed accurately to the
slopes shown on the cross-sections drawings, and care must be exercised
that no material shall be loosened beyond the required slopes. Side
ditches if required shall be excavated in conformity to line, grade, and
cross-section as shown on the Drawings or as directed by the Engineer.
2/11.6 In cut areas, excavation shall be for the full construction width down to
'earthworks formation level'. For a further depth of 15 cm the existing
material shall be scarified, watered as necessary, mixed and compacted to
not less than 95% of maximum dry density as determined by BS 1377 Part
4 : 1990 (Method 3.5 or 3.6, AMD 13925:2002). Field density shall be
determined by BSI BS 1377-9, AMD 17229 (2007)
If the CBR of the subgrade at the formation level does not satisfy
the minimum requirements, a minimum thickness as specified in the
drawings or as directed by the Engineer shall be removed and
replaced with an equal thickness of improved subgrade material and
compacted as described in clauses 2/16 and 2/17 below.
The Contractor shall conduct his operations in such a way that the
necessary cross-sectional measurements can be taken and agreed with the
Engineer before the backfill is placed.
2/11.11 All slopes, lines and grades shall be true, correct, and accurate and
according to those on the drawings or otherwise directed and approved by
the Engineer. The 'earthworks formation level' in cuts shall be accurate to
the authorized profile grade to plus or minus two (2) centimeters and, for
'top of improved subgrade' level, plus or minus one (1) centimeter. Where
discrepancies are found in the Work the Contractor shall make necessary
corrections.
2/11.12 The Engineer will check all or any part of the Work, as he deems
necessary, to determine conformance to the lines, grades, elevations and
cross-sections.
2/12.1 The Contractor shall obtain approval from the Employer for the location of
the borrow pit site. The Contractor shall be responsible to determine the
quantities and quality of the available material in the approved borrow site
to meet the requirements of the Contract. When required the borrow area
shall be cleared and grubbed in accordance with the requirements of
Section 2/1.
2/12.2 The Employer may at any time revoke approval of a borrow site where the
Contractor is obtaining borrow material for the Works. Upon receiving such
notice from the Employer, the Contractor shall immediately cease removing
material from said borrow site. In the event the Employer revokes approval
of the borrow site, the Contractor shall locate a new borrow pit site as
specified above.
2/12.3 The Contractor shall not claim any additional payment for any costs by
reason of the necessity of changing borrow site locations due either to the
shortage of the supply of borrow material available from the borrow pit site
approved by the Employer, or due to the Employer's decision to revoke
approval of the borrow site where the Contractor is obtaining borrow
material for the Works.
2/12.4 The Contractor shall leave borrow pits in a condition acceptable to the
Employer and to the Engineer.
2/12.5 The Contractor will be solely responsible for ascertaining the location of
such approved borrow areas during the tender preparation stage.
Locations, distances to the work site and haulage from such approved
borrow areas shall be taken into consideration when preparing the unit
tender price for Borrow Excavation.
2/13.1 Top Soil shall be fertile, friable soil containing organic matter free from
subsoil, refuse, tree roots, noxious weeds, clay lumps and stones
recovered from well drained arable land. The soil shall be free draining, non
toxic and capable of sustaining healthy plant growth. The properties of
Topsoil shall be as described in Table 2-1 below.
Suitable Material for earthworks shall comprise all material obtained from
excavations within the works or from borrow pits approved by the Engineer
and acceptable in accordance with the Contract for use in the Works.
Suitable material for earthworks shall be an approved soil that meets the
following specifications listed in Table 2-2:
Material for an improved subgrade layer shall meet the requirements listed
in Table 2-4 below:
2/13.5 No excavated suitable material shall be removed from the Site without the
Engineer's written permission. Should the Contractor be permitted to
remove suitable material from the site to suit his operational requirements,
and then he shall make good any consequent deficit or filling arising there
from at his own expense.
2/13.6 Dune sand if used shall not contain more than 2% organic matter (BS
1377:P3:1990 M3, AMD 9028:1996) and may contain up to 20% of stone
fragments or cobbles exceeding 20mm but not more than 63mm in size.
2/13.7 Layers of dune sand between layers of granular materials shall not be
allowed.
2/14.1 The Contractor shall employ only that plant which is suited to the soils to be
handled. He shall not at any time use plant which damages or reduces the
natural strength of the soil either in its in-situ state or during handling and
placing or in its final compacted state. Unsuitable or faulty plant shall be
removed from the work site and borrow pits at the order of the Engineer.
2/14.2 The plant and equipment used for earthworks construction shall be
maintained in good working condition for the duration of the works. The
Contractor shall apply adequate quantities of plant and equipment
necessary for the proper execution of the works in an expeditious manner.
2/14.3 Main plant and equipment shall meet the requirements outlined in Clause
1/29 of these Specifications.
2/15.1 This work shall consist of constructing roadway embankment with suitable
material, including the preparation of the areas upon which they are to be
placed and the placing and compacting of approved material within
roadway areas where unsuitable material has been removed. All
operations will be performed in accordance with the Specifications and in
conformity with the lines, grades, thickness and typical cross-sections
shown on the drawings or as established by the Engineer.
2/15.2 Compaction equipment shall conform to the number and type outlined in
the Contractor's detailed programme of work as approved by the Engineer
and satisfactory performance shall be the basis for such approval.
2/15.3 All materials derived from excavation shall be used in the embankment
unless otherwise declared unsuitable by the Engineer.
2/15.5 During the construction of embankments, the Contractor shall control and
direct construction traffic uniformly over the full width of the embankment
Damage to compacted layers by construction traffic shall be made good by
the Contractor at his own expense.
2/15.6 The Contractor shall be responsible for the stability of all embankments and
shall replace all sections which, in the opinion of the Engineer, have been
damaged or displaced due to carelessness or neglect on the part of the
2/16.1 All debris, unsuitable material and vegetable matter shall be removed from
the surface upon which the embankment is to be placed and the cleared
surface shall be completely broken up by ploughing, scarifying or stepping
to a minimum depth of twenty (20) centimeters.
2/16.2 The foundation material shall be adjusted to a moisture content within the
moisture range of + 3% of the optimum moisture content and compacted to
not less than ninety-five (95) percent of the Maximum Dry Density as
determined by BS 1377 Part 4: 1990 (method 3.5 or 3.6, AMD 13925:
2002) where the embankment is less than one and a half (1.5 m) meters
below subgrade; and compacted to not less than ninety three (93) percent
of the maximum dry density as determined by BS 1377 Part 4: 1990
(Method 3.5 or 3.6, AMD 13925: 2002) ) where the embankment is more
than one and a half (1.5 m) meters below the subgrade.
2/16.3 If the original surface upon which the embankment is to be placed is an old
roadbed, the surface shall be ploughed scarified or broken up. All
aggregate particles shall be reduced to a maximum size of 63 mm. A well-
mixed and uniform layer surface shall be produced. The embankment
layers shall be compacted according to Subsection 2/16 requirements,
regardless of the height of the embankment to be placed, and compacted
to a density not less than ninety five (95) percent of the maximum dry
density as determined by BS 1377 Part 4: 1990 (Method 3.5 or 3.6, AMD
13925: 2002).
sieving (BS 812: Part 103: Section 103.1:1985, cl.7.2 or 7.3, AMD 6003:
1989, or BS 1377: Part 2: 1990: 9.2 or 9.3, AMD 9027: 1996 or latest
edition) complies with the requirements of Table 2-5 below. Such material
shall have a "ten percent fines" value of not less than 5 tones when tested
in accordance with BS 812: 1990 P111 and BS EN 1097-2-1998, AMD
16684: 2006 and may be deposited below water without the associated use
of compaction plant.
2/17.3 The fill material shall be delivered and spread in layers not exceeding 250
mm thickness after compaction. The layers of fill shall be graded, leveled,
pulverized and mixed, with water added as necessary, to ensure
Volume 2, Part 1, General Specifications-Road Works March 2017 Page 15
16 SECTION 2 SITE CLEARANCE AND EARTHWORKS
2/17.4 The compacted density of the fill shall be equal to or greater than as
required under Clause 2/16.2 as determined by BS 1377 Part 4: 1990
(Method 3.5 or 3.6, AMD 13925: 2002).
Dune Sand, if found suitable and approved by the Engineer, may be used
as fill material up to a level of 1.5m from bottom of sub-grade. Dry
compaction (at natural moisture content) of 25cm lifts (tested every 15cm)
can be adopted.
2/17.6 All slopes, lines and grades shall be true, correct, and accurate and
according to those shown on the Drawings or otherwise directed and
approved by the Engineer. The "earthworks formation level" in
embankments shall be accurate to the authorized profile grade to plus or
minus two (2) centimeters and, the 'top of improved subgrade' level, plus or
minus one (1) centimeter for 3 locations maximum each 100 m interval.
Selected material shall be placed wherever required. Where discrepancies
are found in the work the Contractor shall make necessary corrections in a
manner approved by the Engineer.
2/17.7 Grade, level, shape and compact the embankment surface to a uniform
cross-section. At the end of each day's operations, all ruts and depressions
that could hold water should be eliminated.
2/17.9 Use a tamping foot roller to compact embankment side slopes by walking
with a dozer, or by over-building the fill and then removing excess material
to the final slope line. For steeper slopes, compact the slopes as
embankment construction progresses.
2/17.14 Ditches, Slope, grade, and shape ditches. Remove all projecting roots,
stumps, rock, or similar matter. Maintain all ditches in an open condition
and free from leaves, sticks, and other debris. Complete slopes, ditches,
culverts, and other underground minor structures before placing aggregate
courses. Slope, shape, and finish as follows:
2/18.1 When the moisture content of the embankment soil does not fall within +
3% of the optimum moisture content, water shall be added and thoroughly
mixed into the soil, by approved methods or the material shall be aerated,
whichever is needed to adjust the soil to the proper moisture content.
2/18.2 The amount of water to be added shall be only that amount that will, as
determined by the Engineer by field tests, provide moisture content in the
soil within the required range plus a reasonable amount to compensate for
2/18.3 Use of saline water for earthworks will only be permitted if the percentage
of water soluble salts in the compacted fill does not exceed 5% by weight of
dry soil when tested in accordance with BS 1377 Part 3 : 1990 tests 5 & 7,
AMD 9028:1996 for SO3+Cl).
2/18.4 For subgrade material moisture range refers to sub clause 2/13.4.
2/19.1 A dry density moisture content relationship test in accordance with BS 1377
Part 4 : 1990 (method 3.5 or 3.6, AMD13925-2002 ) will be made for each
type of soil to be used in the construction of the work to determine the
Maximum Dry Density, the Optimum Moisture Content and the Moisture
Range required of the soil for satisfactory compaction. The Field Density
and actual Moisture Content of the compacted embankment shall be
determined by field tests according to BS 1377 Part 9: 1990 (method 2.1 or
2.2), AMD17229-2007.
2/19.2 Insitu density of dune sand shall be determined in accordance with B.S.
1377 Part 9 Test 2.1 or 2.2:1990, AMD 17229: 2007. However, where
conventional sand replacement measurement of field density cannot be
undertaken the suitability of the fill material shall be determined using the
Clegg Impact Soil Tester in accordance with ASTM D5874 - 02(2007). A
minimum Impact Value (CIV) = 8 (which corresponds to a CBR value of
8%) shall be achieved.
2/20.1 For the Contractor's general guidance, the following tests will be required
prior to use, and during the construction of the embankment and of the
subgrade.
EMBANKMENT
2/20.2 Soil samples for Soil classification according to BS 1377: Part 1 and Part 2:
1990 latest edition, laboratory moisture/density relationship tests and
California Bearing Ratio shall be taken prior to use, from any proposed
source of material. Each sample shall represent not more than 5,000 Cu.m
of stockpiled material or part of as directed by the Engineer. Sampling shall
be in accordance with ASTM D75: 2009, BS 1377 Pt 1: 1990 and BS
5930:1999.
Volume 2, Part 1, General Specifications-Road Works March 2017 Page 18
19 SECTION 2 SITE CLEARANCE AND EARTHWORKS
2/20.3 For every completed layer of fill, at least FOUR (4) field density tests shall
be performed for every unit of carriageway (One unit being 2250 Sq.m.) or
as directed by the Engineer. Every compacted layer shall be compacted to
not be less than 95% of MDD.
IMPROVED SUBGRADE
2/20.6 For every completed layer of subgrade, three field density tests shall be
performed on each unit of carriageway. (One unit being 1500 Sq.m) or as
directed by the Engineer.
2/20.7 The frequency of field compaction tests on the shoulders shall be three
every unit constructed or as directed by the Engineer (One unit being 1500
Sq.m).
ROCKFILL
2/20.8 Where embankments to be compacted are formed of material consisting
predominantly of rock fragments of such size that the material cannot be
placed in layers of the thickness prescribed without crushing, pulverizing or
further breaking down the pieces resulting from normal excavation
methods, the material may be placed in the embankment in layers not
exceeding a thickness twice the average size of the larger rocks, except
that no layer shall exceed 600 mm of loose measurement.
Materials shall be carefully placed so that all large stones will be well
distributed and the voids completely filled with smaller earth, sand or gravel
to form a solid embankment. Each layer shall be bladed or leveled with
motor grader, bull dozer or similar equipment capable of shifting and
forming the layer into a neat and orderly condition. No. rocks larger than
eighty (80) mm in any dimension shall be placed in the top one hundred
and fifty (150) mm of the embankment unless otherwise noted on the
drawings. Conformance to these provisions and compaction in a manner
and to a point of consolidation approved by the Engineer will be considered
as fulfillment of the requirements for the type of compaction shown on the
drawings.
Normally, compaction tests will not be performed in these areas but the
Engineer reserves the right to test compaction in some other manner if he
deems a test necessary to ensure consolidation. Each layer must be
approved by the Engineer before the next layer is placed.
Embankments, which are formed of materials that contain rock but also
sufficient compatible material other than rock or other hard material to
make rolling feasible, shall be placed and compacted in the manner and to
the point of consolidation approved by the Engineer. Moisture shall be
2/21.1 In the event the foundation on which the embankment or the subgrade
materials will be laid is saturated by water and unstable, the Engineer may
decide to lay crushed granular material to stabilize the foundation.
Stabilising crushed material shall not be laid directly on ground soil but it
shall always be laid on Geotextile fabric covering the area to be stabilised
as shown on the drawings or directed by the Engineer.
2/21.3 The stabilising crushed material shall have the following characteristics
shown in Table 2-7 below:-
decide, after having taken the levels of the existing water table in the area,
and keeping in consideration the finished road levels, to excavate portions
of the foundation saturated by water, disposing of the excavated material,
and replacing it with stabilising crushed material.
2/21.5 Before starting any stabilising of the foundation the Engineer will instruct
the Contractor specifying the areas to be stabilised and the final levels to
be reached with the stabilising crushed material.
2/21.6 Alternative methods of soft area treatment which may be directed by the
Engineer are:
Physical Requirements
All aggregate materials shall comply with the requirements of sections
2/20.8 and 2/21 of the General Specifications in addition to the following:
2/22.1 In areas where the Engineer deems the use of Geotextile fabric necessary,
the Contractor shall furnish and place Geotextile fabric as specified and as
directed by the Engineer.
2/22.3 The surface to receive the Geotextile fabric shall be prepared to a relatively
smooth condition free of obtrusions, depressions, and debris. The
Geotextile fabric shall not be laid in a stretched condition, but shall be laid
loosely with the long dimension parallel to the centerline of the roadway. In
the event that the width of the proposed area for fabric requires more than
one panel width of fabric, the panels shall be overlapped a minimum 15
percent of the panel width. Longitudinal joints in the fabric shall have an
overlap of 50cm. To prevent slippage of the overlapping fabric, the areas
of overlap shall be stabilised as approved by the Engineer with pins, anchor
blocks, or aggregate piles. In the event construction machinery is used to
place the fabric, the working platform for the machinery shall be the soil and
not the previously laid fabric.
2/22.4 Prior to placement of the stabilising crushed material the Contractor shall
spread a layer of sand over the Geotextile fabric as directed by the
Engineer. A 5cm thick layer of Crushed Sand which grading limits are
shown below shall cover the Geotextile fabric.
The aggregate material shall not be dumped directly on the fabric, nor
shall haul trucks be run on the fabric. The aggregate shall be spread by
a wheeled front-end loader.
The blade or bucket shall be kept sufficiently high so that the aggregate is
not being pulled over the fabric, but being dropped at a minimum height to
the satisfaction of the Engineer.
2/23.1 This work shall consist of all excavation for structures, culverts, headwalls,
catch basins, manholes, inlets, and retaining walls and shall include all
necessary clearing and grubbing, all necessary bailing, drainage, pumping,
sheeting, strutting and the construction of coffer dams or cribs, if found
necessary, and their subsequent removal; also the disposal of all material
obtained from such excavation and backfilling to the level of the original
ground; it shall include the removal of that portion of existing structures
below the ground which is necessitated by the construction of the new
structure.
2/23.2 Prior to commencing any structural excavation work 1.5 meters or more in
depth, the Contractor shall design and submit to the Engineer for review
and approval, within a minimum period of 1 week before the intended
commencement date, detailed working drawings of the structural
excavation support member materials, sizes, spacing and engineering
calculations to validate their design, including the maximum theoretical
deflections of the support members. The system shall be designed in such
a manner that no raker struts or any other support members extend through
surfaces exposed in the finished construction, and no shoring or bracing is
placed under permanent structures.
2/23.3 The engineering calculations shall show lateral earth pressure for the full
excavation depths, forces at various stages of support during installation
and removal and concrete placement, the anticipated equipment loads,
surcharge loads of any description, the maximum design loads to be
carried by various members of the support system and strut preload forces.
2/23.4 If the structure support system proposed includes tieback anchors, the
Contractor's submittal drawings shall show the profile of the soil in which
each anchor is to be installed, the design load for the full depth of the
excavation, the maximum design and proof loads, surcharge loads of any
description; equipment loads, forces at various stages, support during
installation and removal, and the criteria proposed for deformations under
proof loads. Where a proposed system of tieback anchors projects beyond
the vertical projection of the Contract limit lines shown on the Drawings on
to the adjoining property, the permission of the owner shall be obtained in
writing and such permission submitted to the Engineer at the time the shop
drawings of the support systems are submitted.
2/23.5 At locations where the excavation extends below the ground water table, a
dewatering system shall be provided which will effectively reduce the
hydrostatic pressure and lower the ground water levels below excavation
levels, as required for the safe and proper execution of the work and which
will result in obtaining a stable, dry subgrade for the execution of
subsequent operations. The Contractor shall design dewatering methods
and settling basins so that no critical amounts of soil, sand or silt are
removed during either the initial operations or the construction operations.
Complete working drawings showing the type of dewatering and ground
water control system proposed shall be submitted to the Engineer for his
review.
2/23.6 The Contractor's submittal drawings shall show the arrangement, location
and depths of the proposed dewatering system if required. A complete
description of the equipment and materials to be used and the procedures
to be followed shall be shown, together with the standby equipment,
standby power supply and the proposed location or locations of points of
discharge of water. Any required dewatering system design shall also
include the measures taken to prevent damage due to settlement of
pavement, utilities, sewers, buildings and other structures outside the
excavation but within the area affected by the procedures.
2/23.7 The designs of the structure excavation support system and the dewatering
systems specified above shall be prepared by and signed by a Professional
Engineer approved by the Engineer specializing in this type of design work.
Approval of the designs and shop drawings shall not relieve the Contractor
of the adequacy and performance of these temporary works.
2/23.9 The Report shall include photographs, drawings and sketches with levels
and dimensions illustrating the structures condition, noting in particular any
existing damage or structural inadequacy. Deficiencies and damage shall
be suitably marked on the structure such that it is not permanently defaced.
2/23.10 Three copies of the Report shall be submitted for the approval of the
Engineer. Once approved, five additional copies shall be supplied to the
Engineer.
2/23.11 The Contractor shall notify the Engineer sufficiently in advance of the
beginning of any excavation so that cross-sectional elevations and
measurements may be taken of the undisturbed ground. The natural
ground adjacent to the structure shall not be disturbed without the
permission of the Engineer.
2/23.14 If during the progress of the work, loose or improperly compacted soil is
encountered below the structural foundation levels, or adjacent thereof,
which is the result of prior removal of utilities or structures, such material
shall be completely removed within the limits as directed by the Engineer,
backfilled with suitable material and it should be not less than 95% of the
maximum dry density as determined by BS 1377 Part 4 : 1990 (method 3.5
or 3.6, AMD 13925: 2002). Any previous excavations encountered which
would in the opinion of the Engineer be detrimental to load distribution of
new foundations to the underlaying soil, shall be excavated and backfilled
with Class 25 concrete (clause 4/15).
2/23.15 After each excavation is completed, the Contractor shall notify the
Engineer, for approval of the depth of excavation and the character of the
material, prior to further structural works. Any over excavation shall be
backfilled with Class 25 concrete (clause 4/15) at the Contractors expense.
2/23.16 All rock or other hard foundation material shall be cleaned of all loose
material and cut to a firm surface, either level, stepped, or serrated as
directed by the Engineer. All seams or crevices shall be cleaned and
grouted. All loose and disintegrated rock and thin strata shall be removed.
When the footing is to rest on material other than rock, excavation to final
grade shall not be made until just before the footing is to be placed and
special care shall be taken not to disturb the excavation. When the
foundation material is soft or otherwise unsuitable as determined by the
Engineer, the Contractor shall remove the unsuitable material and backfill
with approved granular material. This foundation fill shall be placed and
compacted in 150mm layers up to the foundation elevation and compacted
to not less than 95% of the maximum dry density as determined by BS
1377 Part 4 : 1990 (method 3.5 or 3.6, AMD 13925: 2002).
In either case the Contractor will suspend all construction activities in the
vicinity of the structure until such time as the remedial or preventive works
are carried out to the Engineer's satisfaction at the Contractor's expense.