Surendar March

The document outlines work planned from March 11th-March 27th 2023 for various areas including: 1) Phase 2 work such as excavation, welding, and gamma ray testing of new pipelines. 2) Work at the manifold area, power station, water injection sites, and various oil wells including repairs, installations, and isolations. 3) Additional tasks like road repairs, scaffolding erection, and concrete work at sites like the oil center, gas plant, and military accommodation areas. The document provides details on location, scope of work, required documentation and expected duration for each listed task.

Uploaded by

Vipin Haripad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
42 views8 pages

Surendar March

The document outlines work planned from March 11th-March 27th 2023 for various areas including: 1) Phase 2 work such as excavation, welding, and gamma ray testing of new pipelines. 2) Work at the manifold area, power station, water injection sites, and various oil wells including repairs, installations, and isolations. 3) Additional tasks like road repairs, scaffolding erection, and concrete work at sites like the oil center, gas plant, and military accommodation areas. The document provides details on location, scope of work, required documentation and expected duration for each listed task.

Uploaded by

Vipin Haripad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 8

PHASE 2

date w.o.n description remarks


19/3/2023-20/3/2023 To perform gamma ray 18” phase 2
(one day valid) area
17/3/2023-18/3/2023 To perform gamma ray 18” phase 2
(one day valid) area
18/3/2023-20/3/2023 Welding fabrication,installation of 18”new pipe Attach isolation cert,TRA,TRA
line for water injection phase 2 line project work sheet,TPT,TPT name form

22/3/2023-28/3/2023 To perform sand blasting,pipe wrapping of 18” Attach isolation cert,TRA,TRA


new pipeline for water injection Phase2 project work sheet,TPT,TPT name form

19/3/23-25/3/2023 Excavation work at phase 2 area


21/3/23-27/3/23 Form works /shuttering block works,concreting
at water injection Phase-2 line project

MANIFOLD AREA/OIL CENTER


23/3/2023-29/3/2023 C.22/23 To excavate by hand at manifold area/oil
center for water injection phase 2,part 2

POWER STATION AREA


19/3/2023-25/3/2023 To lift and remove PSV for calibration at power
station area /skid/S5/compressor area(re install after
calibration)
19/3/2023-25/3/2023 To install end flange/blind flange and isolate PSV/TSV Attach isolation cert,TRA,TRA
for removal located at skid/S5 tank/power station work sheet,TPT,TPT name
compressor area form

20/3/2023-22/3/2023 To remove scaffolding at S5 tank/power


station area
20/3/23-26/3/23 To repair damaged road between oil center
Gas heater area and power station

WATER INJECTION
17/3/2023-23/3/2023 To install end flange/blind flange to PSV/TSV for
isolation and removal located at water injection area
17/3/2023-23/3/2023 To remove PSV/TSV for maintenance and
recalibration at water injection area(re install after
calibration)
11/3/23-17/3/23 To install insulation on 8”&6”water
(7 days)(done) injection flow line near phase2
11/3/23-13/3/23 To erect scaffolding at water injection (tool box talk&name
well 2 list)

GAS HEATER
To repair damaged road between oil
20/3/2023-26/3/2023 center Gas heater area and power station
area

M2 A-8 AND A41


Welding ,repair, installation New 16 “ M2 Attach isolation cert,TRA,TRA
9/3/2023-11/3/2023 work sheet,TPT,TPT name list
(3 days) (done) flowline location between A-8&A41
11/3/23-17/3/23 Backfilling at 16” new flow line of M2
between A8 & A41
done To perform excavation on 16” leak M2
flow line pipe location A8 & A41

M1 MANIFOLD
16/3/2023-18/3/2023 Welding repair installation of new 8” Attach TRA,TRAwork
sheet,TPTR,TPTR name list
A27 flow line M1 manifold area
Attach isolation cert,TRA,TRA
10/3/2023-16/3/2023 Cold cutting Of 8” leak flow line M1 work sheet,TPT,TPT name
(done) manifold area A-29 form
Welding and connection of new 8” pipe for Attach isolation cert,TRA,TRA
12/3/2023-14/3/2023 work sheet,TPT,TPT name
(done) A29 flow line at M1 manifold area form
17/3/2023-18/3/2023 To Perform Gamma ray on 8” new weld
(one day valid) joint for A27 line at M1 manifold area

17/3/23-23/3/23 To pipe wrapping at M1 manifold area for


A27 line 8”pipe
MTCE&GESE OIL CENTER,SEPARETOR,
19/3/23-25/3/23 Ceramic tile installation,concreting at
oil center,rest room area
5/3/23-11/3/23 Demolise floor,discover leak
(done) line,replace new one at oil center

SEPARETOR
603
Attach isolation
6/3/2023-12/3/23 013/2023 Remove blind disc,de isolate cert,TRA,TRA work sheet,
(7days) (done) closing manhole s.603
6/3/2023-12/3/23 Closing of man hole,remove blind disk
(done) and deisolate seperetor S 603
8/3/2023-to 15 days Seperator S 603
18/3/23-24/3/23 Pipe install&insulation pipe in
(done) installation work at separator S.603
area
18/3/23-24/3/23 Water filling at separator S.603
Attach isolation
14/3/2023-20/3/2023 To remove blind disc and de cert,TRA,TRA work sheet,
(done) isolate separators S603 name list
17/3/2023-19/3/2023 To remove scaffolding at meter
(done) prover area/oil center

MTCE A50
Attach isolation cert,TRA,TRA
11/3/2023-13/3/2023 Welding connection of 8”flow line for work sheet,TPT,TPT name
(done) oil well A50 form

11/3/23-17/3/23 To perform excavation at oil well A50 Attach in(excavation


Map)
(7days) (done) area
9/3/23-15/3/2023 Transport & lay down of pips &materials for Tool box talk&name
oil well A50 /bolt&installation list attach
14/3/2023-16/3/2023 Welding and repair at new 8”flow line pipe TPT,TRA attach
(done) for A50
15/3/2023-15/3/2023 To perform gamma ray for 8” new pipe weld
(done) joint located at oil well A50
14/3/23-20/3/23 Pipe wrapping and backfilling of new 8”
(done) flowline pipe located at oil well A50

NGL ,WAREHOUSE,MTCE&GESE
19/3/2023-25/3/2023 Water mixing of caliche,ground leveling new
warehouse beside NGL plant
5/3/2023-11/3/2023 Ground leveling mixing calichie new ware
(done) house beside ngl plant area
13/3/2023-19/3/2023 To lift remove and transport old container
(done) located near R.O trailers /NGL plant area (For Attach TRA&TPT
transport to rai camp for repair)
15/3/23-21/3/23 To put sealant/epoxy on plastic RO tank TRA&TPT
located at NGL

GAS PLANT
Open bolts ,lift and P7 tank located at gas
13/3/2023-14/3/2023 plant area ,transport to rai camp for cleaning Attach TRA&TPT
inspection
(done)
14/3/2023-20/3/2023 To remove liquid contents of P7 tank by
(done) vaccum
17/3/23-23/3/2023 Lifting and installation of condensate tank P7
gas plant area

ACCOMENDATION MELLITAH,MILITTARY(CAMP)
MTCE Welding fabrication ,installation of new
20/3/2023-22/3/2023 23/26 inlet/outlet 8”water pipe flow line at staff Attach TRA&TPT
1&staff2
9/3/2023/-15/3/23 To install water heater for MOG mess
(done) hall &accomontation area
10/03/2023-16/3/2023 New concrete floor between bathroom
(done) &mess hall for military camp
17/3/2023-23/3/2023 To perform block works and concreting at
Staff2 area/accomendation
20/3/23-22/3/23 To erect scaffolding at football field
(3 days) area/accomendation

18/3/23-24/3/23 To insert blind disc and isolate 6”&4” water


line at staff-2 area(accomendation)
21/3/23-27/3/23 Water line,plumbing repair at MOG-mess
hall/accomendation(for washer equipment
21/3/23-27/3/23 Sand leveling,block works,concreting for new
trailer located back of swimming
pool/accomendation area
17/3/2023-23/3/2023 To constract new concrete floor between
bathroom&mess hall for military camp

PRODUCED WATER ,FT2,API AREA


12/3/2023-18/3/2023 Painting inside filter tank-A/produced
(done) water area
14/3/23-20/3/23 To reinstall sight glass/level
(done) class,instruements PSV,closing of man hole
for filter Tank-A/producd water area
14/3/23-20/3/23 To reinstall pipes and systems,loading of
(done) media filters for nutshell filter Tank
A/produced water area
22/3/23-24/3/23 To remove scaffolding at inside /outside filter
Tank-A located at produced water area
19/3/23-25/3/23 To remove insulation on 3”&4”leak steam
pipe back of API area/near filter tank A
produced water area
21/3/23-27/3/23 To lift and remove PSV/TSV for calibration at
produced water area
21/3/23-27/3/23 To install end flange/blind flange onPSV/TSV TRA,TPT,
for calibration at produced water
22/3/23-28/3/23 Cleaning,inspection & closing manhole

FT2
14/3/23-20/3/23 MTCE To install insulation on 3/4 &1/2 steam
done 23-022 line for FT2 line near API area TRA,TPT attach
19/3/23-25/3/23 To remove insulation on 8” leak pipe at
FT 2 near API area

AUXILARY AREA
23/3/2023-29/3/2023 To re install metal sheet walling for fire
fighting/auxiliary area
23/3/2023-25/3/2023 To erect scaffolding at fire
(scaffold)3 days fighting/auxiliary area(after remove)

RO PLANT ,WATER TREATMENT


15/3/23-21/3/23 Mtce To remove media filters,bed layers and Attach confined
23/025 systems of media filter MM10 at RO space,isolation
plant/auxilury plant area-water treatment
15/3/2023-21/3/2023 To perform internal cleaning and inspection of
media filter MM10 located at RO
plant/auxilury plant area
18/3/23-24/3/21 To install blind disc and isolate media filter
MM11&12 at RO plant/opening of manhole for
ventilation located at internal treatment area
20/3/23-26/3/23 To remove media filter,internal cleaning and
inspection of media filter tank MM12/water
treatment area-RO plant
18/3/23-20/3/21 Welding & repair work at media filtter
MM11&MM12 tank at RO plant area
TPS NGL
18/3/23-24/3/23 To install end flange /blind flange&isolate Attach isolation
PSV/TSV for removal at TPS 11&12 near NGL
plant
18/3/23-24/3/23 To lift and remove PSV/TSV at TPS 11&12 for isolation ,TRA,TPT
calibration /located near NGL plant(Re install attach
after calibration)
21/4/23-23/3/23 To erect at scaffold TPS 11&12 near NGL plant
area(remove after Psv/Tsv installation)

BOILER#3 WATER TREATMENT


20/3/23-22/3/23 23/035 To erect scaffolding at boiler*3/water
treatment area
20/3/23-22/3/23 To remove insulation at boiler *3/water
treatment area (pipe and system)reinstall after
20/3/23-22/3/23 To insert blind disc and isolate boiler *3/water
treatment area opening of manhole for
ventilation(front and back)
21/3/23-27/3/23 To remove PSV of boiler *3 for calibration and TRA,TPT
repair re install after calibration
21/3/23-27/3/23 Internal cleaning and inspection of boiler*3 TRA,TPT
located at water treatment area
21/3/23-27/3/23 To lift and remove PSV/TSV for calibration at TRA
produced water area re install after calipration
21/3/23-27/3/23 To install end flange/blind flange on PSV/TSV
for calibration at produced water area
21/3/23-27/3/23 To remove pave.
. valvs and pipe systems of boiler *3 for
calibration,inspection and repair(include
burner)

A75 WELL PIPE


23/3/23-29/3/23 To perform excavation on 8”
(Excavation) leak flow line of oil well