PROJECT OVERVIEW                                  % COMPLETE
Status for all top-level tasks. To see the status for subtasks, click on the chart and update the
                                                  outline level in the Field List.
                                                            100%             100% 100%
                                                                                          84%
TUE 19/07/22 - SUN 17/09/23                                  90%
                                                             80%
                                                             70%
                                                             60%
  % COMPLETE                                                 50%
                                                             40%
                                                             30%
  12%                                                        20%
                                                             10%
                                                              0%
                                                                       0%                         0%      0%    5%    0%       0%   0%
MILESTONES DUE
Milestones that are coming soon.
  Name                             Finish
  132kV Grid Station EMAAR         Wed 02/11/22
                                                  LATE TASKS
                                                  Tasks that are past due.
                                                    Name                      Start              Finish              Duration        % Complete       Resource
                                                                                                                                                      Names
                                                    132kV Grid Station        Wed                Wed 02/11/22        0 days          0%
                                                    EMAAR                     02/11/22
                                                    Approval of Design        Wed                Tue 08/11/22        7 days          0%               TSW[1]
                                                    From TSW                  02/11/22
                                                    Tandering                 Wed                Wed 02/11/22        1 day?          0%
                                                    Completion                02/11/22
                                                    Commencement of           Wed                Wed 02/11/22        1 day           0%               XEN T&G
                                                    civil works               02/11/22
                                                    132kv Switchyard          Sun 11/09/22       Wed 26/10/22        45 days         0%               Contracor
                                                    Cable Trenches and
                                                    Other works
                                                    Switch Yard               Mon                Mon 31/10/22        36 days         0%               Contracor
                                                    Drainage System           26/09/22
                                                    Switchyard Fence          Thu 06/10/22       Sun 13/11/22        39 days         0%               Contracor
                                                    and Fence Gate
                                                    Transformer way           Sun 16/10/22       Thu 24/11/22        40 days         0%               Contracor
                                                    Backfilling and           Fri 11/11/22       Fri 25/11/22        15 days         0%               Contracor
                                                    Compaction
Gravel Spreading       Sat 26/11/22   Sat 10/12/22   15 days   0%   Contracor
Demarcation of CHB     Fri 19/08/22   Fri 19/08/22   1 day?    0%   Contracor,COS
Excavation of CHB      Fri 29/07/22   Fri 29/07/22   1 day?    0%   Contracor
Substructure           Fri 29/07/22   Wed 21/09/22   55 days   0%   Contracor
Construction of        Thu 22/09/22   Sun 30/10/22   39 days   0%   Contracor
Framework
Brick work             Mon            Mon 05/12/22   36 days   0%   Contracor
                       31/10/22
Plaster                Tue 06/12/22   Wed 04/01/23   30 days   0%   Contracor
Trenches in CHB        Mon            Sun 20/11/22   21 days   0%   Contracor
                       31/10/22
Watersupply            Fri 29/07/22   Wed 17/08/22   20 days   0%   Contracor
sanitary and
Sewerage / Drainage
Works
Flooring and Ceiling   Thu 05/01/23   Sun 29/01/23   25 days   0%   Contracor
Electrification        Mon            Tue 14/02/23   16 days   0%   Contracor
                       30/01/23
Finishing and Allied   Wed            Thu 16/03/23   30 days   0%   Contracor
works                  15/02/23
Water Borings          Wed            Wed 16/11/22   15 days   0%   Contracor
                       02/11/22
Substructure           Wed            Sat 31/12/22   60 days   0%   Contracor
                       02/11/22
Ground Floor Gray      Sun 01/01/23   Tue 14/02/23   45 days   0%   Contracor
Structure
First Floor Gray       Wed            Fri 31/03/23   45 days   0%   Contracor
strcuture              15/02/23
Finishing works        Sat 01/04/23   Mon 15/05/23   45 days   0%   Contracor
Finishing and Allied   Tue 16/05/23   Wed 14/06/23   30 days   0%   Contracor
works
Civil Works            Wed            Wed 02/11/22   1 day?    0%
Completed              02/11/22
Material Shifting      Wed            Thu 01/12/22   30 days   0%   LS with team
from store to Site     02/11/22
Installtion of Power   Fri 02/12/22   Fri 09/12/22   8 days    0%   LS with team
Transformers
Installtion of         Fri 06/01/23   Sun 15/01/23   10 days   0%   LS with team
Gantries & Eath
Mast
Installtion of Beams     Mon            Thu 19/01/23   4 days    0%   LS with team
                         16/01/23
Installtion of Bays      Fri 20/01/23   Fri 03/02/23   15 days   0%   LS with team
Installtion of Surge     Sat 04/02/23   Sun 05/02/23   2 days    0%   LS with team
arrestors
Jumpers& Dropers &       Mon            Fri 17/02/23   12 days   0%   LS with team
Gantry Span &            06/02/23
Skywire
Installtion of 11KV      Sat 18/02/23   Sat 25/02/23   8 days    0%   LS with team
Switchgear Panels
Installtion of Control   Sun 26/02/23   Tue 28/02/23   3 days    0%   LS with team
and Relay Panels
Laying and               Wed            Wed 15/03/23   15 days   0%   LS with team
Termination of           01/03/23
Control and Power
Cables
Installtion of           Thu 16/03/23   Wed 29/03/23   14 days   0%   LS with team
Capacitor Banks
Installtion of           Thu 30/03/23   Mon 03/04/23   5 days    0%   LS with team
Batteries and
Battery Chargers
Installtion of Pad       Tue 04/04/23   Wed 05/04/23   2 days    0%   LS with team
Mounted
Transforemer
Internal Interfacing     Fri 03/03/23   Fri 17/03/23   15 days   0%   LS with team
(Wiring)
Stringing of             Thu 23/03/23   Fri 24/03/23   2 days    0%   LS with team
Condcutor (Subject
to Shut Down on
Existing Line)
Dy-Hydraton of PTF       Thu 06/04/23   Wed 19/04/23   14 days   0%   T&I
Testing of Power         Thu 20/04/23   Sat 22/04/23   3 days    0%   T&I
Transformer
Testing of               Thu 06/04/23   Wed 12/04/23   7 days    0%   T&I
Swicthgear
HI pot test              Thu 13/04/23   Thu 13/04/23   1 day     0%   T&I
Testing of MV            Thu 13/04/23   Tue 18/04/23   6 days    0%   T&I
Swicthgear, Control,
Relay Panels etc
Scheme Checks &          Wed            Thu 20/04/23   2 days    0%   T&I
Pre-Commissioning        19/04/23
Activites
Ready for            Fri 21/04/23   Mon 24/04/23   4 days   0%   T&I
Energization
End of the Project   Tue 25/04/23   Tue 25/04/23   1 day    0%   PD GSC
(Commissioning &
Energization)