ITEM DESCRIPTION QUANTITY AS TO PLAN STANDARD SIZE QUANTITY UNIT COST AMOUNT
NOTES:
PART A. ROOF FRAMING
1. 30 CONSTRUCTION DAYS WILL BE THE DURATION OF THE
2"X4" TUBULAR STEEL (RAFTERS) 139 LNM 2" X 4" X 1.2MM X 6M 32.00 ₱ 1,013.00 ₱ 32,416.00
PROJECT. POSSIBLE TIME EXTENSION DUE TO UNFORESEEN
2"X4" C-PURLINS 321 LNM 2" X 4" X 1.2MM X 6M 71.00 ₱ 703.00 ₱ 49,913.00 EVENTS.
PART B. TINSMITHRY WORKS
2. OVERHEAD, CONTINGENCY AND MISCELLANEOUS FEES WILL BE
INSULATION FOAMS 180 SQM 50M X 1M 5.00 ₱ 2,500.00 ₱ 12,500.00 USED AS A BUDGET FOR UNFORESEEN PROBLEMS THAT WE MAY
PRE-PAINTED (GRAY) RIB-TYPE METAL 1.00 M(EFFECTIVE WIDTH) X 2.44M X
ENCOUNTER ON THE DURATION OF THE PROJECT.
180 SQM 55.00 ₱ 794.00 ₱ 43,670.00
ROOFING SHEETS GA 26 X 2.44M 0.5MM
PRE-PAINTED (GRAY) RIB-TYPE METAL 1.00 M(EFFECTIVE WIDTH) X 1.83M X 3. PAYMENT TERMS, 50% DOWNPAYMENT, PROGRESS BILLINGS.
180 SQM 72.00 ₱ 600.00 ₱ 43,200.00
ROOFING SHEETS GA 26 X 1.83M 0.5MM
PRE-PAINTED (GRAY) GUTTER,
30 LNM 0.701MM THICK X 2.44M LONG 19.00 ₱ 550.00 ₱ 10,450.00
4. DELIVERY OF ROOFING SHEETS WILL TAKE UPTO 7-10 BUSINESS
GA24(0.701MM) X 2.44M
PRE-PAINTED (GRAY) RIDGE ROLL, DAYS. (MADE TO ORDER) .
15 LNM 0.701MM THICK X 2.44M LONG 10.00 ₱ 550.00 ₱ 5,500.00
GA24(0.701MM) X 2.44M
PRE-PAINTED (GRAY) FLASHING,
26 LNM 0.701MM THICK X 2.44M LONG 16.00 ₱ 550.00 ₱ 8,800.00 5. ELECTRICAL LAYOUT AND ESTIMATE WILL FOLLOW DUE TO
GA24(0.701MM) X 2.44M
FASCIA BOARD 58 LNM 5" X 6 METERS 12.00 ₱ 875.00 ₱ 10,500.00
UNAVAILABILITY OF ELECTRICAL ENGINEER.
SOFFIT 58 LNM 9" X METER 332.00 ₱ 98.00 ₱ 32,536.00
TEX SCREW 1500 PCS TEK SCREW 1,950.00 ₱ 3.00 ₱ 5,850.00
FALSEWORKS 1 LOT 1 DAY 39.00 ₱ 875.00 ₱ 34,125.00
PVC PIPES 15 PCS 4" X 3M S-1000 20.00 ₱ 750.00 ₱ 15,000.00
45DEG ELBOW 10 PCS 4" DIAM. 13.00 ₱ 108.00 ₱ 1,404.00
95DEG ELBOW 10 PCS 4" DIAM. 13.00 ₱ 127.00 ₱ 1,651.00
EPOXY PRIMER 12 LITERS 4 LITERS 4.00 ₱ 1,500.00 ₱ 6,000.00
MOBILIZATION/ DEMOBILIZATION 1 LUMPSUM 1 LUMPSUM 1.00 ₱ 10,000.00 ₱ 10,000.00
TOTAL ₱ 323,515.00
(50% OF TOTAL
MANPOWER QUANTITY LABOR COST ₱ 161,757.50
DIRECT COST)
(10% OF TOTAL
TECHNICAL SUPERVISION 1.00 OCM ₱ 32,351.50
DIRECT COST)
(10% OF TOTAL
CONSTRUCTION FOREMAN 1.00 CONTRACTOR'S PROFIT ₱ 32,351.50
DIRECT COST)
SKILLED LABORERS
(TINSMITH, WELDER, ETC.,)
3.00 TOTAL COST ₱ 549,975.50
UNSKILLED LABORERS 3.00
PREPARED BY: CHECKED AND REVIEWED: CONFORMED BY: