Hangar Design Project Report

This project report summarizes the design of a new hangar at O.R. Tambo International Airport in South Africa. Two design options were presented to the client for approval. The report includes annexures that provide the design report, preliminary and final design drawings, member and connection design calculations, and a bill of quantities. The hangar is designed to house a Cessna 172R Skyhawk aircraft.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
137 views8 pages

Hangar Design Project Report

This project report summarizes the design of a new hangar at O.R. Tambo International Airport in South Africa. Two design options were presented to the client for approval. The report includes annexures that provide the design report, preliminary and final design drawings, member and connection design calculations, and a bill of quantities. The hangar is designed to house a Cessna 172R Skyhawk aircraft.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 8

Proposed New Hangar at O.

R Tambo

Assignment 02 : Structural Steel Design IV (Project Report)


By Hannes Gelderblom (46874518)

May 2019

I, Hannes Gelderblom declare that this is my own work.


Contents

1. INTRODUCTION……………………………………………………………………………………………………………….........4
2. DISCUSSION………………………………………………………………………………………………………………………...4
3. CONCLUSION………………………………………………………………………………………………………………………4

2
ACKNOWLEDGEMENT

This report was reviewed by T.B. Jordaan (Mentor / Pr. Engineer and Director of LMV Consulting Engineers), whose
recommendations and significant contributions are appreciated.

Gratitude is expressed to fellow student, G. Cooper student no 48136719 for all the input and assistance on research done.

The analysis and design were done at the Ariscourt building, 74 Hill Street, Kroonstad during March 2019 and June 2019.

This report was done by H. Gelderblom, Cand Eng. Techni, 2nd year (Btech Structural) student at UNISA.

3
1. INTRODUCTION

We confirm that UNISA has appointed us to design a nose-in maintenance hangar for a Cessna 172R Skyhawk located at O.R. Tambo
International Airport.

2. DISCUSSION

It was required to investigate various architectural and structural aspects of a hangar. Two sketch plans were presented to the Client for
approval after all the necessary requirements were discussed. Once we received
final approval, the working drawings, designs and a BOQ were compiled and submitted.

3. CONCLUSION

Please refer to the following Documents:

 Annexure A : Design Report.


 Annexure B : Preliminary and Final Design Drawings.
 Annexure C :Member and Connection Design Calculations.
 Annexure D : Bill Of Quantities.

4
Annexure A :

Design Report.

5
Annexure B :

Preliminary and Final Design Drawings.

6
Annexure C :

Member and Connection Design Calculations.

7
Annexure D :

Bill Of Quantities