NZS 3104 - Concrete Production
NZS 3104 - Concrete Production
COMMITTEE REPRESENTATION
Committee P 3104 was responsible for the preparation of this Standard and
                                                                                                                                                                                                 *
                                                                                                       consisted of the following nominating organizations:
                                                                                                                                                                                                d
                                                                                                       Co-opted Chair
                                                                                                       Cement & Concrete Association of New Zealand
                                                                                                                                                                                                 n
                                                                                                       Building Research Association of New Zealand (BRANZ)
                                                                                                       New Zealand Concrete Society
                                                                                                                                                                                              ala
                                                                                                       New Zealand Ready Mixed Concrete Association
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
© COPYRIGHT
                                                                                                                                                                                            Ze
                                                                                                       The copyright of this document is the property of the Standards Council. No
                                                                                                       part of it may be reproduced by photocopying or by any other means without
                                                                                                       the prior written permission of the Chief Executive of Standards New Zealand
                                                                                                       unless the circumstances are covered by Part III of the Copyright Act 1994.
                                                                                                                                                                                        ew
                                                                                                       Standards New Zealand will vigorously defend the copyright in this Standard.
                                                                                                       Every person who breaches Standards New Zealand’s copyright may be liable
                                                                                                                                                                             sN
                                                                                                       to a fine not exceeding $50,000 or to imprisonment for a term not to exceed
                                                                                                       three months. If there has been a flagrant breach of copyright, Standards
                                                                                                       New Zealand may also seek additional damages from the infringing party, in
                                                                                                       addition to obtaining injunctive relief and an account of profits.
                                                                                                                                                                       rd
                                                                                                       Published by Standards New Zealand, the trading arm of the
                                                                                                       Standards Council, Private Bag 2439, Wellington 6140.
                                                                                                                                                               da
                                                                                                                                       AMENDMENTS
                                                                                                                           py
                                                                                                       4
                                                                                                       On-line Subscription Service PDF Terms & Conditions
                                                                                                       - An Authorised User may download a single copy of a document and retain that copy on their personal
                                                                                                       computer for a maximum of five working days for their internal purposes. At the expiry of five working
                                                                                                       days, the Document must be deleted from the Authorised User's computer.
                                                                                                                                                                                                    *
                                                                                                       - Each Authorised User may print one hard copy of any Document for their internal purposes. These
                                                                                                                                                                                                d
                                                                                                       copies may not be used to build up a hard copy reference collection. A reference collection is defined as a
                                                                                                       collection comprising more than 10% of the number of the Documents within the Authorised User's
                                                                                                                                                                                     n
                                                                                                       subscription portfolio. All hard copies of Documents must be destroyed within 12 months or at the end of
                                                                                                                                                                                  ala
                                                                                                       their course whichever comes first.
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
                                                                                                       - Copyright subsists in each of the Documents and the full title to that copyright is at all times retained by
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                                                                                Ze
                                                                                                       - Except as otherwise may be expressly permitted under the Copyright Act 1994 Authorised Users will
                                                                                                       undertake not to copy, modify, merge with other software or documents, or circulate electronically without
                                                                                                       securing the prior written permission of SNZ. .
                                                                                                                                                                        ew
                                                                                                       - Under no circumstance may a Document, whether in electronic or hard copy form, be sold, or transferred
                                                                                                       to a third party.
                                                                                                       - Under no circumstances may any Document be placed on a network of any sort without express
                                                                                                       permission of SNZ.                                       sN
                                                                                                       - Authorised Users may not modify, adapt, translate, reverse engineer, decompile, disassemble or create
                                                                                                       derivative works based on the Documents.
                                                                                                                                                           rd
                                                                                                       - Right of access to the Subscription Service is personal to Authorised Users and can not be transferred,
                                                                                                       sold, leased, rented or loaned via a timesharing, service bureau or other arrangement.
                                                                                                                                                     da
                                                                                                       - All Authorised User identification information, including logins and passwords, are to be kept secret and
                                                                                                       secure.
                                                                                                                                               an
                                                                                                       - No Authorised User may attempt to damage, interfere or harm the SNZ website, or any network, or
                                                                                                       system underlying or connected to the Subscription Service.
                                                                                                                                          St
                                                                                                                                 ht
                                                                                                                              rig
                                                                                                                           py
                                                                                                                  Co
      Masterspec (429864) subscribers are licensed to termporarily download this document and may print
     it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
Co
  py
             rig
                ht
                                 St
                                        an
                                                 da
                                                                                                                    NOTES
                                                          rd
                                                                  sN
                                                                              ew
                                                                                           Ze
                                                                                             ala
                                                                                                n           d
                                                                                                                *
                                                                                                                                                                                                NZS 3104:2003
CONTENTS PAGE
Copyright.....................................................................................IFC
                                                                                                                                                                                                         *
                                                                                                                         Referenced documents.................................................................. 4
                                                                                                                         Foreword........................................................................................ 5
                                                                                                                                                                                                  d
                                                                                                                         Section
                                                                                                                                                                              n
                                                                                                                         1 GENERAL................................................................................ 7
                                                                                                                                                                           ala
                                                                                                                           1.1 Scope and interpretation................................................. 7
                                                                                                                         		    1.1.1 Scope................................................................. 7
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
1.1.2 Interpretation...................................................... 7
                                                                                                                                                                         Ze
                                                                                                                Amd 2
                                                                                                                           1.2 Definitions....................................................................... 7
                                                                                                               Feb '10
                                                                                                                                                            ew
                                                                                                                           2.1 General......................................................................... 10
                                                                                                                         		     2.1.1 Concrete.......................................................... 10
                                                                                                                         		     2.1.2 Limitations on specified strengths range.......... 10
                                                                                                                         		
                                                                                                                                                sN
                                                                                                                           2.2 Inspection facilities........................................................ 10
                                                                                                                           2.3 Supervision and technical control................................. 10
                                                                                                                                2.3.1 Technical control.............................................. 10
                                                                                                                         		     2.3.2 Supervision...................................................... 10
                                                                                                                                        rd
                                                                                                                         		     2.3.3 Monitoring of test results...................................11
                                                                                                                           2.4 Materials.........................................................................11
                                                                                                                         		     2.4.1 General.............................................................11
                                                                                                                              da
                                                                                                                         		     2.6.4 Accuracy.......................................................... 14
                                                                                                                           2.7 Weighing equipment..................................................... 15
                                                                                                                         		     2.7.1 General............................................................ 15
                                                                                                        py
                                                                                                                                                                                                                              1
                                                                                                       NZS 3104:2003
                                                                                                                                                                                                         *
                                                                                                       		     2.10.3 Compliance ..................................................... 21
                                                                                                         2.11 Mixing records............................................................... 21
                                                                                                                                                                                                        d
                                                                                                       		     2.11.1 Ready-Mixed Concrete.................................... 21
                                                                                                                                                                                                         n
                                                                                                       		     2.11.2 Site-Mixed Concrete........................................ 21
                                                                                                       		     2.11.3 Availability of records....................................... 21
                                                                                                                                                                                                      ala
                                                                                                         2.12 Concrete mixes – general requirements....................... 21
                                                                                                         2.13 Target mean strengths and variability control................ 21
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                                                                                                    Ze
                                                                                                       		     2.13.3 Compliance and evidence of a
                                                                                                       			             variability control.............................................. 25
                                                                                                         2.14 Concrete mix design..................................................... 26
                                                                                                                                                                                                ew
                                                                                                       		     2.14.1 Mix design information..................................... 26
                                                                                                       		     2.14.2 Confirmatory tests............................................ 26
                                                                                                         2.15 Control tests and their evaluation.................................. 26
                                                                                                       		     2.15.1 Slump tests...................................................... 26
                                                                                                       		
                                                                                                       		
                                                                                                                                                                                    sN
                                                                                                              2.15.2 Yield tests........................................................ 27
                                                                                                              2.15.3 Air content tests............................................... 28
                                                                                                       		     2.15.4 Performance test for mixers and
                                                                                                       			             truck mixers...................................................... 28
                                                                                                                                                                             rd
                                                                                                       		     2.15.5 Strength tests for proof of control..................... 29
                                                                                                       		     2.15.6 Evaluation of strength test results.................... 30
                                                                                                                                                                    da
2.16.5 Control............................................................. 33
                                                                                                         3.1 General......................................................................... 34
                                                                                                       		    3.1.1 Production........................................................ 34
                                                                                                                                  rig
                                                                                                       		    3.1.2 Compliance...................................................... 34
                                                                                                       		    3.1.3 Strengths of Prescribed Mix Concrete............. 34
                                                                                                       		    3.1.4 Definition.......................................................... 34
                                                                                                         3.2 Supervision and technical control................................. 34
                                                                                                                          py
                                                                                                       		    3.2.1 Batching........................................................... 34
                                                                                                       		    3.2.2 Certification...................................................... 34
                                                                                                       		    3.2.3 Disputes........................................................... 34
                                                                                                                Co
                                                                                                         3.3 Materials........................................................................ 34
                                                                                                       		    3.3.1 General............................................................ 34
                                                                                                       		    3.3.2 Aggregate........................................................ 35
                                                                                                       		    3.3.3 Proportion of sand and aggregate................... 36
                                                                                                       		    3.3.4 Weight batching............................................... 36
                                                                                                       2
                                                                                                                                                                                       NZS 3104:2003
                                                                                                                                                                                               *
                                                                                                                    		           3.4.3 Accuracy.......................................................... 36
                                                                                                                      3.5        Concrete mixing............................................................ 37
                                                                                                                                                                                        d
                                                                                                                    		           3.5.1 Loading............................................................ 37
                                                                                                                                                                      n
                                                                                                                    		           3.5.2 Remaining water.............................................. 37
                                                                                                                                                                   ala
                                                                                                                    4 	 CONCRETE MIXERS............................................................ 38
                                                                                                                        4.1 General......................................................................... 38
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                    		      4.1.1 Performance.................................................... 38
                                                                                                                    		      4.1.2 Operation......................................................... 38
                                                                                                                                                                 Ze
                                                                                                                    		      4.1.3 Application....................................................... 38
                                                                                                                        4.2 Performance.................................................................. 38
                                                                                                                    		      4.2.1 Mixing............................................................... 38
                                                                                                                                                     ew
                                                                                                                    		      4.2.2 Non-complying mixers..................................... 38
                                                                                                                    		      4.2.3 Mixer maintenance and repair......................... 38
                                                                                                                    		      4.2.4 Identification plates.......................................... 39
                                                                                                                        4.3 Batch mixers................................................................. 39
                                                                                                                    		
                                                                                                                    		
                                                                                                                                         sN
                                                                                                                            4.3.1 Mixer controls................................................... 39
                                                                                                                            4.3.2 Rated mixing capacity...................................... 39
                                                                                                                    		      4.3.3 Minimum mixing criteria................................... 39
                                                                                                                    		      4.3.4 Determination of minimum mixing time or
                                                                                                                                  rd
                                                                                                                    			             number of revolutions...................................... 39
                                                                                                                    		      4.3.5 Identification plates.......................................... 39
                                                                                                                         da
                                                                                                                    Figure
                                                                                                                    2.1 	 Evaluation of coefficient of variation . ................................ 24
                                                                                                               St
                                                                                                                    Table
                                                                                                               ht
                                                                                                                                                                                                                   3
                                                                                                       NZS 3104:2003
REFERENCED DOCUMENTS
                                                                                                                                                                                      *
                                                                                                       NEW ZEALAND STANDARDS
                                                                                                                                                                                     d
                                                                                                       NZS 3109:1997      Concrete construction
                                                                                                                                                                                      n
                                                                                                       NZS 3111:1986      Methods of test for water and aggregate for concrete
                                                                                                                                                                                   ala
                                                                                                       NZS 3112:1986      Methods of test for concrete
                                                                                                                          Part 1: Tests relating to fresh concrete
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                                                                                 Ze
                                                                                                       NZS 3121:1986      Specification for water and aggregate for concrete
                                                                                                                                                                           ew
                                                                                                                          (General and special purpose)
                                                                                                       NZS 3125:1991
                                                                                                                                                                  sN
                                                                                                                          Specification for Portland-limestone filler cement
engineering design
                                                                                                       AUSTRALIAN STANDARDS
                                                                                                                                               an
                                                                                                       AMERICAN STANDARD
                                                                                                       ASTM C1152/C1152M-97 – Standard Test Method for Acid-Soluble
                                                                                                       Chloride in Mortar and Concrete
                                                                                                                     py
                                                                                                       OTHER DOCUMENT
                                                                                                       TR3  – Alkali Aggregate Reaction – Minimizing the Risk of Damage to
                                                                                                              Co
                                                                                                       LATEST REVISIONS
                                                                                                       The users of this Standard   should ensure that their copies of the.
                                                                                                       above mentioned New Zealand Standards and referenced overseas
                                                                                                       Standards are the latest revisions or include the latest amendments.
                                                                                                       Amendments to New Zealand and Joint Australian/New Zealand
                                                                                                       Standards can be found on www.standards.co.nz.
                                                                                                       4
                                                                                                                                                                      NZS 3104:2003
FOREWORD
                                                                                                                                                                            *
                                                                                                                    from the original 1983 Standard.
                                                                                                                                                                       d
                                                                                                                    The principal changes incorporated into this revision are:
                                                                                                                                                          n
                                                                                                                    1. All concrete production is brought into one Standard. The provisions
                                                                                                                                                       ala
                                                                                                                       of NZS 3108 have been revised and form section 3 of this Standard.
                                                                                                                       NZS 3108 is superseded and withdrawn.
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                                                     Ze
                                                                                                                       primarily because the batching/production systems are now all
                                                                                                                       of a similar accuracy. This has been replaced with an auditing
                                                                                                                       process.
                                                                                                                                            ew
                                                                                                                    3. The word “grade” is now used in the international sense as
                                                                                                                       designating strength.
                                                                                                                                   sN
                                                                                                                    4. Consequential changes arising from NZS 3109 are included (e.g.
                                                                                                                       Normal, Special and Prescribed classes of concrete).
                                                                                                                    REVIEW OF STANDARDS
                                                                                                               ht
                                                                                                                                                                                         5
          Masterspec (429864) subscribers are licensed to termporarily download this document and may print
         it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
6
                                                                                                                                NZS 3104:2003
    Co
      py
                 rig
                    ht
                                     St
                                            an
                                                                                                                        NOTES
                                                     da
                                                              rd
                                                                      sN
                                                                                  ew
                                                                                               Ze
                                                                                                 ala
                                                                                                    n           d
                                                                                                                    *
                                                                                                                                                                                                             NZS 3104:2003
                                                                                                                                                                                                                   *
                                                                                                                 SPECIFICATION FOR CONCRETE PRODUCTION
                                                                                                                                                                                                n             d
                                                                                                                 1        GENERAL
                                                                                                                                                                                             ala
                                                                                                                 1.1      Scope and interpretation
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
1.1.1 Scope
                                                                                                                                                                                           Ze
                                                                                                                 1.1.1.1
                                                                                                                 This Standard prescribes minimum requirements for the production of fresh concrete.
                                                                                                                                                                                  ew
                                                                                                                 1.1.1.2
                                                                                                                 Section 1 of this Standard contains general clauses.
                                                                                                                 Section 2 provisions shall be complied with for the production of concrete at batching plants away from
                                                                                                                                                                        sN
                                                                                                                 the construction site, on the construction site and in a precast concrete works.
                                                                                                                 Section 3 sets out provisions for using prescribed concrete mixes.
                                                                                                                 Section 4 sets out requirements for concrete mixers.
                                                                                                                                                                  rd
                                                                                                                 1.1.2    Interpretation
                                                                                                                                                           da
                                                                                                                 1.1.2.1
                                                                                                                 In this Standard, the word “shall” indicates a requirement that is to be adopted in order to comply with
                                                                                                                 the Standard. The word “should” indicates a recommended practice.
                                                                                                                                                    an
                                                                                                                 1.1.2.2
                                                                                                                 The full titles of referenced documents cited in this Standard are given in the list of Referenced Documents
                                                                                                                                               St
                                                                                                        Amd 2
                                                                                                       Feb '10
                                                                                                                 1.2     Definitions
                                                                                                                                   ht
For the purposes of this Standard the following definitions shall apply:
                                                                                                                 ADMIXTURE. A material other than Portland cement, aggregate, or water added to concrete to modify
                                                                                                                                rig
its properties.
                                                                                                                 AGITATOR. A drum mounted integrally with a truck, which when fully or partially loaded with a concrete
                                                                                                                         py
                                                                                                                 mixture, is capable by its rotation of maintaining the concrete in a uniform mass and of discharging it
                                                                                                                 with the required degree of uniformity.
                                                                                                                 Co
                                                                                                                 AUDITING ENGINEER. The auditing person(s), independent of the supplier, who is qualified and
                                                                                                                 experienced in the production and quality control of concrete production in accordance with this Standard.
                                                                                                                 The Auditing Engineer is appointed by the supplier to audit the quality assurance of the supplier’s
                                                                                                                 plant(s) in accordance with the Standard. The Certificates of Audit issued must be signed by a Chartered
                                                                                                                 Professional Engineer or Corporate Member of the Institution of Professional Engineers New Zealand.
                                                                                                                     NOTE – The concrete plant auditing scheme run by the New Zealand Ready Mixed Concrete Association,
                                                                                                                     which itself is independently audited, is able to issue Certificates of Audit as required by this Standard.
                                                                                                                                                                                                                                   7
                                                                                                       NZS 3104:2003
                                                                                                       BATCHING PLANT.  A plant capable of weighing, in the required quantities and to the required degree
                                                                                                       of accuracy, the materials constituting a batch of concrete. A batching plant may also have a concrete
                                                                                                       mixer mounted integrally within it.
                                                                                                                                                                                                            *
                                                                                                       CERTIFICATE OF AUDIT.  A document produced by the Auditing Engineer(s) to indicate that the plant
                                                                                                                                                                                                       d
                                                                                                       complies with the requirements of this Standard at the time of the audit. The document can be issued
                                                                                                                                                                                          n
                                                                                                       as an Annual Certificate of Audit valid for a maximum period of 12 months from the date of issue or as
                                                                                                       an Interim Certificate of Audit, which is valid for three months.
                                                                                                                                                                                       ala
                                                                                                       CONCRETE MIXER.  A rotating drum, tube, trough or pan fitted with fins or paddles which is  capable
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                       of combining all the ingredients of a concrete batch into a uniform mass in not more than 70 revolutions
                                                                                                       at mixing speed and of discharging the concrete with the required uniformity.
                                                                                                                                                                                     Ze
                                                                                                       DESIGNER.   The professional engineer (or architect), his/her deputy, or authorized representative,
                                                                                                       nominated on behalf of the owner to monitor the works to which concrete is being supplied.
                                                                                                                                                                            ew
                                                                                                       GRADE.  A group of mixes produced with a common specified strength (e.g. 20 grade).
                                                                                                       INDEPENDENT EQUIPMENT TESTING.  The periodic testing of batching weigh scales by the supplier
                                                                                                                                                                   sN
                                                                                                       or other specialist, being independent of the plant’s owners or operators.
                                                                                                       NOMINAL MAXIMUM AGGREGATE SIZE.  The sieve size, in the sieve series listed in table 1 of NZS 3121.  
                                                                                                       Pertains to the coarsest sieve on which more than 15 % of the total coarse aggregate is retained.
                                                                                                                                                              rd
                                                                                                       NORMAL CONCRETE.  All concrete specified by 28-day strength within the range 17.5 to 50 MPa and
                                                                                                                                                       da
produced in accordance with the provisions of section 2 and/or sections 3 and 4 of this Standard.
                                                                                                       PLANT ENGINEER.  The engineer experienced in quality control of concrete production, and in mix
                                                                                                       design, nominated by the concrete producer to assume responsibility for mix designs and for the quality
                                                                                                                                                an
                                                                                                       of production.  He or she shall be either a Chartered Professional Engineer, or a person whose name
                                                                                                       is included on the register of the Engineering Associates' Registration Board.
                                                                                                                                           St
                                                                                                       PLANT SUPERVISOR.  The person suitably experienced in the manufacture and quality control of
                                                                                                       concrete to exercise supervision of all aspects of concrete production and delivery.
                                                                                                                               ht
                                                                                                       PRESCRIBED MIX CONCRETE.  Concrete specified by 28-day strength within the range 10 to 25 MPa,
                                                                                                       and produced in accordance to the provisions of section 3 of this Standard
                                                                                                                            rig
                                                                                                       PURCHASER.  The person or organization placing concrete orders, and to whom the producer would
                                                                                                       normally look for payment or its authorization (usually the construction contractor).
                                                                                                                      py
                                                                                                       READY-MIXED CONCRETE.  Concrete made from a mixture of Portland cement, coarse aggregates,
                                                                                                       sand, and water with or without admixtures.  It is batched at a batching plant and mixed in a concrete
                                                                                                       mixer incorporated in the plant or in truck mixers held stationary at the plant until mixing is completed.  
                                                                                                              Co
The Ready-Mixed Concrete is then delivered to the site in a suitably plastic state for placing.
                                                                                                       SAMPLE, REPRESENTATIVE.  A sample of batch concrete taken as prescribed in 3.4.3 of NZS 3112:
                                                                                                       Part 1.
                                                                                                       8
                                                                                                                                                                                            NZS 3104:2003
                                                                                                       SAMPLING, RANDOM.  Sampling by a procedure in which all of the concrete from the selection is to be
                                                                                                       made has an equal chance of being sampled, (e.g. sampled without bias, such as by the use of tables
                                                                                                       of random numbers or by other well established methods).
                                                                                                                                                                                                   *
                                                                                                       SAMPLING, SELECTED.  Sampling after the concrete has been sighted (e.g. on the basis of some
                                                                                                                                                                                              d
                                                                                                       visible feature prompting a check test) or the premeditated sampling of a particular batch prompted by
                                                                                                                                                                                 n
                                                                                                       the desire to have further information about that particular batch.
                                                                                                                                                                              ala
                                                                                                       SATELLITE PLANT.  A plant not permanently staffed but operated by personnel from a plant having a
                                                                                                       current Certificate of Audit of compliance to this Standard, using the same materials and mix designs
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                                                                            Ze
                                                                                                       SLUMP, DELIVERY.  The nominal slump value within specified tolerances that Ready-Mixed Concrete
                                                                                                       is required by the Purchaser to have at the time of its arrival and for up to 30 minutes after, subject to
                                                                                                       the requirements of 2.9.
                                                                                                                                                                   ew
                                                                                                       SLUMP, PLANT.  Slump measured at the plant when the mixing process is complete
                                                                                                       SLUMP, TARGET.  The slump desired by the producer at the time of mixing.
                                                                                                                                                          sN
                                                                                                       SPECIAL CONCRETE.  Concrete where the Purchaser has specified requirements which differ from
                                                                                                       those of normal concrete.
                                                                                                                                                    rd
                                                                                                       SPECIFIED COMPRESSIVE STRENGTH OF CONCRETE.  A singular value of strength, normally at
                                                                                                       age 28 days unless stated otherwise, denoted by the symbol f'c, which classifies a concrete as to its
                                                                                                                                              da
                                                                                                       strength class for purposes of design and construction.  That level of compressive strength is required
                                                                                                       to be equalled or exceeded by 95 % of the concrete produced.
                                                                                                       SUPPLEMENTARY CEMENTITIOUS MATERIALS (SCMs).  Materials such as fly ash, blast furnace
                                                                                                       slag and silica fume.
                                                                                                                                  St
                                                                                                       TARGET AIR CONTENT.  The air content which the concrete mix has been designed to achieve.
                                                                                                                    rig
                                                                                                       TARGET MEAN STRENGTH.  The mean strength which the concrete mix has been designed to achieve
                                                                                                       as determined by 2.13.
                                                                                                       TARGET YIELD.  The volume of concrete which the mix design is calculated to produce.
                                                                                                             py
                                                                                                       TECHNICIAN.  A person trained to take samples of materials and concrete, to prepare test specimens
                                                                                                       and to test them, all in accordance with the relevant NZ Standards.
                                                                                                       Co
                                                                                                       TRUCK MIXER.  A concrete mixer mounted integrally with a truck, and also capable of operating as an
                                                                                                       agitator for delivering a batch of mixed concrete and discharging at a construction site.
                                                                                                                                                                                                               9
                                                                                                       NZS 3104:2003
2.1 General
                                                                                                                                                                                                             *
                                                                                                       2.1.1 Concrete
                                                                                                                                                                                                        d
                                                                                                       Ready-Mixed Concrete and site-mixed concrete production shall conform to the relevant requirements
                                                                                                                                                                                           n
                                                                                                       set out in either section 2 or section 3 (respectively) of this Standard.  A plant claiming compliance with.
                                                                                                       section 2 shall display a current quality Certificate of Audit issued by an Auditing Engineer.
                                                                                                                                                                                        ala
                                                                                                       2.1.2 Limitations on specified strengths range
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                       Concretes described as Normal in NZS 3109 shall be supplied to the strength range 17.5 MPa to 50
                                                                                                       MPa to the provisions of this section.  Concrete described as Special in NZS 3109 shall be supplied
                                                                                                                                                                                      Ze
                                                                                                       to the provisions of this section together with such additional specifications as required by NZS 3109.
C2.1.2
                                                                                                                                                                             ew
                                                                                                           Concrete with strengths over 50 MPa is defined in NZS 3109 as Special Concrete. Where Normal
                                                                                                           Concretes are specified to have performance criteria other or in addition to strength, they will be
                                                                                                           defined as Special.
                                                                                                       manufacturing, quality control, and testing procedures.  He/she shall provide mix design as required
                                                                                                       by 2.14 showing (together with other mix design data) the anticipated water/cement ratio for any mix
                                                                                                       at the designed slump.
                                                                                                                                  ht
                                                                                                       The Plant Engineer shall either be based at or maintain close contact with the plant at all times, and
                                                                                                                               rig
                                                                                                       visit the plant as frequently as may be necessary to effectively discharge these responsibilities, but no
                                                                                                       less than one visit every six months.
                                                                                                           C2.3.1
                                                                                                                        py
                                                                                                           It is recommended that the plant be visited four times a year during the initial year of production or
                                                                                                           when materials, plant or staff are changed.
                                                                                                                 Co
2.3.2 Supervision
                                                                                                       2.3.2.1
                                                                                                       The Plant Supervisor, who shall be suitably experienced in the manufacture and quality control of
                                                                                                       concrete, shall exercise supervision of all aspects of plant operations and concrete production.
                                                                                                       2.3.2.2
                                                                                                       A person trained in concrete testing shall be available at the plant to carry out the appropriate frequency
                                                                                                       sampling and testing of concrete and aggregate to the provisions of NZS 3112 and NZS 3111.
                                                                                                       10
                                                                                                                                                                                                    NZS 3104:2003
                                                                                                        C2.3.2.2
                                                                                                        Testing of hardened concrete samples from a plant may be tested at a laboratory or other plant
                                                                                                        equipped for such testing remotely from the original plant, subject to appropriate transport provisions
                                                                                                                                                                                                           *
                                                                                                        for specimens.
                                                                                                                                                                                                     d
                                                                                                        Concrete Technicians are deemed to be trained if they have satisfied the requirements of New
                                                                                                        Zealand Qualifications Authority (NZQA) Unit Standard 12019 Carry Out Routine Tests on Concrete.
                                                                                                                                                                                       n
                                                                                                                                                                                    ala
                                                                                                       2.3.3 Monitoring of test results
                                                                                                       The results of all routine tests as defined in 2.15 shall be transmitted regularly to both the Plant Engineer
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
and Plant Supervisor no less frequently than monthly. The results are to be monitored by the Plant
                                                                                                                                                                                  Ze
                                                                                                       Supervisor and shall be continuously evaluated by the Plant Engineer to ensure compliance with tables
                                                                                                       2.8A and 2.8B.  Summaries of other control tests shall be reported to the Plant Engineer at intervals
                                                                                                       of not more than one month, except that any non-complying test results shall be reported immediately
                                                                                                       (see also 2.15.6).
                                                                                                                                                                        ew
                                                                                                       The Plant Engineer shall communicate with the plant as frequently as is necessary to both request and
                                                                                                       to follow up on any action, which has been deemed necessary by the monitoring. The Plant Engineer
                                                                                                       shall communicate to the plant in writing no less frequently than every three months.
                                                                                                       2.4       Materials
                                                                                                                                                              sN
                                                                                                       2.4.1 General
                                                                                                                                                        rd
                                                                                                       The materials used shall comply with the following specifications:
                                                                                                                                                 da
                                                                                                             TR3 Alkali Aggregate Reaction – Minimizing the Risk of Damage to Concrete (Guideline notes and
                                                                                                             Model Specification Clauses).
                                                                                                                     rig
                                                                                                       (c) Admixtures
                                                                                                           AS 1478 	 Chemical Admixtures for Concrete
                                                                                                               py
                                                                                                         NOTE – Testing shall generally be to the relevant part of AS 1012, except where this differs substantially from
                                                                                                         the corresponding test to NZS 3112.  Where the AS 1012 test regime is altered, the test method used shall
                                                                                                         be stated in the test report.
                                                                                                       Co
                                                                                                       For Normal Concrete, the concrete producer shall certify that the total alkali content in the concrete will
                                                                                                       not exceed 2.5 kg/m3 from all sources.  If not the concrete shall be designated as Special Concrete.
                                                                                                                                                                                                                           11
                                                                                                       NZS 3104:2003
2.4.3.1
                                                                                                                                                                                                         *
                                                                                                       Where concrete contains a coarse aggregate of nominal maximum size 19 mm or greater, but not
                                                                                                       exceeding 37.5 mm, the coarse aggregate shall be stored and batched in at least two size ranges.  For
                                                                                                                                                                                                      d
                                                                                                       concrete containing a coarse aggregate of nominal maximum size greater than 37.5 mm, the coarse
                                                                                                       aggregate shall be stored and batched in at least three size ranges.
                                                                                                                                                                                        n
                                                                                                        C2.4.3.1
                                                                                                                                                                                     ala
                                                                                                        Table 2.1 gives some grading recommendations for combining coarse aggregates and requirements
                                                                                                        for non-combined coarse aggregates.
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                                                                                   Ze
                                                                                                            Table 2.1 – Grading recommendations for combined and uncombined coarse aggregates
                                                                                                                                                                          ew
                                                                                                           	 (mm)                                           (mm)
                                                                                                       The results shall be recorded for each 100 m3 of aggregate delivered, but tests need not be more
                                                                                                                                   ht
frequent than once per day and shall not be less frequent than once per week.
                                                                                                       Whenever not fewer than 18 of the last 20 consecutive tests show compliance with NZS 3121, the
                                                                                                       frequency of testing may be reduced to one test for each 300 m3 of aggregate delivered, but it shall be
                                                                                                       not less often than once per fortnight.
                                                                                                                             py
                                                                                                       2.4.4     Sand
                                                                                                                 Co
                                                                                                       12
                                                                                                                                                                                                       NZS 3104:2003
                                                                                                                                                                                                              *
                                                                                                                  If a concrete producer has plants sharing the same aggregate supply, the frequency of testing shall
                                                                                                                  apply at one of the plants and a lesser or nil frequency may apply at the other plants, at the discretion
                                                                                                                                                                                                         d
                                                                                                                  of the Plant Engineers.
                                                                                                                                                                                            n
                                                                                                                  2.4.5.2 Aggregate producer tests
                                                                                                                                                                                         ala
                                                                                                                  When an aggregate producer elects to provide testing of materials being supplied to the plant as required
                                                                                                                  under 2.4.3.2 and 2.4.4.1, then no further testing shall be required by the concrete producer.   The
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                  copies of the results of the aggregate producers’ tests shall be held for a minimum of three years by the.
                                                                                                                  concrete producer for inspection.
                                                                                                                                                                                       Ze
                                                                                                                  2.4.5.3 Cleanness of aggregates
                                                                                                                  For each coarse aggregate size range used, samples shall be obtained at the request of the Plant
                                                                                                                                                                              ew
                                                                                                                  Engineer and tested for cleanness for compliance with the requirements of NZS 3121.
                                                                                                                  A sample of sand used shall be obtained at the request of the Plant Engineer, and tested for sand
                                                                                                                  equivalent for compliance with NZS 3121. Where more than one sand is used per batch, a combination
                                                                                                                                                                     sN
                                                                                                                  of the sands in their nominal proportions may be tested.
                                                                                                                  If the aggregate producer makes changes to the source of coarse aggregates or sands, the test frequency
                                                                                                                  required of the aggregate producer shall be one per week for the first month after the change.
                                                                                                                                                               rd
                                                                                                                   C2.4.5.3
                                                                                                                                                         da
                                                                                                                   NZS 3121 permits a sand equivalent test value (SE) as low as 60. For economical mix design, cleaner
                                                                                                                   and hence higher values of SE should be sought. It should be noted that the SE test is primarily
                                                                                                                   suitable for natural sands by evaluating clay and silt content. Manufactured sands recording low
                                                                                                                   SE values may be able to be demonstrated to be satisfactory for concrete production by a series of
                                                                                                                                                  an
June '07
                                                                                                                  This material is outside the scope of Normal Mixes and requires specification provisions under the terms
                                                                                                                  of a Special Mix.
                                                                                                                          py
                                                                                                                  2.5.1.1 Cement
                                                                                                                  Cement shall be stored and handled to provide protection against deterioration or contamination and to
                                                                                                                  be capable of being inspected at all times.  Means shall be employed whereby cement which has been
                                                                                                                  held longest at the plant is the first to be used.
                                                                                                                                                                                                                         13
                                                                                                       NZS 3104:2003
                                                                                                       2.5.1.2 Aggregates
                                                                                                       All aggregates held at or in the vicinity of the plant shall be stored and handled in such manner that
                                                                                                       they will not segregate or be contaminated by any other materials.  Stockpiles shall be free draining.
                                                                                                                                                                                                           *
                                                                                                       Provision shall be made for the separate storage and batching of each sand and each nominal size range
                                                                                                                                                                                                       d
                                                                                                       of coarse aggregate in a manner which will prevent intermingling.  Control of the aggregate feed to the
                                                                                                                                                                                         n
                                                                                                       weighing hopper shall be such that it will ensure compliance with the tolerances of accuracy set out in.
                                                                                                       table 2.2.
                                                                                                                                                                                      ala
                                                                                                       2.5.1.3 Admixtures
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                       All admixtures held at or in the vicinity of the plant shall be stored, handled and protected against
                                                                                                       deterioration or contamination. Any admixture exceeding the storage life recommended by the manufacturer,
                                                                                                                                                                                    Ze
                                                                                                       shall be removed from the plant.  All admixture stock or storage containers shall be clearly labelled.
                                                                                                                                                                           ew
                                                                                                       Product in bags shall be kept in dry storage and expiry dates shall be strictly adhered to.  
                                                                                                        C2.5.1.4
                                                                                                        Paper bags can be water soluble and thus it is essential to keep the product dry.
be so adjusted that there is an even flow of all materials throughout the discharge.
                                                                                                       2.5.3 Admixtures
                                                                                                       Dispensing and associated transfer pipe work shall be such as to prevent the premixing of admixtures
                                                                                                                                                an
                                                                                                       2.6.2 Water
                                                                                                                            rig
                                                                                                       2.6.3 Admixtures
                                                                                                       Admixtures shall be measured by sight glass or pulse meter.
                                                                                                                     py
                                                                                                       2.6.4 Accuracy
                                                                                                       Materials shall be measured in the quantities prescribed in the mix design, within the tolerances shown
                                                                                                              Co
in table 2.2.
                                                                                                       14
                                                                                                                                                                                                NZS 3104:2003
                                                                                                                                                                                                       *
                                                                                                        		                              or volumes
                                                                                                                                                                                                 d
                                                                                                        Cement (1)                       ±1 %
                                                                                                                                                                                    n
                                                                                                        (by mass)
                                                                                                                                                                                 ala
                                                                                                        Water (2)                        ± 2.5 %
                                                                                                        (by mass or volume)
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
Aggregates (1) ±2 % for any fraction provided that the total mass of aggregate
                                                                                                                                                                               Ze
                                                                                                        (by mass)                        is within 1 %
                                                                                                                                                                     ew
                                                                                                        (by mass or volume)
                                                                                                         NOTE –
                                                                                                         (1) For cement and aggregates, the maximum permitted tolerances shall be as in this table or the maximum
                                                                                                         (2)
                                                                                                                                                            sN
                                                                                                             scale division permitted in table 2.3, whichever is the greater.
                                                                                                               For water, the target batch mass/volume may not be fully dispensed, the held back water only being
                                                                                                               used if necessary for workability adjustments.  
                                                                                                                                                      rd
                                                                                                         (3)   The admixture dispenser accuracy shall be checked at the standard admixture dosage levels for a 1 m3
                                                                                                               load.  For admixtures, where the manufacturer recommends greater accuracy, such recommendations
                                                                                                               shall be complied with.
                                                                                                                                                da
                                                                                                       2.7.1   General
                                                                                                                                   St
                                                                                                       2.7.1.1
                                                                                                       The displayed mass shall be readily discernible to the operator.
                                                                                                       2.7.1.2
                                                                                                                        ht
                                                                                                       Where the displayed mass is indicated on a scale, the scales shall be graduated in divisions not greater
                                                                                                       than those given in table 2.3.
                                                                                                                     rig
materials.
                                                                                                       If a combined scale is used, the cement shall be weighed first and the scale accuracy shall be that
                                                                                                       Co
                                                                                                                                                                                                                  15
                                                                                                       NZS 3104:2003
                                                                                                                                                                                                                *
                                                                                                                                                                             (kg)
                                                                                                                                                                                                           d
                                                                                                                                                         Cement scales                  Aggregate scales
                                                                                                                                                                                             n
                                                                                                        Mixers less than 2 m3 capacity                           5                              10
                                                                                                                                                                                          ala
                                                                                                        Mixers of 2 m3 capacity and over                        10                              20
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                                                                                        Ze
                                                                                                       2.7.3   Testing and accuracy of weighing equipment
                                                                                                       2.7.3.1 Facilities
                        Amd 2                                                                          Test weights or weigh testing equipment shall always be available for promptly checking the accuracy of
                                                                                                                                                                               ew
                       Feb '10                                                                         all weighing equipment.  Test weights and weigh testing equipment shall be certified as to their calibration.
                                                                                                                 points at, or near, 10 %, 50 %, and 90 % of the full working range.  An error calculation shall be
                                                                                                                 carried out for each scale check and shall comply with the requirements of table 2.4;
                                                                                                       (b) Independent scale checks shall follow the provisions of (a) above and shall comply with the
                                                                                                                                                  an
                         Amd 2
                        Feb '10                                                                            requirements of table 2.4.
                                                                                                                                            St
                                                                                                       16
                                                                                                                                                                                                           NZS 3104:2003
                                                                                                                                                                                                                 *
                                                                                                                  Routine testing by plant supervisor
                                                                                                                                                                                                            d
                                                                                                                  Cement scales – lever arm              Once per month (2)                    0.4 % of working range
                                                                                                                                                                                                n
                                                                                                                  Cement scales – load cell              Once per 3 months (3)                 0.4 % of working range
                                                                                                                                                                                             ala
                                                                                                                  Aggregate scales – lever arm           Once per 3 months (2)                 0.4 % of working range
                                                                                                                                                         Once per 6 months (3)
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
                                                                                                                                                                                           Ze
                                                                                                                        Scales                           Once per 6 months                     2.0 %
                                                                                                                         Meter                           Once per 6 months                     2.0 %
                                                                                                                  Independent testing by equipment manufacturer/supplier (4)
                                                                                                                                                                                     ew
                                                                                                                  Cement scales                          As required but not less than .       0.2 % of working range
                                                                                                                                                         once per 2 years
                                                                                                                  Aggregate scales                                      sN
                                                                                                                                                         As required but not less than
                                                                                                                                                         once per 2 years
                                                                                                                                                                                               0.2 % of working range
                                                                                                                  Admixture dosing
                                                                                                                       Sight glass                       Once on installation                  2.0 %
                                                                                                                                                           da
(1) Maximum variation relates to the summation of errors at each stage of a weigh check.
                                                                                                                 of table 2.4.  Where error calculations show that the measuring equipment is outside the requirements of
                                                                                                                 table 2.4, the Plant Supervisor shall take immediate steps to correct the error and retest the components.  
                                                                                                                 If independent testing proves that the equipment complies with the requirements of this specification,
                                                                                                                 the equipment manufacturer’s representative shall provide a certificate to that effect, which shall include
                                                                                                                 reference to table 2.4 of this Standard and be available for inspection at the plant.
                                                                                                                                                                                                                            17
                                                                                                       NZS 3104:2003
                                                                                                                                                                                                              *
                                                                                                       2.8.1.1
                                                                                                                                                                                                         d
                                                                                                       The mixing time shall be measured from the time when all materials are in the mixer and the time at
                                                                                                                                                                                           n
                                                                                                       which discharge from the mixer occurs. Such mixing time shall comply with manufacturer's requirements
                                                                                                       for the plant and produce concrete that complies with the uniformity requirements of 2.15.4.
                                                                                                                                                                                        ala
                                                                                                        C2.8.1.1
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                        Typical times for free fall drum mixers are 1.5 minutes for mixers with a capacity of 1 m3 or less; for
                                                                                                        larger mixers this time should be increased by 20 sec for each additional 0.5 m3 capacity. Modern
                                                                                                                                                                                      Ze
                                                                                                        high intensity mixers can have mixing times as low as 60 seconds.
2.8.1.2
                                                                                                                                                                             ew
                                                                                                       The interior of the mixer shall be examined daily and any build up of hardened concrete which may
                                                                                                       reduce the efficiency of the mixer shall be removed before the mixer is used again.
                                                                                                       2.8.2.1
                                                                                                                                                                    sN
                                                                                                       Water shall be measured, added to the mix, and the mixing operation completed at the batching plant.  
                                                                                                       After all materials as batched are in the truck mixer, the drum shall turn a minimum of 70 revolutions
                                                                                                                                                              rd
                                                                                                       at mixing speed.  If further solid material or water is added the drum shall complete at least a further
                                                                                                       30 revolutions at mixing speed before leaving the plant.  Water shall not be added to the bowl after the
                                                                                                                                                        da
truck mixer has left the batching plant except as permitted for Ready-Mixed Concrete in 2.9.3.
                                                                                                       2.8.2.2
                                                                                                       The number of revolutions of the drum, as specified in 2.8.2.1, may be reduced to such a figure as
                                                                                                                                                 an
                                                                                                       is shown to be necessary by the mixer performance test prescribed in 2.15.4 to achieve the required
                                                                                                       degree of uniformity of the concrete.
                                                                                                                                            St
                                                                                                       2.8.2.3
                                                                                                       The rotational speed of the truck-mixing bowl shall be such as to ensure that the requirements of the
                                                                                                       mixer performance test shall be met.  The minimum speed shall not be less than the manufacturer’s
                                                                                                                                ht
                                                                                                       recommendation for optimum mixing speed, and in any case not less than 10 RPM.
                                                                                                                             rig
                                                                                                       2.8.2.4
                                                                                                       If the size of the batch is at least 1 cubic metre less than the rated capacity, the number of revolutions
                                                                                                       at mixing speed may be reduced, but to no fewer than 50, provided the requirement of the mixer
                                                                                                       performance test are met.
                                                                                                                      py
                                                                                                       2.8.2.5
                                                                                                       After completion of mixing, all revolutions of the drum shall be at agitating speed as referenced in 2.9.2.1.
                                                                                                               Co
                                                                                                       2.8.2.6
                                                                                                       The interior of the mixer shall be examined daily and any accretion of hardened concrete which may
                                                                                                       reduce the efficiency of the mixer shall be removed before the mixer is used again.
                                                                                                       18
                                                                                                                                                                                                         NZS 3104:2003
2.9 Transportation
                                                                                                                                                                                                               *
                                                                                                        Amd 2
                                                                                                                 Except as may be provided in 2.9.4, delivery shall be made in a truck mixer or an agitator of the revolving
                                                                                                       Feb '10
                                                                                                                 drum type, either of which shall be capable of maintaining the mix in a homogeneous state complying
                                                                                                                                                                                                          d
                                                                                                                 with 2.15.4 and 2.9.2.
                                                                                                                                                                                            n
                                                                                                                 2.9.2   Delivery by truck mixer or agitator
                                                                                                                                                                                         ala
                                                                                                                 2.9.2.1
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                 The speed of revolution of the drum during agitation while in transit to the site shall be neither less than
                                                                                                                 2 RPM nor more than 6 RPM.
                                                                                                                                                                                       Ze
                                                                                                                 2.9.2.2
                                                                                                                 Full discharge of concrete from agitators and truck mixers shall be completed within 90 minutes or such
                                                                                                                                                                              ew
                                                                                                                 other period as may be designated by the Plant Engineer after the introduction of the cement to the
                                                                                                                 aggregates or of the mixing water to the cement and aggregates.
                                                                                                                   NOTE – The use of some admixtures (e.g. set retarding) and additives (e.g. flyash materials) and ambient
                                                                                                                                                                     sN
                                                                                                                   temperature conditions will influence the time permitted.
                                                                                                                 (b) The amount of water added shall be limited to increase the slump to the nominated value and shall
                                                                                                                     under no circumstances exceed 10 litres per cubic metre of concrete;
                                                                                                                                            St
(c) After the water addition the mixer bowl shall be turned at a minimum of 30 revolutions at mixer speed;
                                                                                                                 (d) The slump shall be re-measured and the amount of added water recorded on the concrete delivery
                                                                                                                                 ht
docket.
                                                                                                                 2.9.3.2
                                                                                                                              rig
                                                                                                                 For concrete that is to be supplied by a Ready-Mixed Concrete producer, no addition to the concrete
                                                                                                                 shall be made on the construction site by the Purchaser, without the prior agreement of the producer.  
                                                                                                                 If any addition is made without such approval, the Purchaser shall assume responsibility for the mix.
                                                                                                                         py
                                                                                                                 2.9.4.1
                                                                                                                 Subject to agreement by the Purchaser and Plant Engineer, concrete may be transported in suitable
                                                                                                                 non-agitating equipment if the mix is designed for this purpose.
                                                                                                                 2.9.4.2
                                                                                                                 The bodies of non-agitating equipment shall be smooth and watertight.
                                                                                                                                                                                                                          19
                                                                                                       NZS 3104:2003
                                                                                                       2.9.4.3
                                                                                                       Covers for protection against weather conditions (either wetting or drying) shall be provided when required.
                                                                                                                                                                                                             *
                                                                                                       2.9.4.4
                                                                                                       Where discharge from non-agitating equipment may not be completed without risk of undue delay, either
                                                                                                                                                                                                        d
                                                                                                       in transit or on site, this type of transport shall not be used.
                                                                                                                                                                                             n
                                                                                                       2.10    Responsibility for mix design
                                                                                                                                                                                          ala
                                                                                                       2.10.1 Normal Concrete (N)
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                       The concrete producer shall assume responsibility for mix designs for all Normal Concrete of specified
                                                                                                       compressive strength (N) 17.5 MPa to 50 MPa and their properties as follows:
                                                                                                                                                                                        Ze
                                                                                                       (a) The proportions and amounts of coarse aggregate and sand;
                                                                                                                                                                             ew
                                                                                                       (b) The water/cement ratio and cement content to meet the appropriate performance requirements set
                                                                                                           out in 2.13.1;
                                                                                                         NOTE – This also applies to grouts supplied to the requirements of NZS 4210.
                                                                                                                                                       da
                                                                                                        C2.10.2
                                                                                                        If a mix from the Normal Concrete range is specified with a special requirement as specified in
                                                                                                                                           St
                                                                                                       2.10.2.1
                                                                                                                               ht
                                                                                                       For all Special Concrete mixes the Purchaser or Designer shall specify the properties required, together
                                                                                                       with specified testing and compliance tolerances.  The concrete producer shall assume responsibility
                                                                                                                            rig
                                                                                                       for mix designs to meet the specified requirements.  Any grounds for the possible non-compliance are
                                                                                                       to be stated by the producer.
                                                                                                        C2.10.2.1
                                                                                                                      py
                                                                                                        The specifier/Purchaser is required to specify the special parameters required for the concrete and to
                                                                                                        give a method by which the producer can demonstrate compliance. A CCANZ publication ‘Specifying
                                                                                                        Concrete for Performance’ gives guidance to the selection of concretes used in special conditions.
                                                                                                              Co
                                                                                                        It may be appropriate to use compressive strength testing at alternative times rather than the normal
                                                                                                        28 day period.
                                                                                                        It will be necessary for the specifier to have discussions with the producer as to initial acceptance of
                                                                                                        test results and the ongoing method of quality assurance.
                                                                                                       20
                                                                                                                                                                                             NZS 3104:2003
                                                                                                       2.10.3 Compliance
                                                                                                       If requested, the Plant Engineer to the plant shall advise the Designer or Auditing Engineer of the source,
                                                                                                       type, and size of aggregates, type and brand of cement, target strength, water/cement ratio, and the
                                                                                                                                                                                                   *
                                                                                                       type and quantity of admixture (if any) being used, together with confirmatory evidence that the concrete
                                                                                                       being produced complies with all the requirements.
                                                                                                                                                                                              d
                                                                                                       2.11    Mixing records
                                                                                                                                                                                 n
                                                                                                                                                                              ala
                                                                                                       2.11.1 Ready-Mixed Concrete
                                                                                                       At a Ready-Mixed Concrete plant records shall be kept which identify for each batch the following:
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                                                                            Ze
                                                                                                       (b) Delivery slump ordered, target slump, and the actual slump when measured;
                                                                                                                                                                   ew
                                                                                                       (c) Details of mix proportions, either directly or by code number and the name and quantity of admixture,
                                                                                                           if any;
                                                                                                       (b) Designed proportions, target slump, amount of added water and admixture dosage;
                                                                                                                                        an
                                                                                                       All concrete shall be proportioned to produce concrete at the nominated or delivery slump, as the case
                                                                                                       may be (within the tolerances permitted in table 2.6) and the concrete shall be able to be compacted to
                                                                                                       a dense state by high frequency vibration or by such other method as has been specified.
                                                                                                              py
                                                                                                       2.13.1.1
                                                                                                       The criteria for the design of Normal Concrete mixes, 17.5 MPa to 50 MPa strengths at 28 days, shall
                                                                                                       be based on random representative samples with not more than 5 % of results falling below f' c .
                                                                                                        C2.13.1.1 The design strength is based upon f'm = f'c + 1.64 Sd where Sd is the standard deviation
                                                                                                        for the particular mix and f'm is the target mean strength.
                                                                                                                                                                                                                     ➤
                                                                                                                                                                                                               21
                                                                                                       NZS 3104:2003
                                                                                                        The use of the above formula provides for a 1 in 20 probability that the concrete strength will be
                                                                                                        below the specified value.
                                                                                                                                                                                                                 *
                                                                                                        The generic equation is f'c + k Sd . Both Sd and k are factors that are influenced by test results and
                                                                                                        the frequency of testing.
                                                                                                                                                                                                          d
                                                                                                        The coefficient of variation (COV) is determined from the equation below wherein 30 results have
                                                                                                                                                                                            n
                                                                                                        been used to develop Sd and mean strength.
                                                                                                                                                                                         ala
                                                                                                       2.13.1.2
                                                                                                       Tables 2.5A and 2.5B set out the criteria for compliance with 2.13.1.1 for Normal Concrete based upon
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                                                                                       Ze
                                                                                                                        Table 2.5A – Criteria for plants with a minimum testing regime of
                                                                                                                                             10 tests per month (f'c + 1.64 Sd )
                                                                                                                                                                               ew
                                                                                                                                                              Specified strength f'c MPa
                                                                                                        C2.13.1.2
                                                                                                                            rig
                                                                                                        Historical data has provided a series of Sd values which for the purposes of providing a monitoring
                                                                                                        mechanism have been used to create the maximum coefficients of variation used in table 2.5A and
                                                                                                        table 2.5B. The calculation to establish the coefficient of variation is based on a minimum of 30 results.
                                                                                                        		                                     Sd
                                                                                                                      py
                                                                                                                            COV =                            x 100
                                                                                                                                         Mean strength
                                                                                                        For plants using the six tests per month criteria there is a requirement to ensure a full set of 30 results
                                                                                                              Co
                                                                                                        is achieved for one strength grade. The balance of testing should be distributed between all other
                                                                                                        mixes produced by the plant in the year.
                                                                                                        For plants having a special testing regime of more than 20 tests per month, an alternative statistical
                                                                                                        system may be agreed on between the producer/Purchaser/Auditing Engineers for Special Concrete
                                                                                                        supply to a project.
                                                                                                        Where there are no historical records of the use or experience of local materials, it is recommended that
                                                                                                        an Sd of 6 MPa be adopted for the initial mix design and the mixes modified as records demonstrate
                                                                                                        lower variability.
                                                                                                       22
                                                                                                                                                                                                              NZS 3104:2003
                                                                                                                  2.13.1.2.1
                                                                                                                  Satellite plants can only be linked with a parent plant complying with the requirements of table 2.5A or
                                                                                                                  table 2.5B.
                                                                                                                                                                                                                    *
                                                                                                                  2.13.1.3 Compliance requirements
                                                                                                                                                                                                                d
                                                                                                                  If the mean strengths of table 2.5A or table 2.5B and/or coefficients of variation are not met, the following
                                                                                                                                                                                                  n
                                                                                                                  actions shall be implemented:
                                                                                                                                                                                               ala
                                                                                                                  (a) Strength below target mean COV within 1 % of value, the target strength of the mix/es shall be raised.
                                                                                                                      An interim Certificate of Audit will be issued for a three-month period after which time test results are
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                                                                                             Ze
                                                                                                                  (b) Strength above target mean of table 2.5C and COV above the limits of table 2.5A or table 2.5B but
                                                                                                                      below the values of  table 2.5C, the cause of the variation shall be determined. An interim Certificate
                                                                                                                      of Audit will be issued for a three-month period after which time test results are to be submitted to
                                                                                                                                                                                    ew
                                                                                                                      the Auditing Engineer for re-assessment;
                                                                                                                  (c) Strength below mean and COV greater than 1 % limit above the values of  table 2.5A or table 2.5B,
                                                                                                                      the target strength of the mix/es shall be raised. The Certificate of Audit shall be withdrawn until such
                                                                                                                                                                        sN
                                                                                                                      time as subsequent resubmitted test data, is deemed to comply. The plant shall operate to the test
                                                                                                                      frequency provisions of one test per day of operation and subsequent testing frequency of one test
                                                                                                                      for each 75 cubic metres of daily production.
                                                                                                                                                                   rd
                                                                                                                    NOTE – The size of sets above 30 results and numbers of sets available for review will influence the decision
                                                                                                                    in respect of actions taken in an overall audit of capacity for the plant.
                                                                                                                                                           da
                                                                                                                  If test frequencies for sampling and testing or calibration checks for equipment are not carried out in
                                                                                                                  accordance with the appropriate clauses of this Standard or nominated Standards, then an Certificate
                                                                                                                  of Audit shall be withdrawn or withheld.
                                                                                                                                                    an
                                                                                                                  Where a plant is submitting a first series of 30 results as under 2.13.3.2, the COV shall meet the
                                                                                                                  requirements of figure 2.1.
                                                                                                                                              St
                                                                                                                   C2.13.1.3
                                                                                                                   Variability and monitoring matters are specified later in this Standard.
                                                                                                                                  ht
                                                                                                                    If the re-assessment referred to in (b) establishes that reducing the variation cannot be achieved,
                                                                                                                    then the audit certificate requiring compliance with table 2.5C could be extended for a further period
                                                                                                                               rig
                                                                                                         Amd 1
                                                                                                       June '07     of 9 months.
Grade 17.5 20 25 30 35 40 45 50
                                                                                                                                                                                                                                 23
                                                                                                       NZS 3104:2003
                                                                                                                                                                                                          *
                                                                                                                                                                                         n           d
                                                                                                                                                                                      ala
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                                                                                    Ze
                           Amd 1
                         June '07
                                                                                                                                                                           ew
                           Amd 1
                         June '07
                                                                                                                                                                  sN
                                                                                                                                                            rd
                                                                                                                                                      da
                                                                                                                                               an
                                                                                                       the Designer.  The Plant Engineer having due regard to the local materials being used to manufacture
                                                                                                       the concrete shall select Sd .
                                                                                                                            rig
                                                                                                        C2.13.2.1
                                                                                                        Significant other issues begin to influence the ability of Special Concrete to reach higher strengths
                                                                                                                     py
                                                                                                        such as aggregate strength and shape. The Plant Engineer may need to discuss the Sd factor with
                                                                                                        the Designer because a skew statistical distribution factor may arise. Historical data indicates that
                                                                                                        typical Sd values for high strength concrete range from 5 – 8 MPa.
                                                                                                              Co
                                                                                                        C2.13.2.2
                                                                                                        The specifier is required to specify the special parameter required for the concrete and to give a
                                                                                                        method by which a producer is required to demonstrate compliance.
                                                                                                       24
                                                                                                                                                                                                           NZS 3104:2003
It may be appropriate to use strength testing at alternative times rather than the normal 28-day period.
It will be necessary to develop a sampling and testing compliance regime for Special Concretes.
                                                                                                                                                                                                                 *
                                                                                                                  2.13.3 Compliance and evidence of a variability control
                                                                                                                                                                                                            d
                                                                                                                  2.13.3.1
                                                                                                                                                                                              n
                                                                                                                  Evidence is required to establish that an effective control of variability is in place as set out in 2.13.3.2,
                                                                                                                                                                                           ala
                                                                                                                  and the suitability of the mix designs as set out in 2.13.3.3.
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                                                                                         Ze
                                                                                                                  with NZS 3109, shall comply with section 3 of this Standard or shall undertake prior testing as set out
                                                                                                                  in (a) and (b).
                                                                                                                                                                                ew
                                                                                                                  (a) A plant shall establish the ratio of materials and cement to be used at the plant by carrying out a
                                                                                                                      series of tests as described in 2.13.3.3, and shall generate a series of not fewer than 30 results in
                                                                                                                      one mix. The relationship of materials, cement, and strength as described in 2.13.3.3, together with
                                                                                                                                                                       sN
                                                                                                                      the analysis of the 30 results for compliance with figure 2.1, shall be carried out by the Plant Engineer
                                                                                                                      and submitted to an Auditing Engineer or Designer; and
                                                                                                                  (b) To establish compliance with the interim audit status in this Standard, a plant shall establish a
                                                                                                                                                                 rd
                                                                                                                      relationship between materials and cement to be used at the plant by carrying out a series of tests
                                                                                                                      to generate a series of not fewer than 10 results in each mix required for audit status. An analysis
                                                                                                                      for compliance with the 28-day target strengths of table 2.5C or the 28-day f'c strengths of table
                                                                                                                                                          da
                                                                                                                      2.5A when compression tested at 7 days, together with compliance with the COV values of table
                                                                                                                      2.5C, shall be carried out by the Auditing Engineer or Designer. If compliance with either condition
                                                                                                                      is met and an independent weigh scale check of the plant has been satisfactorily completed, then a
                                                                                                                                                   an
                                                                                                         Amd 1
                                                                                                       June '07       3-month interim audit certificate can be issued.
                                                                                                                  A group of concrete mixes shall be designed using aggregates and cement to be used at the plant..
                                                                                                                  The mixes shall either be designed on the basis of cement contents of 200, 250, 300, 350, 400 and.
                                                                                                                  450 kg/m3, or on the basis of actual strength design mixes for 17.5, 20, 30, 40, 45 and 50 MPa. All the
                                                                                                                                  ht
mixes shall be designed for a 100 mm slump and use 19 mm maximum aggregate size.
                                                                                                                  A minimum of two mixes at each cement content or strength shall be sampled and tested for compressive
                                                                                                                               rig
                                                                                                                  strength at 28 days. The strength results shall be plotted against cement content to produce group strength
                                                                                                                  relationship curve with MPa strength on the vertical axis and cement content in kg on the horizontal axis.
                                                                                                                        py
                                                                                                                      be included in the curve. Where an admixture may only be used over a range of concrete within
                                                                                                                      the group, the concrete mix at the limit of the range of admixture use shall be tested both with and
                                                                                                                      without the admixture and the results plotted;
                                                                                                                  (b) The group relationship shall be revalidated every three years unless it can be demonstrated to the
                                                                                                                      Auditing Engineer that the production compressive strength results cover the group range and indicate
                                                                                                                      that the relationship has not changed;
                                                                                                                  (c) The group relationship of materials and cement shall be permitted to be adopted for use on other
                                                                                                                      plants that are using the same materials.
                                                                                                                                                                                                                             25
                                                                                                       NZS 3104:2003
                                                                                                                                                                                                             *
                                                                                                       mixes tested.  
                                                                                                                                                                                                        d
                                                                                                       2.14    Concrete mix design
                                                                                                                                                                                           n
                                                                                                       2.14.1 Mix design information
                                                                                                       The total water required for each concrete mix design at the desired target slump shall be determined
                                                                                                                                                                                        ala
                                                                                                       by the Plant Engineer.  Information showing the batch masses, additives dosage, target yield, target
                                                                                                       strength and target slump of each mix design together with other appropriate mix design details shall be
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
available. This information shall be kept at the plant for a minimum of three years and shall be available
                                                                                                                                                                                      Ze
                                                                                                       for inspection by the Designer or Auditing Engineer.  The information shall make due allowance for the
                                                                                                       effect of water in the aggregates on both the added water and the aggregate masses.
                                                                                                                                                                            ew
                                                                                                       2.14.2.1
                                                                                                       At the start of production at the plant, checks on the total water content shall be carried out and during
                                                                                                       production at the discretion of the Plant Engineer and/or Plant Supervisor on random batches.
                                                                                                       2.14.2.2
                                                                                                                                                                    sN
                                                                                                       Where total water content tests are carried out, the following information shall be documented at the plant:
                                                                                                                                                              rd
                                                                                                       (a) Date and time;
                                                                                                       (d) Slump;
                                                                                                                                                an
                                                                                                       (g) Yield;
                                                                                                                               ht
                                                                                                       Where any of the above tests have the method of test specified in NZS 3111 or NZS 3112, such a
                                                                                                       method shall be employed.
                                                                                                              Co
                                                                                                       2.15.1.1
                                                                                                       Practicable measures shall be taken to ensure that the specified delivery slump of the concrete is within
                                                                                                       the tolerances required by table 9.1 of NZS 3109, subject to the provisions of 2.9.1 for Ready-Mixed
                                                                                                       Concrete.  A slump test shall always be taken when a compression test is made.  Slump tests shall be
                                                                                                       carried out in accordance with NZS 3112: Part 1.
                                                                                                       26
                                                                                                                                                                                                                 NZS 3104:2003
                                                                                                                  2.15.1.2
                                                                                                                  No more than 20 % of 30 consecutive tests taken to determine the initial mixing slump shall fall outside
                                                                                                                  the limits set out in table 2.6.
                                                                                                                                                                                                                        *
                                                                                                                                           Table 2.6 – Maximum tolerances for slump at the plant
                                                                                                                                                                                                                    d
                                                                                                                   		                                                                 Tolerance
                                                                                                                                                                                                   n
                                                                                                                        Target slump                    Representative sample                          Snatch sample
                                                                                                                                                                                                ala
                                                                                                                            (mm)                                (mm)                                       (mm)
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                                                                                              Ze
                                                                                                                             70 – 110                               ±20                                       ±30
                                                                                                         Amd 1
                                                                                                       June '07            120 and above                            ±30                                       ±40
                                                                                                                                                                                    ew
                                                                                                                    NOTE – Target slump is the slump selected by the producer to take into account the distance and temperature
                                                                                                                    conditions for delivery. In the case of site production it is likely to be the same as the specified value.
                                                                                                                  2.15.2.1 Purpose
                                                                                                                  The yield test, where the density of the freshly mixed and compacted concrete is measured, has two
                                                                                                                                               St
purposes:
                                                                                                                  (a) For the Purchaser, the volume of concrete yielded by the batch is calculated by comparing the
                                                                                                                      measured wet density of the concrete with the actual batch mass;
                                                                                                                                   ht
                                                                                                                  (b) For the mix Designer, the measured density can be compared with the design density of the mix
                                                                                                                                rig
                                                                                                                      tested. This will give the earliest available indication of a change in water demand or air content that
                                                                                                                      may affect strength.
                                                                                                                    NOTE – The air content should be measured in all yield tests, including non air-entrained concrete, because
                                                                                                                        py
                                                                                                                    there will always be some residual air. This is normally in the range of 1.0 % to 2.0 %. Loss of precision in the
                                                                                                                    evaluation of yield occurs if this air is not allowed for.
                                                                                                                  Co
                                                                                                                  2.15.2.2 General
                                                                                                                  Yield tests shall be carried out in accordance with NZS 3112: Part 1, except for calculating yield Y for
                                                                                                                  the purpose of 2.15.2.1(a), V shall equal the nominal cubic metre of concrete which was batched.
                                                                                                                  2.15.2.3 Frequency
                                                                                                                  Yield tests on random batches covering a wide range of mixes produced shall be carried out not less
                                                                                                                  than once per week. At a ready-mixed satellite plant, a yield test shall be taken for each five days of
                                                                                                                  plant operation.
                                                                                                                                                                                                                                    27
                                                                                                       NZS 3104:2003
                                                                                                       2.15.2.4 Compliance
                                                                                                       For compliance with  2.15.2.1(a), the control shall be such that the average yield of any six consecutive
                                                                                                       yield tests shall not be less than 1.00 and no result shall fall below 0.98. Such results shall be available
                                                                                                                                                                                                             *
                                                                                                       to the Purchaser.
                                                                                                                                                                                                        d
                                                                                                       2.15.2.5 Mix evaluation
                                                                                                                                                                                           n
                                                                                                       A minimum of three confirmatory yield tests shall be carried out on each new basic design when it is
                                                                                                       first introduced for regular production. If the result of any yield test differs by more than ±1 % from the
                                                                                                                                                                                        ala
                                                                                                       target yield established by the Plant Engineer in his mix design, the proportions of the mix concerned
                                                                                                       shall be adjusted and a further yield test conducted until a result within the above tolerances is achieved.
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                                                                                      Ze
                                                                                                       2.15.3.1
                                                                                                       Where air entraining admixtures are used, air entrainment tests shall be carried out at not less than
                                                                                                                                                                            ew
                                                                                                       once a day, except where nine out of 10 consecutive results of tests taken comply with the tolerances
                                                                                                       set out in 2.15.3.3(b).  In this case, the frequency of testing may then be reduced to once per week. At
                                                                                                       a satellite plant one air test shall be taken for every five days of plant operation.
                                                                                                       2.15.3.2                                                     sN
                                                                                                       The method of test shall comply with the requirements of NZS 3112: Part 1.
                                                                                                       2.15.3.3
                                                                                                                                                              rd
                                                                                                       For at least nine out of 10 consecutive results of the tests taken, the total entrained plus entrapped air
                                                                                                       shall fall within the limits set out below:
                                                                                                                                                       da
                                                                                                       (b) The measured air content shall be within ±1.5 % of the target air content.
                                                                                                                                                an
                                                                                                       2.15.4.1
                                                                                                       Evaluation tests shall be conducted on mixers and truck mixers at 12-monthly intervals, and after any
                                                                                                       modification to the mixer or method of charging the mixer.
                                                                                                                               ht
                                                                                                       2.15.4.2
                                                                                                                            rig
                                                                                                       These tests shall be on snatch samples taken at the one-sixth and five-sixths point of a full batch as
                                                                                                       discharged.  Test results shall not differ by more than the amounts set out in table 2.7.
                                                                                                       2.15.4.3
                                                                                                                      py
                                                                                                       Mixing times shall be those normally used for batching concrete at the plant.
                                                                                                              Co
                                                                                                       28
                                                                                                                                                                                                                        NZS 3104:2003
                                                                                                                                                                                                                                *
                                                                                                          Test                                                                Maximum permissible difference between
                                                                                                        		                                                                     the results of two samples from a batch
                                                                                                                                                                                                       n                  d
                                                                                                                     Weight per cubic metre                                                              30 kg
                                                                                                                                                                                                    ala
                                                                                                                                 Slump 	  30 mm
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
Air content 1 %
                                                                                                                                                                                                  Ze
                                                                                                         Mean compressive strength at 28 days of 	                          10 % of f'c or 3.0 MPa whichever is the greater
                                                                                                         5* specimens taken from each sample
* Where the number of test specimens comprising tests for compressive strength is permitted by 2.15.5.2 to
                                                                                                                                                                                      ew
                                                                                                            be reduced to two, the number of test specimens for the mixer test may also be reduced from five to two
                                                                                                            provided the range between the two results does not exceed 2 MPa. If this occurs, the test must be repeated.
Part 2, only by personnel who have had proper training in the techniques required:
                                                                                                        C2.15.5.1
                                                                                                        It should be noted that special precautions are required when sampling and testing concretes of
                                                                                                        strengths more than 50 MPa.
                                                                                                               py
                                                                                                                                                                                                                                               29
                                                                                                       NZS 3104:2003
                                                                                                                                                                                                                      *
                                                                                                       The minimum frequency of compressive strength testing at the Ready-Mixed Concrete plant shall be
                                                                                                       not less than any of the following requirements:
                                                                                                                                                                                                                 d
                                                                                                       (a) An average of one test per 75 m3 of production up to 15,000 m3 per annum, with an additional test
                                                                                                                                                                                                  n
                                                                                                           for every 250 m3 above 15,000 m3;
                                                                                                                                                                                               ala
                                                                                                       (b) At least 10 tests per month except that in the case of plants producing less than 9000 m3 per annum
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                           6 tests per month are permitted, provided that the mixes are designed and evaluated on the basis
                                                                                                           of table 2.5B and 2.15.6;
                                                                                                                                                                                             Ze
                                                                                                       (c) A satellite plant shall test at the rate of one test per 75 cubic metres of production.
NOTE – These test results may be combined with those from the parent plant for analysis purposes as de-
                                                                                                                                                                                   ew
                                                                                                         scribed in 2.15.6.
                                                                                                       When early age or field cured tests are required they shall be considered additional to the above
                                                                                                                                                                  rd
                                                                                                       requirements except at the discretion of the Designer.
                                                                                                       2.15.6.1 General
                                                                                                       Concrete strength results shall be promptly scrutinized and monitored continuously by the Plant Engineer,
                                                                                                                                                    an
                                                                                                       The monitoring procedures adopted by the Plant Engineer shall be fully documented and take into
                                                                                                                                             St
                                                                                                       Testing, recording and evaluation at monthly intervals shall be conducted on at least one mix representative
                                                                                                       of production with a specified strength of not greater than 30 MPa, and also on one mix with a specified
                                                                                                                                 ht
                                                                                                         NOTE – It is recommended that producers, particularly those with a small annual production, should institute
                                                                                                         a compression testing programme, which will place emphasis upon the most commonly produced mixes.  This
                                                                                                         will ensure that sufficient numbers of test results are forthcoming from those mixes to enable a statistically
                                                                                                         valid coefficient of variation to be calculated.
                                                                                                                      py
                                                                                                       values.  If these values are not met, the Plant Engineer, Technician, or Plant Supervisor shall critically
                                                                                                       review all aspects of production to ascertain the possible cause and take appropriate corrective action.
                                                                                                       Alternatively, at the discretion of the Plant Engineer, the monitoring of the most recent results by means
                                                                                                       other than the evaluation of groups of six results, but equally as effective, may be adopted so as to
                                                                                                       ensure that appropriate corrective action is taken promptly when this becomes necessary.
                                                                                                         NOTE – Appropriate corrective action could mean no action at all, particularly if evidence from other mixes
                                                                                                         taken in much the same circumstances shows no falling off in quality.  The reason for this is that the value
                                                                                                         chosen for the mean of six results is such that there is a small chance of failure with a particular group of six
                                                                                                         results in a series that is fully complying.
                                                                                                       30
                                                                                                                                                                                                       NZS 3104:2003
2.15.6.3.1
                                                                                                                                                                                                              *
                                                                                                       Tests on the mix, or mixes chosen for control purposes, shall be evaluated monthly for mean strength
                                                                                                       and coefficient of variation.  This series of tests is to be continuous for 12 months.  After that time, as
                                                                                                                                                                                                        d
                                                                                                       each month’s fresh results come to hand, they are to be included in the series and an equal number of
                                                                                                                                                                                         n
                                                                                                       early results is to be eliminated, achieving a continual updating.
                                                                                                                                                                                      ala
                                                                                                         NOTE – The greater the number of test results in a series in a given time, the more confidence that there can
                                                                                                         be in the information on variability.  As described in 2.13.3.2, 30 is the least number that is generally accepted
                                                                                                         as giving any reliable indication.  It takes numbers well over 100 before there is any accurate appreciation of
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                         the true variability.  This is why a continual updating of the 12 months’ series has been selected to give an
                                                                                                         assessment of variability.  As the new month’s tests are added, they would need to be markedly different to
                                                                                                                                                                                    Ze
                                                                                                         have a discernible effect on the mean strength.  Tests should therefor be monitored on a day-to-day basis as
                                                                                                         they come to hand.  A procedure should be adopted that would, if necessary, sound a warning before the end
                                                                                                         of the month, thereby avoiding the possibility of lowering of quality.
                                                                                                                                                                          ew
                                                                                                       2.15.6.3.2
                                                                                                       The best estimated overall coefficient of variation of the series shall be calculated by the method given
                                                                                                       in NZS 3112:Part 2.  If the coefficient of variation is not more than 1 % greater than the appropriate
                                                                                                                                                                sN
                                                                                                       value in tables 2.8A and 2.8B and the mean strength is equal or greater than the minimum target mean
                                                                                                       strength shown in tables 2.8A and 2.8B, it shall be deemed the series is complying.
                                                                                                         NOTE –  The appropriate value for mean strength would in general be the target mean strength, but for a
                                                                                                         single set of 30 results, the value could be the figure shown in item (c) of tables 2.8A and 2.8B.  In this case,
                                                                                                                                                         rd
                                                                                                         further evidence from earlier test results should be examined to ensure that the target mean strength is being
                                                                                                         achieved for the continuing series of results.
                                                                                                         It is envisaged that Plant Engineers will set concrete Target Mean Strengths a little above the minimum values
                                                                                                                                                  da
given in tables 2.8A and 2.8B so as to give some protection against the unexpected.
                                                                                                       2.15.6.3.3
                                                                                                                                           an
                                                                                                       If the mean strength required by item (c) of tables 2.8A and 2.8B is not achieved, then reference to
                                                                                                       2.13.1.3 shall be made and the consequential actions followed.
                                                                                                                                    St
                                                                                                        C2.15.6.3.3
                                                                                                        The principal course of action will be to increase the target strength of the concrete mix(es) in question
                                                                                                        until such time as the cause of the variation can be identified and dealt with.
                                                                                                                       ht
                                                                                                         NOTE –  Minor variations in cement content to compensate for variations in cement quality during the year,
                                                                                                         or minor adjustments to mix designs to compensate for fluctuating sand or aggregate gradings, need not be
                                                                                                         considered as significant changes warranting the starting of a new series.
                                                                                                                                                                                                                          31
                                                                                                       NZS 3104:2003
                                                                                                                                                                                                           *
                                                                                                                                  Table 2.8A – Evaluation of compression test results
                                                                                                                                                                                                        d
                                                                                                                                       Plants opting for not fewer than 10 tests per month
                                                                                                                                                                                        n
                                                                                                                                                                                     ala
                                                                                                        Grade MPa                                 17.5   20      25      30       35    40         45     50
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                                                                                   Ze
                                                                                                        Min target mean strength mix MPa          22     24.5    30.5    36       42    47.5       53     58
Cautionary limit to be equalled or exceeded by the mean of any consecutive group of six results (b)
                                                                                                                                                                          ew
                                                                                                                                                  20     22.5    28.5    33.5     39    44.5     49.5     55
Cautionary limit to be equalled or exceeded by the mean of any consecutive group of 30 results (c)
                                                                                                                                                  21      24.0
                                                                                                                                                                 sN
                                                                                                                                                                 29.5    35      40.5   46       51.5      56.5
  Amd 1
June '07
                                                                                                        Snatch sample                             14     16      20.5    25.5    30.5   35.5     40.5     45.5
                                                                                                                                  Plants opting for not fewer than six tests per month
                                                                                                                                         St
                                                                                                        Cautionary limit to be equalled or exceeded by the mean of any consecutive group of six results (b)
                                                                                                                           rig
Cautionary limit to be equalled or exceeded by the mean of any consecutive group of 30 results (c)
                                                                                                                                                  23     26      32      37.5    43       49      54       59.5
                                                                                                              Co
                                                                                                       32
                                                                                                                                                                                              NZS 3104:2003
                                                                                                                                                                                                     *
                                                                                                       Compliance with this Standard requires an Certificate of Audit, issued by an Auditing Engineer.  The
                                                                                                       Certificate of Audit must be revalidated within a maximum period of 12 months.
                                                                                                                                                                                               d
                                                                                                        C2.16.1
                                                                                                                                                                                  n
                                                                                                        The object of the audit is to check that the requirements of this Standard are met in all respects. The
                                                                                                                                                                               ala
                                                                                                        plant report is designed to provide as much of the necessary information as possible, certified by the
                                                                                                        Plant Engineer and the Plant Supervisor. Both the plant report and the on-site inspections facilitate
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                        the process. Whilst the Auditing Engineer could, in time, compile the reported information from the
                                                                                                        original records during a plant inspection the opportunity to study the report prior to the inspection,
                                                                                                                                                                             Ze
                                                                                                        provides focus to the inspection. In addition to the review of data, including the documentation of
                                                                                                        monitoring by the Plant Engineer, the audit permits the review of the tests carried out (including
                                                                                                        frequency of testing and the success of the quality assurance system) to be confirmed by the review
                                                                                                                                                                    ew
                                                                                                        of the year’s results.
                                                                                                       (by appointment after receipt of the plant report).  It will be necessary for the Plant Engineer, the Plant
                                                                                                       Supervisor, the testing Technician, and the batcher to be present.  All records shall be available for
                                                                                                       examination.   The assessor will require to see concrete being produced, and sampling and testing
                                                                                                                                  St
                                                                                                       carried out.  In the case of revalidation audits, physical site assessments will be made at intervals not
                                                                                                       exceeding three years.
                                                                                                                       ht
consisting of a summary of the number of tests carried out during the quarter.
                                                                                                       2.16.5 Control
                                                                                                       Control of materials, equipment, yield, slump, air content, and mixing efficiency are to be certified in
                                                                                                              py
                                                                                                                                                                                                                33
                                                                                                       NZS 3104:2003
3.1 General
                                                                                                                                                                                                          *
                                                                                                       3.1.1 Production
                                                                                                                                                                                                     d
                                                                                                       Production of Prescribed Mix Concrete shall conform to the relevant requirements set out in this section.
                                                                                                                                                                                            n
                                                                                                           C3.1.1
                                                                                                                                                                                         ala
                                                                                                           Prescribed Mix Concrete was formerly referred to as ordinary grade.
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                       3.1.2 Compliance
                                                                                                       Compliance of concrete manufactured to this section shall be by confirmation that the mix proportions
                                                                                                                                                                                       Ze
                                                                                                       specified in table 3.1 have been met.
                                                                                                                                                                              ew
                                                                                                       Production of Prescribed Mix Concrete is limited to 10, 15, 17.5, 20, and 25 MPa nominal strengths at
                                                                                                       28 days as prescribed in table 3.1.
                                                                                                           C3.1.3
                                                                                                                                                                     sN
                                                                                                           Note that the basis of compliance for these nominal prescribed strength mixes is not by compressive
                                                                                                           strength but as in table 3.1.
                                                                                                           Concrete of 15 and 10 MPa shall not be used for reinforced concrete applications.
                                                                                                                                                               rd
                Amd 2
                                                                                                       3.1.4 Definition
                                                                                                       This definition is additional to those in 1.2 and relates specifically to section 3.
                                                                                                                                                        da
Feb '10
                                                                                                       BUILDER'S MIX (all-in aggregate). A combined aggregate consisting of graded proportions of coarse
                                                                                                       aggregate with a maximum size 20 mm through to graded proportions of sand.
                                                                                                                                                 an
                                                                                                       3.2.1 Batching
                                                                                                       The supervision of the concrete production shall ensure that the prescribed quantities of materials are
                                                                                                       batched in accordance with table 3.1.
                                                                                                                                 ht
                                                                                                       3.2.2 Certification
                                                                                                                              rig
                                                                                                       On request from the Purchaser, the supervisor of concrete production shall certify that compliance with
                                                                                                       the batching requirements of table 3.1 has been met.
                                                                                                       3.2.3 Disputes
                                                                                                                        py
                                                                                                       In the event of a dispute, concrete shall either be wet sampled and the proportions determined, or
                                                                                                       hardened concrete shall be submitted for chemical analysis to determine cement content.
                                                                                                                Co
3.3 Materials
                                                                                                       3.3.1 General
                                                                                                       All materials used shall comply with 2.4, except as provided for by 3.3.2.
                                                                                                       34
                                                                                                                                                                                                   NZS 3104:2003
                                                                                                        Mix
                                                                                                         Proportions (volume)   Prescribed mixes – basic information
                                                                                                                                                                                                          *
                                                                                                             damp(1)
                                                                                                        			                     Amount per cubic metre            Yield per
                                                                                                                                                                                                     d
                                                                                                        						                                                    cement 		
                                                                                                        			                   SSD(2)     Damp(3)      Wet(4)      bag
                                                                                                                                                                                      n
                                                                                                                                                                                   ala
                                                                                                        10 MPa dry mix 	 Cement                    1        200 kg          200 kg          200 kg        0.200 m3
                                                                                                        50mm slump       builder’s mix             9        2050 kg         2110 kg         2160 kg
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                                                                                 Ze
                                                                                                        15 MPa    	         Cement                 1        240 kg          240 kg          240 kg        0.145 m3
                                                                                                        130mm slump         builder’s mix          6.75     1875 kg         1925 kg         1975 kg
                                                                                                                            water                  0.8      200 litres      150 litres      100 litres
                                                                                                                                                                         ew
                                                                                                        17.5/20 MPa 	       Cement                 1        300 kg          300 kg          300 kg      0.135 m3
                                                                                                        130mm slump 	       builder’s mix          5.5      1860 kg         1910 kg         1960 kg
                                                                                                                            water 	                0.6      200 litres      150 litres      100 litres			
                                                                                                        25 MPa  	           Cement                 1
                                                                                                                                                              sN
                                                                                                                                                            340 kg          340 kg          340 kg		 0.120 m3
                                                                                                        130mm slump         builder’s mix          4.75     1835 kg         1885 kg         2035 kg
                                                                                                                            water                  0.55     200 litres      150 litres      100 litres
                                                                                                                                                         rd
                                                                                                         NOTE –
                                                                                                         (1) Materials are batched in bulk volume except as provided for in 3.3.4.
                                                                                                                                                da
                                                                                                         (2) SSD is the mix design based around aggregates which are assumed to be saturated inside but have a
                                                                                                             dry surface so that the builder's mix neither absorbs water from the mix nor contributes free water to the
                                                                                                                                         an
mix.
                                                                                                         (3) Damp conditions are considered to be 3 % free moisture in the builder’s mix.
                                                                                                                                   St
                                                                                                         Where a problem is consistently experienced with water demand, the aggregate grading needs to be checked.
                                                                                                                       ht
                                                                                                       3.3.2 Aggregate
                                                                                                                    rig
                                                                                                       Aggregate for use with this section shall be supplied as a combined grading of coarse and fine aggregates
                                                                                                       complying with  table 3.2 except as provided for in 3.3.3.  The aggregate supplier shall, when requested,
                                                                                                       supply the particle size distribution information of the builder’s mix supplied.
                                                                                                              py
                                                                                                       Co
                                                                                                                                                                                                                      35
                                                                                                       NZS 3104:2003
                                                                                                                                                                                                                 *
                                                                                                                               19 mm                                           100 	– 	90
                                                                                                                                                                                                            d
                                                                                                                               13 mm                                           100 	– 	70
                                                                                                                                                                                                n
                                                                                                                              9.5 mm                                            80 	– 	55
                                                                                                                                                                                             ala
                                                                                                                              4.75 mm                                           60 	– 	40
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
2.36 mm 52 – 36
                                                                                                                                                                                           Ze
                                                                                                                              1.18 mm                                           42 	– 	26
600 microns 30 – 18
300 microns 18 – 8
                                                                                                                                                                               ew
                                                                                                                            150 microns                                          5 	– 	0
                                                                                                       the cement contents of the prescribed mixes in table 3.1 may be reduced by 20 kg and the aggregate
                                                                                                       quantities adjusted accordingly.
                                                                                                                                                  an
                                                                                                       The proportions of materials as shown in table 3.1 shall be batched. The table provides mixes for the
                                                                                                       following applications:
                                                                                                       10 MPa dry mix 	   50mm slump 	           Bedding concrete: Fence posts, etc.
                                                                                                                                ht
                                                                                                       25 MPa  	         130mm slump             As required for NZS 3604 or NZS 4229 for exposed concrete in
                                                                                                                                                 seaspray zone (e.g. dairy shed floors, pig slats, etc.).
                                                                                                         NOTE – The proportions for prescribed mixes (P) 17.5 and 20 are identical. The design accuracy for the mixes
                                                                                                                      py
                                                                                                       Aggregate and cement shall be volume batched using either gauge boxes or buckets.  The cement
                                                                                                       gauge box or bucket shall be used exclusively for cement.
                                                                                                        C3.4.2
                                                                                                        Cement should be placed in the volume measure and the measuring container shall be slightly tapped
                                                                                                        on the ground. The volume measure should then be topped up if required.
                                                                                                       3.4.3 Accuracy
                                                                                                       The accuracy of measurement shall be within the limits of table 3.3.
                                                                                                       36
                                                                                                                                                                                            NZS 3104:2003
Material Volume
                                                                                                                                                                                                  *
                                                                                                                       Cement                                             ± 2.5 %
                                                                                                                                                                                             d
                                                                                                                       Water                                              ±2.5 %				
                                                                                                                       Aggregates	  ±5 %
                                                                                                                                                                                 n
                                                                                                                                                                              ala
                                                                                                       3.5    Concrete mixing
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                       3.5.1 Loading
                                                                                                       The initial loading of the mixer shall include 80 % of the estimated water demand given in table 3.1.
                                                                                                                                                                            Ze
                                                                                                        C3.5.1
                                                                                                        In wet weather the water content in the builder’s mix will increase, and therefore the mix will require
                                                                                                                                                                  ew
                                                                                                        less water to be added to achieve a homogenous workable state. Over-dosing the water will reduce
                                                                                                        all the important properties of concrete such as strength, durability and abrasion resistance. It will
                                                                                                        also increase the amount of shrinkage that will occur.
                                                                                                                                                                                                               37
                                                                                                       NZS 3104:2003
4 CONCRETE MIXERS
4.1 General
                                                                                                                                                                                                               *
                                                                                                       4.1.1 Performance
                                                                                                                                                                                                          d
                                                                                                       The performance of concrete mixers both for manufacture and subsequent operation shall comply with
                                                                                                                                                                                            n
                                                                                                       relevant requirements of this section.
                                                                                                                                                                                         ala
                                                                                                       4.1.2 Operation
                                                                                                       Operation and maintenance of concrete mixers shall be conducted in accordance with 2.8.
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
4.1.3 Application
                                                                                                                                                                                       Ze
                                                                                                       The provisions of this part apply to both batch and continuous mixers.
4.2 Performance
                                                                                                                                                                              ew
                                                                                                       4.2.1 Mixing
                                                                                                       When operated at or below their rated mixing capacity, mixers shall be capable of thoroughly mixing all
                                                                                                       the concrete materials, within a specified interval of time, so that the ingredients are uniformly distributed
                                                                                                                                                                     sN
                                                                                                       throughout the volume of mixed concrete.  A mixer shall be deemed to comply with this requirement if:
                                                                                                       (a) It is one of a series or a model of which at least one prototype has been tested and found to comply
                                                                                                           with all the criteria of 2.15.4, when using a concrete mix with a slump in the range of 40 to 80 mm,
                                                                                                                                                               rd
                                                                                                           and has not been altered as to design, or has not undergone a major repair (e.g. design alteration)
                                                                                                           of the components of the mixing mechanism, since original manufacture.
                                                                                                                                                        da
                                                                                                       (b) It has undergone a major repair of its components forming the mixing mechanism (e.g. design
                                                                                                           alteration) since original manufacture, and since that repair, has been tested and found to comply
                                                                                                           with all the criteria of 2.15.4; and
                                                                                                                                                 an
                                                                                                       (c) In both (a) and (b) above, it has been regularly inspected to ensure that the mixing mechanism has
                                                                                                           not become worn to a degree, protection to the free edges has not been lost, holes have not formed
                                                                                                                                           St
                                                                                                           in the rotating parts, and any concrete adhering to the mechanism, or to the interior surface of the
                                                                                                           mixing chamber, has been substantially removed.
                                                                                                                                ht
non-complying if, for a batch mixer, either one of the following applies:
(b) The mixer is not capable of operating at more that half the rated mixing capacity.
                                                                                                       If non-uniformity of mixing due to wear is apparent, the mixer shall be repaired and, if the repair is major
                                                                                                       (i.e. design alteration), the mixer shall be retested as set out in 2.15.4 before being reused (see Note).
                                                                                                       38
                                                                                                                                                                                                  NZS 3104:2003
                                                                                                       If minor repairs to the mixer have been carried out, or routine periodic assessment for compliance with
                                                                                                       2.15.4 is required, the mixer shall be deemed to comply if it is tested in accordance with this clause and
                                                                                                       the test results for slump, air content and mass per unit volume are within the corresponding limits given.
                                                                                                                                                                                                        *
                                                                                                         NOTE – Uniformity of mixing can be seriously affected by the method of charging the mixer. If wear is small,
                                                                                                                                                                                                   d
                                                                                                         this should be investigated before carrying out repairs or routine uniformity tests on the mixer.
                                                                                                                                                                                     n
                                                                                                       4.2.4 Identification plates
                                                                                                                                                                                  ala
                                                                                                       Each mixer shall have a metal plate which is clearly inscribed with at least the following information
                                                                                                       permanently affixed to it in a prominent place:
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
                                                                                                                                                                                Ze
                                                                                                       (b) A model and serial number which identifies the particular mixer.
In addition, identification plates for batch mixers and continuous mixers shall be inscribed with the further
                                                                                                                                                                      ew
                                                                                                       information given in 4.3.5 and 4.4.2 respectively.
                                                                                                       of a batch mixer shall be not more than 65 % of the gross internal volume of the mixing chamber.  If a
                                                                                                       batch mixer is operated as an agitator, the rated agitating capacity for this purpose only may be taken
                                                                                                       as not more than 80 % of the gross internal volume of the mixing chamber.
                                                                                                                                         an
                                                                                                       The reduced mixer uniformity test referred to in 2.15.4 shall be carried out on a batch mixer for given
                                                                                                       concrete mixes:
                                                                                                                    rig
                                                                                                       (a) To confirm the mixer manufacturer’s recommended minimum number of revolutions or minimum
                                                                                                           mixing time at the mixer manufacturer’s rated capacity and mixing speed; or
                                                                                                             py
                                                                                                       (b) To determine an acceptable minimum number of revolutions or minimum mixing time at the mixer
                                                                                                           manufacturer’s rated capacity, or at a different working capacity, at the mixer manufacturer’s
                                                                                                           recommended mixing speed.
                                                                                                       Co
                                                                                                       If the uniformity test is used to confirm a recommended minimum mixing time, the required samples shall
                                                                                                       be obtained immediately after the nominated mixing time. If the uniformity test is used to determine an
                                                                                                       acceptable minimum mixing time, the acceptable time for a given capacity shall be taken as the least
                                                                                                       time at which the uniformity requirements of 2.15.4 are met but in no case shall this be more than 5 min.
                                                                                                                                                                                                                    39
                                                                                                       NZS 3104:2003
                                                                                                                                                                                                           *
                                                                                                       (c) The recommended minimum:
                                                                                                                                                                                                        d
                                                                                                             (i)   Number of revolutions of the mixing mechanism required to achieve uniformity, or
                                                                                                                                                                                           n
                                                                                                             (ii) Mixing time, in minutes, and the corresponding rotational speed of the mixing mechanism, in
                                                                                                                                                                                        ala
                                                                                                                  revolutions per minute;
 Masterspec (429864) subscribers are licensed to termporarily download this document and may print
it but not more than 10% of the documents subscribed to may be held in printed form at any one time.
(d) If the mixer is designed to be used also as an agitator, the rated agitating capacity and speed of the
                                                                                                                                                                                      Ze
                                                                                                           mixing mechanism in revolutions per minute.
MANUFACTURER’S NAME
                                                                                                                                                                           ew
                                                                                                                                              Manufacturer’s address
SERIAL No.
DATE TESTED*
                                                                                                         First
                                                                                                                                  ht
                                                                                                         Latest
                                                                                                                               rig
(a) The mixer manufacturer’s specified discharge capacity is not exceeded; and
(b) The mixer uniformity tests, carried out in accordance with 2.15.4, are passed.
                                                                                                       40
                                                        NZS 3104:2003