INSPECTION AND TEST REPORT REPORT. NO.
:
FOR PAD LEVEL PAGE : OF
PROJECT: JOB NO.:
Area / Unit : Date :
Location : Subcon. Name :
Equipment Name : Equipment No. :
Ref. Dwg. : Rev No. :
◎ FOUNDATION CHECK
Projection DWG:
Elevation Actual:
DWG:
Actual:
UNIT : mm
No. Elevation No. Elevation
1 16
2 17
3 18
4 19
5 20
6 21
7 22
8 23
9 24
10 25
11 26
12 27
13 28
14 29
15 30
Tolerance :
Note :
Inspection Result : □ Accept □ Conditionally Accept □ Reject
Inspection by Subcontractor Contractor Client
Name
Signature
Date
Form No. : ITR-MRE-001
INSPECTION AND TEST REPORT REPORT. NO. :
FOR EQUIPMENT FOUNDATION PAGE : OF
PROJECT: JOB NO.:
Area / Unit : Date :
Location : Subcon. Name :
Equipment Name : Equipment No. :
Ref. Dwg. : Rev No. :
◎ EQUIPMENT LOCATION CHECK (BOX TYPE)
DIS. CENTER
SUC. CENTER
Tolerance :
Note :
Inspection Result : □ Accept □ Conditionally Accept □ Reject
Inspection by Subcontractor Contractor Client
Name
Signature
Date
Form No. : ITR-MRE-002
INSPECTION AND TEST REPORT REPORT. NO. :
FOR PAD PAGE : OF
PROJECT: JOB NO.:
Area / Unit : Date :
Location : Subcon. Name :
Equipment Name : Equipment No. :
Ref. Dwg. : Rev No. :
Bolt No. "A" Pad "B" Pad Result Remarks
Equipment "A" (Running) Equipment "A"
1 2 3 1
2
3
4
4 5 6 5
6
Equipment "B" (Stand-by) Equipment "B"
1 2 3 1
2
3
4
4 5 6 5
6
Unit : mm
Elevation : See table
Tolerance : ±3mm
Note :
Inspection Result : □ Accept □ Conditionally Accept □ Reject
Inspection by Subcontractor Contractor Client
Name
Signature
Date
Form No. : ITR-MRE-003
INSPECTION AND TEST REPORT REPORT. NO. :
FOR ALIGNMENT OF ROTATING
EQUIPMENT(1ST, 2ND) PAGE : OF
PROJECT: JOB NO.:
Area / Unit : Date :
Location : Subcon. Name :
Equipment Name : Equipment No. :
Ref. Dwg. : Rev No. :
◎ COUPLING ALIGNMENT (1st, 2nd) UNIT : mm
90
TOLERANCE : ±0.05mm
POSITION AXIAL RIM
90
180
270
◎ COUPLING DISTANCE
DWG : ACTUAL :
Note :
Inspection Result : □ Accept □ Conditionally Accept □ Reject
Inspection by Subcontractor Contractor Client
Name
Signature
Date
Form No. : ITR-MRE-004A
INSPECTION AND TEST REPORT REPORT. NO. :
FOR ALIGNMENT OF ROTATING
EQUIPMENT(FINAL) PAGE : OF
PROJECT: JOB NO.:
Area / Unit : Date :
Location : Subcon. Name :
Equipment Name : Equipment No. :
Ref. Dwg. : Rev No. :
◎ COUPLING ALIGNMENT (FINAL) UNIT : mm
90
BEFORE PIPING TOLERANCE : ±0.05mm AFTER PIPING
POSITION AXIAL RIM POSITION AXIAL RIM
0 0
90 90
180 180
270 270
◎ COUPLING DISTANCE
DWG : ACTUAL :
Note :
Inspection Result : □ Accept □ Conditionally Accept □ Reject
Inspection by Subcontractor Contractor Client
Name
Signature
Date
Form No. : ITR-MRE-004B
INSPECTION AND TEST REPORT REPORT. NO. :
FOR ALIGNMENT OF COMPRESSOR &
TURBINE(1ST, 2ND) PAGE : OF
PROJECT: JOB NO.:
Area / Unit : Date :
Location : Subcon. Name :
Equipment Name : Equipment No. :
Ref. Dwg. : Rev No. :
◎ COUPLING ALIGNMENT (1st, 2nd) UNIT : mm
TOLERANCE : ±0.05mm
COMPRESSOR TURBINE
POSITION
DWG ACTUAL DWG ACTUAL
90
180
270
◎ COUPLING DISTANCE
DWG : ACTUAL :
Note :
Inspection Result : □ Accept □ Conditionally Accept □ Reject
Inspection by Subcontractor Contractor Client
Name
Signature
Date
Form No. : ITR-MRE-005A
INSPECTION AND TEST REPORT REPORT. NO. :
FOR ALIGNMENT OF COMPRESSOR &
TURBINE(FINAL) PAGE : OF
PROJECT: JOB NO.:
Area / Unit : Date :
Location : Subcon. Name :
Equipment Name : Equipment No. :
Ref. Dwg. : Rev No. :
◎ COUPLING ALIGNMENT (FINAL) UNIT : mm
BEFORE PIPING TOLERANCE : ±0.05mm AFTER PIPING
COMPRESSOR TURBINE COMPRESSOR TURBINE
POSITION POSITION
DWG ACTUAL DWG ACTUAL DWG ACTUAL DWG ACTUAL
0 0
90 90
180 180
270 270
◎ COUPLING DISTANCE
DWG : ACTUAL :
Note :
Inspection Result : □ Accept □ Conditionally Accept □ Reject
Inspection by Subcontractor Contractor Client
Name
Signature
Date
Form No. : ITR-MRE-005B
INSPECTION AND TEST REPORT REPORT. NO. :
FOR GROUTING WORK PAGE : OF
PROJECT: JOB NO.:
Area / Unit : Date :
Location : Subcon. Name :
Equipment Name : Equipment No. :
Ref. Dwg. : Rev. No. :
Results
No Items to be Checked Remarks
Accept Reject
1 Foundation Chipping Condition
2 Foundation Chipping Condition
3 Formworks
4 Foundation Wet Condition
5 Grouting Works
a.) Grout Material and Water Ratio
b.) Mixed Grout Temperature
c.) Casting Method
d.) Finishing Works
6 Curing of Grout at site
7 Cube sample
a.) 3 Days
b.) 7 Days
c.) 28 Days
Tolerance :
Note :
Inspection Result : □ Accept □ Conditionally Accept □ Reject
Inspection by Subcontractor Contractor Client
Name
Signature
Date
Form No. : ITR-MRE-006
INSPECTION AND TEST REPORT REPORT. NO. :
FOR HORIZONTAL CENTRIFUGAL
COMPRESSOR(LEVELING WORK) PAGE : OF
PROJECT: JOB NO.:
Area / Unit : Date :
Location : Subcon. Name :
Equipment Name : Equipment No. :
Ref. Dwg. : Rev No. :
◎ LEVELING WORK UNIT : mm
Tolerance :
Note :
Inspection Result : □ Accept □ Conditionally Accept □ Reject
Inspection by Subcontractor Contractor Client
Name
Signature
Date
Form No. : ITR-MRE-007
INSPECTION AND TEST REPORT REPORT. NO. :
FOR MULTIPLE OR SKID WITH
LOCATION PAGE : OF
PROJECT: JOB NO.:
Area / Unit : Date :
Location : Subcon. Name :
Equipment Name : Equipment No. :
Ref. Dwg. : Rev No. :
Location
Elevation
North ( N-S ) East ( E - W )
Drawing Actual Drawing Actual Drawing Actual
1)
2)
3)
Tolerance : UNIT : mm
Note :
Inspection Result : □ Accept □ Conditionally Accept □ Reject
Inspection by Subcontractor Contractor Client
Name
Signature
Date
Form No. : ITR-MRE-008
INSPECTION AND TEST REPORT REPORT. NO. :
FOR SETTING INSPECTION OF
HORIZONTAL PUMP PAGE : OF
PROJECT: JOB NO.:
Area / Unit : Date :
Location : Subcon. Name :
Equipment Name : Equipment No. :
Ref. Dwg. : Rev No. :
◎ ELEVATION CHECK UNIT : mm
X Elevation DWG :
Actual :
(Tolerance ±3mm)
(Allowable ±3mm)
◎ LEVELING WORK
Allowable : 0.05mm
Tolerance :
Note :
Inspection Result : □ Accept □ Conditionally Accept □ Reject
Inspection by Subcontractor Contractor Client
Name
Signature
Date
Form No. : ITR-MRE-009
INSPECTION AND TEST REPORT REPORT. NO. :
FOR COUPLING ALIGNMENT PAGE : OF
PROJECT: JOB NO.:
Area / Unit : Date :
Location : Subcon. Name :
Equipment Name : Equipment No. :
Ref. Dwg. : Rev No. :
Date & Time :
Ambient Temperature(°C) :
Dial "B"
Dial "A"
*1 "C"
Alignment
Description Gap "C" Result
Dial "A" Dial "B"
0°
90°
180°
270°
*1. See the Anchor Bolt Check List
Tolerance :
Note :
Inspection Result : □ Accept □ Conditionally Accept □ Reject
Inspection by Subcontractor Contractor Client
Name
Signature
Date
Form No. : ITR-MRE-010
INSPECTION AND TEST REPORT REPORT. NO. :
FOR FINAL INSPECTION PAGE : OF
PROJECT: JOB NO.:
Area / Unit : Date :
Location : Subcon. Name :
Equipment Name : Equipment No. :
Ref. Dwg. : Rev No. :
Result
No. Items to be Checked Remarks
Accept Reject
. Check the name plate is properly attached to the equipment.
. Check the foundation bolts are securely tightened.
. Check the insulation condition.
. Check the equipment for internal cleanliness before final sealing.
Check whether the lubrication system has been properly flushed and is
.
clean.
Check the direction of rotation. An arrow, indicating the direction of
.
rotation.
. Check the shaft alignment between driving and driven unit.
. Check cold setting position of spring hanger.
. Check whether coupling is clean and lubricated.
. Check coupling guard and flexible connections.
Note :
Inspection Result : □ Accept □ Conditionally Accept □ Reject
Inspection by Subcontractor Contractor Client
Name
Signature
Date
Form No. : ITR-MRE-011