SESSION PLAN
Sector                 :   Electrical and Electronics Sector
Qualification Title :      Electrical Installation and Maintenance NC II
Unit of Competency : Perform Roughing-in Activities, Wiring and Cabling works for Single-Phase
Distribution, Power, Lighting and Auxiliary Systems
Module Title        : Performing Roughing-in Activities, Wiring and Cabling works for Single-Phase
Distribution, Power, Lighting and Auxiliary Systems
Learning Outcomes:
LO1   Install electrical metallic /nonmetallic (PVC conduit)
LO2    Install wire ways and cable tray
LO3   Install Auxiliary terminal cabinet and distribution panel
LO4   Prepare for cable pulling and installation
LO5   Perform wiring and cabling lay out
LO6   Notify completion of work
                           Electrical Installation and     Date Developed:                            Document No.
                               Maintenance NC II                    August 2021        Issued by:
                                                           Date Revised:                 TSDC                   Page 1 of 25
                        Perform Roughing-in Activities,    Developed by:
                         Wiring and Cabling works for              Nelson M. Divino
                       Single-Phase Distribution, Power,                              Revision # 00
                        Lighting and Auxiliary Systems
   A. INTRODUCTION
                This unit covers the knowledge, skills and attitudes on installing electrical metallic and non-metallic
conduit, wire ways and cable clamp, auxiliary terminal cabinet and distribution frame panel board/safety switch and used
in roughing-in based on the required performance standards.
                This unit also covers the outcomes required in preparing for cable pulling and installation, performing
wiring and cabling lay-out and notifying completion of work for single-phase distribution, power, lighting and auxiliary
systems.
   B. LEARNING ACTIVITIES
   Learning
                    Methods           Presentation             Practice             Feedback            Resources                 Time
   Content
LO 1:   Install electrical metallic /nonmetallic (PVC conduit)
                                                                                                LCD Projector/ TV
                                      Power point          Oral Questions            Answer     Laptop
                    Lecture           presentation              1.1.1               Questions                                  20 minutes
                                                                                      1.1.1     Power point references
                                     Oral interview
Safety
                                                                                                CBLM / TR/CBC
procedures
                                                                                                CBLM
                    Self-paced     Read Information
                                   Sheet 1.1-1 on           Answer Self         Compare to      TR/CBC                         15 minutes
                   Instruction
                                   safety procedures        Check 1.1-1         Answer Key      Other References
                        Electrical Installation and      Date Developed:                                        Document No.
                            Maintenance NC II                     August 2021                    Issued by:
                                                         Date Revised:                             TSDC                   Page 2 of 25
                      Perform Roughing-in Activities,    Developed by:
                       Wiring and Cabling works for              Nelson M. Divino
                     Single-Phase Distribution, Power,                                          Revision # 00
                      Lighting and Auxiliary Systems
                                                                                     1.1-1     (Internet/Textbook)
                                                                                               Hand Outs
                                                                                               CBLM
                                     Power point                               Compare to      TR/CBC
                                     presentation          Answer Self
                   Lecture                                                     Answer Key      Other References               20 minutes
                                                           Check 1.1-2
                                    Oral interview                               1.1-2         (Internet/Textbook)
Different types
                                                                                               Hand Outs
of metallic /
non-metallic                                                                                   CBLM
conduits                          Read Information
                                                           Answer Self         Compare to      TR/CBC
                   Self paced     Sheet 1.1-2 on
                                                           Check 1.1-2         Answer Key                                     15 minutes
                  Instruction     different types of                                           Other References
                                                                                 1.1-2
                                  metallic/non-                                                (Internet/Textbook)
                                  metallic conduits                                            Hand Outs
                                                                                               LCD Projector/ TV
                                                                                               Laptop
                                     Power point                                    Answer
                    Group            presentation         Oral Questions                       Power point
                                                                                   Questions                                  20 minutes
                  Discussion                                   1.1-2                           presentation references
                                    Oral interview                                   1.1.2
                                                                                               CBLM
                                                                                               TR/CBC
                       Electrical Installation and      Date Developed:                                        Document No.
                           Maintenance NC II                     August 2021                    Issued by:
                                                        Date Revised:                             TSDC                   Page 3 of 25
                     Perform Roughing-in Activities,    Developed by:
                      Wiring and Cabling works for              Nelson M. Divino
                    Single-Phase Distribution, Power,                                          Revision # 00
                     Lighting and Auxiliary Systems
                                                                                               LCD Projector/ TV
                                     Power point          Oral Questions            Answer     Laptop
                   Lecture           presentation              1.1.3               Questions                                  25 minutes
                                                                                     1.1.3     Power point references
                                    Oral interview
                                                                                               CBLM / TR/CBC
                                                                                               CBLM
                                  Read Information
                                                           Answer Self         Answer Key      TR/CBC
                   Self paced     Sheet 1.1-3 on
                                                           Check 1.1-3           1.1-3                                        15 minutes
 Familiarize of   Instruction     familiarize of                                               Other References
fittings and                      fittings and                                                 (Internet/Textbook)
accessories                       accessories                                                  Hand Outs
                                                                                               LCD Projector/ TV
                                                          Oral Questions                       Laptop
                                     Power point               1.1-3                Answer
                    Group            presentation                                              Power point
                                                             Written               Questions                                  20 minutes
                  Discussion                                                                   presentation references
                                                           Examination               1.1-3
                                                              1.1-3                            CBLM
                                                                                               TR/CBC
Proper tools                         Power point                                               LCD Projector/ TV
and equipment                        presentation            Written                Answer
                                                                                               Laptop
needed to          Lecture                                 Examination             Questions                                  15 minutes
                                        Video                 1.1-4                  1.1-4     Power point
complete
                                     presentation                                              presentation references
requirements
                       Electrical Installation and      Date Developed:                                        Document No.
                           Maintenance NC II                     August 2021                    Issued by:
                                                        Date Revised:                             TSDC                   Page 4 of 25
                     Perform Roughing-in Activities,    Developed by:
                      Wiring and Cabling works for              Nelson M. Divino
                    Single-Phase Distribution, Power,                                          Revision # 00
                     Lighting and Auxiliary Systems
                                                                                                CBLM
                                                                                                TR/CBC
                                   Read Information                                             CBLM
                                   Sheet 1.1-3 on           Answer Self         Answer Key      TR/CBC
                    Self paced     proper tools and         Check 1.1-4           1.1-4                                        15 minutes
                   Instruction     equipment                                                    Other References
                                   needed to                                                    (Internet/Textbook)
                                   complete                                                     Hand Outs
                                   requirements
                                                                                                LCD Projector/ TV
                                                           Oral Questions                       Laptop
                                      Power point               1.1-4                Answer
                     Group            presentation                                              Power point
                                                              Written               Questions                                  20 minutes
                   Discussion                                                                   presentation references
                                                            Examination               1.1-4
                                                               1.1-4                            CBLM
                                                                                                TR/CBC
Installation of                                                                                 LCD Projector/ TV
electrical metal                                           Oral Questions                       Laptop
                                      Power point
conduits, wire                                                  1.1-5                Answer
                                      presentation                                              Power point
ways and            Lecture                                                         Questions                                  20 minutes
                                                              Written                           presentation references
cables trays,                            Video                                        1.1-5
                                                            Examination
and auxiliary                         presentation                                              CBLM
                                                               1.1-5
terminal
cabinets with                                                                                   TR/CBC
                        Electrical Installation and      Date Developed:                                        Document No.
                            Maintenance NC II                     August 2021                    Issued by:
                                                         Date Revised:                             TSDC                   Page 5 of 25
                      Perform Roughing-in Activities,    Developed by:
                       Wiring and Cabling works for              Nelson M. Divino
                     Single-Phase Distribution, Power,                                          Revision # 00
                      Lighting and Auxiliary Systems
distribution                    Read Information
panel                           Sheet 1.1-3 on           Answer Self         Answer Key    CBLM
                                installation of          Check 1.1-5           1.1-5
                                electrical metal                                           TR/CBC
                 Self paced     conduits, wire
                                                                                           Other References               15 minutes
                Instruction     ways and cables
                                                                                           (Internet/Textbook)
                                trays, and
                                auxiliary terminal                                         Hand Outs
                                cabinets with
                                distribution panel
                                                       Perform tasks           Check           1. Tools, equipment
                                                       1.1-5 on              performanc           and testing
                                                       installation of        e criteria          devices:
                                                       electrical metal       checklist               boxes
                                                       conduits, wire           1.1-5                 utility box
                                                       ways and                                       junction
                                                                             Procedural
                                                       cables trays,                                    box
                                                                              Checklist
                                    Trainer’s          and auxiliary                                  pull box/
               Demonstration                                                    1.1-5                                       4 hours
                                  Demonstration        terminal                                         splice box
                                                       cabinets with                                  conduit
                                                       distribution                                     supports
                                                       panel                                          conduit
                                                                                                        strap
                                                                                                      connectors
                                                                                                        (straight
                                                                                                        and angle)
                     Electrical Installation and      Date Developed:                                      Document No.
                         Maintenance NC II                     August 2021                  Issued by:
                                                      Date Revised:                           TSDC                   Page 6 of 25
                   Perform Roughing-in Activities,    Developed by:
                    Wiring and Cabling works for              Nelson M. Divino
                  Single-Phase Distribution, Power,                                        Revision # 00
                   Lighting and Auxiliary Systems
                                                                                                      spirit level
                                                                                                      hacksaw
                                                                                                      pipe cutter
                                                                                                      pipe
                                                                                                       reamer
                                                                                                      plumb bob
                                                                                                      pipe
                                                                                                       threader
                                                                                                      pipe
                                                                                                       bender
                                                                                                      bolt cutter
                                                                                                      electric
                                                                                                       drill
                                                                                        2. electrical power
                                                                                           tools
                                                                                               power drills
                                                                                               portable
                                                                                                  grinder
LO 2:   Install wire ways and cable tray
                        Electrical Installation and      Date Developed:                              Document No.
                            Maintenance NC II                     August 2021        Issued by:
                                                         Date Revised:                 TSDC                     Page 7 of 25
                      Perform Roughing-in Activities,    Developed by:
                       Wiring and Cabling works for              Nelson M. Divino
                     Single-Phase Distribution, Power,                              Revision # 00
                      Lighting and Auxiliary Systems
Identify use of                                          Oral Questions                       LCD Projector/ TV
materials, tools                    Power point               1.2-1                Answer     Laptop
and equipment      Lecture          presentation                                  Questions
                                                            Written
                                                                                    1.2-1     Power point                    20 minutes
                                                          Examination                         presentation references
                                                             1.2-1
                                 Read Information
                                 Sheet 1.2-1 on
                                                          Answer Self         Compare to
                                 uses of materials,       Check 1.2-1         Answer Key
                   Modular       tools and                                                    CBLM                           30 minutes
                                                                                1.2-1
                                 equipment
Interpret
Electrical/Mec                                           Oral Questions                       LCD Projector/ TV
                                    Power point
hanical                                                       1.2-2                Answer
                                    presentation                                              Laptop
drawing            Lecture                                                        Questions
                                                            Written
                                       Video                                        1.2-2     Power point                    20 minutes
                                                          Examination
                                    presentation                                              presentation references
                                                             1.2-2
                                 Read Information
                                 Sheet 1.2-2 on           Answer Self         Compare to
                   Modular       Interpreting                                                 CBLM                           30 minutes
                                                          Check 1.2-2         Answer Key
                                 Electrical/Mecha
                                                                                1.2-2
                                 nical drawing
                      Electrical Installation and      Date Developed:                                        Document No.
                          Maintenance NC II                     August 2021                    Issued by:
                                                       Date Revised:                             TSDC                   Page 8 of 25
                    Perform Roughing-in Activities,    Developed by:
                     Wiring and Cabling works for              Nelson M. Divino
                   Single-Phase Distribution, Power,                                          Revision # 00
                    Lighting and Auxiliary Systems
Determine                                                                                     LCD Projector/ TV
suitability for                     Power point             Written                Answer     Laptop
installation
                   Lecture          presentation          Examination             Questions
and used of                                                                                   Power point                    20 minutes
bus way, cable                                               1.2-3                  1.2-3     presentation references
tray, fittings
and panels,
conformity                       Read Information       Answer Self-          Compare to
with the                         Sheet 1.2-3 on         check 1.2-3           Answer Key
provision of the                 Determining                                  1.2-2
PEC Code.                        suitability for
                                 installation and
                   Modular       used of bus way,                                             CBLM                           30 minutes
                                 cable tray,
                                 fittings and
                                 panels,
                                 conformity with
                                 the provision of
                                 the PEC Code.
Practice wire
way and cable
tray
installation
                      Electrical Installation and      Date Developed:                                        Document No.
                          Maintenance NC II                     August 2021                    Issued by:
                                                       Date Revised:                             TSDC                   Page 9 of 25
                    Perform Roughing-in Activities,    Developed by:
                     Wiring and Cabling works for              Nelson M. Divino
                   Single-Phase Distribution, Power,                                          Revision # 00
                    Lighting and Auxiliary Systems
LO 3: Install auxiliary terminal cabinet and distribution panel
PEC/NEC                                                                                        LCD Projector/ TV
provisions on                                       Oral Questions
                                   Power point           1.3-1                                 Laptop
terminal                                                                            Answer
cabinet             Lecture        presentation                                    Questions   Power point references         20 minutes
                                                        Written
                                                     Examination                     1.3-1     CBLM
                                                         1.3-1
                                                                                               TR/CBC
                                  Read Information                                             CBLM /TR/CBC
                   Self paced     Sheet 1.3-1 on           Answer Self         Compare to      Other References               15 minutes
                  Instruction     PEC/NEC                  Check 1.3-1         Answer Key      (Internet/Textbook)
                                  provisions on                                  1.3-1
                                  terminal cabinet                                             Hand Outs
                    Group            Power point          Oral Questions                       LCD Projector/ TV
                                                                                    Answer                                    15 minutes
                  Discussion         presentation              1.3-1               Questions   Laptop
                       Electrical Installation and      Date Developed:                                        Document No.
                           Maintenance NC II                     August 2021                    Issued by:
                                                        Date Revised:                             TSDC                   Page 10 of 25
                     Perform Roughing-in Activities,    Developed by:
                      Wiring and Cabling works for              Nelson M. Divino
                    Single-Phase Distribution, Power,                                          Revision # 00
                     Lighting and Auxiliary Systems
                                                              Written                 1.3-1     Power point
                                                            Examination                         presentation references
                                                               1.3-1                            CBLM
                                                                                                TR/CBC
Procedures                                                                                      LCD Projector/ TV
installation of                                            Oral Questions
                     Lecture          Power point                                               Laptop
auxiliary                                                       1.3-2                Answer
                                      presentation
terminal                                                      Written               Questions   Power point references           20 minutes
                                         Video                                        1.3-2
cabinet                                                     Examination                         CBLM
                                      presentation
                                                               1.3-2
                                                                                                TR/CBC
                                   Read Information                                             CBLM
                                   Sheet 1.3-9 on           Answer Self         Compare to      TR/CBC
                                   procedures               Check 1.3-2         Answer Key
                    Self paced     installation of                                              Other References                 15 minutes
                                                                                  1.3-2
                   Instruction     auxiliary terminal                                           (Internet/Textbook)
                                   cabinet                                                      Hand Outs
                                                          Perform tasks           Check         Tools:
                                                          1.3-2 on              performanc                        boxes
                                       Trainer’s
                  Demonstration                           procedures             e criteria                       utility box   4 hours
                                     Demonstration
                                                          installation of        checklist                        junction
                                                          auxiliary                1.3-2                           box
                        Electrical Installation and      Date Developed:                                          Document No.
                            Maintenance NC II                     August 2021                    Issued by:
                                                         Date Revised:                             TSDC                     Page 11 of 25
                      Perform Roughing-in Activities,    Developed by:
                       Wiring and Cabling works for              Nelson M. Divino
                     Single-Phase Distribution, Power,                                          Revision # 00
                      Lighting and Auxiliary Systems
                                     terminal              Procedural                     pull box/
                                     cabinet                Checklist                      splice box
                                                              1.3-2                       conduit
                                                                                           supports
                                                                                          conduit
                                                                                           strap
                                                                                          connectors
                                                                                           (straight
                                                                                           and angle)
                                                                                          spirit level
                                                                                          hacksaw
                                                                                          pipe cutter
                                                                                          pipe
                                                                                           reamer
                                                                                          plumb bob
                                                                                          pipe
                                                                                           threader
                                                                                          pipe
                                                                                           bender
                                                                                          bolt cutter
                                                                                          electric
                                                                                           drill
   Electrical Installation and      Date Developed:                                       Document No.
       Maintenance NC II                     August 2021                 Issued by:
                                    Date Revised:                          TSDC                     Page 12 of 25
 Perform Roughing-in Activities,    Developed by:
  Wiring and Cabling works for              Nelson M. Divino
Single-Phase Distribution, Power,                                       Revision # 00
 Lighting and Auxiliary Systems
Installation of                                                                                 LCD Projector/ TV
distribution                                               Oral Questions
                     Lecture          Power point                                               Laptop
frames                                                          1.3-4                Answer
                                      presentation                                              Power point                    20 minutes
                                                              Written               Questions
                                         Video                                                  presentation references
                                                            Examination               1.3-4
                                      presentation                                              CBLM
                                                               1.3-4
                                                                                                TR/CBC
                                                                                                LCD Projector/ TV
                                   Read Information
                                                            Answer Self         Compare to      Laptop                         15 minutes
                                   Sheet 3.3.3 on
                                                            Check 1.3.4         Answer Key
                    Self paced     Installation of                                              Power point
                                                                                  1.3.4
                   Instruction     distribution                                                 presentation references
                                   frames                                                       CBLM
                                                                                                TR/CBC
                                                          Perform tasks           Check         Tools and device
                                                          1.3-4 on              performanc      drivers:
                                                          Installation of        e criteria               boxes
                                                          distribution           checklist                utility box
                                       Trainer’s
                  Demonstration                           frames                   1.3-4                  junction              4 hours
                                     Demonstration
                                                                                Procedural                  box
                                                                                 Checklist                pull box/
                                                                                   1.3-4                    splice box
                                                                                                          conduit
                        Electrical Installation and      Date Developed:                                        Document No.
                            Maintenance NC II                     August 2021                    Issued by:
                                                         Date Revised:                             TSDC                   Page 13 of 25
                      Perform Roughing-in Activities,    Developed by:
                       Wiring and Cabling works for              Nelson M. Divino
                     Single-Phase Distribution, Power,                                          Revision # 00
                      Lighting and Auxiliary Systems
                                                                                                                  supports
                                                                                                                 conduit
                                                                                                                  strap
                                                                                                                 connectors
                                                                                                                  (straight
                                                                                                                  and angle)
                                                                                                                 spirit level
                                                                                                                 hacksaw
                                                                                                                 pipe cutter
                                                                                                                 pipe
                                                                                                                  reamer
                                                                                                                 plumb bob
                                                                                                                 pipe
                                                                                                                  threader
                                                                                                                 pipe
                                                                                                                  bender
                                                                                                                 bolt cutter
                                                                                                                 electric
                                                                                                                  drill
LO4 Prepare for cable pulling and installation
Proper tools,                       Power point           Written Exam                         LCD Projector/ TV
                   Lecture                                                          Answer                                       20 minutes
equipment,                         presentation                 1.4-1              Questions   Laptop
                       Electrical Installation and      Date Developed:                                          Document No.
                           Maintenance NC II                     August 2021                    Issued by:
                                                        Date Revised:                             TSDC                     Page 14 of 25
                     Perform Roughing-in Activities,    Developed by:
                      Wiring and Cabling works for              Nelson M. Divino
                    Single-Phase Distribution, Power,                                          Revision # 00
                     Lighting and Auxiliary Systems
materials and                       Oral interview                                   1.4-1     Power point references
PPE needed for                                                                                 CBLM / TR/CBC
the job
                                  Read Information                                             CBLM
                                  Sheet 1.1-8 on           Answer Self         Compare to      TR/CBC
                   Self paced     Proper tools,            Check 1.4-1         Answer Key                                     15 minutes
                  Instruction     equipment,                                                   Other References
                                                                                 1.4-1
                                  materials and                                                (Internet/Textbook)
                                  PPE needed for                                               Hand Outs
                                  the job
                                                                                               LCD Projector/ TV
                                                                                               Laptop
                                     Power point             Written                Answer
                    Group            presentation                                              Power point
                                                           Examination             Questions                                  20 minutes
                  Discussion                                                                   presentation references
                                                              1.3-3                  1.3-3
                                                                                               CBLM
                                                                                               TR/CBC
Cable layout                                                                                   LCD Projector/ TV
and                                  Power point          Written Exam
                                                                                    Answer     Laptop
installation       Lecture           presentation               1.4-2              Questions                                  20 minutes
using the right                                                                      1.4-2     Power point references
                                    Oral interview
equipment                                                                                      CBLM / TR/CBC
                   Self paced     Read Information                                             CBLM                           15 minutes
                  Instruction     Sheet 1.1-8 on            Answer Self        Compare to
                       Electrical Installation and      Date Developed:                                        Document No.
                           Maintenance NC II                     August 2021                    Issued by:
                                                        Date Revised:                             TSDC                   Page 15 of 25
                     Perform Roughing-in Activities,    Developed by:
                      Wiring and Cabling works for              Nelson M. Divino
                    Single-Phase Distribution, Power,                                          Revision # 00
                     Lighting and Auxiliary Systems
                 Cable layout and         Check 1.4-2         Answer Key    TR/CBC
                 installation using                             1.4-2       Other References
                 the right                                                  (Internet/Textbook)
                 equipment
                                                                            Hand Outs
Demonstration        Trainer’s          Perform Task            Check       Tools and device                 4 hours
                   Demonstration        Sheet 1.4-3 on        performanc    drivers:
                                        cable layout           e criteria             boxes
                       Video
                                        and installation       checklist              utility box
                    presentation
                                        using the right          1.4-3                junction
                                        equipment                                       box
                                                              Procedural
                                                               Checklist              pull box/
                                                                 1.4-3                  splice box
                                                                                      conduit
                                            Hands On                                    supports
                                             Practice
                                                                                      conduit
                                                                                        strap
                                                                                      connectors
                                                                                        (straight
                                                                                        and angle)
                                                                                      spirit level
                                                                                      hacksaw
                                                                                      pipe cutter
                                                                                      pipe
                                                                                        reamer
      Electrical Installation and      Date Developed:                                      Document No.
          Maintenance NC II                     August 2021                  Issued by:
                                       Date Revised:                           TSDC                   Page 16 of 25
    Perform Roughing-in Activities,    Developed by:
     Wiring and Cabling works for              Nelson M. Divino
   Single-Phase Distribution, Power,                                        Revision # 00
    Lighting and Auxiliary Systems
                                                                                                              plumb bob
                                                                                                              pipe
                                                                                                               threader
                                                                                                              pipe
                                                                                                               bender
                                                                                                              bolt cutter
                                                                                                              electric
                                                                                                               drill
Safety                                                 Oral Questions
                                                                                            LCD Projector/ TV
procedure in                                                1.4-3
                                  Power point                                    Answer
installing                                                                                  Laptop
                Lecture           presentation         Written Exam             Questions                                    20 minutes
cables                                                                                      Power point references
                                 Oral interview              1.4-3                1.4-3
                                                                                            CBLM / TR/CBC
                               Read Information
                               Sheet 1.1-8 on                                               CBLM
                                                        Answer Self         Compare to
                               cable lay out &                                              TR/CBC
                Self paced                              Check 1.4-3         Answer Key
                               installation                                                                                  15 minutes
               Instruction                                                    1.4-3         Other References
                               equipment is set
                                                                                            (Internet/Textbook)
                               up in accordance
                               with                                                         Hand Outs
                               manufacturer's
                    Electrical Installation and      Date Developed:                                          Document No.
                        Maintenance NC II                     August 2021                    Issued by:
                                                     Date Revised:                             TSDC                     Page 17 of 25
                  Perform Roughing-in Activities,    Developed by:
                   Wiring and Cabling works for              Nelson M. Divino
                 Single-Phase Distribution, Power,                                          Revision # 00
                  Lighting and Auxiliary Systems
                                  and job
                                  requirements.
Proper usage of                                           Oral Questions
                                                                                               LCD Projector/ TV
PPE and safety                                                 1.4-4
                                     Power point                                    Answer
devices                                                                                        Laptop
                   Lecture           presentation         Written Exam             Questions                                  20 minutes
                                                                                     1.4-4     Power point references
                                    Oral interview              1.4-4
                                                                                               CBLM / TR/CBC
                                  Read Information                                             CBLM
                                  Sheet 1.1-8 on           Answer Self         Compare to      TR/CBC
                   Self paced     Proper usage of          Check 1.4-4         Answer Key      Other References               15 minutes
                  Instruction     PPE and safety                                 1.4-4         (Internet/Textbook)
                                  devices
                                                                                               Hand Outs
LO5 Perform wiring and cabling lay out
Safety                                                    Oral Questions
                                                                                               LCD Projector/ TV
procedures                                                     1.5-1
                                  Power point                                       Answer     Laptop
                   Lecture        presentation            Written Exam             Questions                                  20 minutes
                                                                                     1.5-1     Power point references
                                    Oral interview              1.5-1
                                                                                               CBLM / TR/CBC
                       Electrical Installation and      Date Developed:                                        Document No.
                           Maintenance NC II                     August 2021                    Issued by:
                                                        Date Revised:                             TSDC                   Page 18 of 25
                     Perform Roughing-in Activities,    Developed by:
                      Wiring and Cabling works for              Nelson M. Divino
                    Single-Phase Distribution, Power,                                          Revision # 00
                     Lighting and Auxiliary Systems
                                 Read Information                                             CBLM
                                 Sheet 1.5-1 on           Answer Self         Compare to      TR/CBC
                  Self paced     safety procedures        Check 1.5-1         Answer Key      Other References               15 minutes
                 Instruction                                                    1.5-1         (Internet/Textbook)
                                                                                              Hand Outs
Proper tools                                             Oral Questions
                                                                                              LCD Projector/ TV
and materials                                                 1.5-2
                                    Power point                                    Answer
for the work                                                                                  Laptop
                  Lecture           presentation         Written Exam             Questions                                  20 minutes
needed                                                                                        Power point references
                                   Oral interview              1.5-2                1.5-2
                                                                                              CBLM / TR/CBC
                                 Read Information
                                 Sheet 1.5-2 on                                               CBLM
                                                          Answer Self         Compare to
                                 Proper tools and         Check 1.5-2         Answer Key      TR/CBC
                                 materials for the
                  Self paced                                                    1.5-2
                                 work needed                                                  Other References               15 minutes
                 Instruction
                                                                                              (Internet/Textbook)
                                                                                              Hand Outs
Securing cable                      Power point          Oral Questions            Answer
                  Lecture                                                                     LCD Projector/ TV              20 minutes
support                             presentation              1.5-3               Questions
                      Electrical Installation and      Date Developed:                                        Document No.
                          Maintenance NC II                     August 2021                    Issued by:
                                                       Date Revised:                             TSDC                   Page 19 of 25
                    Perform Roughing-in Activities,    Developed by:
                     Wiring and Cabling works for              Nelson M. Divino
                   Single-Phase Distribution, Power,                                          Revision # 00
                    Lighting and Auxiliary Systems
structure                           Oral interview        Written Exam               1.5-3     Laptop
                                                                1.5-3                          Power point references
                                                                                               CBLM / TR/CBC
                                                                                               CBLM
                                  Read Information         Answer Self         Compare to      TR/CBC
                   Self paced     Sheet 1.5-3 on           Check 1.5-3         Answer Key      Other References               15 minutes
                  Instruction     Securing cable                                 1.5-3         (Internet/Textbook)
                                  support structure
                                                                                               Hand Outs
                                                                                               LCD Projector/ TV
                                                                                               Laptop
                                     Power point             Written                Answer
                    Group            presentation                                              Power point
                                                           Examination             Questions                                  15 minutes
                  Discussion                                                                   presentation references
                                                              1.5-3                  1.5-3
                                                                                               CBLM
                                                                                               TR/CBC
Action taken to                                           Oral Questions
                                                                                               LCD Projector/ TV
unplanned                                                      1.5-4
                                     Power point                                    Answer
event that may                                                                                 Laptop
                   Lecture           presentation         Written Exam             Questions                                  20 minutes
occur in the                                                                                   Power point references
work area                           Oral interview              1.5-4                1.5-4
                                                                                               CBLM / TR/CBC
                       Electrical Installation and      Date Developed:                                        Document No.
                           Maintenance NC II                     August 2021                    Issued by:
                                                        Date Revised:                             TSDC                   Page 20 of 25
                     Perform Roughing-in Activities,    Developed by:
                      Wiring and Cabling works for              Nelson M. Divino
                    Single-Phase Distribution, Power,                                          Revision # 00
                     Lighting and Auxiliary Systems
                                  Read Information                                             CBLM
                                  Sheet 1.1-8 on           Answer Self         Compare to      TR/CBC
                   Self paced     action taken to          Check 1.5-4         Answer Key                                     15 minutes
                  Instruction     unplanned event                                              Other References
                                                                                 1.5-4
                                  that may occur in                                            (Internet/Textbook)
                                  the work area                                                Hand Outs
                                                                                               LCD Projector/ TV
                                                                                               Laptop
                                     Power point             Written                Answer
                    Group            presentation                                              Power point
                                                           Examination             Questions                                  15 minutes
                  Discussion                                                                   presentation references
                                                              1.5-4                  1.5-4
                                                                                               CBLM
                                                                                               TR/CBC
Checking the                                              Oral Questions
                                                                                               LCD Projector/ TV
quality of work                                                1.5-5
                                     Power point                                    Answer
after                                                                                          Laptop
                   Lecture           presentation         Written Exam             Questions                                  20 minutes
performing                                                                                     Power point references
wiring and                          Oral interview              1.5-5                1.5-5
cable layout                                                                                   CBLM / TR/CBC
                                  Read Information                                             CBLM
                   Self paced     Sheet 1.5-5 on           Answer Self         Compare to      TR/CBC                         15 minutes
                  Instruction     Checking the             Check 1.5-5         Answer Key
                                  quality of work                                              Other References
                       Electrical Installation and      Date Developed:                                        Document No.
                           Maintenance NC II                     August 2021                    Issued by:
                                                        Date Revised:                             TSDC                   Page 21 of 25
                     Perform Roughing-in Activities,    Developed by:
                      Wiring and Cabling works for              Nelson M. Divino
                    Single-Phase Distribution, Power,                                          Revision # 00
                     Lighting and Auxiliary Systems
                 after performing                                 1.5-5     (Internet/Textbook)
                 wiring and cable                                           Hand Outs
                 layout
Demonstration        Trainer’s            Perform Task          Check       Tools and device                 4 hours
                   Demonstration           Sheet 1.5-5        performanc    drivers:
                                                               e criteria             boxes
                       Video
                                                               checklist              utility box
                    presentation            Hands On             1.5-5                junction
                                             Practice                                   box
                                                              Procedural
                                                               Checklist              pull box/
                                                                 1.5-5                  splice box
                                                                                      conduit
                                                                                        supports
                                                                                      conduit
                                                                                        strap
                                                                                      connectors
                                                                                        (straight
                                                                                        and angle)
                                                                                      spirit level
                                                                                      hacksaw
                                                                                      pipe cutter
                                                                                      pipe
                                                                                        reamer
                                                                                      plumb bob
      Electrical Installation and      Date Developed:                                      Document No.
          Maintenance NC II                     August 2021                  Issued by:
                                       Date Revised:                           TSDC                   Page 22 of 25
    Perform Roughing-in Activities,    Developed by:
     Wiring and Cabling works for              Nelson M. Divino
   Single-Phase Distribution, Power,                                        Revision # 00
    Lighting and Auxiliary Systems
                                                                                                             pipe
                                                                                                              threader
                                                                                                             pipe
                                                                                                              bender
                                                                                                             bolt cutter
                                                                                                             electric
                                                                                                              drill
LO6 Notify completion of work
Inspecting and                                           Oral Questions
                                                                                           LCD Projector/ TV
checking the                                                  1.6-1
                                    Power point
finished work                                                                 Answer key   Laptop
                  Lecture           presentation         Written Exam                                                       20 minutes
                                                                                1.6-1      Power point references
                                   Oral interview              1.6-1
                                                                                           CBLM / TR/CBC
                                 Read Information                                          CBLM
                                 Sheet 1.1-8 on           Answer Self-        Answer Key TR/CBC
                  Self paced     inspecting and           Check 1.6-1           1.6-1                                       15 minutes
                 Instruction     checking the                                            Other References
                                 finished work                                           (Internet/Textbook)
                                                                                           Hand Outs
                      Electrical Installation and      Date Developed:                                       Document No.
                          Maintenance NC II                     August 2021                 Issued by:
                                                       Date Revised:                          TSDC                     Page 23 of 25
                    Perform Roughing-in Activities,    Developed by:
                     Wiring and Cabling works for              Nelson M. Divino
                   Single-Phase Distribution, Power,                                       Revision # 00
                    Lighting and Auxiliary Systems
 Ensuring the                                                                                 LCD Projector/ TV
work is done                        Power point          Written Exam
                                                                              Answer key      Laptop
properly          Lecture           presentation               1.6-2                                                         20 minutes
                                                                                1.6-2         Power point references
                                   Oral interview
                                                                                              CBLM / TR/CBC
                                                                                              CBLM
                                 Read Information
                                                          Answer Self         Answer Key TR/CBC
                  Self paced     Sheet 1.1-8 on
                                                          Check 1.6-2           1.6-2                                        15 minutes
                 Instruction     ensuring the                                            Other References
                                 work is done                                            (Internet/Textbook)
                                 properly                                                     Hand Outs
Tools,                                                   Oral Questions
                                                                                              LCD Projector/ TV
materials and                                                 1.6-3
                                    Power point                                    Answer
equipment                                                                                     Laptop
                  Lecture           presentation         Written Exam             Questions                                  20 minutes
should be                                                                                     Power point references
check and                          Oral interview              1.6-3                1.6-3
store it to                                                                                   CBLM / TR/CBC
proper storage
                                 Read Information                                             CBLM
                  Self paced     Sheet 1.1-8 on           Answer Self         Compare to      TR/CBC
                                 tools, materials                                                                            15 minutes
                 Instruction                              Check 1.6-3         Answer Key
                                 and equipment                                                Other References
                                                                                1.6-3
                                 should be check                                              (Internet/Textbook)
                      Electrical Installation and      Date Developed:                                        Document No.
                          Maintenance NC II                     August 2021                    Issued by:
                                                       Date Revised:                             TSDC                   Page 24 of 25
                    Perform Roughing-in Activities,    Developed by:
                     Wiring and Cabling works for              Nelson M. Divino
                   Single-Phase Distribution, Power,                                          Revision # 00
                    Lighting and Auxiliary Systems
                                    and store it to                                              Hand Outs
                                    proper storage
Cleaning the                                                Oral Questions
                                                                                                 LCD Projector/ TV
work area and                                                    1.6-4
                                       Power point                                    Answer
made safe for                                                                                    Laptop
                      Lecture          presentation         Written Exam             Questions                                  20 minutes
the usage of                                                                                     Power point references
the area                              Oral interview              1.6-4                1.6-4
                                                                                                 CBLM / TR/CBC
                                    Read Information                                             CBLM
                                    Sheet 1.1-8              Answer Self         Compare to      TR/CBC
                     Self paced     cleaning the work        Check 1.6-4         Answer Key      Other References               15 minutes
                    Instruction     area and made                                  1.6-4         (Internet/Textbook)
                                    safe for the usage
                                    of the area                                                  Hand Outs
C. ASSESSMENT PLAN
    Written Test – in giving written test based it on the self-check.
    Performance Test- in testing the students’ comprehension squared it by following the performance criteria.
D. TEACHER’S SELF-REFLECTION OF THE SESSION
      Encourage students’ participation during the discussion to reinforce their learning.
      Allowing the students/give chance to share their own experiences related to the lesson.
                         Electrical Installation and      Date Developed:                                        Document No.
                             Maintenance NC II                     August 2021                    Issued by:
                                                          Date Revised:                             TSDC                   Page 25 of 25
                       Perform Roughing-in Activities,    Developed by:
                        Wiring and Cabling works for              Nelson M. Divino
                      Single-Phase Distribution, Power,                                          Revision # 00
                       Lighting and Auxiliary Systems