Renovation - B5

The document contains details of tasks for a renovation project including task codes, names, durations, statuses, predecessors, resources assigned, and costs. It lists 10 tasks that have been completed, 1 task currently in progress, and 6 tasks that have not yet started. Resources assigned to the tasks include project managers, designers, site engineers, supervisors, carpenters, painters, cement, bricks, and equipment like JCB.

Uploaded by

s4hana work
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
40 views11 pages

Renovation - B5

The document contains details of tasks for a renovation project including task codes, names, durations, statuses, predecessors, resources assigned, and costs. It lists 10 tasks that have been completed, 1 task currently in progress, and 6 tasks that have not yet started. Resources assigned to the tasks include project managers, designers, site engineers, supervisors, carpenters, painters, cement, bricks, and equipment like JCB.

Uploaded by

s4hana work
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 11

TASK

task_code status_code wbs_id wbs_name task_name target_drtn_hr_cnt


Activity ID Activity Status WBS Code (*)WBS Name Activity Name Original Duration(d)
A1000 Completed renovation - B5.1.1 landscape level of the land 10
A1010 Completed renovation - B5.1.1 landscape lay flooring tile 6
A1020 Completed renovation - B5.1.1 landscape artifical grass 3
A1030 Completed renovation - B5.1.2 painting finish exterior wall 7
A1040 Completed renovation - B5.1.2 painting paint the wall 9
A1050 In Progress renovation - B5.2.1 flooring takeout old tile 22
A1060 Not Started renovation - B5.2.1 flooring lay new tile 5
A1070 Not Started renovation - B5.2.1 flooring polish the tile 5
A1090 Not Started renovation - B5.2.2 interior decor paint the wall 6
A1100 Not Started renovation - B5.2.2 interior decor decor interior 2
A1080 Not Started renovation - B5.2.2 interior decor remove old item 8

Page 1
TASK

start_date end_date resource_list delete_record_flag


(*)Start (*)Finish (*)Resources Delete This Row
14-01-2024 09:00:00 30-01-2024 18:00:00 PROJECT MANAGER, DESIGN ENGG
25-01-2024 09:00:00 04-02-2024 18:00:00 SITE ENGG, SUPERVISIOR, CEMENT
25-01-2024 09:00:00 30-01-2024 18:00:00 SITE ENGG, CARPENTER, CEMENT
01-02-2024 09:00:00 08-02-2024 18:00:00 PAINTER, JCB
10-02-2024 09:00:00 19-02-2024 18:00:00 SITE ENGG, BRICK
20-02-2024 09:00:00 16-03-2024 18:00:00 CARPENTER, SUPERVISIOR, CEMENT
17-03-2024 09:00:00 23-03-2024 18:00:00 CEMENT, CARPENTER, JCB, BRICK
24-03-2024 09:00:00 28-03-2024 18:00:00
27-03-2024 09:00:00 02-04-2024 18:00:00
03-04-2024 09:00:00 04-04-2024 18:00:00
17-03-2024 09:00:00 26-03-2024 18:00:00

Page 2
TASKPRED

pred_task_id task_id pred_type PREDTASK__status_code TASK__status_code


Predecessor Successor Relationship Type (*)Predecessor Activity Status (*)Successor Activity Status
A1030 A1040 FS Completed Completed
A1050 A1080 FS In Progress Not Started
A1060 A1070 FS Not Started Not Started
A1080 A1090 FS Not Started Not Started
A1000 A1010 FS Completed Completed
A1000 A1020 FS Completed Completed
A1050 A1060 FS In Progress Not Started
A1040 A1050 FS Completed In Progress
A1090 A1100 FS Not Started Not Started
A1010 A1030 FS Completed Completed

Page 3
TASKPRED

predtask__task_name task__task_name lag_hr_cnt delete_record_flag


(*)Predecessor Activity Name (*)Successor Activity Name Lag(d) Delete This Row
finish exterior wall paint the wall 0
takeout old tile remove old item 0
lay new tile polish the tile 0
remove old item paint the wall 0
level of the land lay flooring tile 0
level of the land artifical grass 0
takeout old tile lay new tile 0
paint the wall takeout old tile 0
paint the wall decor interior 0
lay flooring tile finish exterior wall 0

Page 4
PROJCOST

task_id cost_name TASK__status_code target_cost act_cost remain_cost total_cost


Activity IDExpense Item (*)Activity Status Budgeted Cost Actual Cost Remaining Cost At Completion Cost

Page 5
PROJCOST

delete_record_flag
Delete This Row

Page 6
RSRC

rsrc_short rsrc_name rsrc_type unit_id role_id def_qty_per_hr


Resource I Resource (*)ResourcUnit of Me(*)Role ID Default Units / Time(h/d)
E&C ResouE&C ResouLabor 8
Trades Trades Labor 8
CretefinishConcrete F Labor Trades
Operator Operator Labor Trades
OPTGP Operations Labor 8
INSP Inspection Labor 8
Hydro HydroblastLabor 22
Tasameem Direct Res Labor 8
L1 Carpenter Labor 8
L2 Steel Fixer Labor 8
L4 Helper Labor 8
L5 AC Tech. Labor 8
L6 Plumber Labor 8
L7 Electrician Labor 8
L3 Mason Labor 8
L9 False Ceili Labor 8
L10 Glass TechLabor 8
L11 Alum. TechLabor 8
L12 Steel Tech.Labor 8
L8 Painter Labor 8
L15 Operator Labor 8
L16 Scaffolder Labor 8
L17 Insulation Labor 8
E1 Excavator Nonlabor 8
L14 Fire Fighti Labor 8
E4 Mobile Cr Nonlabor 8
E6 Concrete VNonlabor 8
E7 CompactorNonlabor 8
E8 Jack HammNonlabor 8
E2 Piling mac Nonlabor 8
E10 DumptruckNonlabor 8
E11 Bar bendin Nonlabor 8
L18 Garbage ChLabor 8
L19 Lift Tech. Labor 8
E9 Loader Nonlabor 8
E13 CompressoNonlabor 8
E14 Generator Nonlabor 8
E15 Rig Machi Nonlabor 8
L20 Joinery Te Labor 8
E12 JCB Nonlabor 8
PM PROJECT Labor 8
DE DESIGN Labor 8
SE SITE ENG Labor 8
SUP SUPERVISLabor 8
CARP CARPENTLabor 8
PAINTER PAINTER Labor 8
CEMENT CEMENT Material BAGS 0
BR BRICK Material NUMBER 0

Page 7
RSRC

JCB JCB Nonlabor 8

Page 8
TASKRSRC

task_id TASK__status_code rsrc_id role_id acct_id rsrc_type cost_per_qty


Activity ID(*)Activity Status Resource ID Role ID Cost Account ID (*)Resource Type (*)Price / Unit($/h)
A1000 Completed PM Labor 700
A1000 Completed DE Labor 600
A1010 Completed SE Labor 600
A1010 Completed SUP Labor 400
A1020 Completed SE Labor 600
A1020 Completed CARP Labor 200
A1030 Completed PAINTER Labor 150
A1020 Completed CEMENT Material 450
A1010 Completed CEMENT Material 450
A1040 Completed SE Labor 600
A1040 Completed BR Material 8
A1030 Completed JCB Nonlabor 400
A1050 In Progress CARP Labor 200
A1050 In Progress SUP Labor 400
A1050 In Progress CEMENT Material 450
A1060 Not Started CEMENT Material 450
A1060 Not Started CARP Labor 200
A1060 Not Started JCB Nonlabor 400
A1060 Not Started BR Material 8

Page 9
TASKRSRC

start_date end_date delete_record_flag


(*)Start (*)Finish Delete This Row
14-01-2024 09:00:00 30-01-2024 18:00:00
14-01-2024 09:00:00 30-01-2024 18:00:00
25-01-2024 09:00:00 04-02-2024 18:00:00
25-01-2024 09:00:00 04-02-2024 18:00:00
25-01-2024 09:00:00 30-01-2024 18:00:00
25-01-2024 09:00:00 30-01-2024 18:00:00
01-02-2024 09:00:00 08-02-2024 18:00:00
25-01-2024 09:00:00 30-01-2024 18:00:00
25-01-2024 09:00:00 04-02-2024 18:00:00
10-02-2024 09:00:00 19-02-2024 18:00:00
10-02-2024 09:00:00 10-02-2024 09:00:00
01-02-2024 09:00:00 08-02-2024 18:00:00
20-02-2024 09:00:00 16-03-2024 18:00:00
20-02-2024 09:00:00 16-03-2024 18:00:00
20-02-2024 09:00:00 20-02-2024 09:00:00
17-03-2024 09:00:00 17-03-2024 09:00:00
17-03-2024 09:00:00 23-03-2024 18:00:00
17-03-2024 09:00:00 23-03-2024 18:00:00
17-03-2024 09:00:00 17-03-2024 09:00:00