ACC TOILET ESTIMATION FOR MARTHA & JIVAN
Lalitpur
                                                           Bills of Quantity
                                                                                                            Total
S.N.                         Description of Works                          Unit     Quantity    Rate       Amount       Remarks
                                                                                                            (NPR)
A.     MATERIALS:
 1     Bricks                                                              300.00     Nos.        18.00     5,400.00
 2     Cement                                                                5.00     Bag        900.00     4,500.00
 3     Sand                                                                 50.00   Cu.Feet      120.00     6,000.00
 4     Gravel (Roda)                                                        40.00   Cu.Feet      120.00     4,800.00
 5     Toilet Pan with Syphon (Asian Type)                                   1.00     Nos.     2,000.00     2,000.00
 6     Tap                                                                   1.00     Nos.       500.00       500.00
 7     Plumbing Pipes and fittings (Sewarage and Water supply)               1.00     L/S       4,000.00    4,000.00
 8     Electrical works                                                      1.00     L/S       1,000.00    1,000.00
                                                                                                                       Salla wood
                                                                                                                     Frame & Plain
 9     Aluminium Door with Frame and all fittings                            1.00     Nos.     22,000.00   22,000.00 Sheet Door =
                                                                                                                        Rs10,000
10     Tiles for surface and 1 feet above walls                             48.00     Sqft       150.00     7,200.00 Optional
                                             TOTAL MATERIALS COST                                          57,400.00
 B.    MANPOWER:
 1     Skilled Meson (Mistri)                                                4.00 Man/Day       1,500.00    6,000.00
 2     Helping Labourer                                                      6.00 Man/Day       1,000.00    6,000.00
 3     Plumbing Charges                                                      2.00 Man/Day       1,500.00    3,000.00
                                                  TOTAL LABOUR COST                                        15,000.00
                                                                 TOTAL COST FOR 1 TOILET                   72,400.00
                                    ACC TOILET ESTIMATION FOR MARTHA & JIVAN
                                                                 Imadol, Lalitpur
                                                                Bills of Quantity
 S.N.                            Description of Works                         Unit       Quantity     Rate         Total Amount     Remarks
                                                                                                                       (NPR)
 A.        MATERIALS:
     1     Bricks                                                             400.00       Nos.            18.50          7,400
     2     Cement                                                                 6.00     Bag         900.00             5,400
     3     Sand                                                                50.00     Cu.Feet       120.00             6,000
     4     Gravel (Roda)                                                       40.00     Cu.Feet       120.00             4,800
     5     Aluminium Door with Frame and all fittings                             1.00     Nos.      22,000.00           22,000
     6     Aluminium Ventilator with Frame and all fittings                       1.00     Nos.       4,000.00            4,000
     7     Tiles for surface and 6 feet above walls                           160.00       Sqft        140.00            22,400
     8     False Ceiling to cover CGI (Jasta) Roofing                          42.00       Sqft        100.00             4,200
     9     Painting Works                                                     210.00       Sqft            32.00          6,720
 10        Electrical works                                                       1.00     L/S        5,000.00            5,000
     9     Commode, Basin, Pipes & Fitting all Bathroom Appliances          Details given below                          65,720 see detais
                                                 TOTAL MATERIALS COST                                                   153,640
  B.       MANPOWER:
     1     Skilled Meson (Mistri)                                                 6.00 Man/Day        1,500.00            9,000
     2     Helping Labourer                                                    12.00 Man/Day          1,000.00           12,000
     3     Plumbing Charges including commode & Basin Installation                6.00 Man/Day        1,800.00           10,800
                                                      TOTAL LABOUR COST                                                  31,800
                                                                    TOTAL COST FOR 1 BATHROOM                          185,440
           DETAILS OF BATHROOM FITTINGS & ACCESSORIES:
SN         DESCTIPTION                                                      UNITS                   RATE           AMOUNT         REMARKS
            Porcelain clay white glaze IPWC Comode with dual flush and
          1 primium seat cover- all complete set cascade type               nos             1        17,000.00           17,000
          2 Toilet Sprayer- Chrome type with Nose                           nos             1         1,500.00            1,500
          3 55x40cm Porcelain clay white glaze Wash basin Regular           nos             1         5,000.00            5,000
          4 Porcelain clay toilet paper holder (Recessed type)              nos             1           800.00              800
          5 Chrome plate soap tray                                          nos             1           850.00              850
          6 Chrome plate Towel rod 1.5 x 45cm size                          nos             1         1,200.00            1,200
          7 Looking mirror 55x40cm size                                     nos             1         3,000.00            3,000
          8 Chrome plate shower ordinary type                               nos             1         5,000.00            5,000
          9 Tap Mixture                                                     nos             1         8,000.00            8,000
         10 C P 15 mm bib cock ordinary type                                nos             1           700.00              700
         11 PVC Floor trap 11x7.5cm                                         nos             2           500.00            1,000
         12 15mm dia. UPVC pipe ( Medium ) Cold                             Rm              9           400.00            3,600
         13 15mm dia. UPVC pipe ( Medium ) Hot                              Rm              6           500.00            3,000
         14 50 mm PVC Pipe 4 kg/cm2.                                        Rm              3           820.00            2,460
         15 110 mm PVC Pipe 4 kg\cm2.                                       Rm              4         1,200.00            4,800
         16 110 mm Vent cowl                                                nos             1           400.00              400
         17 110 mm Plain tee                                                nos             2           515.00            1,030
         18 110 mm Door tee                                                 nos             1           650.00              650
         19 110 mm Bend 90 degree                                           nos             2           650.00            1,300
         20 110 mm Door bend                                                nos             1           700.00              700
         21 110 mm Bend 45 degree                                           nos             2           550.00            1,100
         22 110 mm Pipe clip                                                nos            20            20.00              400
         23 110 mm Gully trap                                               nos             1           980.00              980
24 G.M. 15mm Gate valve                                nos   1   1,250.00    1,250
                          Estimated Cost of Sanitary                        65,720
Project Name:   Commercial Building of In Nepal
Location:       Lalitpur
                                                Commercial Building of In Nepal
                                                           Lalitpur
                                                    Cost Summary Sheet
S.N.                                  Description of Works
       General Items
 A     CIVIL WORKS
 B     ELECTRICAL WORKS (detail estimate of electrical)
 C     SANITARY WORKS (detil sanitary estimate)
                                                                            Sub-Total (A)
       Administrative Cost (@ 20%)
       Supervision and Consulting cost (@12%)
       Contingencies (@ 5%)
       Physical contingencies @ 7%
                                                                             Sub-Total (B)
                                                                              VAT @ 13%
                                                                      Total including VAT
l
    Duration:12 months
      Amount (NPR)
                           Remarks
          In Figure
                2,000.00
                 Err:509
             476,756.11
              65,720.00              With VAT             Corner stone
                 Err:509                        Err:509            22,414,834.09    19,836,136.36
                 Err:509                                                  Err:509          Err:509
                 Err:509                                                  Err:509          Err:509
                 Err:509
                 Err:509
                 Err:509
                 Err:509
                 Err:509
                             ACC TOILET ESTIMATION FOR MARTHA & JIVAN
                                                                Lalitpur
                                                           Bills of Quantity
                                                                                                            Total
S.N.                         Description of Works                          Unit     Quantity    Rate       Amount       Remarks
                                                                                                            (NPR)
A.     MATERIALS:
 1     Bricks                                                              300.00     Nos.        18.00     5,400.00
 2     Cement                                                                5.00     Bag        900.00     4,500.00
 3     Sand                                                                 50.00   Cu.Feet      120.00     6,000.00
 4     Gravel (Roda)                                                        40.00   Cu.Feet      120.00     4,800.00
 5     Toilet Pan with Syphon (Asian Type)                                   1.00     Nos.     2,000.00     2,000.00
 6     Tap                                                                   1.00     Nos.       500.00       500.00
 7     Plumbing Pipes and fittings (Sewarage and Water supply)               1.00     L/S       4,000.00    4,000.00
 8     Electrical works                                                      1.00     L/S       1,000.00    1,000.00
                                                                                                                       Salla wood
                                                                                                                     Frame & Plain
 9     Aluminium Door with Frame and all fittings                            1.00     Nos.     22,000.00   22,000.00 Sheet Door =
                                                                                                                        Rs10,000
10     Tiles for surface and 1 feet above walls                             48.00     Sqft       150.00     7,200.00 Optional
                                             TOTAL MATERIALS COST                                          57,400.00
 B.    MANPOWER:
 1     Skilled Meson (Mistri)                                                4.00 Man/Day       1,500.00    6,000.00
 2     Helping Labourer                                                      6.00 Man/Day       1,000.00    6,000.00
 3     Plumbing Charges                                                      2.00 Man/Day       1,500.00    3,000.00
                                                  TOTAL LABOUR COST                                        15,000.00
                                                                 TOTAL COST FOR 1 TOILET                   72,400.00
                                             Commercial Building of In Nepal
                                                        Lalitpur
                                                   Detail Estimate
S.N. Descriptions                       No.           L            B            H      Quantity   Unit
 A Civil Works
1.0 Site Clearance
                        Main Building   1             Area =                  2,034.22 2,034.22
                                                                  Total Site Clearance 2034.22    Sq.ft
2.0 Earthwork
2.1 E/W in excavation
    Isolated Footings
                                  F1    4            6.00         6.00         5.50     792.00
                                  F2    4            7.00         7.00         5.50    1078.00
                                  F3    4            8.00         8.00         5.50    1408.00
    Toe wall
               Along grid A-A to F-F    6           17.25       2.50        3.50     905.63
                Along grid 1-1 & 2-2    2           55.67       2.50        3.50     974.14
                                                      Total Earthwork in Excavation 5157.76       Cu.ft
3.0 Brick soling works
    Isolated Footings
                                  F1    4            6.00         6.00                 144.00
                                  F2    4            7.00         7.00                 196.00
                                  F3    4            8.00         8.00                 256.00
    Toe wall
              Along grid A-A to F-F     6           17.25         1.50                 155.25
               Along grid 1-1 & 2-2     2           55.67         1.50                 167.00
    Ground Floor Rooms
                 Between Grid A-B       1           11.25       18.08                 203.43
                 Between Grid B-C       1           11.25       18.08                 203.43
                 Between Grid C-D       1           11.33       18.08                 204.88
                 Between Grid D-E       1           11.25       18.08                 203.43
                 Between Grid E-F       1           13.08       18.08                 236.58
                                                         Total of Brick Soling Works 1970.00      Sq.ft
4.0 Concrete Works
4.1 PCC (M15/40) works in foundation, Door Sill and Lintel Beam
    Isolated Footings
                                  F1  4        6.00         6.00               0.25     36.00
                                  F2  4        7.00         7.00               0.25     49.00
                                  F3  4        8.00         8.00               0.25     64.00
    Toe wall
               Along grid A-A to F-F  6       12.33         1.50               0.25     27.74
                Along grid 1-1 & 2-2  2       25.50         1.50               0.25     19.12
    Ground Floor Rooms
                  Between Grid A-B    1       11.25        18.08               0.25     50.86
                  Between Grid B-C    1       11.25        18.08               0.25     50.86
                  Between Grid C-D    1       11.33        18.08               0.25     51.22
                  Between Grid D-E    1       11.25        18.08               0.25     50.86
                  Between Grid E-F    1       13.08        18.08               0.25     59.14
    Below Plinth Beam
               Along grid A-A to F-F  6       17.25         0.23               0.25     5.95
                Along grid 1-1 & 2-2  2       55.67         0.23               0.25     6.40
                                                                                       471.16
    Sill Bands
    Ground Floor
               Along grid 1-1 & 2-2     2           55.67        0.750         0.330    27.55
                      Deduct door       -1           3.00        0.750         0.330    -0.74
                   Along Grid A-A    1    17.25   0.750   0.330    4.27
                   Deduct shutter    -1   10.00   0.750   0.330   -2.48
                  Along Grid D-D     1    17.25   0.330   0.330    1.88
Toilet wall between D-D and E-E      1    11.33   0.330   0.330    1.23
                      Deduct door    -1    2.50   0.330   0.330   -0.27
                   Along Grid E-E    1    17.25   0.330   0.330    1.88
                      Deduct door    -1    3.00   0.330   0.330   -0.33
 Toilet wall between E-E and F-F     1    13.33   0.330   0.330    1.45
                      Deduct door    -1    2.50   0.330   0.330   -0.27
                   Along Grid F-F    1    17.25   0.750   0.330    4.27
                      Deduct door    -1    4.00   0.750   0.330   -0.99
First Floor
              Along grid 1-1 & 2-2   2    55.67   0.750   0.330   27.55
                   Along Grid A-A    1    17.25   0.750   0.330    4.27
                   Along Grid E-E    1    17.25   0.330   0.330    1.88
                      Deduct door    -1    3.00   0.330   0.330   -0.33
 Toilet wall between E-E and F-F     1    13.33   0.330   0.330    1.45
                      Deduct door    -1    2.50   0.330   0.330   -0.27
                   Along Grid F-F    1    17.25   0.750   0.330    4.27
                      Deduct door    -1    3.00   0.750   0.330   -0.74
               Deduct Ventilations   -1    6.00   0.750   0.330   -1.49
Second Floor
              Along grid 1-1 & 2-2   2    55.67   0.750   0.330   27.55
                   Along Grid A-A    1    17.25   0.750   0.330    4.27
                   Along Grid E-E    1    17.25   0.330   0.330    1.88
                      Deduct door    -1    3.00   0.330   0.330   -0.33
 Toilet wall between E-E and F-F     1    13.33   0.330   0.330    1.45
                      Deduct door    -1    2.50   0.330   0.330   -0.27
                   Along Grid F-F    1    17.25   0.750   0.330    4.27
                      Deduct door    -1    3.00   0.750   0.330   -0.74
               Deduct Ventilations   -1    6.00   0.750   0.330   -1.49
Top Floor
              Along grid 1-1 & 2-2   2    34.00   0.750   0.330   16.83
                      Deduct door    -1    3.00   0.750   0.330   -0.74
                  Along Grid 1'-1'   1    11.92   0.330   0.330    1.30
                  Along Grid C-C     1    17.25   0.750   0.330    4.27
                      Deduct door    -1    3.00   0.750   0.330   -0.74
                  Along Grid D-D     1    17.25   0.330   0.330    1.88
                      Deduct door    -2    3.00   0.330   0.330   -0.65
 Toilet wall between E-E and F-F     1    13.33   0.330   0.330    1.45
                      Deduct door    -1    2.50   0.750   0.330   -0.62
                  Along Grid E'-E'   1    17.25   0.330   0.330    1.88
                      Deduct door    -1    4.00   0.330   0.330   -0.44
                   Along Grid F-F    1    17.25   0.750   0.330    4.27
               Deduct Ventilations   -1    6.00   0.750   0.330   -1.49
Lintel Bands
Ground Floor
              Along grid 1-1 & 2-2   2    55.67   0.750   0.500   41.75
                  Along Grid D-D     1    17.25   0.330   0.500    2.85
Toilet wall between D-D and E-E      1    11.33   0.330   0.500    1.87
                   Along Grid E-E    1    17.25   0.330   0.500    2.85
 Toilet wall between E-E and F-F     1    13.33   0.330   0.500    2.20
                   Along Grid F-F    1    17.25   0.750   0.500    6.47
First Floor
              Along grid 1-1 & 2-2   2    55.67   0.750   0.500   41.75
                   Along Grid A-A    1    17.25   0.750   0.500    6.47
                   Along Grid E-E    1    17.25   0.330   0.500    2.85
     Toilet wall between E-E and F-F     1    13.33     0.330      0.500       2.20
                       Along Grid F-F    1    17.25     0.750      0.500       6.47
    Second Floor
                  Along grid 1-1 & 2-2   2    55.67     0.750      0.500      41.75
                       Along Grid A-A    1    17.25     0.750      0.500       6.47
                       Along Grid E-E    1    17.25     0.330      0.500       2.85
                       Along Grid F-F    1    17.25     0.750      0.500       6.47
    Top Floor
                  Along grid 1-1 & 2-2   2    34.00     0.750      0.500      25.50
                      Along Grid 1'-1'   1    11.92     0.330      0.500       1.97
                      Along Grid C-C     1    17.25     0.750      0.500       6.47
                      Along Grid D-D     1    17.25     0.330      0.500       2.85
     Toilet wall between E-E and F-F     1    13.33     0.330      0.500       2.20
                      Along Grid E'-E'   1    17.25     0.330      0.500       2.85
                       Along Grid F-F    1    17.25     0.750      0.500       6.47
    Kitchen Counter Slab
                         Counter Slab    2    13.25     2.000      0.330       17.49
                                                                              378.88
                                                         Total of PCC works   850.03   Cu.ft
4.2 RCC (M25/20) works
    a) Sub-Structure
    Isolated Footings
    F1
                        Footing Slab     4     6.00      6.00      1.00       144.00
                 Trapezoidal Section     4    Area =    19.68      1.17        91.79
    F2
                        Footing Slab     4     7.00      7.00      1.33       260.68
                 Trapezoidal Section     4    Area =    26.18      1.17       122.10
    F3
                        Footing Slab     4     8.00      8.00      1.33       340.48
                 Trapezoidal Section     4    Area =    33.68      1.17       157.08
    Columns upto the Plinth level
                     All the columns     12    1.17     1.17       5.25       85.65
    Footing Beam
                Along grid A-A to F-F    6    17.25     0.75       1.00       77.63
                 Along grid 1-1 & 2-2    2    55.67     0.75       1.00       83.50
    Plinth Beam
                Along grid A-A to F-F    6    17.25     0.75       1.00       77.63
                 Along grid 1-1 & 2-2    2    55.67     0.75       1.00       83.50
    b) Super-Structure
    Ground Floor
    Columns                              12    1.17     1.17       9.00       146.83
    Beams
                Along grid A-A to F-F    6    17.25     0.75       1.00       77.63
                 Along grid 1-1 & 2-2    2    55.67     0.75       1.00       83.50
    Slab
                           Total Area    1    Area =   1254.72     0.42       521.96
                Deduct staircase void    -1   Area =    67.64      0.42       -28.14
    Staircase
                         Lower Flight     1    7.17     3.50       0.42       10.43
                        First Landing     1    3.50     3.50       0.42        5.10
                        Middle Flight     1    2.00     3.50       0.42        2.91
                     Middle Landing       1    3.50     3.50       0.42        5.10
                         Upper Flight     1    7.17     3.50       0.42       10.43
                                Steps    16    3.50     0.83       0.58       27.20
    First Floor
    Columns                              12    1.17     1.17       9.00       146.83
    Beams
                Along grid A-A to F-F    6    17.25        0.75        1.00       77.63
                 Along grid 1-1 & 2-2    2    55.67        0.75        1.00       83.50
    Slab
                           Total Area    1    Area =     1254.72       0.42      521.96
                Deduct staircase void    -1   Area =      67.64        0.42      -28.14
    Staircase
                         Lower Flight     1    7.17        3.50        0.42       10.43
                        First Landing     1    3.50        3.50        0.42        5.10
                        Middle Flight     1    2.00        3.50        0.42        2.91
                      Middle Landing      1    3.50        3.50        0.42        5.10
                         Upper Flight     1    7.17        3.50        0.42       10.43
                                Steps    16    3.50        0.83        0.58       27.20
    Second Floor
    Columns                              12    1.17        1.17        9.00      146.83
    Beams
              Along grid A-A to F-F      6    17.25        0.75        1.00       77.63
               Along grid 1-1 & 2-2      2    55.67        0.75        1.00       83.50
    Slab
                         Total Area      1    Area =     1551.56       0.42      645.45
              Deduct staircase void      -1   Area =      67.64        0.42      -28.14
    Staircase
                       Lower Flight       1    7.17        3.50        0.42       10.43
                      First Landing       1    3.50        3.50        0.42        5.10
                      Middle Flight       1    2.00        3.50        0.42        2.91
                    Middle Landing        1    3.50        3.50        0.42        5.10
                       Upper Flight       1    7.17        3.50        0.42       10.43
                              Steps      16    3.50        0.83        0.58       27.20
    Top Floor
    Columns                              8     1.17        1.17        9.00       97.89
    Beams
              Along grid C-C to F-F      6    17.25        0.75        1.00       77.63
               Along grid 1-1 & 2-2      2    34.00        0.75        1.00       51.00
    Slab
                         Total Area      1    Area =      945.18      0.42     393.19
                                                              Total RCC works 4856.06        Cu.ft
5.0 Steel work (Fe 500)
                                                From the detail calculatlion sheet 29094.25
                                                            Total Rebar Works         29.09 Ton
6.0 Formwork
    a) Sub-Structure
    Isolated Footings
    F1
                          Footing Slab   4    24.00                    1.00       96.00
    F2
                          Footing Slab   4    28.00                    1.33      148.96
    F3
                       Footing Slab      4    32.00                    1.33      170.24
    Columns upto the Plinth level
                    All the columns      12    4.66                    5.25      293.83
    Plinth Beam
               Along grid A-A to F-F     6    17.25        2.75                  284.63
                Along grid 1-1 & 2-2     2    55.67        2.75                  306.16
    b) Super-Structure
    Ground Floor
    Columns                              12    4.66                    9.00      503.71
    Beams
              Along grid A-A to F-F   6    17.25     2.75            284.63
               Along grid 1-1 & 2-2   2    55.67     2.75            306.16
Slab
                         Total Area   1    Area =   1254.72          1254.72
              Deduct staircase void   -1   Area =    67.64            -67.64
Staircase
                       Lower Flight    1    7.17     3.50             25.08
                      First Landing    1    3.50     3.50             12.25
                      Middle Flight    1    2.00     3.50              7.00
                    Middle Landing     1    3.50     3.50             12.25
                       Upper Flight    1    7.17     3.50             25.08
                              Steps   16    3.50     1.42             79.30
First Floor
Columns                               12    4.66              9.00   503.71
Beams
              Along grid A-A to F-F   6    17.25     2.75            284.63
               Along grid 1-1 & 2-2   2    55.67     2.75            306.16
Slab
                         Total Area   1    Area =   1254.72          1254.72
              Deduct staircase void   -1   Area =    67.64            -67.64
Staircase
                       Lower Flight    1    7.17     3.50             25.08
                      First Landing    1    3.50     3.50             12.25
                      Middle Flight    1    2.00     3.50              7.00
                    Middle Landing     1    3.50     3.50             12.25
                       Upper Flight    1    7.17     3.50             25.08
                              Steps   16    3.50     1.42             79.30
Second Floor
Columns                               12    4.66              9.00   503.71
Beams
             Along grid A-A to F-F    6    17.25     2.75            284.63
              Along grid 1-1 & 2-2    2    55.67     2.75            306.16
Slab
                        Total Area    1    Area =   1551.56          1551.56
            Deduct staircase void     -1   Area =    67.64            -67.64
Staircase
                      Lower Flight     1    7.17     3.50             25.08
                     First Landing     1    3.50     3.50             12.25
                     Middle Flight     1    2.00     3.50              7.00
                  Middle Landing       1    3.50     3.50             12.25
                      Upper Flight     1    7.17     3.50             25.08
                             Steps    16    3.50     1.42             79.30
Top Floor
Columns                               8     4.66              9.00   335.81
Beams
            Along grid C-C to F-F     6    17.25     2.75            284.63
              Along grid 1-1 & 2-2    2    34.00     2.75            186.99
Slab
                        Total Area    1    Area =   945.18           945.18
Sill Bands
Ground Floor
              Along grid 1-1 & 2-2    2    55.67     2.000           222.66
                      Deduct door     -1    3.00     2.000            -6.00
                   Along Grid A-A     1    17.25     2.000            34.50
                   Deduct shutter     -1   10.00     2.000           -20.00
                  Along Grid D-D      1    17.25     2.000            34.50
Toilet wall between D-D and E-E       1    11.33     2.000            22.66
                      Deduct door    -1    2.50   2.000   -5.00
                   Along Grid E-E    1    17.25   2.000   34.50
                      Deduct door    -1    3.00   2.000   -6.00
 Toilet wall between E-E and F-F     1    13.33   2.000   26.66
                      Deduct door    -1    2.50   2.000   -5.00
                   Along Grid F-F    1    17.25   2.000   34.50
                      Deduct door    -1    4.00   2.000   -8.00
First Floor
              Along grid 1-1 & 2-2   2    55.67   2.000   222.66
                   Along Grid A-A    1    17.25   2.000    34.50
                   Along Grid E-E    1    17.25   2.000    34.50
                      Deduct door    -1    3.00   2.000    -6.00
 Toilet wall between E-E and F-F     1    13.33   2.000    26.66
                      Deduct door    -1    2.50   2.000    -5.00
                   Along Grid F-F    1    17.25   2.000    34.50
                      Deduct door    -1    3.00   2.000    -6.00
               Deduct Ventilations   -1    6.00   2.000   -12.00
Second Floor
              Along grid 1-1 & 2-2   2    55.67   2.000   222.66
                   Along Grid A-A    1    17.25   2.000    34.50
                   Along Grid E-E    1    17.25   2.000    34.50
                      Deduct door    -1    3.00   2.000    -6.00
 Toilet wall between E-E and F-F     1    13.33   2.000    26.66
                      Deduct door    -1    2.50   2.000    -5.00
                   Along Grid F-F    1    17.25   2.000    34.50
                      Deduct door    -1    3.00   2.000    -6.00
               Deduct Ventilations   -1    6.00   2.000   -12.00
Top Floor
              Along grid 1-1 & 2-2   2    34.00   2.000   136.00
                      Deduct door    -1    3.00   2.000    -6.00
                  Along Grid 1'-1'   1    11.92   2.000    23.83
                  Along Grid C-C     1    17.25   2.000    34.50
                      Deduct door    -1    3.00   2.000    -6.00
                  Along Grid D-D     1    17.25   2.000    34.50
                      Deduct door    -2    3.00   2.000   -12.00
 Toilet wall between E-E and F-F     1    13.33   2.000    26.66
                      Deduct door    -1    2.50   2.000    -5.00
                  Along Grid E'-E'   1    17.25   2.000    34.50
                      Deduct door    -1    4.00   2.000    -8.00
                   Along Grid F-F    1    17.25   2.000    34.50
               Deduct Ventilations   -1    6.00   2.000   -12.00
Lintel Bands
Ground Floor
              Along grid 1-1 & 2-2   2    55.67   1.750   194.83
                  Along Grid D-D     1    17.25   1.330    22.94
Toilet wall between D-D and E-E      1    11.33   1.330    15.07
                   Along Grid E-E    1    17.25   1.330    22.94
 Toilet wall between E-E and F-F     1    13.33   1.330    17.73
                   Along Grid F-F    1    17.25   1.750    30.19
First Floor
              Along grid 1-1 & 2-2   2    55.67   1.750   194.83
                   Along Grid A-A    1    17.25   1.750    30.19
                   Along Grid E-E    1    17.25   1.330    22.94
 Toilet wall between E-E and F-F     1    13.33   1.330    17.73
                   Along Grid F-F    1    17.25   1.750    30.19
Second Floor
              Along grid 1-1 & 2-2   2    55.67   1.750   194.83
                      Along Grid A-A     1    17.25   1.750               30.19
                      Along Grid E-E     1    17.25   1.330               22.94
                      Along Grid F-F     1    17.25   1.750               30.19
    Top Floor
                  Along grid 1-1 & 2-2   2    34.00   1.750               119.00
                      Along Grid 1'-1'   1    11.92   1.330                15.85
                      Along Grid C-C     1    17.25   1.750                30.19
                      Along Grid D-D     1    17.25   1.330                22.94
     Toilet wall between E-E and F-F     1    13.33   1.330                17.73
                      Along Grid E'-E'   1    17.25   1.330                22.94
                       Along Grid F-F    1    17.25   1.750                30.19
    Kitchen Counter Slab
                         Counter Slab    2    13.25   2.000                53.00
                                                         Total Formworks 13149.51   sq.ft
7   BRICK MASONRY WORKS
    Toe wall
                Along grid A-A to F-F    6    17.25   1.17       3.50     422.38
                 Along grid 1-1 & 2-2    2    55.67   1.17       3.50     454.34
    Ground Floor
                 Along grid 1-1 & 2-2    2    55.67   0.750     8.250    688.85
                         Deduct door     -1    3.00   0.750     7.000     -15.75
                    Deduct Windows       -9    6.00   0.750     4.500    -182.25
                    Deduct Windows       -2    3.00   0.750     4.500     -20.25
                      Along Grid A-A     1    17.25   0.750     8.250    106.73
                      Deduct shutter     -1   10.00   0.750     8.250     -61.88
                      Along Grid F-F     1    17.25   0.750     8.250    106.73
                         Deduct door     -1    4.00   0.750     8.250     -24.75
                  Deduct ventilations    -1    6.00   0.750     5.000     -22.50
    First Floor
                 Along grid 1-1 & 2-2    2    55.67   0.750     8.250    688.85
                    Deduct Windows       -9    6.00   0.750     4.500    -182.25
                    Deduct Windows       -1    3.00   0.750     4.500     -10.13
                      Along Grid A-A     1    17.25   0.750     8.250    106.73
                    Deduct Windows       -1   10.00   0.750     4.500     -33.75
                      Along Grid F-F     1    17.25   0.750     8.250    106.73
                         Deduct door     -1    3.00   0.750     7.000     -15.75
                 Deduct Ventilations     -1    6.00   0.750     8.250     -37.13
    Second Floor
                 Along grid 1-1 & 2-2    2    55.67   0.750     8.250    688.85
                    Deduct Windows       -9    6.00   0.750     4.500    -182.25
                    Deduct Windows       -1    3.00   0.750     4.500     -10.13
                      Along Grid A-A     1    17.25   0.750     8.250    106.73
                    Deduct Windows       -1   10.00   0.750     4.500     -33.75
                      Along Grid F-F     1    17.25   0.750     8.250    106.73
                         Deduct door     -1    3.00   0.750     7.000     -15.75
                 Deduct Ventilations     -1    6.00   0.750     8.250     -37.13
    Top Floor
                 Along grid 1-1 & 2-2    2    34.00   0.750     8.250     420.74
                         Deduct door     -1    3.00   0.750     7.000     -15.75
                    Deduct Windows       -4    6.00   0.750     4.500     -81.00
                    Deduct Windows       -1    2.00   0.750     4.500      -6.75
                    Deduct Windows       -1    3.00        0.750      4.500     -10.13
                     Along Grid C-C      1    17.25        0.750      8.250     106.73
                        Deduct door      -1    3.00        0.750      7.000     -15.75
                    Deduct Windows       -1    6.00        0.750      4.500     -20.25
                    Deduct Windows       -1    4.33        0.750      4.500     -14.61
                        Deduct door      -1    2.50        0.750      7.000     -13.13
                     Along Grid F-F      1    17.25        0.750      8.250     106.73
                 Deduct Ventilations     -1    6.00        0.750      5.000     -22.50
                    Deduct Windows       -1    4.75        0.750      4.500     -16.03
    Vertical designs
                         Front face      2    72.00         0.75       0.75      81.00
                           Left Face     1    49.66         0.75       0.75      27.93
                         Right Face      1    76.83         0.75       0.75      43.22
    Kitchen Counter Slab
               Kitchen Counter Slab      2     8.00         0.33       3.00      15.84
    Parapet wall
                       Second Floor      1    145.29        0.33       2.00      95.89
                          Top Floor      1    144.83        0.33       2.00      95.59
    Approns
                       Ground Floor      1    170.42        1.50       1.50     383.44
    Front steps
                       Ground Floor      1    22.08         Area =      1.50     33.12
                                                       Total Brick Masonry work 3892.66   Cu.ft
8.0 Interlocking Brick Work
    Ground Floor
                       Along Grid D-D    1    17.25                   8.250     142.31
     Toilet wall between D-D and E-E     1    11.33                   9.000     101.97
                          Deduct door    -1    2.50                   7.000     -17.50
                       Along Grid E-E    1    17.25                   8.250     142.31
                          Deduct door    -1    3.00                   7.000     -21.00
     Toilet wall between E-E and F-F     1    13.33                   9.000     119.97
                          Deduct door    -1    2.50                   7.000     -17.50
    First Floor
                       Along Grid E-E    1    17.25                   8.250     142.31
                          Deduct door    -1    3.00                   7.000     -21.00
     Toilet wall between E-E and F-F     1    13.33                   9.000     119.97
                          Deduct door    -1    2.50                   7.000     -17.50
    Second Floor
                       Along Grid E-E    1    17.25                   8.250     142.31
                          Deduct door    -1    3.00                   7.000     -21.00
     Toilet wall between E-E and F-F     1    13.33                   9.000     119.97
                          Deduct door    -1    2.50                   7.000     -17.50
    Top Floor
                      Along Grid 1'-1'   1    11.92                   9.000     107.24
                       Along Grid D-D    1    17.25                   8.250     142.31
                          Deduct door    -2    3.00                   7.000     -42.00
     Toilet wall between E-E and F-F     1    13.33                   9.000     119.97
                   Along Grid E'-E'   1          17.25                  9.000    155.25
                      Deduct door     -1          4.00                  7.000    -28.00
                                           Total Of Interlocking Beam           1352.91   Sq.ft
9.0 Cement Plaster and Finishing works
9.1 Inner Plaster
    Ground Floor
    Parking Room
                            Ceilings 1           35.33      18.08               638.87
                              Walls  1          106.83                  9.00    961.43
                 Deduction Windows   -6           6.00       0.50       4.50    -81.00
                  Deduction Shutter  -1          10.00       0.50       8.25    -41.25
    Guard Room
                            Ceilings 1          Area =      189.08              189.08
                              Walls  1         length =      60.00      9.00    540.00
                 Deduction Windows   -2          6.00         0.50      4.50    -27.00
                   Deduction doors   -1          2.50         0.50      7.00     -8.75
                   Deduction doors   -1          3.00         0.50      7.00    -10.50
    Toilet
                            Ceilings 1           7.00        4.00                28.00
                              Walls  1          22.00                   4.00     88.00
                 Deduction Windows   -1          2.00        0.50       2.00     -2.00
                   Deduction doors   -1          2.50        0.50       2.00     -2.50
    Next toilet
                            Ceilings 1           8.33        4.75                39.57
                              Walls  1          26.16                   4.00    104.64
                 Deduction Windows   -1          2.00        0.50       2.00     -2.00
                   Deduction doors   -1          2.50        0.50       2.00     -2.50
    Lobby Room +Staircase
                            Ceilings 1          Area =      188.05              188.05
                              Walls  1         length =      61.42      9.00    552.74
                 Deduction Windows   -2          6.00         0.50      4.50    -27.00
                   Deduction doors   -1          4.00         0.50      8.00    -16.00
                   Deduction doors   -1          3.00         0.50      7.00    -10.50
                   Deduction doors   -1          2.50         0.50      7.00     -8.75
    First Floor
    Lobby Room +Staircase
                            Ceilings 1          Area =      865.16               865.16
                              Walls  1         length =     131.92      9.00    1187.24
                 Deduction Windows   -8           6.00       0.50       4.50    -108.00
                 Deduction Windows   -1          10.00       0.50       4.50     -22.50
                   Deduction doors   -1           4.00       0.50       7.00     -14.00
    Toilet
                            Ceilings 1           8.33        4.75                39.57
                              Walls  1          26.16                   4.00    104.64
                 Deduction Windows   -1          2.00        0.50       2.00     -2.00
                   Deduction doors   -1          2.50        0.50       2.00     -2.50
    Lobby Room +Staircase
                            Ceilings 1          Area =      188.05              188.05
                         Walls    1    length =   61.42    9.00   552.74
            Deduction Windows     -2     6.00      0.50    4.50   -27.00
              Deduction doors     -1     4.00      0.50    8.00   -16.00
              Deduction doors     -1     3.00      0.50    7.00   -10.50
              Deduction doors     -1     2.50      0.50    7.00    -8.75
Second Floor
Lobby Room +Staircase
                       Ceilings   1     Area =    865.16           865.16
                         Walls    1    length =   131.92   9.00   1187.24
            Deduction Windows     -8      6.00     0.50    4.50   -108.00
            Deduction Windows     -1     10.00     0.50    4.50    -22.50
              Deduction doors     -1      4.00     0.50    7.00    -14.00
Toilet
                       Ceilings   1      8.33      4.75            39.57
                         Walls    1     26.16              4.00   104.64
            Deduction Windows     -1     2.00      0.50    2.00    -2.00
              Deduction doors     -1     2.50      0.50    2.00    -2.50
Lobby Room +Staircase
                       Ceilings   1     Area =    188.05          188.05
                         Walls    1    length =    61.42   9.00   552.74
            Deduction Windows     -2     6.00       0.50   4.50   -27.00
              Deduction doors     -1     4.00       0.50   8.00   -16.00
              Deduction doors     -1     3.00       0.50   7.00   -10.50
              Deduction doors     -1     2.50       0.50   7.00    -8.75
Top Floor
Bed Room
                       Ceilings   1     11.58      9.17           106.17
                         Walls    1     41.50              9.00   373.48
            Deduction Windows     -2     6.00      0.50    4.50   -27.00
              Deduction doors     -1     3.00      0.50    7.00   -10.50
Bed Room
                       Ceilings   1     11.58      8.50            98.46
                         Walls    1     40.17              9.00   361.49
            Deduction Windows     -2     5.00      0.50    4.50   -22.50
              Deduction doors     -2     3.00      0.50    7.00   -21.00
Kitchen
                       Ceilings   1     12.00      7.58            91.00
                         Walls    1     39.17              9.00   352.49
            Deduction Windows     -1     5.00      0.50    4.50    -11.25
              Deduction doors     -1     3.00      0.50    7.00    -10.50
                Deduction wall    -1    12.00              9.00   -108.00
Living Room
                       Ceilings   1     17.17     10.00           171.66
                         Walls    1     54.33              9.00   488.99
            Deduction Windows     -1     6.00      0.50    4.50    -13.50
              Deduction doors     -2     4.00      0.50    7.00    -28.00
                Deduction wall    -1    17.17              9.00   -154.49
Toilet
                          Ceilings    1      8.33      4.75                   39.57
                            Walls     1     26.16                  4.00      104.64
               Deduction Windows      -1     2.00      0.50        2.00       -2.00
                  Deduction doors     -1     2.50      0.50        2.00       -2.50
    Lobby Room +Staircase
                          Ceilings    1     Area =    188.05                  188.05
                            Walls     1    length =    61.42        9.00      552.74
               Deduction Windows      -2     6.00       0.50        4.50      -27.00
                  Deduction doors     -1     4.00       0.50        8.00      -16.00
                  Deduction doors     -1     3.00       0.50        7.00      -10.50
                  Deduction doors     -1     2.50       0.50        7.00       -8.75
                                                        Total inside Plaster 10998.20   Sq.ft
8.2 External Plasterings
    Ground Floor
                        Front face    1     62.58                  9.42      589.28
                         Back face    1     62.58                  9.42      589.28
                         Left Face    1     19.58                  9.42      184.39
                        Right Face    1     19.58                  9.42      184.39
                       Deductions:
                                  D   -1     4.00      0.50        8.00       -16.00
                                 D1   -1     3.00      0.50        7.00       -10.50
                           Shutter    -1    10.00      0.50        8.00       -40.00
                          Windows     -9     6.00      0.50        4.50      -121.50
                          Windows     -2     2.00      0.50        4.50        -9.00
                       Ventilations   -1     6.00      0.50        4.00       -12.00
    First Floor
                         Front face   1     62.58                  9.42      589.28
                         Back face    1     62.58                  9.42      589.28
                          Left Face   1     19.58                  9.42      184.39
                        Right Face    1     19.58                  9.42      184.39
                        Verandhah     1     13.42                  4.33       58.09
                       Deductions:
                                 D1   -1     3.00      0.50        7.00       -10.50
                          Windows     -1    10.00      0.50        4.50       -22.50
                          Windows     -9     6.00      0.50        4.50      -121.50
                          Windows     -2     2.00      0.50        4.50        -9.00
                       Ventilations   -1     6.00      0.50        8.00       -24.00
    Second Floor
                         Front face   1     62.58                  9.42      589.28
                         Back face    1     62.58                  9.42      589.28
                          Left Face   1     19.58                  9.42      184.39
                        Right Face    1     19.58                  9.42      184.39
                        Verandhah     1     13.42                  4.33       58.09
                       Deductions:
                                 D1   -1     3.00      0.50        7.00       -10.50
                          Windows     -1    10.00      0.50        4.50       -22.50
                          Windows     -9     6.00      0.50        4.50      -121.50
                          Windows     -2     2.00      0.50        4.50        -9.00
                       Ventilations   -1     6.00      0.50        8.00       -24.00
     Top Floor
                             Front face    1      38.58                     9.42       363.30
                             Back face     1      38.58                     9.42       363.30
                              Left Face    1      19.58                     9.42       184.39
                            Right Face     1      19.58                     9.42       184.39
                            Verandhah      1     145.50                     4.33       630.02
                           Deductions:
                                     D1    -2     3.00          0.50        7.00       -21.00
                              Windows      -1    10.00          0.50        4.50       -22.50
                              Windows      -6     6.00          0.50        4.50       -81.00
                              Windows      -2     2.00          0.50        4.50        -9.00
                              Windows      -2     4.75          0.50        4.50       -21.38
                              Windows      -2     4.33          0.50        4.50       -19.49
                           Ventilations    -1     6.00          0.50        8.00       -24.00
     Roof floor
                            Verandhah      1     144.83                     4.33      627.13
                                                               Total Outside Plaster 6328.40     Sq.ft
10.0 Painting works
10.1 Wall Putty works
  as per the internal plastering surface   1    10998.20                             10998.20
                                                              Total wall putty works 10998.20    Sq.ft
10.2 Plastic emulsion paint (Internal)
  as per the internal plastering surface   1    10998.20                              10998.20
                                                             Total of Internal Paints 10998.20   Sq.ft
10.3 External weather coat apex paint
     Outside Plaster                       1    6328.40                               6328.40
                                                             Total of External Paints 6644.82    Sq.ft
10.4 Chapra Polish
                       On Door Shutter
                                  MD       4      4.00           2.00       7.00       224.00
                                    D      2      3.50           2.00       7.00        98.00
                                   D1      7      3.00           2.00       7.00       294.00
                                   D2      8      2.50           2.00       7.00       280.00
                                                           Total Chapra Polish Paint   896.00    Sq.ft
10.5 Enamel paint
                             Lump sum      1                  1792.00              1792.00
                                                                Total Enamel Paint 1792.00       Sq.ft
11.0 Doors and Windows works
11.1 Wooden Frame Works
                                    MD     4     18.00           0.33      0.25         5.94
                                     D     2     17.50           0.33      0.25         2.89
                                    D1     7     17.00           0.33      0.25         9.82
                                    D2     8     16.50           0.33      0.25        10.89
                                                         Total of Wood frame works     29.54     Cu.ft
11.2 Flush Door Shutters
                                      D    2      3.50                     7.00         49.00
                                     D1    7      3.00                     7.00        147.00
                                     D2    8      2.50                     7.00        140.00
                                                      Total of Flush Door Shutters     336.00    Sq.ft
11.3 Panel Door Shutters
                                    MD     4      4.00                     7.00        112.00
                                                      Total of Panel Door Shutters     112.00    Sq.ft
11.4 Aluminium Sliding Window
                                     W1     13     8.00                     4.50      468.00
                                     W2      2     3.92                     4.50       35.24
                                     W3      2     3.75                     4.50       33.75
                                     W4      2     8.00                     4.50       72.00
                                      V      4     2.00                     4.50       36.00
                                                          Total of Aluminium Works    644.99   Sq.ft
 12 Flooring Works
12.1 Screeding and Punning
     Ground Floor
                     Parking Room           1     35.33        18.08                  638.87
                      Guard Room            1     12.25        10.75                  131.69
     Second Floor
                        Bed Room            1    11.58          9.17                  106.17
                        Bed Room            1    11.58          8.50                   98.46
                      Living Room           1    17.17         10.00                  171.66
                     Open Terrace           1    Area =       798.84                  798.84
     Top Floor
                     Open Terrace           1    Area =       945.18                945.18
                                                             Total Screeding works 2890.87     Sq.ft
12.2 Cement Skirting (100 mm)
     Ground Floor
                      Parking Room          1    106.83                               106.83
                        Guard Room          1     46.00                                46.00
     Second Floor
                          Bed Room          1     41.50                                41.50
                          Bed Room          1     40.17                                40.17
                        Living Room         1     54.33                                54.33
                       Open Terrace         1    Length =     200.17                  200.17
     Top Floor
                       Open Terrace         1    Length =    132.42                   132.42
                                                      Total Cement Skirting works     652.47   R.ft
12.3 Ceramic wall Tile
     Ground Floor
     Toilet 1 walls                         1     22.00                    6.00       132.00
                           Deduct Door      -1     2.50                    6.00       -15.00
                         deduct window      -1     2.00                    2.00        -4.00
     Toilet 2 walls                         1     26.16                    6.00       156.96
                           Deduct Door      -1     2.50                    6.00       -15.00
                         deduct window      -1     2.00                    2.00        -4.00
     Kitchen walls                          1     11.25                    4.00        45.00
     First Floor
     Toilet 1 walls                         1     26.16                    6.00       156.96
                           Deduct Door      -1     2.50                    6.00       -15.00
                         deduct window      -1     2.00                    2.00        -4.00
     Second Floor
     Toilet 1 walls                         1     26.16                    6.00       156.96
                           Deduct Door      -1     2.50                    6.00       -15.00
                         deduct window      -1     2.00                    2.00        -4.00
     Top Floor
     Toilet 1 walls                         1     26.16                     6.00      156.96
                           Deduct Door      -1     2.50                     6.00      -15.00
                         deduct window      -1     2.00                     2.00       -4.00
     Kitchen walls                          1     11.25                     4.00       45.00
                                                              Total Wall Tile Works   754.84   Sq.ft
12.4 Bathroom floor Tiles
                             4 x 7 toilet   1      4.00        7.00                   28.00
                       4'9"x8'4" toilet   4       5.75       8.33                      191.59
                                               Total Bathroom Tile Flooring works      219.59   sq.ft
12.5 Floor Tile Works
     Ground Floor Kitchen                 1       7.08         7.33                 51.92
     Multipurpose hall                    2      35.92        18.08                1298.94
     Second Floor Kitchen                 1      12.00         7.58                 91.00
                                                         Total Tile Flooring Works 1441.85      Sq.ft
12.6 Marble Flooring
     Front Steps                           1     22.08        4.50                      99.37
     Lobby Room                            4     12.92        9.42                     486.47
     Staircase Riser                      48      3.50                     0.58         97.94
     Tread                                42      3.50        0.83                     122.45
     Landings                              6      3.50        3.50                      73.50
                                                    Total of marble flooring works     879.74   Sq.ft
13 Stainless Steel Railing works
   Staircase                              3       18.33                                 54.99
   Verandhah                              3       13.50                                 40.50
   Second floor terrace                   1      132.83                                132.83
   Top floor terrace                      1      132.42                                132.42
                                                   Total of Stainless steel railings   360.74   R.ft
Remarks
 222.66
135.996
SN                  DESCTIPTION                     UNITS          RATE       AMOUNT       REMARKS
    Porcelain clay white glaze IPWC Comode
    with dual flush and primium seat cover- all
  1 complete set(Hindustan, Parryware or nos                  1    17000.00    17,000.00
    equivalent ) Constellation type, cascade
    type
      Toilet Sprayer- Chrome type with Nose        nos        1     1500.00     1,500.00
    55x40cm Porcelain clay white glaze Wash
  2 basin (Hindware, Parryware, Classica or nos               1     5000.00     5,000.00
    equivalent ) Regular
    Porcelain clay toilet paper holder (Recessed                                 800.00
  4                                                nos        1      800.00
     type)
  5 Chrome plate soap tray                         nos         1     850.00       850.00
  6 Chrome plate Towel rod 1.5 x 45cm size         nos         1    1200.00     1,200.00
  7 Looking mirror 55x40cm size                    nos         1    3000.00     3,000.00
  8 Chrome plate shower ordinary type              nos         1    5000.00     5,000.00
    Tap Mixture                                    nos         1    8000.00     8,000.00
  9 C P 15 mm bib cock ordinary type               nos         1     700.00       700.00
 10 PVC Floor trap 11x7.5cm                        nos         2     500.00     1,000.00
 11 15mm dia. UPVC pipe ( Medium ) Cold            Rm       9.00     400.00     3,600.00
 12 15mm dia. UPVC pipe ( Medium ) Hot             Rm       6.00     500.00     3,000.00
 13 50 mm PVC Pipe 4 kg/cm2.                       Rm       3.00     820.00     2,460.00
 15 110 mm PVC Pipe 4 kg\cm2.                      Rm       4.00    1200.00     4,800.00
 23 110 mm Vent cowl                               nos         1     400.00       400.00
 24 110 mm Plain tee                               nos         2     515.00     1,030.00
 25 110 mm Door tee                                nos         1     650.00       650.00
 26 110 mm Bend 90 degree                          nos         2     650.00     1,300.00
 27 110 mm Door bend                               nos         1     700.00       700.00
 28 110 mm Bend 45 degree                          nos         2     550.00     1,100.00
 31 110 mm Pipe clip                               nos        20      20.00       400.00
 32 110 mm Gully trap                              nos         1     980.00       980.00
 33 G.M. 15mm Gate valve                    nos               1     1250.00     1,250.00
                   Estimated Cost of Sanitary                                  65,720.00
             Item                                                                               Total   Rate                     Remarks
                                        Description of Works                          Unit                        Amount (NPR)
              No.                                                                            Quantity   (NPR)
                 1   DISTRIBUTION BOARDS
                     Supply, installation, testing and commissioning of factory
                     fabricated and factory assembled, sheet steel clad
                     powder coated, recessed mounting dust and vermin
                     proof, double door Distribution Boards fabricated from
                     16 SWG sheet steel provided with hinged gasketted
                     door with locking facility and including suitably rated
                     copper phase bars, Earth & Neutral Links all complete
                     as     required.     Make      of   DB    &     breakers:
                     ABB/Siemens/Hager/Schnieder or equvalent. All MCBs
                     shall be 10 kA
             1.1 4 way TPN Vertical Distribution board                                No          1     14,088      14,087.50
                 Incoming
                 1 x 32 A TP MCB
                 Outgoing
                 4 x 32 A DP MCB
                     1 set of TP & N copper busbar of at least 100A
                     capacity complete with terminal lugs and solderless
                     connectors. 1 set of inducator lamp with fuse
             1.2 12 way SPN                                                           No          1       8,683       8,682.50
                 Incoming
                 1 x 32 A DP MCB
                 12 way copper phase bar
                 12 way copper Neutral & Earth Links
                 Outgoing
                 4 x 16 A SP MCB
                 5 x 6 A SP MCB
             1.3 10 way SPN (DB#2,DB#3,DB#4)                                          No          3       6,670     20,010.00
                 Incoming
                 1 x 32 A DP MCB
                 12 way copper phase bar
                 12 way copper Neutral & Earth Links
                 Outgoing
                 4 x 16 A SP MCB
                 5 x 6 A SP MCB
                 1 no of earth bus bar
              2 CABLES & WIRES
                 Supply, installation, testing & commissioning of following
                 sizes of PVC insulated multistranded Copper conductor
                 cables/wires of 1.1 KV grade to be drawn in recessed
                 mounted 2 mm thick PVC pipe as deemed including
                 fixing hardware, fish wires etc. as required all complete.
             2.1 (2 x 6 + 1x4 )Sqmm with 25 mm dia 2 mm thick HDP
                                                                                      Rm         25        462      11,555.25
                 pipe from MPB to DB #1,DB#2,DB#3,DB#4
              3 General Service Light /power Point Wiring
Arunodaya S.S.                                                         Page37 of 40                                                   Electrical Works
             Item                                                                            Total   Rate                     Remarks
                                     Description of Works                          Unit                        Amount (NPR)
              No.                                                                         Quantity   (NPR)
             3.1 Supplying, wiring, testing and commissioning of light
                 point circuit wiring using (2x 2.5+1x 1.5 ) sq mm multi
                 stranded copper conductor, 1100 volts grade, PVC
                 insulated wires drawn through 20 mm dia HDP Pipe as
                 a cable sleeve concealed in wall and floor including all
                 fixing and connecting materials .The rate fo wiring shall
                 include the circuit wiring from deginated Distribution            Pts        17        824      14,008.00
                 Board (DB) up to the switch board required size of GI
                 metal box, GI fish wire, cutting and filling chases for
                 recessed pipes as deemed as per drawing and lay out
                 plan all complete
             3.2 Supplying, wiring, testing and commissioning and
                 putting into operation of for lights, ceiling fans, exhaust
                 fans points using 2.5 sq mm multi stranded copper
                 conductor, 1100 volts grade, PVC insulated wires drawn
                 through 20 mm dia HDP Pipe as a cable sleeve
                 concealed in wall and floor including all fixing and
                 connecting materials from switch board up to the first
                 light/fan/ control switch on wards to light/fan then the          Pts        36        627      22,564.08
                 looping between switches /lights/fans/ etc. (No cable
                 jointing is allowed except switch and fixture). The cost
                 shall be including HDP Pipes, GI metal box, GI fish
                 wire, cutting and filling chases for recessed pipes as
                 deemed as per drawing and lay out plan all complete.
            3.3 Same as item No 3.2 above but point to point
                                                                                   Pts        21        449        9,418.92
                 wiring(secondary point)
            3.4. Same as above item No. 3.2 but one light point control
                                                                                   Pts        11        722        7,936.94
                 by two 2-way switch.
             4     Power Socket Wiring
            4.1 Supplying, wiring, testing and commissioning and
                 putting into operation for 16 A power point using 2 x 4
                 sq mm + 1 x 2.5 Sq mm multi stranded copper
                 conductor, 1100 volts grade, PVC insulated wires drawn
                 through      20 mm dia 2 mm thick HDP pipe, cable
                 sleeve/support but including specified dia pipes
                 concealed in wall and floor including all fixing and
                 connecting materials. The rate for point wiring shall
                 include the circuit wiring from deginated Distribution            Pts        50       1,753     87,649.50
                 Board (DB) up to the first power point then the looping
                 between sockets. The cost shall be excluding GI metal
                 box including GI fish wire, cutting and filling chases for
                 recessed pipes as deemed as per drawing and lay out
                 plan all complete.
             4.2 Supplying, wiring, testing and commissioning and
                 putting into operation for 6 A lpower point looping from
                 first power point to power point using 2 x 2.5 sq mm + 1
                 x 2.5 Sq mm multi stranded copper conductor, 1100
                 volts grade, PVC insulated wires drawn through 20 mm
                 dia 2 mm thick HDP pipe, cable sleeve/support but
                 including specified dia pipes concealed in wall and floor
                 including all fixing and connecting materials. The rate for       Pts        11        990      10,894.84
                 point wiring shall include the circuit wiring from first
                 point to loop between sockets, GI metal box, including
                 GI fish wire, cutting and filling chases for recessed pipes
                 as deemed as per drawing and lay out plan all complete.
            5.0     Telephone/networking/television point wiring
Arunodaya S.S.                                                      Page38 of 40                                                   Electrical Works
             Item                                                                             Total     Rate                      Remarks
                                       Description of Works                         Unit                           Amount (NPR)
              No.                                                                          Quantity     (NPR)
            5.1
                     Supply ,intallation ,testing and commisioning of Point
                    wiring from Telephone Junction Box ( TJB ) to individual        Pts    4.00         908.50       3634.00
                    telephone points with 2 pair Telephone wires in 20 mm
                    HDPE conduit including metal box terminations at both
                    ends and providing marking ferrules / sleeves
            5.2 Supply laying and installation of 2 paire telephone cable
                in 20 mm HDPE conduit from main TJB at ground
                floor to each floor TJB .                                 mtr              25.0           42.00 1050.00
            5.3
                Supply , installation & testing of computer point wiring
                with CAT 6 , 4 pair , in 20 mm HDPE conduit including Pts                  4.0         1,635.88      6543.52
                metal box terminations at both ends and providing
                marking ferrules / sleeves.
            5.5 Supply , laying & testing of TV point wiring with TV
                coaxial cable through 20 mm HDP conduit from top Pts                       2.0         1,067.78      2135.56
                of terrace TJB to each room .
             6 Switch Socket Outlets
                Supply, installation, interconnection, testing and
                commissioning of following types of modular formation
                flush mounted switch socket including to be installed in
                specified location and height all complete. (North West,
                Siemens, Philips or equvalent)
            6.1.    16 A 3 Pin Switch Socket                                        No            50       332    16600.00
            6.2     6 A 3/5 Pin Switch Socket                                       No            11       240    2640.00
            6.3     10A 1 way 1 module switch                                       No            47       139    6533.00
            6.4     16A 1 way 1 module switch                                       No            50       223    11150.00
            6.5     10A 2 way 1 module switch                                       No            14       167    2338.00
            6.6     RJ 11 telephone socket                                          No             4       159    636.00
            6.7     RJ 45 networking socket                                         No             4       557    2228.00
            6.8     RG 6 Television Socket                                          No             2       161    322.00
            6.9     1 moudle plate                                                  No             8        72    576.00
            6.10    2 moudle plate                                                  No            15        77    1155.00
            6.11    3 moudle plate                                                  No            69        84    5796.00
             7      Light Fixtures/Luminaires & Accessories                          .                            0.00
                    Supply, storing, assembling, installation, testing and
                    commissioning of following types            wall/ceiling,
                    surface/recessed, suspended Flourescent/CFL/LED
                    lighting fixtures including lamp, power factor
                    improvement capacitor electronic ballast, control gear
                    etc. and including making connections with 1.5 Sq.mm             .
                    PVC insulated copper conductor wire fixing and
                    connecting materials complete as per specification.
                    (Legro/Wipro/Homdec or equvalent)
             7.1 36 watt 4ft LED battentype surface mounted tube light
                                                                                    nos           26      3,071 79833.00
                 fixture
             7.2
                                                                                    nos           10      1,633 16330.00
                 12 watt LED Surface mounted dounlight( used in room)
             7.3 9 watt LED Surface mounted dounlight fixture( used in
                                                                                    nos           17      1,173 19941.00
                 corridore, toilet, staircase)
             7.4 9 watt LED wall light fixture                                      nos           10      1,921 19205.00
             7.5 6 watt mirror LED light fixture                                    nos            5      2,151 10752.50
              8 Pull Box/JTB
                 Supply, fabrication and installation of 250x250x100 mm
                 recessed type Pull Box/junction box at specified
                 locations made out of 2 mm thick hot dip galvanised MS
                 sheets having four corner counter shunk steel screws
                 opening stainless steel cover. The pull box hsall be               nos           6        500 3000.00
                 suitable for four sides entry of Telephone cable pipes
                 complete as per drawing and site conditions.
Arunodaya S.S.                                                       Page39 of 40                                                      Electrical Works
             Item                                                                         Total   Rate                   Remarks
                                    Description of Works                        Unit                      Amount (NPR)
              No.                                                                      Quantity   (NPR)
              9 Earthing & Lighting Protection
             9.1 Supply, installation, testing and commissioning of GI
                 plate earthing stations making earth pits, earthing with
                 GI earth plate 600 mm x 600 mm x 6 mm thick including
                 funnel, charcoal/coke, salt, all earth work. Providing
                 masonry enclosure with 10 mm thick C.I. cover plate            set         1     25,000 25000.00
                 having locking arrangement and watering pipe,
                 disconnecting/ testing links etc as per IS –3043
                 complete as required.
             9.2 Earthing Strip/Wires :
                 Supply, installation, testing and commissioning of
                 following sizes of GI/ Copper strip/wire clamped to
                 walls/building stuctures/underground as deemed
                 including inter connection between length at joints, all
                 fixing accessories saddles, clamps, fixing hardwares all
                 complete.
            9.3 12 SWG Cu wire                                                  mtr        15        170 2550.00
             10 NEA supply cable / Energy Meter                                                          0.00
            10.1 Supply, installation, testing and commissioning of
                 Energy Meter ( 30 A, single Ph, 230 v, 50 Hz ) as per          lot         1     10,000 10000.00
                 NEA rules and regulation .
            10.2 Supply ,installation, testing and commissioning of 2
                 core 10 sq mm copper armourd cable for NEA                     mtr        50        400 20000.00
                 supply.
                           Total of Electrical Works(without VAT) carried over to Summary                   476,756.11
Arunodaya S.S.                                                   Page40 of 40                                                 Electrical Works