ABSTRACT ESTIMATE FOR THE PROPOSED R.C.C.
ROOF RESIDENTIAL BUILDING AT Sulur
  Ground Floor : Mss.shaymila devi                               20/01/2020
S.No      DESCRIPTION OF WORK              Qty            Total Qty Rate/unit   Unit    Amount
  1 Earth work excavation for foundation 1250.00           1250.00    13.69      cft     17113.10
 2   River sand Filling
2a   Below ground level                          875.00
                                                          2489.00    15.11       cft     37603.09
2b   Above ground level                         1614.00
 3   Bed Concrete in P.C.C. 1:4:8 mix
3a   Below ground level                         125.00
                                                           536.50    139.00      cft     74573.50
3b   Above ground level                         411.50
 4   Shuttering
4a   Footing and Column, Plinth, Lintel         833.93
                                                          1533.93    33.00       sft     50619.69
4b   Roof Beam and Slab                         700.00
 5   Reinforcement Steel
5a   Footing Mat                                 0.25
5b   Columns                                     0.70
                                                            1.99    57000.00    MT      113430.00
5c   Plinth Beam                                 0.31
5d   Roof Beam and Slab                          0.69
 6   R.C.C 1:1.5:3
6a   Footing,Plinth,Columns                     481.83
                                                           721.89    182.00      cft    131383.62
6b   Roof Beam,Slab                             240.06
 7   Brick Work in C.M 1:6 mix
7a   External 9" Wall (Basement)                 336.38
7b   9" Wall (External and Internal)            1224.18
                                                          1421.35    149.00      cft    211781.15
7c   Internal 4" Wall                            76.78
                                                 (-)216
 8   Plastering in Ceiling and Wall Surface
8a   Internal Plastering                    2710.00
                                                          4803.00    39.88      sq.ft   191543.64
8b   External Plastering                    2093.00
 9   Tile Work
9a   Virtified tile Flooring                      730
9b   Toilet and Kitchen wall tiles upto 7' ht    178.5     908.50    104.74     sq.ft    95160.09
 .   .                                             .
10   Granite for Steps and Counter Tops          57.88     57.88     208.00     sq.ft    12039.04
 11    Supply and Fixing Joineries Necessary fittings etc
11a     Main door( Teak wood )                               1.00     30000.00     L.S     30000.00
11b    Internal doors                                        1.00     10000.00     L.S     10000.00
11c    Toilet doors(PVC doors)                               1.00      3000.00     L.S      3000.00
11d    Windows(w4)                                           1.00     10000.00     L.S     10000.00
11e    Windows(Kw)                                           2.00      8000.00     L.S     16000.00
11f    French Windows (Fw)                                   2.00     10000.00     L.S       20000
11g    Ventilator                                            2.00      3000.00    L.S       6000.00
 12 Painting Work
12a Exterior Paint- Emulsion                  2710.00
                                                            4803.00     24.00     sq.ft   115272.00
12b Interior Paint- Emulsion                  2093.00
13     Plumbing Work                            1.00                  20000.00    L.S      20000.00
14     Electrical Work                          1.00                  30000.00    L.S      30000.00
15      Rain water harversting                  1.00                   5000.00    L.S       5000.00
16      M.S Gate                                1.00                  35000.00    L.S      35000.00
17     Over Head Water Tank                     2.00                  20000.00    L.S      20000.00
18     Under Ground Water Sump + Septic tank1.00                      100000.00   L.S     100000.00
19     Staircase                                1.00                   9000.00    L.S       9000.00
       TOTAL                                                                              1364518.91
                                              CERTIFICATE
      Certified that the cost required forthe above mentioned building work is Rs.13,64,518.91/-
        (Rupees Thirteen Lakhs Sixty Four Thousand Five Hundred and Eighteen Rupees Only)