1
1
AREA 575
                                                pcs          kg              pcs        kg
                                   16mm                             0 25mm                       0
                                   12mm               2160    11534.4 20mm         65        963.3
                                   10mm                             0                            0
           0            0            0                             19728
                                                                    9828
                                     0
12497.7
                                                      DETAILED ESTIMATE
                           DESCRIPTION                   DAYS        QTY
           Construction of Temp Facilities                            1
            A. MATERIALS
               a.   Temporary/First Aide Facilities                   1
            B. LABOR
               a. Foreman                                        1    3
               b. Masons                                         3    3
               a. Carpenters                                     3    3
               b. Laborers                                       6    3
            C. EQUIPMENT
               a. One Bagger Mixer                               1    2
               b. Minor Tools (10% of labor)
            E.   OCM                                            8%         OF D
            F.   CONTRACTOR'S PROFIT                            8%         OF D
            G.   VAT                                            5%   OF (D+E+F)
            H.   TOTAL COST OF WORK ITEM                             (D+E+F+G)
    I.   UNIT COST
    A. MATERIALS
       a. Diesel Fuel                                     1500
       b Engine Oil and Lubricants                          1
       c  Spareparts etc.                                   1
    B. LABOR
       a. Service Driver                             60    1
    C. EQUIPMENT
       a.
    E.   OCM                                         8%         OF D
    F.   CONTRACTOR'S PROFIT                         8%         OF D
    G.   VAT                                         5%   OF (D+E+F)
    H.   TOTAL COST OF WORK ITEM                          (D+E+F+G)
    I.   UNIT COST
    A. MATERIALS
       a. Stake Plan                                       30
       b. Blue Printing                                    90
    B. LABOR
       a. Geodetic Engineer                           5    1
       b. Skilled Laborer                             5    3
       c. Unskilled Laborer                           5    3
    C. EQUIPMENT
       a. TS w/ Complete Accessories                  5    1
    E.   OCM                                         8%          OF D
    F.   CONTRACTOR'S PROFIT                         8%          OF D
G. VAT                                          5%   OF (D+E+F)
H. TOTAL COST OF WORK ITEM                           (D+E+F+G)
I. UNIT COST
A. MATERIALS
   a.        Billboard/Tarpauline                     3
B. LABOR
   a. Foreman                                    1    1
   b. Skilled Laborer                            1    1
   c. Unskilled Laborer                          1    1
C. EQUIPMENT
   a.
E.   OCM                                        8%         OF D
F.   CONTRACTOR'S PROFIT                        8%         OF D
G.   VAT                                        5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                         (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a.
B. LABOR
   a. Operator                                   6    3
   b. Unskilled Worker                           6    20
C. EQUIPMENT
   a. DOZER                                      6    3
A. MATERIALS
   a. 40kg Cement                              400
   b. Sand                                      25
   c  3/4 Gravel                                50
   d Soil Guard                                 45
B. LABOR
   a. Unskilled Worker                     6    20
C. EQUIPMENT
   a. Plate Compactor                      6    10
E.   OCM                                  8%         OF D
F.   CONTRACTOR'S PROFIT                  8%         OF D
G.   VAT                                  5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                   (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. Form Board                                250
   b. Wooden Framings                          2375
   c. Nails                                      32
C. EQUIPMENT
D. TOTAL DIRECT COST
E.   OCM                                         8%         OF D
F.   CONTRACTOR'S PROFIT                         8%         OF D
G.   VAT                                         5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                          (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. Form Board                                       440
   b. Wooden Framings                                 3650
   c. Nails                                             32
C. EQUIPMENT
   a. H-Frame 1.7 m x 1.2m, set                  10    15
   b Shoring Jack, 3.8 m full extension          10    8
   c   Adjustable U-head Jack, 0.6m              10    8
   d Adjustable Base Jack, 0.6m                  10    8
   e 1-1/2" GI Pipe x 6.0 m                      10    8
   f   1-1/2" GI Pipe x 4.0 m                    10    8
   g 1-1/2" GI Pipe x 3.0 mn                     10    8
   h 1-1/2" GI Pipe x 1.0 mn                     10    8
   i   Tie Rod x 0.60m                           10    25
   j   Round Wing Nut                            10    50
E.   OCM                                         8%         OF D
F.   CONTRACTOR'S PROFIT                         8%         OF D
G.   VAT                                         5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                          (D+E+F+G)
I.   UNIT COST
C. EQUIPMENT
   a. H-Frame 1.7 m x 1.2m, set                  10    15
   b Shoring Jack, 3.8 m full extension          10    8
   c   Adjustable U-head Jack, 0.6m              10    8
   d Adjustable Base Jack, 0.6m                  10    8
   e 1-1/2" GI Pipe x 6.0 m                      10    8
   f   1-1/2" GI Pipe x 4.0 m                    10    8
   g 1-1/2" GI Pipe x 3.0 mn                     10    8
   h 1-1/2" GI Pipe x 1.0 mn                     10    8
   i   Tie Rod x 0.60m                           10    25
   j   Round Wing Nut                            10    50
E.   OCM                                         8%         OF D
F.   CONTRACTOR'S PROFIT                         8%         OF D
G.   VAT                                         5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                          (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. Form Board                                       440
   b. Wooden Framings                                 3650
   c. Nails                                             32
C. EQUIPMENT
   a. H-Frame 1.7 m x 1.2m, set                  10    15
     b   Shoring Jack, 3.8 m full extension          10    8
     c   Adjustable U-head Jack, 0.6m                10    8
     d   Adjustable Base Jack, 0.6m                  10    8
     e   1-1/2" GI Pipe x 6.0 m                      10    8
     f   1-1/2" GI Pipe x 4.0 m                      10    8
     g   1-1/2" GI Pipe x 3.0 mn                     10    8
     h   1-1/2" GI Pipe x 1.0 mn                     10    8
     i   Tie Rod x 0.60m                             10    25
     j   Round Wing Nut                              10    50
E.   OCM                                             8%         OF D
F.   CONTRACTOR'S PROFIT                             8%         OF D
G.   VAT                                             5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                              (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. Form Board                                           440
   b. Wooden Framings                                     3650
   c. Nails                                                 32
C. EQUIPMENT
   a. H-Frame 1.7 m x 1.2m, set                      10    15
   b Shoring Jack, 3.8 m full extension              10    8
   c   Adjustable U-head Jack, 0.6m                  10    8
   d Adjustable Base Jack, 0.6m                      10    8
   e 1-1/2" GI Pipe x 6.0 m                          10    8
   f   1-1/2" GI Pipe x 4.0 m                        10    8
   g 1-1/2" GI Pipe x 3.0 mn                         10    8
   h 1-1/2" GI Pipe x 1.0 mn                         10    8
   i   Tie Rod x 0.60m                               10    25
   j   Round Wing Nut                                10    50
    A. MATERIALS
       a. 25mm Steel Bar 6m                       3000
       b. #18 GI Wire                              225
    B. LABOR
       a. Skilled Worker                     25    30
       b. Unskilled Worker                   25    40
    C. EQUIPMENT
       a. Bar Cutter                         25    20
       a. Bar Bender                         25    20
    E.   OCM                                 8%         OF D
    F.   CONTRACTOR'S PROFIT                 8%         OF D
    G.   VAT                                 5%   OF (D+E+F)
    H.   TOTAL COST OF WORK ITEM                  (D+E+F+G)
    I.   UNIT COST
    A. MATERIALS
       a. 25mm Steel Bar 7.5m                       25
       b. 20mm Steel Bar 7.5m                     1150
       c. 12 mm Steel Bar 7.5m                     655
`      d. 10 mm Steel Bar 7.5m                     450
       e #18 GI Wire                               270
    B. LABOR
       a. Skilled Worker                     10    30
       b. Unskilled Worker                   10    40
    C. EQUIPMENT
       a. Bar Cutter                         10    20
       b. Bar Bender                         10    20
    D. TOTAL DIRECT COST
    E.   OCM                                 8%         OF D
    F.   CONTRACTOR'S PROFIT                 8%         OF D
    G.   VAT                                 5%   OF (D+E+F)
    H.   TOTAL COST OF WORK ITEM                  (D+E+F+G)
    I.   UNIT COST
    A. MATERIALS
       a. 25mm Steel Bar 6m                         18
       b. 20mm Steel Bar 6m                       1140
       c. 12 mm Steel Bar 6m                      2925
`      d. 10 mm Steel Bar 6m                       480
       e #18 GI Wire                               315
    B. LABOR
       a. Skilled Worker                     14    30
       b. Unskilled Worker                   14    40
    C. EQUIPMENT
       a. Bar Cutter                         14    20
       b. Bar Bender                         14    20
    E.   OCM                                 8%         OF D
    F.   CONTRACTOR'S PROFIT                 8%         OF D
    G.   VAT                                 5%   OF (D+E+F)
    H.   TOTAL COST OF WORK ITEM                  (D+E+F+G)
    I.   UNIT COST
    A. MATERIALS
       a. 25mm Steel Bar 6m                         18
       b. 20mm Steel Bar 6m                       1090
       c. 12 mm Steel Bar 6m                      2950
`      d. 10 mm Steel Bar 6m                       520
       e #18 GI Wire                               315
    B. LABOR
         a.    Skilled Worker                  14    30
         b.    Unskilled Worker                14    40
    C. EQUIPMENT
       a. Bar Cutter                           14    20
       b. Bar Bender                           14    20
    E.   OCM                                   8%         OF D
    F.   CONTRACTOR'S PROFIT                   8%         OF D
    G.   VAT                                   5%   OF (D+E+F)
    H.   TOTAL COST OF WORK ITEM                    (D+E+F+G)
    I.   UNIT COST
    A. MATERIALS
       a. 25mm Steel Bar 6m                           18
       b. 20mm Steel Bar 6m                         1280
       c. 12 mm Steel Bar 6m                        3075
`      d. 10 mm Steel Bar 6m                         610
       e #18 GI Wire                                 365
    B. LABOR
       a. Skilled Worker                       15    30
       b. Unskilled Worker                     15    40
    C. EQUIPMENT
       a. Bar Cutter                           15    20
       b. Bar Bender                           15    20
    E.   OCM                                   8%         OF D
    F.   CONTRACTOR'S PROFIT                   8%         OF D
    G.   VAT                                   5%   OF (D+E+F)
    H.   TOTAL COST OF WORK ITEM                    (D+E+F+G)
    I.   UNIT COST
    A. MATERIALS
       a. 20mm Steel Bar 6m                          35
     b.   12 mm Steel Bar 6m                2160
     c    #18 GI Wire                        75
B. LABOR
   a. Skilled Worker                    5    30
   b. Unskilled Worker                  5    40
C. EQUIPMENT
   a. Bar Cutter                        5    20
   b. Bar Bender                        5    20
E.   OCM                               8%         OF D
F.   CONTRACTOR'S PROFIT               8%         OF D
G.   VAT                               5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. 40kg Cement                           5155
   b. Sand                                   290
   c. 3/4 Gravel                             580
B. LABOR
   a. Skilled                          25    15
   b. Operator                         25    6
   c. Unskilled Worker                 25    40
C. EQUIPMENT
   a. BAGGER MIXER                     25    6
   a. Concrete Vibrator                25    15
E.   OCM                               8%         OF D
F.   CONTRACTOR'S PROFIT               8%         OF D
G.   VAT                               5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                (D+E+F+G)
I.   UNIT COST
            DESCRIPTION        DAYS        QTY
         CONCRETE Basement                 110
A. MATERIALS
   a. 40kg Cement                          935
   b. Sand                                  55
   c. 3/4 Gravel                           110
B. LABOR
   a. Skilled                          5    15
   b. Operator                         5    6
   c. Unskilled Worker                 5    40
C. EQUIPMENT
   a. BAGGER MIXER                     5    6
   b. Concrete Vibrator                5    15
E.   OCM                              8%         OF D
F.   CONTRACTOR'S PROFIT              8%         OF D
G.   VAT                              5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM               (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. 40kg Cement                          1950
   b. Sand                                  112
   c. 3/4 Gravel                            225
B. LABOR
   a. Skilled                         10    15
   b. Operator                        10    6
   c. Unskilled Worker                10    40
C. EQUIPMENT
   a. BAGGER MIXER                    10    6
   a. Concrete Vibrator               10    15
D. TOTAL DIRECT COST
E.   OCM                              8%         OF D
F.   CONTRACTOR'S PROFIT              8%         OF D
G.   VAT                              5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM               (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. 40kg Cement                          2025
   b. Sand                                  115
   c. 3/4 Gravel                            230
B. LABOR
   a. Skilled                         10    15
   b. Operator                        10    6
   c. Unskilled Worker                10    40
C. EQUIPMENT
   a. BAGGER MIXER                    10    6
   a. Concrete Vibrator               10    15
E.   OCM                              8%         OF D
F.   CONTRACTOR'S PROFIT              8%         OF D
G.   VAT                              5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM               (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. 40kg Cement                          2025
   b. Sand                                  115
   c. 3/4 Gravel                            230
B. LABOR
   a. Skilled                         10    15
      b.   Operator                           10    6
      c.   Unskilled Worker                   10    40
C. EQUIPMENT
   a. BAGGER MIXER                            10    6
   a. Concrete Vibrator                       10    15
E.    OCM                                     8%         OF D
F.    CONTRACTOR'S PROFIT                     8%         OF D
G.    VAT                                     5%   OF (D+E+F)
H.    TOTAL COST OF WORK ITEM                      (D+E+F+G)
I.    UNIT COST
A. MATERIALS
   a. 40kg Cement                                  1010
   b. Sand                                           58
   c. 3/4 Gravel                                    115
B. LABOR
   a. Skilled                                  5    15
   b. Operator                                 5    6
   c. Unskilled Worker                         5    40
C. EQUIPMENT
   a. BAGGER MIXER                             5    6
   a. Concrete Vibrator                        5    15
E.    OCM                                     8%         OF D
F.    CONTRACTOR'S PROFIT                     8%         OF D
G.    VAT                                     5%   OF (D+E+F)
H.    TOTAL COST OF WORK ITEM                      (D+E+F+G)
I.    UNIT COST
B. LABOR
   a. Skilled                         10    30
   b. Operator                        10    4
   c. Unskilled Worker                10    40
C. EQUIPMENT
   a. BAGGER MIXER                    10    4
   b. Concrete Vibrator               10    6
   c. Bar Cutter                      10    6
   d. Bar Bender                      10    6
E.   OCM                              8%         OF D
F.   CONTRACTOR'S PROFIT              8%         OF D
G.   VAT                              5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM               (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. CHB #6                                980
   b. CHB #5                               3325
   c. CHB #4                               2810
   d. 40kg Cement                           640
   e. Sand                                   70
   f. 12 mm Steel Bar 6m                    100
   g. #16 GI Wire                            25
B. LABOR
   a. Skilled                          5    20
   b. Operator                         5    2
     c.   Unskilled Worker             5    30
C. EQUIPMENT
   a. BAGGER MIXER                     5    2
   b. Bar Cutter                       5    6
   c. Bar Bender                       5    6
E.   OCM                              8%         OF D
F.   CONTRACTOR'S PROFIT              8%         OF D
G.   VAT                              5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM               (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. CHB #6                                980
   b. CHB #5                               3950
   c. CHB #4                               3560
   d. 40kg Cement                           740
   e. Sand                                   75
   f. 12 mm Steel Bar 6m                    110
   g. #16 GI Wire                            25
B. LABOR
   a. Skilled                          5    20
   b. Operator                         5    2
   c. Unskilled Worker                 5    30
C. EQUIPMENT
   a. BAGGER MIXER                     5    2
   b. Bar Cutter                       5    6
   c. Bar Bender                       5    6
E.   OCM                              8%         OF D
F.   CONTRACTOR'S PROFIT              8%         OF D
G.   VAT                              5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM               (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. CHB #6                                980
   b. CHB #5                               1500
   c. CHB #4                               4870
   d. 40kg Cement                           600
   e. Sand                                  175
   f. 12 mm Steel Bar 6m                    100
   g. #16 GI Wire                            22
B. LABOR
   a. Skilled                          6    20
   b. Operator                         6    2
   c. Unskilled Worker                 6    30
C. EQUIPMENT
   a. BAGGER MIXER                     6    2
   b. Bar Cutter                       6    6
   c. Bar Bender                       6    6
E.   OCM                              8%         OF D
F.   CONTRACTOR'S PROFIT              8%         OF D
G.   VAT                              5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM               (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. 2mm THHN                              3
   b. PVC Electrical Tape                   7
   c  4 Gang Switch                         25
   d Single Gang Switch                     10
   e 20 mmΦ uPVC Pipe                       70
   f. Panel Board                           1
B. LABOR
     a   Skilled                       1    12
     b   Unskilled Worker              1    12
C. EQUIPMENT
E.   OCM                              8%         OF D
F.   CONTRACTOR'S PROFIT              8%         OF D
G.   VAT                              5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM               (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. 3.5mm THHN                            2
   b. 2.0mm THHN                            4
   c. PVC Electrical Tape                   7
   d. Outlet/Receptacle                     15
   e. Covenience Outlet                     39
   f. ACU Outlet                            6
   g Double Pole Switch                     10
   h 20 mmΦ uPVC Pipe                      120
   i  Panel Board                           7
B. LABOR
   b. Skilled                          2    12
   c. Unskilled Worker                 2    12
C. EQUIPMENT
E.   OCM                              8%         OF D
F.   CONTRACTOR'S PROFIT              8%         OF D
G.   VAT                              5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM               (D+E+F+G)
I.   UNIT COST
             DESCRIPTION           DAYS        QTY
          ELECTRICAL Second                     1
A. MATERIALS
   a. 3.5mm THHN                                2
   b. 2.0mm THHN                                5
   c. PVC Electrical Tape                       10
   d. Lighting Outlet/Receptacle                15
   e. Covenience Outlet                         12
   f. ACU Outlet                                8
   g. Single Pole Switch                        2
   h. Double Pole Switch                        10
   i  20 mmΦ uPVC Pipe                          65
   j  Panel Board                               9
B. LABOR
   b. Skilled                              8    4
   c. Unskilled Worker                     8    4
C. EQUIPMENT
E.   OCM                                  8%         OF D
F.   CONTRACTOR'S PROFIT                  8%         OF D
G.   VAT                                  5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                   (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. 3.5mm THHN                                2
   b. 2.0mm THHN                                5
   b. 5.0mm THHN                                1
   c. PVC Electrical Tape                       7
   d. Lighting Outlet/Receptacle                65
   e. Covenience Outlet                         50
   f. Range Outlet                              3
   f. ACU Outlet                                12
   g. Single Pole Switch                        8
   h. Double Pole Switch                        25
   i. Triple Pole Switch                        10
     j.   20 mmΦ uPVC Pipe                     65
     k.   Panel Board                          2
B. LABOR
   b. Skilled                             7    4
   c. Unskilled Worker                    7    4
C. EQUIPMENT
E.   OCM                                 8%         OF D
F.   CONTRACTOR'S PROFIT                 8%         OF D
G.   VAT                                 5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                  (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. PVC Pipe 12.7mm                          75
   b. PVC tee 12.70mm                         115
   c. PVC elbow 12.70mm                       125
   d. PVC end cap 12.70mm                     100
   e. PVC union patente 12.70mm                50
   f. gate valve 12.70mm                       2
   g. 100mm PVC PIPE                           75
   h. 100x50 Tee                               90
   i. 100 wye                                  90
   j. 100 90 deg elbow                         50
   k. 100 dia clean out                        50
   l. 150 dia pvc pipe                         50
   m. 150mm dia p-trap                         20
   n. 150mm dia 90 deg elbow                   50
   o. Water Meter                              5
B. LABOR
   b. Skilled                            10    6
   c. Unskilled Worker                   10    6
C. EQUIPMENT
D. TOTAL DIRECT COST
E.   OCM                                 8%         OF D
F.   CONTRACTOR'S PROFIT                 8%         OF D
G.   VAT                                 5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                  (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. PVC Pipe 12.7mm                          75
   b. PVC tee 12.70mm                         115
   c. PVC elbow 12.70mm                       125
   d. PVC end cap 12.70mm                     100
   e. PVC union patente 12.70mm                50
   f. 100mm PVC PIPE                           75
   g. 100x50 Tee                              100
   h. 100 wye                                 100
   i. 100 90 deg elbow                         20
   j. 100 dia clean out                        50
   k. 150 dia pvc pipe                         50
   l. 150mm dia p-trap                         20
   m. 150mm dia 90 deg elbow                   50
B. LABOR
   b. Skilled                             9    5
   c. Unskilled Worker                    9    5
C. EQUIPMENT
E.   OCM                                 8%         OF D
F.   CONTRACTOR'S PROFIT                 8%         OF D
G.   VAT                                 5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                  (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. PVC Pipe 12.7mm                               80
   b. PVC tee 12.70mm                              100
   c. PVC elbow 12.70mm                            120
   d. PVC end cap 12.70mm                          100
   e. PVC union patente 12.70mm                     60
   f. 100mm PVC PIPE                                60
   g. 100x50 Tee                                   100
   h. 100 wye                                      100
   i. 100 90 deg elbow                              50
   j. 100 dia clean out                             50
   k. 150 dia pvc pipe                              50
   l. 150mm dia p-trap                              20
   m. 150mm dia 90 deg elbow                        50
B. LABOR
   b. Skilled                                 12    5
   c. Unskilled Worker                        12    5
C. EQUIPMENT
E.   OCM                                      8%         OF D
F.   CONTRACTOR'S PROFIT                      8%         OF D
G.   VAT                                      5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                       (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. Flush Hollow Core Door (D1)                   10
   b. uPVC Door (D2)                                25
   c. Steel Door (D3)                               40
   d Flush Hollow Core Door (D4)                    2
   e Aluminum Double Glass Door(DD1)                4
   f  Solid Core Double Door (DD2)                  9
   g Hollow Core Double Door (DD3)                  5
   h Stainless Door (E1)                            9
   i  Aluminum Glass Window (PW1)                   75
     j   Aluminum Glass Window (PW2)                50
     k   Aluminum Glass Window (PW3)                80
     l   Aluminum Glass Window (PW4)               150
     m   Aluminum Glass Window (PW5)                3
     n   Aluminum Glass Window (PW6)                40
     o   Aluminum Glass Window (PW6)                10
     p   Aluminum Glass Window (PW6)                5
     q   Glass Railings                             25
B. LABOR
   b. Skilled                                 36    15
   c. Unskilled Worker                        36    15
C. EQUIPMENT
E.   OCM                                      8%         OF D
F.   CONTRACTOR'S PROFIT                      8%         OF D
G.   VAT                                      5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                       (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. Railings Tubular 25x50                        95
   b. Railings Tubular 50x50                        35
   a. Cladding Tubular 50x50                        65
   b. Cladding Tubular 100x100                      60
   c. Consumables                                   1
B. LABOR
   b. Skilled                                  9    15
   c. Unskilled Worker                         9    15
C. EQUIPMENT
   a. Welding Machine                          9    15
   a. Steel Cutting Machine                    9    15
D. TOTAL DIRECT COST
E.   OCM                               8%         OF D
F.   CONTRACTOR'S PROFIT               8%         OF D
G.   VAT                               5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. Hardiflex                              205
   b. Metal Furring                          280
   c. Carrying Channel                       180
   d. Wall Angle                             520
   e W Clip                                 2700
   f  Blind Rivets                            20
   g Concrete Nails                           15
B. LABOR
   a. Skilled                           7    15
   b. Unskilled Worker                  7    15
C. EQUIPMENT
E.   OCM                               8%         OF D
F.   CONTRACTOR'S PROFIT               8%         OF D
G.   VAT                               5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. Hardiflex                              205
   b. Metal Furring                          280
   c. Carrying Channel                       180
   d. Wall Angle                             520
   e W Clip                                 2700
   f  Blind Rivets                            20
     g   Concrete Nails                      15
B. LABOR
   a. Skilled                           7    15
   b. Unskilled Worker                  7    15
C. EQUIPMENT
E.   OCM                               8%         OF D
F.   CONTRACTOR'S PROFIT               8%         OF D
G.   VAT                               5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. Hardiflex                              205
   b. Metal Furring                          280
   c. Carrying Channel                       180
   d. Wall Angle                             520
   e W Clip                                 2700
   f  Blind Rivets                            20
   g Concrete Nails                           15
B. LABOR
   a. Skilled                           7    15
   b. Unskilled Worker                  7    15
C. EQUIPMENT
E.   OCM                               8%         OF D
F.   CONTRACTOR'S PROFIT               8%         OF D
G.   VAT                               5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. Hardiflex                              220
   b. Metal Furring                          310
   c. Carrying Channel                       205
   d. Wall Angle                             580
   e W Clip                                 2750
   f  Blind Rivets                            25
   g Concrete Nails                           20
B. LABOR
   a. Skilled                           8    15
   b. Unskilled Worker                  8    15
C. EQUIPMENT
E.   OCM                               8%         OF D
F.   CONTRACTOR'S PROFIT               8%         OF D
G.   VAT                               5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. Patching Compound                     410
   b. Primer                                265
   c. Semi Gloss (2Coat)                    620
   d. Neutralizer                           145
   e. Consumables
B. LABOR
   b. Skilled                          13    20
   c. Unskilled Worker                 13    20
C. EQUIPMENT
E.   OCM                              8%         OF D
F.   CONTRACTOR'S PROFIT              8%         OF D
G.   VAT                              5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM               (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. Patching Compound                    390
   b. Primer                               250
   c. Semi Gloss (2Coat)                   590
   d. Neutralizer                          130
   e. Consumables
B. LABOR
   b. Skilled                         12    20
   c. Unskilled Worker                12    20
C. EQUIPMENT
E.   OCM                              8%         OF D
F.   CONTRACTOR'S PROFIT              8%         OF D
G.   VAT                              5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM               (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. Patching Compound                    420
   b. Primer                               320
   c. Semi Gloss (2Coat)                   550
   d. Neutralizer                          160
     e.   Consumables
B. LABOR
   b. Skilled                           14    20
   c. Unskilled Worker                  14    20
C. EQUIPMENT
E.   OCM                                8%         OF D
F.   CONTRACTOR'S PROFIT                8%         OF D
G.   VAT                                5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                 (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. Patching Compound                      405
   b. Primer                                 295
   c. Semi Gloss (2Coat)                     550
   d. Neutralizer                            145
   e. Consumables
B. LABOR
   b. Skilled                           14    20
   c. Unskilled Worker                  14    20
C. EQUIPMENT
E.   OCM                                8%         OF D
F.   CONTRACTOR'S PROFIT                8%         OF D
G.   VAT                                5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                 (D+E+F+G)
I.   UNIT COST
              DESCRIPTION      DAYS        QTY
          TILE WORKS Ground                 1
A. MATERIALS
   a. Tiles unglazed                       770
   b. Cement                               180
   c. Sand                                  35
   d. Tile Grout                            90
B. LABOR
   b. Skilled                         14    10
   c. Unskilled Worker                14    10
C. EQUIPMENT
E.   OCM                              8%         OF D
F.   CONTRACTOR'S PROFIT              8%         OF D
G.   VAT                              5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM               (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. Tiles unglazed                       770
   b. Cement                               165
   c. Sand                                  35
   d. Tile Grout                            85
B. LABOR
   b. Skilled                          7    20
   c. Unskilled Worker                 7    20
C. EQUIPMENT
A. MATERIALS
   a. Tiles unglazed                             770
   b. Cement                                     165
   c. Sand                                        35
   d. Tile Grout                                  85
B. LABOR
   b. Skilled                                7    20
   c. Unskilled Worker                       7    20
C. EQUIPMENT
E.   OCM                                    8%         OF D
F.   CONTRACTOR'S PROFIT                    8%         OF D
G.   VAT                                    5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                     (D+E+F+G)
I.   UNIT COST
A. MATERIALS
   a. CHB #6                                     1550
   b. 3/4 Gravel                                   45
   c. 40kg Cement                                 160
   d. Sand                                         55
   e. 10 mm Steel Bar 6m                          205
   f. #16 GI Wire                                 465
B. LABOR
   b. Skilled                                5    15
     b.   Operator                              5    3
     d.   Unskilled Worker                      5    30
C. EQUIPMENT
   a. BAGGER MIXER                              5    3
E.   OCM                                       8%         OF D
F.   CONTRACTOR'S PROFIT                       8%         OF D
G.   VAT                                       5%   OF (D+E+F)
H.   TOTAL COST OF WORK ITEM                        (D+E+F+G)
I.   UNIT COST
A. MATERIALS
      ACU Split Type                                 40
      Floor Mounted ACU                              4
      Ceiling Fan                                    20
      Water Closet set                               40
      Lavatory set                                   25
      Kitchen Cabinet/Bar                            2
      Cabinet                                        2
      Led Bulb                                       50
      Pin Light                                     220
      Wall Light                                     30
      Double Insulated Light                         70
      CCTV                                           40
      Light Force Grill Louver                       50
      Ventilation Unit                               3
      Elevator Unit                                  1
      Lake Wood                                      1
B. LABOR
   b. Skilled                                  25    60
   d. Unskilled Worker                         25    60
C. EQUIPMENT
   a.
₱ 69,069,054.14
MATE
            UNIT      UNIT COST (PHP)   TOTAL COST (PHP)
             ls         121563.708        121563.708
(A+B+C)= ₱ 99,806.00
                                    =   ₱       7,984.48
                                    =   ₱       7,984.48
                                    =   ₱       5,788.75
                                    =   ₱     121,563.71
                               = ₱       121,563.71
                                                  -
                   SUB-TOTAL C =                  -
(A+B+C)= ₱ 165,550.00
                               =   ₱      13,244.00
                               =   ₱      13,244.00
                               =   ₱       9,601.90
                               =   ₱     201,639.90
                               =   ₱     201,639.90
(A+B+C)= ₱ 26,050.00
                               = ₱          2,084.00
                               = ₱          2,084.00
                          = ₱         1,510.90
                          = ₱        31,728.90
                          = ₱        31,728.90
   ls           2500                  7,500.00
              SUB-TOTAL A = ₱         7,500.00
                                             -
              SUB-TOTAL C =                  -
(A+B+C)= ₱ 9,470.00
                          =   ₱         757.60
                          =   ₱         757.60
                          =   ₱         549.26
                          =   ₱      11,534.46
                          =   ₱       3,844.82
                                             -
              SUB-TOTAL A = ₱                -
                   (A+B+C)= ₱       391,500.00
                         =   ₱      31,320.00
                         =   ₱      31,320.00
                         =   ₱      22,707.00
                         =   ₱     476,847.00
                         =   ₱     476,847.00
               1200                 72,000.00
             SUB-TOTAL C =          72,000.00
(A+B+C)= ₱ 393,500.00
                         =   ₱      31,480.00
                         =   ₱      31,480.00
                         =   ₱      22,823.00
                         =   ₱     479,283.00
                         =   ₱     479,283.00
(A+B+C)= ₱ 456,990.00
                          =   ₱      36,559.20
                          =   ₱      36,559.20
                          =   ₱      26,505.42
                          =   ₱     556,613.82
                          =   ₱     556,613.82
(A+B+C)= ₱ 786,990.00
                          =   ₱      62,959.20
                          =   ₱      62,959.20
                          =   ₱      45,645.42
                          =   ₱     958,553.82
                          =   ₱     958,553.82
(A+B+C)= ₱ 786,990.00
                          =   ₱      62,959.20
                          =   ₱      62,959.20
                          =   ₱      45,645.42
                          =   ₱     958,553.82
                          =   ₱     958,553.82
(A+B+C)= ₱ 786,990.00
                          =   ₱      62,959.20
                          =   ₱      62,959.20
                          =   ₱      45,645.42
                          =   ₱     958,553.82
                          =   ₱     958,553.82
                   (A+B+C)= ₱       786,990.00
                          =   ₱     62,959.20
                          =   ₱     62,959.20
                          =   ₱     45,645.42
                          =   ₱    958,553.82
                          =   ₱    958,553.82
(A+B+C)= ₱ 5,064,500.00
                          =   ₱     405,160.00
                          =   ₱     405,160.00
                          =   ₱     293,741.00
                          =   ₱   6,168,561.00
                          =   ₱          89.04
(A+B+C)= ₱ 1,862,050.00
                          =   ₱      148,964.00
                          =   ₱      148,964.00
                          =   ₱      107,998.90
                          =   ₱    2,267,976.90
                          =   ₱           89.71
(A+B+C)= ₱ 2,302,165.00
                          =   ₱      184,173.20
                          =   ₱      184,173.20
                          =   ₱      133,525.57
                          =   ₱    2,804,036.97
                          =   ₱           89.07
(A+B+C)= ₱ 2,283,190.00
                          =   ₱     182,655.20
                          =   ₱     182,655.20
                          =   ₱     132,425.02
                          =   ₱   2,780,925.42
                          =   ₱          89.00
(A+B+C)= ₱ 2,507,015.00
                          =   ₱     200,561.20
                          =   ₱     200,561.20
                          =   ₱     145,406.87
                          =   ₱   3,053,544.27
                          =   ₱          88.86
(A+B+C)= ₱ 782,500.00
                          =   ₱      62,600.00
                          =   ₱      62,600.00
                          =   ₱      45,385.00
                          =   ₱     953,085.00
                          =   ₱          88.25
(A+B+C)= ₱ 3,710,200.00
                          =   ₱      296,816.00
                          =   ₱      296,816.00
                          =   ₱      215,191.60
                          =   ₱    4,519,023.60
                          =   ₱        7,791.42
  UNIT      UNIT COST (PHP)   TOTAL COST (PHP)
  cu.m          7805.17          858568.2
(A+B+C)= ₱ 704,900.00
                          =   ₱      56,392.00
                          =   ₱      56,392.00
                          =   ₱      40,884.20
                          =   ₱     858,568.20
                          =   ₱       7,805.17
                          =   ₱      115,208.00
                          =   ₱      115,208.00
                          =   ₱       83,525.80
                          =   ₱    1,754,041.80
                          =   ₱        7,795.74
(A+B+C)= ₱ 1,470,500.00
                          =   ₱      117,640.00
                          =   ₱      117,640.00
                          =   ₱       85,289.00
                          =   ₱    1,791,069.00
                          =   ₱        7,787.26
(A+B+C)= ₱ 1,470,500.00
                          =   ₱      117,640.00
                          =   ₱      117,640.00
                          =   ₱       85,289.00
                          =   ₱    1,791,069.00
                          =   ₱        7,787.26
(A+B+C)= ₱ 735,300.00
                          =   ₱      58,824.00
                          =   ₱      58,824.00
                          =   ₱      42,647.40
                          =   ₱     895,595.40
                          =   ₱       7,787.79
(A+B+C)= ₱ 1,786,300.00
                          =   ₱      142,904.00
                          =   ₱      142,904.00
                          =   ₱      103,605.40
                          =   ₱    2,175,713.40
                          =   ₱    2,175,713.40
                                                  CE         SA         ST
   pcs            14                 13,720.00         123        12         12
   pcs            12                 39,900.00         320        29         41
   pcs            10                 28,100.00         180        16         34
  bags           240                153,600.00
  cu.m          1300                 91,000.00
   pcs           225                 22,500.00
   kgs            80                  2,000.00
              SUB-TOTAL A = ₱       350,820.00
(A+B+C)= ₱ 529,820.00
                          =   ₱      42,385.60
                          =   ₱      42,385.60
                          =   ₱      30,729.56
                          =   ₱     645,320.76
                          =   ₱     645,320.76
                                                 CE         SA        ST
   pcs            14                 13,720.00        123        12        12
   pcs            12                 47,400.00        378        34        48
   pcs            10                 35,600.00        228        20        43
  bags           240                177,600.00
  cu.m          1300                 97,500.00
   pcs           225                 24,750.00
   kgs            80                  2,000.00
              SUB-TOTAL A = ₱       398,570.00
(A+B+C)= ₱ 574,570.00
                          =   ₱      45,965.60
                          =   ₱      45,965.60
                          =   ₱      33,325.06
                          =   ₱     699,826.26
                          = ₱       699,826.26
                                                 CE          SA         ST
   pcs            14                 13,720.00         123         12        12
   pcs            12                 18,000.00         144         13        18
   pcs            10                 48,700.00         320        140        59
  bags           240                144,000.00
  cu.m          1300                227,500.00
   pcs           225                 22,500.00
   kgs            80                  1,760.00
              SUB-TOTAL A = ₱       476,180.00
(A+B+C)= ₱ 687,380.00
                          =   ₱      54,990.40
                          =   ₱      54,990.40
                          =   ₱      39,868.04
                          =   ₱     837,228.84
                          =   ₱     837,228.84
SUB-TOTAL C = -
(A+B+C)= ₱ 44,350.00
                         =   ₱       3,548.00
                         =   ₱       3,548.00
                         =   ₱       2,572.30
                         =   ₱      54,018.30
                         =   ₱      54,018.30
SUB-TOTAL C = -
(A+B+C)= ₱ 108,755.00
                         =   ₱       8,700.40
                         =   ₱       8,700.40
                         =   ₱       6,307.79
                         =   ₱     132,463.59
                         =   ₱     132,463.59
  UNIT     UNIT COST (PHP)   TOTAL COST (PHP)
   lot       148662.99          148662.99
SUB-TOTAL C = -
(A+B+C)= ₱ 122,055.00
                         =   ₱       9,764.40
                         =   ₱       9,764.40
                         =   ₱       7,079.19
                         =   ₱     148,662.99
                         =   ₱     148,662.99
SUB-TOTAL C = -
(A+B+C)= ₱ 104,285.00
                         =   ₱       8,342.80
                         =   ₱       8,342.80
                         =   ₱       6,048.53
                         =   ₱     127,019.13
                         =   ₱     127,019.13
(A+B+C)= ₱ 253,400.00
                         =   ₱      20,272.00
                         =   ₱      20,272.00
                         =   ₱      14,697.20
                         =   ₱     308,641.20
                         =   ₱     308,641.20
SUB-TOTAL C = -
(A+B+C)= ₱ 221,900.00
                         =   ₱      17,752.00
                         =   ₱      17,752.00
                         =   ₱      12,870.20
                         =   ₱     270,274.20
                         =   ₱     270,274.20
SUB-TOTAL C = -
(A+B+C)= ₱ 229,100.00
                         =   ₱      18,328.00
                         =   ₱      18,328.00
                         =   ₱      13,287.80
                         =   ₱     279,043.80
                         =   ₱     279,043.80
SUB-TOTAL C = -
(A+B+C)= ₱ 3,362,700.00
                          =   ₱      269,016.00
                          =   ₱      269,016.00
                          =   ₱      195,036.60
                          =   ₱    4,095,768.60
                          =   ₱    4,095,768.60
                         =   ₱      59,253.00
                         =   ₱      59,253.00
                         =   ₱      42,958.43
                         =   ₱     902,126.93
                         =   ₱     902,126.93
SUB-TOTAL C = -
(A+B+C)= ₱ 455,850.00
                         =   ₱      36,468.00
                         =   ₱      36,468.00
                         =   ₱      26,439.30
                         =   ₱     555,225.30
                         =   ₱     555,225.30
SUB-TOTAL C = -
(A+B+C)= ₱ 455,850.00
                         =   ₱      36,468.00
                         =   ₱      36,468.00
                         =   ₱      26,439.30
                         =   ₱     555,225.30
                         =   ₱     555,225.30
SUB-TOTAL C = -
(A+B+C)= ₱ 455,850.00
                         =   ₱      36,468.00
                         =   ₱      36,468.00
                         =   ₱      26,439.30
                         =   ₱     555,225.30
                         = ₱       555,225.30
SUB-TOTAL C = -
(A+B+C)= ₱ 505,700.00
                         =   ₱      40,456.00
                         =   ₱      40,456.00
                         =   ₱      29,330.60
                         =   ₱     615,942.60
                         =   ₱     615,942.60
(A+B+C)= ₱ 1,335,570.00
                         =   ₱      106,845.60
                         =   ₱      106,845.60
                         =   ₱       77,463.06
                         =   ₱    1,626,724.26
                         =   ₱    1,626,724.26
SUB-TOTAL C = -
(A+B+C)= ₱ 1,254,860.00
                         =   ₱      100,388.80
                         =   ₱      100,388.80
                         =   ₱       72,781.88
                         =   ₱    1,528,419.48
                         =   ₱    1,528,419.48
SUB-TOTAL C = -
(A+B+C)= ₱ 1,354,995.00
                         =   ₱      108,399.60
                         =   ₱      108,399.60
                         =   ₱       78,589.71
                         =   ₱    1,650,383.91
                         =   ₱    1,650,383.91
SUB-TOTAL C = -
(A+B+C)= ₱ 1,317,142.50
                         =   ₱      105,371.40
                         =   ₱      105,371.40
                         =   ₱       76,394.27
                         =   ₱    1,604,279.57
                         =   ₱    1,604,279.57
  UNIT     UNIT COST (PHP)   TOTAL COST (PHP)
   lot        717462.9          717462.9
SUB-TOTAL C = -
(A+B+C)= ₱ 589,050.00
                         =   ₱      47,124.00
                         =   ₱      47,124.00
                         =   ₱      34,164.90
                         =   ₱     717,462.90
                         =   ₱     717,462.90
SUB-TOTAL C = -
                  (A+B+C)= ₱       583,800.00
                         =   ₱      46,704.00
                         =   ₱      46,704.00
                         =   ₱      33,860.40
                         =   ₱     711,068.40
                         =   ₱     711,068.40
SUB-TOTAL C = -
(A+B+C)= ₱ 583,800.00
                         =   ₱      46,704.00
                         =   ₱      46,704.00
                         =   ₱      33,860.40
                         =   ₱     711,068.40
                         =   ₱     711,068.40
   pcs           18                 27,900.00
   pcs         1800                 81,000.00
  bags          250                 40,000.00
  cu.m         1500                 82,500.00
   pcs          210                 43,050.00
   kgs           80                 37,200.00
             SUB-TOTAL A = ₱       311,650.00
(A+B+C)= ₱ 452,650.00
                          =   ₱      36,212.00
                          =   ₱      36,212.00
                          =   ₱      26,253.70
                          =   ₱     551,327.70
                          =   ₱     551,327.70
SUB-TOTAL C = -
                   (A+B+C)= ₱      9,572,800.00
=   ₱      765,824.00
=   ₱      765,824.00
=   ₱      555,222.40
=   ₱   11,659,670.40
=   ₱   11,659,670.40
       4
BC4
      16
      48   750
      60   250
           450
           190
       4
c4         beam         slab
      64          750
      72          250          2150
                  450
                  190            65
       6            5             4
c2         c3           c4
      12            4
      24           60            64
     108           90            72
       6         5         4
c2         c3        c4
      12         4
      24        60        64
     108        90        72
Tie
      1.5
        2
ST
TIE
       3
       9
       8
ST
TIE
       3
      10
       9
      ST
      TIE
             3
             4
            13
ght
Wall
        7
wall
        7
dbl
       70
dbl
      70
                                             EQUIPMENT RENTAL RATES & CAPABILITIES, ACEL RATES January 2003 Ed.
Wekding Machine Electric Driven/ DC output                                                     Weilding / Cutting          500         APMS     Capacity
Oxy-Acetylene/Cutting outfit                                                                   Cutting
Chainsaw w/out blade                                                                           Cutting
Generator Set                                                                                  Power Generation            64-125     KVA       51-100 HP
Dumpt truck (12-15 cu.Yds)                                                                     Hauling / Transporting      9.17-11.46 Cu.M.     Capacity
Water Truck ( 5000-6000 Gals)                                                                  Water Supply                5000-6000 Gals.      Capacity
Trailer 60 Ton PhP4.25/HR./Km                                                                  Transporting                15         TONS      Capacity
( PhP 4.25 X Wt. (Min.=15T) X No. of KM. +
50% Surcharge, Return trip Example (100KM)
= (4.25 X 15 X 100) X 1.5 = PhP 16,576 per
Day
Cargot Truck ( 9-10 Tons)                                                                      Hauling / Transporting      9-10        TONS     Capacity
                                                                               EQUIPMENT CAPABILITIES
Type of Equipment                                                           Average Capabilities
FACTORS TO BE MULTIPLIED TO
DETERMINE THE REQUIRED QUANTITY
OF EACH MATERIAL CONCRETE
I. MECHANIZED ASPECT
B.2 DOZER
Horse                                                         Production ( cu.m./hr. ) Bank Volume
Power                                                            Canal                            Structure
                       120                                        30                                 15
                       140                                        35                                 20
                       160                                        40                                 25
                       180                                        45                                 30
                       200                                        50                                 35
B.3 BACKHOE
Bucket ( cu.m.)                                                            Production ( cu.m./hr.) Bank Volume
                                                                 Canal                            Structure                 Creek
                       0.5                                        20                                 15                      15
                       0.75                                       30                                 20                      20
                        1                                         40                                 30                      30
                       1.25                                       50                                 40                      40
                       1.5                                        60                                 45                      45
C. QUARRYING
Dozer ( H.P.)                                                              Production ( cu.m./hr.) Bank Volume
                                                                Common                            Aggregate            Cobbles/Boulders
                       140                                        55                                 60                      27
                       160                                        60                                 65                      29
                       180                                        65                                 70                      31
                       200                                        70                                 75                      33
D. LOADING
                  Bucket (cu.m.)                                           Production ( cu.m./hr.) Bank Volume
                                                                Common                            Aggregate            Cobbles/Boulders
                         1                                        50                                  55                     35
                        1.5                                       75                                  80                     55
                         2                                        100                                110                     75
                        2.5                                       125                                135                     90
                         3                                        150                                165                     110
E. SPREADING
                  Grader ( H.P.)                                    Road ( cu.m./hr. ) cmp.
                                                                Common                           Aggregate
                      80-100                                      60                                70
                      100-125                                     70                                80
                      125-150                                     90                               100
                      150-175                                     100                              110
F. SIDE BORROW ( Common Materials)
            Dozer ( H.P.)            Production ( cu.m./hr.) Compacted Volume
                140                                                             35
                160                                                             40
                180                                                             45
                200                                                             50
G. STR BACKFILL WITH SPREADING &
COMPACTION
             Dozer ( H.P.)                                    Production cu.m./hr. Compacted Volume
                 140                                                            50
                 160                                                            70
                 180                                                            80
                 200                                                            90
H. EMBANKMENT COMPACTION
                                                              Capacity ( cu.m./hr.) Compacted Volume
                     Tons                                                  Self- Propelled
                                                              Tam. Foot drum                      Vib. Drum
                      10                                            80                                60
                      12                                            90                                70
                      15                                           120                                90
K. DEMOLITION OF CONCRETE
L. DRIVING OF PILES
Steel Pipes : Crane 25 tons with 2-tons drop
hammer, Capacity= 8 L.M./Hr.
Concrete Piles : Crane 25 tons with 2500
kgs.m. Pile hammer, Capacity= 2.00 L.M. per
Hr.,
4.00 L.M./Hr. for thick & thin concrete piles.
M. MANUAL ASPECT
A. EXCAVATION
A.1. Common Materials
                                                                      Capacity (cu.m./day) Bank Volume & Depth of Excavation
                Type of Work                                                                 ( meter )
                 Farmditchs                                           3.00                             2.50                      2.00
                   Canal                                              2.50                             2.00                      1.75
                  Structure                                           2.00                             1.75                      1.50
               E. QUARRYING
                  Capability                     cu.m./day/man
                Sand & Gravel                                     Cobbles                            Boulder
                     3.5                                            2.5                                2
      F. DEMOLITION OF CONCRETE
               Slab & Wall                       0.50 cu.m./man-day
            Massive Concrete                     0.20 cu.m./man-day
    G. SCREENING OF AGGREGATES
               Gravel                            4.00 cu.m./day/man
                 Sand                     6.00 cu.m./day/man
        H. MANUAL BACKFILL
      Capacity : 3.00 cu.m./day/man
          L. GROUTED RIPRAP
Crew : 1- Foreman, 2- Mason, 10- Laborers,
             & 1- L.E. Operator
          Capacity : 7.50 cu.m./day
           N. CONCRETE LINING
   Crew : 1- Foreman, 2- Mason, 1- L.E.
 Operator, 10- Laborers with one (1) bagger
                   mixer
         Capacity : 4.50 cu.m./day
          P. CONCRETE WORKS
 P.1. Fabrication, Placing & Dismantling of
                   Forms
    Crew : 2- Carpenters & 4- Laborers;
   Capacity : 3.50 cu.m./day for 3000 psi
Crew : 1- Carpenter & 1- Laborer; Capacity :
        4.50 cu.m./day Canal Lining
          G. I. LAYING OF C.H.B.
                    Size                         Cement                                           Sand
                                                 Bag/sq.m.                                        Cu.m./sq.m.
                      4"                                                                   0.55                     0.046
                      6"                                                                   1.07                     0.089
Lumpsum
Installation:
Timber:
Paintings:
Paint Rollers                                   125 sq.m./man-days
Paint Brush                                     50 sq.m./man-days
Neutralizer                                     100 sq.m./man-days
Truss Fabrication                               0.25 truss/man-days
Purlins Installation                            60 L.M./man-days
Fascia Boards                                   0.05 cu.m./man-days
Roof Coverings ( G.I. sheets )                  35 pcs./man-days
Concrete Works:
Concrete Pouring                                0.30 cu.m./man-days
Rebars                                          20 - 30 kgs.man-days
Finishing:
Rough Finish                                    10 sq.m./man-days
Plain/Fine Finish                               8 sq.m./man-days
CHB Filling/Laying                              6 - 8 sq.m./man-days
A. CEMENT MORTAR
                               MAINTENANCE BY CONTRACT
                                        ( MBC )
                               METHODS OF CONSTRUCTION