Rail Stakeholder Consultation Report

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
33 views6 pages

Rail Stakeholder Consultation Report

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

Annex 1: Stakeholder

consultation
Considering the nature and the level of details of the information needed, relevant stakeholders in the rail
sector in the different MS have been involved in the data collection. The approach adopted for engaging them
and the current progress of the consultation are outlined in the following paragraphs.

1.1. Stakeholder consultation

The stakeholder consultation has been designed to collect:

 qualitative information on country level specificities and factors that may impact project costs (e.g.
market conditions, legislation, procurement practices, cost estimation methodologies, etc.);
 quantitative information on the projects under analysis, regarding technical characteristics and costs
(estimated and final).
While the former is gathered by consulting different stakeholders involved in the design and implementation of
rail projects (e.g. Ministries, Transport Agencies, IM, MA etc.); the latter is primarily provided by IM.

As a result, a qualitative survey exploring conditions and factors impacting rail project costs has been
distributed to all relevant stakeholders in the design and implementation of railway infrastructure. In addition
to this, IM have been asked to fill-in quantitative questionnaires with information on the projects implemented
within the railway network they manage.

Although in the Inception Report it was considered to carry forward the consultations separately, to ensure
higher efficiency in the process, due to the limited time at disposal, they have been launched together.

The consultation process and its current progress are outlined hereunder.

1.1.1. Approach
The stakeholder consultation process consisted of the following steps:
1. definition of the stakeholder contact list;
2. preparation of the qualitative survey and quantitative questionnaires;
3. management of the consultation.
Step 1: Definition of the stakeholder contact list
The creation of the contact list represented a fundamental step for the consultation, as the nature of the
information sought required to identify the most appropriate person within each organisation, able to deal with
the specific request.
The stakeholder list was created including three categories of stakeholders, namely:
 Managing Authorities. The targeted MA were responsible for the National and Regional operational
programmes in 3 programme periods: 2000 - 2006; 2007 - 2013; 2014 - 2020 under the operational
programme ‘Transport’, Thematic priority 7 - ‘Transport and energy networks’. This group was
expected to provide responses reflecting planning of rail infrastructure project, rather than direct
project implementation and technical specifications.
 Infrastructure Managers. This is the most relevant stakeholder group for the study as IM are fully
involved in all stages of the project’s development - planning, implementation and operation.
 Ministries of transport / agencies. This group comprises of the national ministries that are in
charge of transport development on country level. In some countries the Ministry of Transport is an
independent authority, while in some cases they were absorbed by other sectors (e.g. France where the
Ministry of Transport became part of the Ministry of the Environment, Energy and the Sea). This group
was considered as highly relevant for the qualitative survey because of its involvement in the planning
of rail infrastructure development and knowledge on factors impacting cost in the rail infrastructure
projects.
Step 2. Preparation of the qualitative survey and quantitative questionnaires
The qualitative data collection was conducted through an online survey consisting of the following main
sections:

 Section 1 gathering inputs to identify the respondent;


 Section 2 requiring information regarding the planning of rail infrastructure projects and the role of the
respondent in this phase;
 Section 3 aiming to identify which external factors affect costs of rail infrastructure projects and what
their impact is;
 Section 4 focusing on future investments in rail infrastructure (only MA and MoT).
The quantitative questionnaire consisted of an excel file, where the required information was classified
into three different tiers, corresponding to progressive level of details, in accordance with the approach adopted
for the analysis. For each tier, both estimated costs (reported in the feasibility study or assessed in the planning
& design phase) and final costs (reported in the contracts) were required.

The questionnaires used for the consultation are reported in Annex 2 and 3.

3. Management of the consultation


The stakeholder consultation was launched 9th of June 2017, after the Commission approved the consultation
package. Invitation e-mails were sent to 120 organizations: 46 MA, 41 IM and 37 MoT.

On a general basis, three organisations (i.e. the national MA, MoT and IM) have been consulted for each MS,
except for countries where the same organisations perform the role of MA and MoT and countries where
Regional Managing Authorities are highly involved in the project implementation and had to be included in the
process (e.g. Italy, Poland).

The geographical distribution of stakeholders involved in the consultation is presented in the figure hereunder.
Figure 1 - Number of consulted organizations (MA, MoT and IM) per MS

To enhance the response rate and the data coverage, telephone contacts have been established with all
stakeholders and reminders have been constantly sent.

Details are shown in the monitoring consultation sheet included in Annex 1.

1.1.2. Progress of the qualitative consultation


The qualitative part of the Stakeholder Consultation is focused on obtaining qualitative information on the cost
factors that have a strong influence on the public procurement process and the rail unit cost on a country basis.
This information is relevant for the deliverable of the country sheets which will later be translated into a
qualitative section of the REGIO Rail Unit Cost Benchmarking Tool (RRUCBT) that will provide country
specific information on potential deviations from the standard rail unit cost in each country.
To gather this information PwC has sent out online questionnaires to relevant IM, MA and MoT from the 26
Member States with relevant rail projects. Furthermore, PwC contacted all stakeholders via email and
telephone to offer support in filling out the questionnaires to ensure a high level of participation.
After being postponed from the end of July the new deadline for the qualitative Stakeholder Survey was the 31 st
of August 2017. However, several responses from stakeholders arrived up until the 2nd of October, which were
also included by the team. The total amount of responses received which could be included was 41 as several of
the responses sent had to be discarded due to the respondents not being involved in the planning of any rail
infrastructure projects and incomplete responses.
The 41 replies that were considered for the final analysis were distributed as follows (sometimes multiple people
from the same organisation responded with complementing information which have been combined to one
response of that organisation and in some cases there was more than one relevant body or organisation per
country and stakeholder category wherefore there might be more than one response per country and
stakeholder category):
Table 1 - Replies per country and stakeholder category
Countries IM MA MoT
AT 1 0 1
BE 1 0 1
BG 1 0 1
CZ 1 1 1
DE 0 0 1
DK 2 0 0
EE 1 1 0
ES 0 0 0
FR 0 0 0
GR 1 0 0
HR 1 0 1
HU 2 1 0
IE 1 0 1
IT 1 0 0
LT 1 0 3
LU 0 0 1
LV 0 1 1
NL 1 0 1
PL 0 0 1
PT 1 0 0
RO 1 2 0
SE 1 0 0
SI 0 0 1
SK 1 0 1

It is to note that the participation is unfortunately not complete and relatively low compared to the amount of
stakeholders contacted, which leads to a limitation of the quality of the analysis. Several of the organisations
were unable to provide their help in filling in the requested information despite several attempts to contact the
stakeholders and offering PwC’s help and assistance in gathering the data. The Commission has been informed
of this issue in advance and contacted the stakeholders during the month of July 2017. Nevertheless, the
combined efforts have not lead to the desired level of participation. Details are provided in the section below.

1.1.3. Limitations of the qualitative consultation


The main problem of the qualitative stakeholder consultation was an unexpectedly low participation from the
national bodies that make up the relevant stakeholders who are able to provide the necessary information on
the Member States’ procurement processes and country specific cost factors. Despite the intensive effort of PwC
to contact the organisations repeatedly offering assistance and extensions of the deadline to fill out the
information the majority of stakeholders either never replied or in a few cases refused to participate.
For the 26 Member States with rail projects there are a total of around 100 relevant authorities that make up
the Infrastructure Managers, Managing Authorities and Ministries of Transport. In the majority of countries
these are three different entities, however for example in the cases of Austria there is no MA, because Austria
does not use EU structural funds for the railway development, whereas in Denmark and Hungary two different
Infrastructure Managers exist. The team received responses from only 41 of all these authorities. From the
country with the most information on rail projects available to the team, Spain, the only response came from
the Ministry of Companies and Public Functions (Ministerio de Hacienda y Función Pública, Dirección
General de Fondos Comunitarios), which declared not to be involved in the process of planning rail
infrastructure projects.

1.1.4. Progress of the quantitative consultation


The request for providing quantitative information has been sent to 41 IM, which have been subsequently
contacted via e-mail and telephone to prompt their participation in the study (as reported in Annex 1).
Nonetheless, gathering specific information on each project requires effort and time and several stakeholders
asked for an extension of the time foreseen for the consultation. Additionally, PwC assisted a large part of the
infrastructure managers in gathering the data by mobelising the local PwC branch to enter or translate the
information prepared by the Infrastructure Manager, as it was often not possible otherwise due to a lack of
resources (see next section).
Table 2 - Status of the Stakeholders consultations per IM
Number of
Country IM Name projects
received
Austria Österreichische Bundesbahn (ÖBB) Infrastruktur Bau AG 4
Belgium Infrabel 5
Bulgaria National Railway Infrastructure Company 7
Croatia Croatian Railways Infrastructure - HŽ Infrastruktura d.o.o 6
Czech Railway Infrastructure Administration, state organisation
18
Republic (RIA)
Denmark Banedanmark (Rail Net Denmark) 1
Estonia AS Eesti Raudtee (Estonian Railways Lt) 1
Finland Finnish Transport Agency 1
France SNCF Réseau 1
Germany DB Netz AG 3
Hellenic Railways Organisation (OSE) & ERGOSE S.A.
Greece 16
(Rail Infrastructure Development)
MÁV (Hungarian State Railways Infrastructure) & Gysev &
Hungary 5
NIF Zrt.
Ireland Irish Rail 1
Italy Rete Ferroviaria Italiana S.p.A.
Latvia Latvian Railways (VAS Latvijas Dzelzcels) 3
Joint Stock Company Lithuanian Railways: JSC Lietuvos
Lithuania 4
geležinkeliai
Société Nationale des Chemins de Fer Luxembourgeois
Luxembourg
(SNCFL)
Netherlands Prorail BV 5
Poland PKP Polskie Linie Kolejowe S.A. 28
Portugal Infraestuturas de Portugal 8
Compania Nationala de Cai Ferate "CFR"-SA (National
Romania 1
Railway Company "CFR" SA)
Slovakia Železnice Slovenskej republiky 6
Slovenia Slovenian Railways & Slovenian infrastructure agency 10
Spain Administrador de Infraestructuras Ferroviarias (ADIF)
Sweden TRAFIKVERKET - Swedish Transport Administration 8
UK Network Rail & Translink (Northern Ireland) 4
Department for Regional Development Northern Ireland
EU Cross- (DRDNI) & TELT & TP Ferro & GEIE SEA Vitoria-Dax;
4
border ADIF & BBT (Brenner Base Tunnel) & RB Rail AS &
Femern A/S
Total 38 150
As of the 2nd of November, information on 150 projects has been sent to the team by infrastructure managers
from nearly all Member States. The majority of this data was very extensive and allowed for at least a basic cost
breakdown of the final project cost.

1.1.5. Limitations of the quantitative consultation


The main limitation of the quantitative stakeholder consultation was that the infrastructure managers were not
always able to provide the data requested on the rail infrastructure projects for different reasons. On one hand
some stakeholders were not able to provide the data, due to the mass of information required and thus the time
required to extract the information on the apprlicable format; on the other hand some stakeholders were not
allowed to provide the data for competition reasons. Lastly, some stakeholders never replied to any contact
attempts made during the process (phone or email).
In light of the stakeholders’ low level of participation, PwC attempted to convince the stakeholders who were
unable to provide the data due to a lack of human resources by reducing the amount of projects requested and
offering help in the extraction of the data from the local database by mobilising the international network of
PwC and the respective branches relative to the country of the stakeholder. To this aim international teams of
PwC assisted Infrastructure Managers from the Czech Republic, Greece, Latvia, Lithuania, Poland and Slovakia
to directly extract the information from the respective stakeholder’s database in the local language. These
international teams provided in sito assistance to extract, translate and transfer the data into the database for
approximately 65 person-days.
Also the Commission was made aware of this issue (see above) and reached out to the stakholders. With the
joint effort between the stakeholders, PwC and the Commission, the information on the aformentioned number
of 150 projects from 23 countries could be retrieved.