Catchup Plan
Catchup Plan
C D J H F P M
SPL3 800(1) 903(2) 900(1) 804(1)b 1018(1)
Name of Project: Construction of Emergency Operation and Training Center (Ground Floor & Second Floor Slab Only) START
1047 1101
Critical Path
R N O END
B E G K L
SPL2 803(1)a 804(4) 1001(1)a 1003(1) 1008 1010(2)b
1027(1)
August 31 , 2022 - November 2, 2022 November 2, 2022 - January 4, 2023 January 4, 2023 - March 10, 2023 March 10, 2023 - May 17, 2023
No. of Days to
1st QUARTER 2ND QUARTER 3rd Quarter 4th Quarter
Activity No. Item No. DESCRIPTION Quantity Unit Unit Cost TOT. EST. COST % WT. for checking
Complete
3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57 60 63 66 69 72 75 78 81 84 87 90 93 84 86 88 90 93 96 99 102 105 108 111 114 117 120 123 126 129 132 135 138 141 144 147 150 153 156 159 162 165 168 171 174 177 180 183 186 189 192 195 198 201 204 207 210 213 216 219 222 225 228 231 234 237 240 243 246 249 252 255 259
N 1008 Aluminum Glass Door (Sliding type/Casement/Awning/Fixed) 73.84 sq.m. 3,007.64 222,084.14
2.87 2.865505 8.00 1.435 1.435
Q 1047 Masonry Works (CHB Layering) 486.60 sq.m. 681.88 331,802.81 0.535 0.535 0.535 0.535 0.535 0.535 0.535 0.535
4.28 4.281183 20.00
R 1027(1) Masonry Works (Plastering) 125.15 sq.m. 168.08 21,034.77 0.090 0.090 0.090
0.27 0.271407 12.00
S 1101 Electrical Works 1.00 lot 947,604.53 947,604.53 2.446 2.446 2.446 2.446 2.446
12.23 12.226744 22.00 0
ENGR. JUSTINE JOSEPH Y. SIMBULAN HECTOR P. CABRIANA, MPA ZALDY A. GAYOSA, REA, REB RUEL C. TIANCHON, MPA, REA, REB
PROPRIETOR ENGINEER IV ENGINEER IV CITY ENGINEER
MANPOWER SCHEDULE
CONTRACT NAME: Construction of Emergency Operation and Training Center (Ground Floor & Second Floor Slab Only)
LOCATION: City Hall Compound, Brgy. Zone III, Koronadal City
NO. OF DAYS
1ST QUARTER 2ND QUARTER 3RD QUARTER 4TH QUARTER
MANPOWER NO. 10 20 30 40 50 60 NO. 70 80 90 100 110 120 NO. 130 140 150 160 170 180 NO. 190 200 210 220 230 240 250 259
Project Engineer 1 1 1 1
Foreman 1 1 1 1
Steelman 2 2 3 3
Mason 4 4 8 8
SUSPENDED 4
SUSPENDED 7 7
Carpenter 4
Laborers 8 8 10 10
Electrician 3 3 5 5
Plumber 3 3 3 3
TOTAL NO. OF MANPOWER 26 26 38 38
ENGR. JUSTINE JOSEPH Y. SIMBULAN HECTOR P. CABRIANA, MPA ZALDY A. GAYOSA, REA, REB RUEL C. TIANCHON, MPA, REA, REB
PROPRIETOR ENGINEER IV ENGINEER IV CITY ENGINEER
EQUIPMENT UTLIZATION SCHEDULE
CONTRACT NAME: Construction of Emergency Operation and Training Center (Ground Floor & Second Floor Slab Only)
LOCATION: City Hall Compound, Brgy. Zone III, Koronadal City
NO. OF DAYS
1ST QUARTER 2ND QUARTER 3RD QUARTER 4TH QUARTER
EQUIPMENT NO. 10 20 30 40 50 60 NO. 70 80 90 100 110 120 NO. 130 140 150 160 170 180 NO. 190 200 210 220 230 240 250 259
Backhoe 1
Dumptruck 2 2 2 2
One bagger mixer 1 2 2 2
Concrete Vibrator 1 1 2 2
SUSPENDED SUSPENDED
Bar Cutter (Electric Drive) 1 1 1 1
Bar Bender (Manual) 1 1 3 3
Welding Machine 1 1 1 1
Cutting Outfit 1 1 2 2
TOTAL NO. OF MANPOWER 9 9 13 13
ENGR. JUSTINE JOSEPH Y. SIMBULAN HECTOR P. CABRIANA, MPA ZALDY A. GAYOSA, REA, REB RUEL C. TIANCHON, MPA, REA, REB
PROPRIETOR ENGINEER IV ENGINEER IV CITY ENGINEER