Table of content
Contents Page
Table of contents…………………………………………………………………………………………………1
1 Title the Project……………………………………………………………………………………………….
2. Executive summary..............................................................................................3
3. Background and Justification of the project.........................................................4
4. Target Groups......................................................................................................5
5. Objectives............................................................................................................ 5
6. Project Output......................................................................................................6
7. Project Activities and Time table.........................................................................6
Work Plan /time plan...............................................................................................6
Cost break down...................................................................................................... 7
8. Project inputs....................................................................................................... 8
9. Project Organization and management.................................................................8
The structure of the school...................................................................................8
10. Project Monitoring and Evaluation....................................................................9
11. Risks and Assumptions....................................................................................10
12. Project Sustainability.......................................................................................11
1
1. TITLE OF THE PROJECT
BUILDING SCHOOL LIBRARY IN GAMBELLA SECONDARY
& PREPARATORY SCHOOL OF AGNUWA ZONE.
2
1. Executive Summary
2.1. Project Title:-Building School Library in Gambella Secondary & Preparatory
school of Agnuwa Zone
2.2.Project Location:-Gambella Regional State in Agnuwa Zone of Gambella
Town
2.3. Sector:- Education Sector
2.4.Executive Organization:-Gambella Secondary & Preparatory School
2.5. Contact Person & Address:
Name: Betiglu Dinka
Mobile no: 0917834039
Email: betigludinka@gmail.com
2.6.Project Description:-The major purpose of this project is to improve students’
academic performance through constructing standardized library.
2.7. Target Groups:
Immediate Beneficiaries:
3
The direct beneficiary of this project is the whole students of Gambella
Secondary & preparatory School.
Ultimate Beneficiaries:
The indirectbeneficiary of this project is the community & country in
general.
2.8. Project Cost:-The total budget of this project is 1,000,000 Birr(one million
birr)
2.9.Project Duration:-This project will take time:
Starting Time: September 01/2009 E.C
Ending Time : March 30/2009 E.C
2.10. Collaborative Agencies: The collaborative agency of this project isworeda
education office, Community, Donors, Colleges and other concerned bodies.
3. Background and Justification
Education is the corner stone for any development of the countries in general as
well for individual in particular. It is essential instruments to bring change in
human mind and it helps to improve the life of the society at whole. To provided
equality, equity and the relevance of education fulfilling the necessary resources is
mandatory. So without supplementary materials and equipment’s teaching and
learning process are very difficult. Therefore, such necessary inputs, visionary
school leaders, qualified teachers and standardized learning rooms,laboratory,
library and different instructional materials are not available in the school as a
demands this due to shortage of financial resources. Education in Ethiopian policy
where governed the participation of community, stakeholders and NGOs to share
challenges of education expenditure in order to accomplish the objectives of new
education policy. And alsowithout collaboration of such institutions, and other
concerned bodies promoting the general education quality improvement program
cannot be achieved successfully. In relation to this, there are a number of problems
that needs to be improved through collaborativeparticipation of the society in
4
Gambella Secondary and Preparatory School. These are Lack of school
clinic ,Shortage of text books, Lack of library, Shortage of desks, Shortage of
laboratory chemicals and equipment’s are the obstacles in my school that affect
teaching -learning activities in the school and influence the academic performance
of the students. From these problems the most serious problem is lack of school
library.Because of this problem more students are not accessible to use the
librarycannot have the place to read and to refer the books during the exam time is
very difficult for the students. The purpose of this project is to improve students’
academic performance through constructing standardized library. Therefore,
Gambella Region is found in western part of Ethiopia, and it far from Addis Ababa
777km.The town is divided by the biggest river of Baro and the whether condition
of the town is mostly hottest. In addition to this,ingambella region there are five
indigenous ethnic groups. These are Agnuwa, Nuer, Majang, Komo, and Opo and
other highlanders also live in this region. Although, Gambella Secondary &
Preparatory School is found at the center of the town. Generally, to overcome this
problem in our school constructing new library for the students is very important in
this time. To improve the existing problem all stakeholders and concerned bodies
are be part of the the problem and can have contribution in the solving of this
problem in our school.
4. Target Groups (Beneficiaries)
4.1 Direct (immediate ) Beneficiaries
The primary beneficiaries of the constructed library are Gambella
secondary and preparatory school 1568 students are primary
beneficiaries.
4.2 Indirect (Ultimate) Beneficiaries
The ultimate beneficiaries of this project will be school community,
parents and a country in general will be secondary beneficiaries.
5
5. Objectives of the project
5.1 General Objective
The ge`neral objectives of this project are:-
T`oassure quality education in the school by building standardized school
lib`rary.
To promote instructional access throughimproving students’ academic
achievement.
5.2 Specific objectives
To improve students’ academic achievement
To assure accessible library
To motivate students teaching –learning process
To increase students referring demands
To facilitate students reading ability
6. Project out Puts
Effectively and efficiently constructed library
Facilitated students reading
Fulfilled reference center
Improved students’ academic
Accessible library center
7. Project Activities and Time Table
Work Plan /time plan
No Activities Time schedule Responsibl Rema
1st Q. 2ndQ. 3rdQ. 4thQ. e body rks
J A S O N D J F M A M J
1 Conducting need assessment √ Principals
2 Designing project proposal √ Principal
6
3 Establishing committee √ Principals
4 Searching Aid & mobilizing the √ Committee
resources
5 Negotiating with donors √ Committee
6 Receiving the Aid √ Committee
7 Mobilizing the community √ Committee
8 Conducting construction agreement √ Committee
9 Facilitating and clearing land √ Committee
10 Constructing/ Building √ Contractor
11 Monitoring & evaluation √ Principal
12 Reporting the progress √ Principal
Cost Breakdown
The expected materials price for the construction of this project is identified in the
following table.
No Types of construction Unit Quantity Unit price Total price Rema
materials and labors rk
Birr Cent Birr Cent
1 Land clearance & - - 15,000 - 15,000
preparation
2 Construction stone In no 20 lorry 1500 - 30,000 -
3 Aluminum tine In no 300 500 - 50,000 -
4 Cement Quintal 200 460 - 92,000 -
5 Radish (mmc) In no 10 lorry 3500 - 35,000 -
6 Blocket In no 650 15 - 10,000 -
7 Construction wood - - - - 25,000 -
7
8 Roof assembling - - - - 20,000 -
9 Mirror assembling - - - - 85,000 -
10 Different doors - - - - 60,000 -
11 Electric installations - - - - 70,000 -
12 Labor cost - - - - 308,000 -
13 Salary - - - - 100,000 -
14 Finishing (painting ) - - - - 100,000 -
Total 1,000,000
8. Project Inputs
The expected input of the project will be:
Fully constructed library
Trained library workers
Materials and financial resources
Human resources
Library furniture’s
Reference books and others
9. Project Organization and Management
-Thestructures of the school are organized as the following:
KebeleEducation and
Training Board (KETB)
Principal PTA
Administrative Academic Vice
Vice principal principal
8
Unit leader
Co-curricular
Library
Departments
Record office
Monitor
Pedagogical Center
Teachers
Students
-The Stakeholder’s involvement in the management of the project.These concerned
bodies are:-
Woreda Education Office
NGOs
University and Colleges
Teachers
Investors
Alumni
Parents
Students
Religious leaders
Community leaders (Idir, Equb…)
10. Project Monitoring and Evaluation
This project will be monitored during the construction(the of processing and
implementation) then will be evaluated after completion(March 15-30), by the
facilitators, coordinators and responsible bodies.
The Materials or Instruments which are used to monitor and evaluate the
project
9
Coaching personally
Check list
Construction process
The materials which are purchased
The purchased receipt
Receiving models(19)
The responsible authority to monitor the effectiveness and efficiency of
construction.
School principal
Education & training board chair man
Committee members
The data to be needed to monitor the project implementation and promotion
process will be through:
Comment records during construction time
Staff feedback
School principal
Supervisors and government officials
The committee comment and supervision is possible
The monitoring outcomes will be analyzed and assessed coordinately. If the
problem will be happened or faced it will be improved immediately and the report
will be transferred to the community and concerned body.
Project Evaluation
This project output will be evaluated at the end of completion of the construction.
Additionally it will be evaluated after the progress will be achieved and the
10
expected library service will be utilized by students, teachers and staff members.
And the final process of construction and the activities of the collaborators and the
beneficiaries will be evaluated.
11.Project Assumption and Risks
There are project implementation treats and opportunities.
-The Opportunities of the project are:-
The activities should be recognized in policy issues
School structures organized as a decentralized manner
Each concerned authority assigned a head
Presence of construction committee team
Availability of contractors
The land launched library building
The interests of the school community
The presence of advisors
The presence of productive values(collaboration)
The interests of the school vision, mission & values
-Threats (expected risks) of the project
Motivation of concerned bodies
The interests of expected Donors(NGOs)
Pre-conditions of Aid providers
Acceleration of the contractors
Instability of market price(labors, goods)
Time constraints
The inflation of construction materials
Instability of political officials
The awareness gap of school community
11
12. Project Sustainability
To ensure the sustainability of the project first of all creating awareness and
developing belongingness of the community of the school and primary
beneficiaries and ultimate owners will be the most agreed approach of project
providers and implementers enforcing the beneficiaries to recognize the project
values as his/her property is very important and advisable practice of the personals
who are devoted to assure the expected goal of the project.
WOLAITA SODO UNIVERSITY
SCHOOL OF EDUCATION AND BEHAVIORAL SCIENCE
DEPARTMENT OF EDUCATIONAL PLANNING AND
MANAGEMENT
INDIVIDUAL ASSIGNMENT OF SCHOOL IMPROVEMENT AND PROJECT
DESIGN (ScL-606)
PROJECT PROPOSAL ON:
Building School Library InGambellaSecondary &
Preparatory School In Agnwa Zone
BY:-BETIGLU DINKA
12
ID No:-EdSL/Msum/005/07
Summer: II
SUBMITTED TO: INSTRUCTOR–ATO DERIBE DEBELLA
Aug, 2016
WSU
13