Contract ID: Contract Name
Contract ID: Contract Name
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
Item No :               100(1)
Description :                                                  Clearing and Grubbing
Quantity :                              1.180 ha
COST ANALYSIS
A. MATERIALS
                        NONE                                                                                       P           0
                                                                        Sub-total,A                                P           0
B. EQUIPMENT/FUEL/OIL
        1 unit   Backhoe                      @P               2,156.00 /day for                      15.00 days   P    32,340.00
        1 unit   Boom truck                   @P               1,254.00 /day for                      15.00 days   P    18,810.00
                                                                        Sub-total,B                                P    51,150.00
C. LABOR
       1                Engineer              @P                 650.00 /day for                      15.00 days   P     9,750.00
       1                Foreman               @P                 566.08 /day for                      15.00 days   P     8,491.20
       2                Laborers              @P                 316.72 /day for                      15.00 days   P     9,501.60
                                                                        Sub-total C                                P    27,742.80
Item No :               103(1)a
Description :                                                        Structure Excavation (Common)
Quantity :                             582.00 cu.m.
COST ANALYSIS
A. MATERIALS
                        NONE                                                                                       P           0
                                                                        Sub-total,A                                P           0
B. EQUIPMENT/FUEL/OIL
        1 unit   Backhoe                      @P              17,542.00 /day for                      21.00 days   P   368,382.00
        1 unit   Dumptruck                    @P              15,487.00 /day for                      21.00 days   P   325,227.00
        1 unit   Boom Truck                   @P               8,520.00 /day for                      21.00 days   P   178,920.00
Contract ID:            17G00023
Contract Name:          Improvement/Widening of San Dionisio
                        – Capinang Road including RROW, San Dionisio, Iloilo, K0198+480 – K0200+100
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
Sub-total,B P 872,529.00
C. LABOR
        1               Engineer                 @P             1,250.00 /day for                       21.00 days    P    26,250.00
        1               Foreman                  @P               650.00 /day for                       21.00 days    P    13,650.00
       10               Laborers                 @P               350.00 /day for                       21.00 days    P    73,500.00
                                                                         Sub-total C                                  P   113,400.00
Item No :               103(3)
Description :                                                                   Foundation Fill
Quantity :                                  25.00 cu.m.
COST ANALYSIS
A. MATERIALS
B. EQUIPMENT/FUEL/OIL
        1 unit   Grader                          @P             5,452.00 /day for                         2.00 days   P    10,904.00
        1 unit   Roller                          @P             4,521.00 /day for                         2.00 days   P     9,042.00
        1 unit   Water truck                     @P             1,245.00 /day for                         2.00 days   P     2,490.00
                                                                         Sub-total,B                                  P    22,436.00
C. LABOR
       1                Engineer                 @P               765.00 /day for                         2.00 days   P     1,530.00
       1                Foreman                  @P               650.00 /day for                         2.00 days   P     1,300.00
       3                Laborers                 @P               300.00 /day for                         2.00 days   P     1,800.00
                                                                         Sub-total C                                  P     4,630.00
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
Item No :               103(6)a
Description :                                                       Pipe Culvert and Drain Excavation
Quantity :                             649.00 cu.m.
COST ANALYSIS
A. MATERIALS
                        NONE                                                                                       P           0
                                                                        Sub-total,A                                P           0
B. EQUIPMENT/FUEL/OIL
        1 unit   Bakhoe                       @P               4,547.00 /day for                      60.00 days   P   272,820.00
        1 unit   Dumptruck                    @P               3,214.00 /day for                      60.00 days   P   192,840.00
        1 unit   Boom Truck                   @P               1,214.00 /day for                      60.00 days   P    72,840.00
                                                                        Sub-total,B                                P   538,500.00
C. LABOR
        1               Engineer              @P                 860.00 /day for                      60.00 days   P    51,600.00
        1               Foreman               @P                 765.00 /day for                      60.00 days   P    45,900.00
       10               Laborers              @P                 300.00 /day for                      60.00 days   P   180,000.00
                                                                        Sub-total C                                P   277,500.00
COST ANALYSIS
A. MATERIALS
Contract ID:            17G00023
Contract Name:          Improvement/Widening of San Dionisio
                        – Capinang Road including RROW, San Dionisio, Iloilo, K0198+480 – K0200+100
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
                        NONE                                                                                         P             0
                                                                          Sub-total,A                                P             0
B. EQUIPMENT/FUEL/OIL
        1 unit   Grader                       @P              16,920.00   /day for                    20.00   days   P     338,400.00
        3 unit   Dump truck                   @P              20,300.00   /day for                    20.00   days   P   1,218,000.00
        1 unit   Roller                       @P              12,056.00   /day for                    20.00   days   P     241,120.00
        1 unit   Water truck                  @P               8,520.00   /day for                    20.00   days   P     170,400.00
                                                                          Sub-total,B                                P   1,967,920.00
C. LABOR
       1                Engineer              @P                 860.00 /day for                      20.00 days     P     17,200.00
       1                Foreman               @P                 456.00 /day for                      20.00 days     P      9,120.00
       3                Laborers              @P                 350.00 /day for                      20.00 days     P     21,000.00
                                                                        Sub-total C                                  P     47,320.00
COST ANALYSIS
A. MATERIALS
                        NONE                                                                                         P             0
                                                                          Sub-total,A                                P             0
B. EQUIPMENT/FUEL/OIL
        1 unit   Grader                       @P              16,920.00 /day for                      20.00 days     P    338,400.00
        1 unit   Roller                       @P              12,056.00 /day for                      20.00 days     P    241,120.00
        1 unit   Water truck                  @P               8,520.00 /day for                      20.00 days     P    170,400.00
                                                                        Sub-total,B                                  P    749,920.00
C. LABOR
       1                Engineer              @P                 860.00 /day for                      20.00 days     P     17,200.00
       1                Foreman               @P                 456.00 /day for                      20.00 days     P      9,120.00
Contract ID:            17G00023
Contract Name:          Improvement/Widening of San Dionisio
                        – Capinang Road including RROW, San Dionisio, Iloilo, K0198+480 – K0200+100
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
Item No :               105(1)a
Description :                                      Subgrade Preparation (Common Material)
Quantity :                            16,686.00 sq.m.
COST ANALYSIS
A. MATERIALS
                        NONE                                                                                        P             0
                                                                        Sub-total,A                                 P             0
B. EQUIPMENT/FUEL/OIL
        1 unit   Backhoe                       @P             17,384.00 /day for                      110.00 days   P   1,912,240.00
        1 unit   Dumptruck                     @P             12,056.00 /day for                      110.00 days   P   1,326,160.00
        1 unit   Boom Truck                    @P              8,520.00 /day for                      110.00 days   P     937,200.00
                                                                        Sub-total,B                                 P   4,175,600.00
C. LABOR
        1               Engineer               @P                860.00 /day for                      110.00 days   P     94,600.00
        1               Foreman                @P                456.00 /day for                      110.00 days   P     50,160.00
       10               Laborers               @P                350.00 /day for                      110.00 days   P    385,000.00
                                                                        Sub-total C                                 P    529,760.00
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
Item No :               200(1)
Description :                                                     Aggregate Subbase Course (0.20m thick)
Quantity :                             2,631.00 cu.m.
COST ANALYSIS
A. MATERIALS
                        Aggregates subbase     @P               1,200.00 /cu.m.                   4,256.00 cu.m.     P   5,107,200.00
                                                                         Sub-total,A                                 P   5,107,200.00
B. EQUIPMENT/FUEL/OIL
        2 unit   Grader                        @P              17,505.73 /day for                     20.00 days     P     700,229.00
        2 unit   Roller                        @P              12,056.00 /day for                     20.00 days     P     482,240.00
        1 unit   Water truck                   @P               8,520.00 /day for                     20.00 days     P     170,400.00
                                                                         Sub-total,B                                 P   1,352,869.00
C. LABOR
       1                Engineer               @P                950.00 /day for                      20.00 days     P     19,000.00
       1                Foreman                @P                650.00 /day for                      20.00 days     P     13,000.00
       2                Laborers               @P                300.00 /day for                      20.00 days     P     12,000.00
                                                                        Sub-total C                                  P     44,000.00
Item No :               311(1)e1
Description :                                   PCC Pavement (Unreinforced) – 280mm. hk. At 14 days
Quantity :                            11,826.00 Sq.m.
COST ANALYSIS
A. MATERIALS
         Portland cement                       @P                 250.00   /bag                   9,524.00   bags    P   2,381,000.00
         Reinforcing steel bars                @P                 310.00   /kg.                   8,654.00   kgs.    P   2,682,740.00
         Curing compound                       @P                 200.00   /lit.                  7,214.00   lit.    P   1,442,800.00
         Asphalt sealant                       @P                  75.00   /lit.                  2,154.00   lit.    P     161,550.00
         Steel forms                           @P                  60.00   /lm.                     458.00   lm.     P      27,480.00
         Gravel                                @P               1,000.00   /cu.m.                   215.00   cu.m.   P     215,000.00
         Sand                                  @P               1,000.00   /cu.m.                   125.00   cu.m.   P     125,000.00
         Tie Wire                              @P                  56.00   /kg.                   3,512.00   kgs.    P     196,672.00
         G.I Pipes                             @P                 300.00   /lm.                     234.00   lm.     P      70,200.00
         Grease tar                            @P                 250.00   /lit.                    958.00   lit.    P     239,500.00
                                                                           Sub-total,A                               P   7,541,942.00
Contract ID:            17G00023
Contract Name:          Improvement/Widening of San Dionisio
                        – Capinang Road including RROW, San Dionisio, Iloilo, K0198+480 – K0200+100
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
B. EQUIPMENT/FUEL/OIL
        2 unit   Transit mixer                  @P               7,070.00   /day for                  65.00   days   P     919,100.00
        2 unit   Conc. Vibrator                 @P               1,191.04   /day for                  65.00   days   P     154,835.20
        1 unit   Batching plant                 @P               9,664.24   /day for                  65.00   days   P     628,175.60
        1 unit   Payloader                      @P              13,864.00   /day for                  65.00   days   P     901,160.00
        1 unit   Conc. Sceeder                  @P               4,360.00   /day for                  65.00   days   P     283,400.00
        1 unit   Water truck                    @P               2,400.00   /day for                  65.00   days   P     156,000.00
        1 unit   Conc. Saw                      @P               1,339.04   /day for                  65.00   days   P      87,037.60
        1 unit   Bar cutter                     @P               1,758.00   /day for                  65.00   days   P     114,270.00
                                                                            Sub-total,B                              P   3,243,978.40
C. LABOR
        1               Engineer                @P                650.00    /day for                  65.00   days   P     42,250.00
        1               Foreman                 @P                566.08    /day for                  65.00   days   P     36,795.20
        8               Mason                   @P                410.64    /day for                  65.00   days   P    213,532.80
       12               Laborers                @P                316.72    /day for                  65.00   days   P    247,041.60
                                                                            Sub-total C                              P    539,619.60
B. EQUIPMENT/FUEL/OIL
        1 unit   Bar Cutter                     @P               1,245.00 /day for                    50.00 days     P     62,250.00
                                                                          Sub-total,B                                P     62,250.00
C. LABOR
       1                Engineer                @P                655.00    /day for                  50.00   days   P     32,750.00
       1                Foreman                 @P                432.00    /day for                  50.00   days   P     21,600.00
       2                Skilled                 @P                650.00    /day for                  50.00   days   P     65,000.00
       2                Laborers                @P                160.00    /day for                  50.00   days   P     16,000.00
                                                                            Sub-total C                              P    135,350.00
Contract ID:            17G00023
Contract Name:          Improvement/Widening of San Dionisio
                        – Capinang Road including RROW, San Dionisio, Iloilo, K0198+480 – K0200+100
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
COST ANALYSIS
A. MATERIALS
         Portland cement                      @P                  250.00   /bag                         122.00   bags    P    30,500.00
         Reinforcing steel bars               @P                  310.00   /kg.                          87.00   kgs.    P    26,970.00
         Curing compound                      @P                  200.00   /lit.                         52.00   lit.    P    10,400.00
         Asphalt sealant                      @P                   75.00   /lit.                         12.00   lit.    P       900.00
         Steel forms                          @P                   60.00   /lm.                          42.00   lm.     P     2,520.00
         Gravel                               @P                1,000.00   /cu.m.                        12.00   cu.m.   P    12,000.00
         Sand                                 @P                1,000.00   /cu.m.                         1.00   cu.m.   P     1,000.00
         Tie Wire                             @P                   56.00   /kg.                          14.00   kgs.    P       784.00
         G.I Pipes                            @P                  300.00   /lm.                          12.00   lm.     P     3,600.00
         Grease tar                           @P                  250.00   /lit.                         12.00   lit.    P     3,000.00
                                                                           Sub-total,A                                   P    91,674.00
B. EQUIPMENT/FUEL/OIL
        2 unit   Transit mixer                @P               10,232.00   /day for                       7.00   days    P   143,248.00
        2 unit   Conc. Vibrator               @P                1,191.04   /day for                       7.00   days    P    16,674.56
        1 unit   Batching plant               @P                9,664.24   /day for                       7.00   days    P    67,649.68
        1 unit   Payloader                    @P               13,864.00   /day for                       7.00   days    P    97,048.00
        1 unit   Conc. Sceeder                @P                4,360.00   /day for                       7.00   days    P    30,520.00
        1 unit   Water truck                  @P                2,400.00   /day for                       7.00   days    P    16,800.00
        1 unit   Conc. Saw                    @P                1,339.04   /day for                       7.00   days    P     9,373.28
        1 unit   Bar cutter                   @P                1,758.00   /day for                       7.00   days    P    12,306.00
                                                                           Sub-total,B                                   P   393,619.52
C. LABOR
        1               Engineer              @P                  650.00   /day for                       7.00   days    P     4,550.00
        1               Foreman               @P                  566.08   /day for                       7.00   days    P     3,962.56
        8               Mason                 @P                  410.64   /day for                       7.00   days    P    22,995.84
       12               Laborers              @P                  316.72   /day for                       7.00   days    P    26,604.48
                                                                           Sub-total C                                   P    58,112.88
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
B. EQUIPMENT/FUEL/OIL
        1 unit   Truck                          @P                 8,520.00 /day for                      21.00 days     P   178,920.00
                                                                            Sub-total,B                                  P   178,920.00
C. LABOR
       1                Engineer                @P                   655.00   /day for                    21.00   days   P    13,755.00
       1                Foreman                 @P                   432.00   /day for                    21.00   days   P     9,072.00
       2                Skilled                 @P                   650.00   /day for                    21.00   days   P    27,300.00
       2                Laborers                @P                   160.00   /day for                    21.00   days   P     6,720.00
                                                                              Sub-total C                                P    56,847.00
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
B. EQUIPMENT/FUEL/OIL
        1 unit   Truck                         @P              8,520.00 /day for                       3.00 days     P    25,560.00
                                                                        Sub-total,B                                  P    25,560.00
C. LABOR
       1                Engineer               @P                655.00   /day for                     3.00   days   P     1,965.00
       1                Foreman                @P                432.00   /day for                     3.00   days   P     1,296.00
       2                Skilled                @P                650.00   /day for                     3.00   days   P     3,900.00
       2                Laborers               @P                160.00   /day for                     3.00   days   P       960.00
                                                                          Sub-total C                                P     8,121.00
Item No :               502(1)b3
Description :                                   Manholes, 910mm dia CHB (Class A)
Quantity :                                73.00 each
COST ANALYSIS
A. MATERIALS
B. EQUIPMENT/FUEL/OIL
        1 unit   Truck                         @P              8,520.00 /day for                      12.00 days     P   102,240.00
                                                                        Sub-total,B                                  P   102,240.00
C. LABOR
       1                Engineer               @P                655.00   /day for                    12.00   days   P     7,860.00
       1                Foreman                @P                432.00   /day for                    12.00   days   P     5,184.00
       2                Skilled                @P                650.00   /day for                    12.00   days   P    15,600.00
       2                Laborers               @P                160.00   /day for                    12.00   days   P     3,840.00
                                                                          Sub-total C                                P    32,484.00
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
Item No :               505(5)
Description :                                   Grouted Riprap
Quantity :                               304.00 cu.m.
COST ANALYSIS
A. MATERIALS
B. EQUIPMENT/FUEL/OIL
        1 unit   Truck                         @P                8,520.00 /day for                     7.00 days     P    59,640.00
                                                                          Sub-total,B                                P    59,640.00
C. LABOR
       1                Engineer               @P                  655.00   /day for                   7.00   days   P     4,585.00
       1                Foreman                @P                  432.00   /day for                   7.00   days   P     3,024.00
       2                Skilled                @P                  650.00   /day for                   7.00   days   P     9,100.00
       2                Laborers               @P                  160.00   /day for                   7.00   days   P     2,240.00
                                                                            Sub-total C                              P    18,949.00
Item No :               506(1)
Description :                                   Stone Masonry
Quantity :                               801.00 cu.m.
COST ANALYSIS
A. MATERIALS
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
B. EQUIPMENT/FUEL/OIL
        1 unit   Truck                         @P               8,520.00 /day for                      4.00 days     P      34,080.00
                                                                         Sub-total,B                                 P      34,080.00
C. LABOR
       1                Engineer               @P                 655.00   /day for                    4.00   days   P       2,620.00
       1                Foreman                @P                 432.00   /day for                    4.00   days   P       1,728.00
       2                Skilled                @P                 650.00   /day for                    4.00   days   P       5,200.00
       2                Laborers               @P                 160.00   /day for                    4.00   days   P       1,280.00
                                                                           Sub-total C                               P      10,828.00
Item No :               600(3)
Description :                                  Curb and Gutter (Cast in Place)
Quantity :                            2,920.00 lm.
COST ANALYSIS
A. MATERIALS
B. EQUIPMENT/FUEL/OIL
        1 unit   Truck                         @P               8,520.00 /day for                     30.00 days     P     255,600.00
                                                                         Sub-total,B                                 P     255,600.00
C. LABOR
       1                Engineer               @P                 655.00   /day for                   30.00   days   P      19,650.00
       1                Foreman                @P                 432.00   /day for                   30.00   days   P      12,960.00
       2                Skilled                @P                 650.00   /day for                   30.00   days   P      39,000.00
       2                Laborers               @P                 160.00   /day for                   30.00   days   P       9,600.00
                                                                           Sub-total C                               P      81,210.00
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
Item No :               601(1)
Description :                                  Sidewalk (100mm thk.)
Quantity :                            3,458.00 sq m
COST ANALYSIS
A. MATERIALS
B. EQUIPMENT/FUEL/OIL
        1 unit   Truck                        @P               8,520.00 /day for                      25.00 days     P     213,000.00
                                                                        Sub-total,B                                  P     213,000.00
C. LABOR
       1                Engineer              @P               1,254.00   /day for                    25.00   days   P      31,350.00
       1                Foreman               @P                 750.00   /day for                    25.00   days   P      18,750.00
       2                Skilled               @P                 650.00   /day for                    25.00   days   P      32,500.00
       2                Laborers              @P                 160.00   /day for                    25.00   days   P       8,000.00
                                                                          Sub-total C                                P      90,600.00
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
B. EQUIPMENT/FUEL/OIL
        1 unit   Truck                        @P               3,233.00 /day for                       5.00 days     P   16,165.00
                                                                        Sub-total,B                                  P   16,165.00
C. LABOR
       1                Engineer              @P                 655.00   /day for                     5.00   days   P    3,275.00
       1                Foreman               @P                 432.00   /day for                     5.00   days   P    2,160.00
       2                Skilled               @P                 650.00   /day for                     5.00   days   P    6,500.00
       2                Laborers              @P                 160.00   /day for                     5.00   days   P    1,600.00
                                                                          Sub-total C                                P   13,535.00
Item No :               605(1)c2
Description :                                 Warning Signs (Horizontal Alignment Curve)(W1-3B)
Quantity :                               2.00 each
COST ANALYSIS
A. MATERIALS
B. EQUIPMENT/FUEL/OIL
        1 unit   Truck                        @P               8,520.00 /day for                       4.00 days     P   34,080.00
                                                                        Sub-total,B                                  P   34,080.00
C. LABOR
       1                Engineer              @P                 655.00   /day for                     4.00   days   P    2,620.00
       1                Foreman               @P                 432.00   /day for                     4.00   days   P    1,728.00
       2                Skilled               @P                 650.00   /day for                     4.00   days   P    5,200.00
       2                Laborers              @P                 160.00   /day for                     4.00   days   P    1,280.00
                                                                          Sub-total C                                P   10,828.00
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
Item No :               605(1)l2
Description :                                 Warning Signs (Side Road Junction)(W2-6B)
Quantity :                               1.00 each
COST ANALYSIS
A. MATERIALS
B. EQUIPMENT/FUEL/OIL
        1 unit   Truck                        @P               8,520.00 /day for                       3.00 days     P   25,560.00
                                                                        Sub-total,B                                  P   25,560.00
C. LABOR
       1                Engineer              @P               1,254.00   /day for                     3.00   days   P    3,762.00
       1                Foreman               @P                 750.00   /day for                     3.00   days   P    2,250.00
       2                Skilled               @P                 650.00   /day for                     3.00   days   P    3,900.00
       2                Laborers              @P                 160.00   /day for                     3.00   days   P      960.00
                                                                          Sub-total C                                P   10,872.00
Item No :               612(1)
Description :                                 Reflectorized Thermoplastic Pavement Markings White
Quantity :                             729.00 sq.m.
COST ANALYSIS
A. MATERIALS
Contract ID:            17G00023
Contract Name:          Improvement/Widening of San Dionisio
                        – Capinang Road including RROW, San Dionisio, Iloilo, K0198+480 – K0200+100
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
B. EQUIPMENT/FUEL/OIL
        1 unit   Backhoe                      @P               1,376.00 /day for                       8.00 days   P    11,008.00
        1 unit   Truck                        @P               3,256.00 /day for                       8.00 days   P    26,048.00
                                                                        Sub-total,B                                P    37,056.00
C. LABOR
       1                Engineer              @P                 655.00 /day for                       8.00 days   P     5,240.00
       1                Foreman               @P                 432.00 /day for                       8.00 days   P     3,456.00
       2                Laborers              @P                 160.00 /day for                       8.00 days   P     2,560.00
                                                                        1.00                                       P    11,256.00
               DIRECT COST                    :         Php                                    427,392.00
               OCM                            :         Php                                     38,465.28
               PROFIT                         :         Php                                     34,191.36
               TAXES                          :         Php                                     60,007.74
               TOTAL COST                               Php                                    560,056.38
Item No :               620(1)a
Description :                                   Chevron Signs (450mm x 600mm)
Quantity :                              25.00 each
COST ANALYSIS
A. MATERIALS
B. EQUIPMENT/FUEL/OIL
        1 unit   Truck                        @P               8,520.00 /day for                      12.00 days   P   102,240.00
                                                                        Sub-total,B                                P   102,240.00
C. LABOR
       1                Engineer              @P                 655.00 /day for                      12.00 days   P     7,860.00
       1                Foreman               @P                 432.00 /day for                      12.00 days   P     5,184.00
       2                Laborers              @P                 160.00 /day for                      12.00 days   P     3,840.00
                                                                        Sub-total C                                P    16,884.00
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
COST ANALYSIS
A. MATERIALS
Construction of Field Office for the Engineer @P                55,000.00                                   1.00 l.s.    P   55,000.00
                                                                            Sub-total,A                                  P   55,000.00
B. EQUIPMENT/FUEL/OIL
C. LABOR
       1                Engineer                @P                 650.00 /day for                         30.00 days    P   19,500.00
       1                Security                @P                 566.08 /day for                         30.00 days    P   16,982.40
       1                Laborers                @P                 316.72 /day for                         30.00 days    P    9,501.60
                                                                          Sub-total C                                    P   45,984.00
Item No :               A.1.1(16)
Description :                                   Operation and Maintenance of Field Office of the Engineer
Quantity :                              7.270      Mos.
COST ANALYSIS
A. MATERIALS
Operation and Maintenance of Field Office of@P                   8,500.00                                  7.270 Mos.    P   61,795.00
(materials)                                                                 Sub-total,A                                  P   61,795.00
B. EQUIPMENT/FUEL/OIL
C. LABOR
       1                Engineer                @P                 650.00 /day for                         60.00 days    P   39,000.00
       1                Security                @P                 566.08 /day for                         60.00 days    P   33,964.80
       1                Laborers                @P                 316.72 /day for                         60.00 days    P   19,003.20
                                                                          Sub-total C                                    P   91,968.00
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
B. EQUIPMENT/FUEL/OIL
                 NONE
C. LABOR
        1        Engineer                     @P                 650.00 /day for                         2.00 days      P    1,300.00
        1        Foreman                      @P                 566.08 /day for                         2.00 days      P    1,132.16
        4        Laborers                     @P                 316.72 /day for                         2.00 days      P    2,533.76
                                                                        Sub-total C                                     P    4,965.92
Item No :               B.8
Description :                                 Traffic Management
Quantity :                               7.27 Month
COST ANALYSIS
A. MATERIALS
     Traffic Signages & Warnings, ect.        @P              18,500.00 /set                             4.00 set       P   74,000.00
                                                                        Sub-total,A                                     P   74,000.00
B. EQUIPMENT/FUEL/OIL
                 NONE
Sub-total,B P 0.00
C. LABOR
Contract ID:            17G00023
Contract Name:          Improvement/Widening of San Dionisio
                        – Capinang Road including RROW, San Dionisio, Iloilo, K0198+480 – K0200+100
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
Item No :               B.9
Description :                                 MOBILIZATION & DEMOBILIZATION
Quantity :                               1.00 L.S.
COST ANALYSIS
A. MATERIALS
                        NONE                                                                                             P
                                                                        Sub-total,A                                      P          -
B. EQUIPMENT/FUEL/OIL
Sub-total,B P 804,524.00
C. LABOR
                        NONE                                                                                             P         0.00
                                                                        Sub-total C                                      P         0.00
Item No :               B.7
Description :                                 Construction Safety and Health
Quantity :                               7.27 Month
COST ANALYSIS
Contract ID:            17G00023
Contract Name:          Improvement/Widening of San Dionisio
                        – Capinang Road including RROW, San Dionisio, Iloilo, K0198+480 – K0200+100
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
A. MATERIALS
B. EQUIPMENT/FUEL/OIL
Sub-total,B P 0.00
C. LABOR
       1                Engineer               @P                 650.00 /day for                     115.00 days    P    74,750.00
       1                Foreman                @P                 566.08 /day for                     115.00 days    P    65,099.20
       1                Laborers               @P                 316.72 /day for                     115.00 days    P    36,422.80
                                                                         Sub-total C                                 P   176,272.00
Item No :               B.5
Description :                                  Project Billboard/Signboard
Quantity :                                3.00 each
COST ANALYSIS
A. MATERIALS
B. EQUIPMENT/FUEL/OIL
Sub-total,B P 0.00
C. LABOR
       1                Engineer               @P                 650.00 /day for                        1.00 days   P       650.00
       1                Foreman                @P                 566.08 /day for                        1.00 days   P       566.08
       1                Laborers               @P                 316.72 /day for                        1.00 days   P       316.72
                                                                         Sub-total C                                 P     1,532.80
Contract ID:            17G00023
Contract Name:          Improvement/Widening of San Dionisio
                        – Capinang Road including RROW, San Dionisio, Iloilo, K0198+480 – K0200+100
Location of Contract:
                        Iloilo City
DETAILED ESTIMATES
Submitted By:
EARL L. NAVARRO
Proprietor/General Manager
PYRAMID CONSOLIDATED BUILDERS & GEN. MDSE.
Marchy 3, 2017
CONTRACT ID    :   17G00023
Contract       :   Improvement/Widening of San Dionisio
                   – Capinang Road including RROW, San Dionisio, Iloilo, K0198+480 – K0200+100
Name
                                                     BILL OF QUANTITIES
 Pay Item
   No.              Description           Quantity        Unit                 Unit Price                              Amount
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
                                                                                                                                 Page 1 of 23
  DPWH-INFR-17-2016
CONTRACT ID    :   17G00023
Contract       :   Improvement/Widening of San Dionisio
                   – Capinang Road including RROW, San Dionisio, Iloilo, K0198+480 – K0200+100
Name
Location           Iloilo
            Subgrade      City
                      Preparation
            (Common Material)
               :
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
                                                                                                                          Page 1 of 24
  DPWH-INFR-17-2016
CONTRACT ID    :   17G00023
Contract       :   Improvement/Widening of San Dionisio
                   – Capinang Road including RROW, San Dionisio, Iloilo, K0198+480 – K0200+100
Name
               :
                                                                  In Figure: Php         1,814.98 In Figure: Php           72,599.37
 502(1)b3 Manholes, 910mm dia CHB               73.00     each    In words:                       In words:
          (Class A)
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
                                                                                                                          Page 1 of 25
  DPWH-INFR-17-2016
CONTRACT ID     :   17G00023
Contract        :   Improvement/Widening of San Dionisio
                    – Capinang Road including RROW, San Dionisio, Iloilo, K0198+480 – K0200+100
Name
             Warning Signs (Side Road
             Junction)(W2-6B)
Location            Iloilo City
: #VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
                                                                                                                          Page 1 of 26
  DPWH-INFR-17-2016
CONTRACT ID      :   17G00023
Contract         :   Improvement/Widening of San Dionisio
                     – Capinang Road including RROW, San Dionisio, Iloilo, K0198+480 – K0200+100
Name
Submitted by :
EARL L. NAVARRO                                                                                     Date :      Marchy 3, 2017
Proprietor/General Manager
PYRAMID CONSOLIDATED BUILDERS AND GENERAL MERCHANDISE
                                                                                                                                 Page 1 of 27
   DPWH-INFR-17-2016
                                                                Department of Public Works and Highways (DPWH)
CONTRACT ID       :        17G00023
                           Improvement/Widening of San Dionisio
                           – Capinang Road including RROW, San Dionisio, Iloilo, K0198+480 – K0200+100
NAME              :
                           Iloilo City
LOCATION          :
SUBMITTED BY:
EARL L. NAVARRO
Proprietor/General Manager
PYRAMID CONSOLIDATED BUILDERS & GEN. MDSE.
Marchy 3, 2017
       DPWH-INFR-19-2016                                                                                                                            Page 1 of 28
                                                      Department of Public Works and Highways
CONTRACT ID : 17G00023
NAME :
                          Iloilo City
LOCATION             :
-----------------------------------------------------------------------------------------------------------------------------------------------------
Iloilo City
      (b)
               we offer to execute the Works for this Contract in accordance with the Bidding Documents, including the Bid
               Data Sheet, General and Special Conditions of the Contrac, Specifications and Drawings therein;
               we present our Bid to execute the Works, consisting of our Technical Proposal (Annex "A") and our Financial Proposal
      (c)      (Annex "B");
      (d)      our Technical Proposal includes the following required documents;
               (1) Bid Security in the required form, amount and validity period, using Form DPWH-INFR-09,10 or 11, as applicable
                   (Annex ";A-1")
               (2) Organizatiuonal Chart for the Contract, using Form DPWH-INFR-13 (Annex "A-3")
               (3) Contractor's Certification on Key Personnel for the Contract, with the Key Personnel's Affidavits of Commitment to
                   Work on the Contract, using Form DPWH-INFR-14 (Annex "A-4")
               (4) List of Contractor's Major Equipment Pledged for the Contract, using Form DPWH-INFR-15 (Annex "A-5")
               (5)
                   Omnibus Sworn Statement required under RA 9184-IRR Sec. 25.2b)iv), using Form DPWH-INFR-15(Annex "A-6")
      (e)      our Finanacial Proposal includes the following required documents:
            DPWH-INFR-09-2016                                                                                                                           Page 1 of 29
            (1)   This Bid Form (Annex "B-1")
            (2)   Bid Prices in the Bill of Quantities Form, using Forms DPWH-INFR-16 and 17 (Annex "B-2")
            (3)   Detailed estimates (Annex "B-3")
            (4)   Cash Flow by quarter, using Form DPWH-INFR-18 (Annex "B-4");
            the total price of our Bid for this Contract based on the unit proces in the said Bill of Quantities, excluding any
    (f)     discounts offered in item(g) below, is:
            #VALUE!
Php46,742,601.08
(g) the discounts we offer and the methodology for their application for this Contract are:
None
    (h)     our Bid shall be valid for a period of 120 Calendar Days after the date fixed for the opening of bids in accordance with
            the Bidding Documents, and it shall remain binding upon us and may be accepted by you at any time before the
            expiration of that period;
    (i)     if our Bid is accepted and we receive from you a Notice of Award, we commit, within ten (10) calendar days, after our
            receipt of the said Notice, (1) to submit to you the rquired Performance Security and other documents prescribed in
            the Bidding Documents, and (2) to sign the Contract Agreement;
            we understand that, if the contract is awarded to us, this Bid, together with your writeen acceptance thereof through
    (j)     your Notice of Award, shall constitute a binding contract between us, until a formal Contract Agreement os prepared
            and executed;
    (k)
            we understand that you are not bound to accept the Lowest Calculated Bid or any other Bid that you may receive; and
    (l)     we acknowledge that failure to sign each page of this Form of Bid and the accomplished Bill of Quantites shall be a
            ground for the rejection of our Bid.
Signed                                                           :
Duly authorized to sign the Bid for & In Behalf of               : PYRAMID CONSOLIDATED BUILDERS & GEN. MDSE.
Date                                                             :     Marchy 3, 2017
          DPWH-INFR-09-2016                                                                                                Page 1 of 30
DPWH-INFR-09-2016   Page 1 of 31
CONTRACT ID      :   17G00023
Contract         :   Improvement/Widening of San Dionisio
                     – Capinang Road including RROW, San Dionisio, Iloilo, K0198+480 – K0200+100
Name
Submitted by :
EARL L. NAVARRO
Proprietor/General Manager
PYRAMID CONSOLIDATED BUILDERS AND GENERAL MERCHANDISE
Marchy 3, 2017
                                                                                                         Page 1 of 32
   DPWH-INFR-17-2016
     58,656.53
   1,291,961.36
     68,227.29
   1,069,286.40
   2,640,770.50
   1,044,703.30
   6,165,903.74
   8,522,932.02
 14,270,180.40
   1,338,945.03
    684,692.06
    387,221.17
     72,599.37
    228,487.18
    202,575.33
    628,798.65
   2,519,075.55
   2,858,369.56
     40,343.87
     60,272.44
     48,453.94
    560,056.38
    172,426.95
    106,033.20
    161,451.15
     13,800.53
    304,109.57
    844,750.20
 46,742,601.08
                    Page 1 of 33
DPWH-INFR-17-2016