HV Earthing Standards for NSW Substations
HV Earthing Standards for NSW Substations
0
                                                EP 12 10 00 10 SP
                                                EP 12 10 00 11 SP
                                                        Standard
                                                        Disclaimer
              This document has been prepared by Transport for NSW (TfNSW) specifically for its own use
              and is also available for use by NSW public transport agencies for transport assets.
              Any third parties considering use of this document should obtain their own independent
              professional advice about the appropriateness of using this document and the accuracy of its
              contents. TfNSW disclaims all responsibility and liability arising whether directly or indirectly out
              of or in connection with the contents or use of this document.
              The inclusion of any third party material in this document, does not represent an endorsement
              by TfNSW of any third party product or service.
For queries regarding this document, please email Transport for NSW Asset Management Branch at
standards@transport.nsw.gov.au or visit www.transport.nsw.gov.au
Document information
Document history
                                                         Preface
              This standard supersedes both EP 12 10 00 10 SP and EP 12 10 00 11 SP. This is the first
              issue of this standard under the designation TS 03726.
              Substations and distribution systems are widespread throughout the Transport Network. These
              assets supply and distribute power from the supply authorities to a wide range of assets. This
              standard is issued by the Asset Management Branch (AMB) (formerly the Asset Standards
              Authority (ASA)) to stipulate the minimum earthing requirements for the whole life cycle of HV
              and LV earthing systems at traction substations, sectioning huts, HV ac switching stations,
              distribution substations (pole mounted and ground mounted) and systems (aerial lines and
              cables) for the heavy rail network.
The contents of this standard are developed from the following documents:
Table of contents
1      Scope ........................................................................................................................................................ 7
2      Application ............................................................................................................................................... 7
3      Referenced documents ........................................................................................................................... 7
4      Terms, definitions and abbreviations .................................................................................................. 10
5      Authorisation requirements ................................................................................................................. 12
6      General requirements ........................................................................................................................... 12
6.1       Design .................................................................................................................................................. 13
6.2       Construction ......................................................................................................................................... 15
6.3       Commissioning .................................................................................................................................... 15
6.4       Asset handover .................................................................................................................................... 15
6.5       Maintenance ........................................................................................................................................ 15
6.6       SFAIRP ................................................................................................................................................ 16
7      Lightning protection .............................................................................................................................. 16
7.1       General ................................................................................................................................................ 16
7.2       Lightning protection system ................................................................................................................. 16
7.3       Existing locations ................................................................................................................................. 17
7.4       Critical locations................................................................................................................................... 17
7.5       Documentation ..................................................................................................................................... 18
8      Electromagnetic fields .......................................................................................................................... 18
9      HV aerial lines ........................................................................................................................................ 19
9.1       General ................................................................................................................................................ 19
9.2       Overhead earth wire ............................................................................................................................ 19
9.3       UGOH poles ........................................................................................................................................ 21
9.4       Stay poles ............................................................................................................................................ 21
9.5       Steel poles ........................................................................................................................................... 21
10     System substation earthing ................................................................................................................. 22
10.1      General ................................................................................................................................................ 22
10.2      Equipment to be earthed ..................................................................................................................... 22
10.3      Supplies to nearby loads ..................................................................................................................... 23
11     Distribution substation earthing .......................................................................................................... 23
11.1      General ................................................................................................................................................ 24
11.2      Equipment to be earthed ..................................................................................................................... 24
11.3      Combined earthing system .................................................................................................................. 25
11.4      Other locations supplied from a distribution substation ....................................................................... 26
12     Earthing grid .......................................................................................................................................... 26
12.1      Standard electrode .............................................................................................................................. 27
12.2      Electrode spacing ................................................................................................................................ 27
12.3      Installation of electrodes ...................................................................................................................... 27
12.4      Test electrode ...................................................................................................................................... 28
1             Scope
              This document specifies the minimum earthing requirements for the whole life cycle of HV and
              LV earthing systems at traction substations, sectioning huts, HV ac switching stations,
              distribution substations (pole mounted and ground mounted) and distribution systems (aerial
              lines and cables) for the heavy rail network.
              This document does not cover the requirements for earthing design risk management. For this
              process refer to TS 00006.
2             Application
              This standard applies to all new HV and LV earthing systems at traction substations, sectioning
              huts, HV ac switching stations, distribution substations (pole mounted and ground mounted) and
              systems (aerial lines and cables).
              Existing installations may not be consistent with the requirements of this document. Due to the
              changes in the surrounding environment and the deterioration of earthing systems over time, an
              earthing installation may no longer perform as originally designed. For these reasons,
              modification of interfacing systems can lead to challenging considerations for the Technically
              Assured Organisation (TAO). Where the requirements of this standard cannot be practically
              met, alternative solutions aligned to the philosophy of this standard may be accepted subject to
              a request for concession.
3             Referenced documents
              The following documents are cited in the text. For dated references, only the cited edition
              applies. For undated references, the latest edition of the referenced document applies.
International standards
              EN 50122-1:2011 Railway applications – Fixed installations – Electrical safety, earthing and the
              return circuit – Part 1: Protective provisions against electric shock
Australian standards
              AS IEC 61000.6.4 Electromagnetic compatibility (EMC) Part 6.4: Generic standards – Emission
              standard for industrial environments
              AS IEC 61000.6.5 Electromagnetic compatibility (EMC) Part 6.5: Generic standards – Immunity
              for equipment used in power station and substation environment
                    Note: Code of practice for the mitigation of hazardous voltages induced into
                    telecommunication lines.
              EL0005630 Substations and sectioning huts earthing system for fibre glass padmount
              substation
EL0008409 33kV/ 500 – 250V transformer single pole structure operating notice
EL0000930 Earthing arrangement substation on timber pole with low voltage earthed
EL0000931 Earthing arrangement substation on timber pole with low voltage unearthed
EL0017051 Eastern suburbs railway H.V. & L.V. equipment earthing arrangement
EL0017446 Transmission lines conductor spacing – earth wire ground wire arrangement
EL0017447 Transmission lines conductor spacing – earth wire ground wire arrangement
EL0017448 Transmission lines conductor spacing – earth wire ground wire arrangement
              EL0284008 General high voltage aerial lines and cables OHEW & UGOH earth electrodes
              typical installation details
Legislation
              Energy Networks Australia 2022, Power System Earthing Guide (EG-0) Part 1: Management
              Principles, ENA DOC 025-2022
Energy Networks Australia 2022, Substation Earthing Guide, ENA DOC 045-2022 (EG-1)
ac alternating current
              ac switching stations these locations contain high voltage ac circuit breakers and there is no
              1500 V dc equipment.
clearing time the time taken for the protective devices to identify and isolate the fault current
              conductive part a part capable of conducting current, although it may not necessarily be used
              for carrying service current
                    Note: For the purpose of this document conductive parts can include, but are not
                    limited to, elements built from conductive materials, for example, steel fences, steel
                    horizontal safety screens, steel vertical safety screens and steel balustrades.
dc direct current
              distribution system the electricity power lines and associated equipment and electricity
              structures used to convey and control the conveyance of electricity to, from and along the rail
              network electricity system operated by, for or on behalf of Sydney Metro, Sydney Trains,
              Transport Asset Holding Entity of New South Wales or Transport for NSW (tailored from
              Electricity Supply Act 1995 No 94 Section 12A)
earth fault occurrence of an accidental conductive path between a live conductor and the earth
              earth grid interconnected uninsulated conductors installed in contact with the earth (or an
              intermediate material) intended for the conduction and dissipation of current and or for the
              provision of a uniform voltage reference. One part of the earthing system (source
              ENA DOC 025-2022)
earth potential rise (EPR) a voltage between an earthing system and a remote earth reference
              earthing system an arrangement of earth conductors which typically includes but not limited to
              an earth grid, earth electrodes and additional earth conductors such as overhead earth wires
              (OHEWs), cable sheaths, earth continuity conductors (ECCs) and parallel earthing conductors
              electrolysis an electrochemical reaction involving an electrolyte and metals which are carrying
              a dc current
fault clearance the amount of time it takes a circuit protection device to clear a fault
              remote a location where the contact frequency is suitably low that the fault/contact coincidence
              probability is less than the target fatality probability. It is typically a location with few people
              around such as a rural area.
              remote earth an electric potential outside the zone of influence of the relevant earthing
              arrangement which is conventionally taken as zero
              sectioning huts these locations sectionalise the overhead wiring for 1500 V dc protection and
              voltage regulation. If the Sectioning hut includes any high voltage ac equipment, then the design
              shall be the same as for a traction substation
              soil resistivity specific resistivity of a material is used to define the resistance of a material to
              current flow and is defined as the electric field strength (V/m) divided by the current density
              (A/m2). Values tabled are normalised to 1 amp flowing into a one metre cube of material yielding
              units of ohmmeter (Ωm)
              step voltage a voltage between two points on the earth’s surface that are 1 m distant from each
              other while a person is making contact with these points by their feet
              system substation umbrella term which includes traction substations, sectioning huts, and HV
              ac switching stations
              traction substations these locations supply traction power to the 1500 V dc overhead wire.
              The incoming HV ac supply is converted to 1500 V dc using rectifiers. Some equipment that
              may be encountered at traction substations may include HV ac switchgear, 1500 V dc
              switchgear, HV and LV transformers, traction supply equipment (rectifiers/harmonic
              filters/reactors), batteries, and Rail Earth Contactors (REC)
                    Note: The value of the effective touch voltage may be influenced by the impedance of
                    the person in contact with these conductive parts
5             Authorisation requirements
              All earthing design, construction and commissioning activities shall be undertaken by a TAO
              with suitable authorisation in "earthing, bonding, electrolysis and lightning protection" for the
              applicable life cycle stage.
              The following AMB documents provide information and guidance on TfNSW requirements and
              responsibilities of TAOs who are engaged in the provision of engineering services to TfNSW:
• TS 10504
• T MU AM 06016 GU
• TS 10507
• T MU MD 20001 ST.
6             General requirements
              The HV earthing design process is documented in TS 00006. Designers shall take into account
              the entire life cycle of an asset as well as the whole of life costs when assessing earthing design
              options as specified in T MU AM 01001 ST.
6.1           Design
              Earthing designs are typically documented in three stages to allow for appropriate stakeholder
              consultation, agreement and endorsement at the concept, detailed and for construction design
              stages. These stages are aligned with TS 01455 and summarised as follows:
              •     description of the proposed earthing ‘functional design’ that complies with TfNSW
                    standards
              •     for existing earth grids (brownfield sites), current injection testing and fall of potential
                    measurements
• soil resistivity measurement and modelling. This typically includes the following:
              •     ac HV earth fault levels with associated primary and backup earth total fault clearance
                    times
              •     touch, step and transfer voltage safety limits. Limits for touch and step voltage shall be
                    determined for all identified contact scenarios in accordance with TS 00006.
              •     hazard log and risk analysis shall be updated, as required, particularly when further
                    hazards and risks are identified in the design process
              •     earthing system impedance and EPR calculation. This includes any calculated transfer
                    voltage hazards
              •     conductor sizes shall be calculated in accordance with IEEE 80 using maximum future
                    earth fault levels and backup total clearance time.
              •     final EPR, earthing system impedance (local & global), current distribution, touch, step and
                    transfer voltage simulation results
6.2           Construction
              All earthing systems shall be constructed using the approved equipment, materials and
              methods identified in this document and reference general arrangement drawings. Equivalent
              products and methods may be used subject to agreement by the relevant asset steward and the
              AMB.
              All inspection test plans (ITP) shall be provisioned with adequate witness and hold points to
              facilitate inspection and testing of earthing activities and components such as, but not limited to,
              the following:
6.3           Commissioning
              All substation earthing systems shall pass commissioning testing in accordance with
              T HR EL 99001 ST and TS 00006 before being put into service. The designer shall provide the
              commissioning test plan and the final approval of the commissioning test results to the relevant
              asset steward and O&M, to certify that the asset is fit for purpose.
              A commissioning test report is required to demonstrate that the asset is fit for purpose and all
              risks have been reduced SFAIRP. The test report shall include details of the test plan, results
              analysis and calibration certificates of all test equipment used. The test report shall be
              forwarded to the relevant asset steward and O&M.
6.5           Maintenance
              All earthing systems shall be designed and installed with consideration given to RAMS across
              the whole-of-life cycle. Consideration shall also be given to maintenance activities and TMPs.
              Where a claim of similarity cannot be made against an existing TMP then any additional or
              residual maintenance processes and frequencies shall be documented and agreed with the
              operator maintainer and submitted as supporting evidence with a request for concession.
6.6           SFAIRP
              AS 2067 was revised in 2016 to align with the SFAIRP and due diligence principles of the Work
              Health and Safety Act 2011.Duty of care (due diligence) is demonstrated when all reasonably
              practicable precautions have been taken. Refer to TS 00006 for further guidance on the
              SFAIRP process.
7             Lightning protection
              A LPS is required to protect infrastructure and assets from a lightning strike by intercepting the
              stroke current and safely dissipating the energy to earth. The earthing requirements of LPS
              systems, both above and below ground, are critical to ensure efficient operation.
7.1           General
              General requirements relating to lightning protection and requirements relating to insulation co-
              ordination can be found in T HR EL 21001 ST.
              Compliance with the requirements of this section is required for all new Traction substations and
              HV ac switching stations. All existing Traction substations and HV ac switching stations shall
              comply where modifications result in one or more of the following:
                    Note: For existing substations, modifications to the existing LPS may be required
                    subject to the extent of the modifications to the substation identified in Section 7.1 or
                    the identification of damage to the substation, see Section 7.3.
              The LPS shall be designed to reduce the risk of overvoltage surges from direct and indirect
              lighting strikes:
              •     shielding of the substation building and equipment from direct lightning strikes using an
                    LPS including lightning intercept conductors (for example, air terminals, external protective
                    conductors), down conductors and an earthing system
              •     protect substation equipment from indirect strikes and system generated overvoltage’s
                    using surge protective devices (SPD’s)
              •     installation of overhead earth wire (OHEW) on aerial lines entering or leaving substations,
                    see Section 9.2.
              The lighting intercept conductors providing shielding from direct strikes shall be designed using
              the rolling sphere method and shall meet the requirements for Lightning Protection Level 1 as
              defined in AS 1768.
              Additional guidance for the implementation of LPS against lightning strikes can be found in
              AS 1768 including the following:
              •     best practice for the design of LPS (earthing system configurations, conductor types,
                    routes and lengths)
              Where a lightning strike has resulted in damage to a substation an assessment of the LPS
              system for the installation shall be conducted. Where the existing LPS does not meet the
              requirements of Section 7.2 the LPS shall be modified to achieve compliance.
              connected to a combined HV/LV earthing system the LPS shall be interconnected and form part
              of the HV earthing system.
              Due to the high frequency nature of lightning surges an earthing system may not dissipate
              lightning surges as effectively as system generated earth faults. At critical locations a computer
              simulated lightning transient analysis (such as CDEGS) shall be done in order to ensure the
              earthing system surge impedance is adequate to effectively dissipate a lightning strike.
7.5           Documentation
              For new installations the LPS above ground components are designed as part of the power
              frequency earthing design and therefore the design process is documented as part of the power
              frequency earthing design. Where an independent lightning protection assessment or design is
              required to modify an existing installation, to reflect the detail that would otherwise be captured
              in the power frequency design documentation the following independent documentation shall be
              produced:
              •     design report with all design inputs, hazard logs, assumptions, criteria, calculations,
                    software simulation graphs and plots, compliance and reference to standards. The report
                    shall include all drawings produced for the assessment, design and construction of the LPS
                    in particular connection details to an existing LPS.
                    3.   all major equipment located outdoors (for example transformers and bays, fences,
                         lighting poles and aerial line structures)
              •     details and connections shall also be shown on drawings to enable the construction and
                    installation of the LPS. Drawings shall include a detailed parts list and comprehensive
                    construction notes.
8             Electromagnetic fields
              In accordance with the requirements of T MU AM 06006 ST all HV substations shall comply with
              AS 7722, CJC 5-1997/SAA HB101-1997, AS IEC 61000.6.5, and AS IEC 61000.6.4.
9             HV aerial lines
              This section documents the minimum requirements for earthing and lightning protection of HV
              aerial lines.
9.1           General
              An earthing design shall be done for the HV aerial line installation and associated equipment for
              each project as part of the earthing design for the overall project.
• overhead earthwire at each support structure (see Section 9.2.3 for further information)
              •     cable screens, catenary wire, and the base of surge arresters at the pole for the transition
                    of 11 kV ABC to bare aerial conductors
              •     11 kV ABC catenary wire for tension arrangements, such as arrangement 11/48 (drawing
                    number EL 0002979), where an earth down lead is installed
• steel poles.
              Additional requirements relating to the design and construction of OHEW systems for HV aerial
              lines are documented in TS 00006, T HR EL 10001 ST and AS/NZS 7000.
              Refer to T HR EL 21001 ST for requirements related to aerial line outages due to lightning
              strikes.
              For modifications to existing installations, the extent of overhead earthwire coverage may be
              reduced with justification by a cost-benefit analysis. The resultant configuration shall provide for
              the following as a minimum:
              •     all new poles for aerial lines with a nominal voltage of 33 kV and above shall be designed
                    to be suitable for overhead earthwire installation.
              Where the minimum 800 m length cannot be achieved a request for concession shall be
              submitted to AMB which includes a SFAIRP justification for the reduced length. For significant
              deviations to the minimum OHEW length (greater than 10% or one transmission line span) a
              lightning insulation coordination study shall also be provided which includes the following:
• power frequency earth system modelling to determine the impact on the earthing system.
Refer to drawings EL0013170, EL0013171, and EL0013172 for information on typical practices.
              The earth down lead shall be spaced from the surface of the pole with a nominal distance of
              275 mm by pole stand-off supports (as shown in EL0015788). The vertical distance between a
              pole stand-off support and any crossarm or insulator support shall not be less than 400 mm.
              A cable guard shall be provided for the down earth lead up to a minimum height of 2.4 m from
              ground. Non-conductive cable guards are preferred as they do not require earthing assessment
              prior to installation. Metallic cables guards may be used (subject to an earthing assessment)
              where there is an increased risk of theft, repeated malicious damage or in fire prone areas
              (although fire resistant PVC may also be used). Refer to drawing EL0284008 for further detail.
              At joint use poles the down earth lead shall be insulated or segregated from other utilities
              equipment and earthing systems to provide a minimum 2.0 m clearance between exposed
              earthing systems.
              Refer to drawings EL0017446, EL0017447, and EL0017448 for typical arrangements for the
              down earth lead, and EL0284008 for details of connection to pole earth electrodes.
              Earthing connections are not required for stay poles supporting aerial lines that do not have
              OHEW installed.
10.1          General
              The earthing system at system substations shall be a combined HV and LV earthing
              arrangement with the combined earth impedance to meet the requirements of TS 00006 but
              shall not be greater than 5Ω. There may be rare occurrences at system substations that are not
              considered HV installations such as sectioning huts where a separate HV and LV earthing
              system may be preferred. Where a separate HV and LV earthing system has been identified as
              the preferred solution, it shall be agreed with the asset steward (operator/maintainer) and a
              request for concession shall be submitted to the AMB.
• a number of items of electrical equipment with electrical protection of various clearing times
• fences with associated prospective touch voltages for people external to the substation
• fixed metal items within the substation (for example metal roofs and down pipes)
              •     all accessible exposed and continuous metal parts containing or supporting HV conductors,
                    (for example, cable trays and ladders)
• cable sheaths/screens/armouring
• transformer LV neutrals.
The following equipment shall not be connected to the combined HV and LV earthing system:
              •     1500 V dc rectifier cubicles, circuit breaker frames, and rectifier auxiliary transformers. In
                    most cases, and any future designs, this equipment shall be connected to earth through a
                    frame leakage relay
              •     Cable support systems that are not considered part of any significant fault path (for
                    example, non-continuous fixings and fittings secured to the floor to support cables).
              Where an isolating transformer is used in a system substation the case of the transformer shall
              be connected to the substation earth. This requirement is based on the necessity to earth all
              metalwork in a substation. It is not an electrical requirement with regard to isolation.
              The screen of the isolating transformer shall also be connected to the substation earth grid. The
              connection shall be sized to carry the maximum fault currents that may flow for the time required
              for the back-up protective device to operate. The minimum size of the earthing cable shall be
              16 mm2 copper.
11.1          General
              Distribution substations are located throughout the network and are often adjacent to the
              traction system. They have a relatively low fault level compared to system substations and are
              typically designed in accordance with general arrangements. The general arrangements outline
              the minimum requirements for distribution substation earthing. Refer to the following drawings
              for details of the approved padmount substation design:
• EL0455388
• EL0480394
• EL0474177.
A concession shall be submitted to the AMB for any deviation from the minimum requirements.
              This separation shall also apply to conductors connected to the electrodes unless the
              conductors are suitably insulated to at least 0.6/1 kV insulation level or the maximum earth
              potential (EPR) across the insulation whichever is greater.
              Conductors and metallic parts: Unless insulated to at least 0.6/1 kV insulation level or maximum
              EPR across the insulation whichever is greater; a clearance of not less than 35 mm shall be
              provided to any conductors or metallic parts which are connected to the HV earthing system.
• HV cable sheaths/screens/armouring
• equipotential loop.
              Equipment to be individually connected to the LV earth bar on the first main switchboard (the
              supply main switchboard) shall be as follows:
• LV earth grid
• LV SPD’s
11.3.1        General
              The primary reasons for not using a combined HV and LV earthing systems for distribution
              substations are as follows:
              •     A combined earthing system provides a relatively low earth path for dc stray current. This
                    could permit stray current to flow between the earths and cable screens at the local
                    substation and traction substation and corrode the earthing system leading to a significant
                    safety risk
              •     The difficulty in obtaining a sufficiently low earth impedance to achieve compliance with
                    safety requirements. The ac system does not have sufficient multiple earth-neutral
                    connections along its reticulated neutral as an MEN system which increases the difficulty in
                    obtains low earth impedances.
              For above ground locations a combined HV and LV earthing system may be used subject to a
              request for a concession to the AMB. Where it can be demonstrated that the SFAIRP solution
              combines the HV and LV earthing systems then the following shall be addressed:
              •     the combined earthing system shall not be adversely affected if part of the earthing system
                    is removed including temporary disconnections
              •     a stray current risk assessment shall be provided in accordance with T HR EL 12005 ST.
                    The installation of a type approved hybrid voltage limiting device (HVLD) or stray current
                    blocking device shall be considered in accordance with T HR EL 12002 GU and
                    T HR EL 12009 SP.
              Examples of existing substations that are based on this principle are the substations for the City
              and Eastern Suburbs underground railway stations. Keeping the HV and LV earthing systems
              separate to minimise traction return leakage current may not be feasible at these locations. The
              drawing for the earthing arrangement of the Eastern Suburbs Railway, EL0017051 shall be
              used for maintenance purposes only.
              In the situation where a sectioning hut is not supplied from a dedicated distribution substation,
              that is, other loads are connected to the same distribution substation as the Sectioning Hut,
              then the Sectioning hut shall be supplied through an isolating transformer located within the
              boundary of the sectioning hut. If the HV supply to the distribution substation is greater than
              11 kV, then a detailed design shall be carried out to ensure the withstand voltage of the isolating
              transformer is rated for all possible fault conditions. The screen of the isolating transformer shall
              also be connected to the sectioning hut earth grid. The connection shall be sized to carry the
              maximum fault currents that may flow for the time required for the back-up protective device to
              operate. The minimum size of the earthing cable shall be 16 mm2 copper.
12            Earthing grid
              Earth impedance shall be designed to achieve compliance with TS 00006 but not be greater
              than the earth system impedance requirements specified in this standard.
              For alkaline and acidic soils or in other situations where corrosion is likely, it may be necessary
              to oversize the electrodes or to apply other measures to give a reasonable lifetime.
              The current rating of the earthing electrode is 5 kA for one second when tested in free air with
              an ambient of 25oC without exceeding a temperature rise of 380oC. A limit of 250oC (absolute) is
              relevant for bolted connections since extreme thermal cycling can lead to loosening over time.
              Conductor ratings may be modelled or calculated in accordance with IEEE 80.
              At system substations, the minimum of four electrodes shall be installed around the perimeter of
              the substation. If more electrodes are required, then the final number and location of each
              electrode shall be subject to detail design.
              Electrodes which are connected to form an earthing grid shall be positioned with consideration
              given to mutual coupling as a result of the proximity of other connected electrodes. The
              efficiency of the current dissipation diminishes exponentially the closer the electrodes are to
              each other. Space permitting, it is ideal for the electrode spacing to be equal to or greater than
              their length.
              Earth electrodes shall be installed in suitable pits in accordance with EL0284008. Where the
              electrode is installed within the rail corridor, consideration should be given to the accessibility of
              the electrode pit. Installation of an electrode pit within a ballast area is non-ideal.
              Although deep insulated earth electrodes have been installed across the heavy rail network,
              they carry a residual risk associated with the maintenance of the insulation integrity. Where a
              deep insulated earth electrode is required to mitigate hazards relating to EPR, a concession
              shall be submitted to AMB. The concession shall demonstrate a SFAIRP argument, TMP
              process and agreement from the asset steward and O&M.
              The test electrode shall be placed where it is easily accessible and can be withdrawn without
              the need to isolate equipment in service. The test electrode shall be identified with the word
              “Test” marked on the lid.
• hydraulic crimp: two crimps with a 70 mm² die over the 75 mm of insert
              The main LV earthing conductor shall be insulated green/yellow (with 0.6/1 kV rating or to EPR
              across the insulation, whichever is greater) until connection of the first LV electrode. The LV
              earthing conductor between electrodes shall be bare copper conductor to minimise earth
              impedance. Insulated conductors may be used where a stray current risk has been identified.
              Refer to T HR EL 12005 ST and T HR EL 12002 GU for further information regarding stray
              current risk.
13            Equipment earthing
              Equipment earthing connections noted in Sections 10.2 and 11.2 that are expected to carry HV
              earth fault current shall be suitably rated for the maximum fault level at that location but shall not
              be less than 70 mm2 copper. Considerations shall also be given to thermal effects, conductor
              annealing, insulation integrity, and conductor sag.
              A redundancy level of N-1 shall be provided for earthing connections from the main earth grid to
              primary equipment such as switchgear, current/voltage transformers, power transformers and
              so on. Connections to the same infrastructure for the purpose of redundancy shall be made at
              diverse locations, that is, on opposite sides of the structure. For further information regarding
              redundancy see ENA DOC 045-2022 (EG-1).
              Earthing for equipment that is not expected to carry HV earth fault current (for example, battery
              charger, fire inspection panel) may only carry a minor percentage of fault current compared to
              main earth fault current carrying earths. Redundancy is not required for earthing connections to
              support structures and infrastructure that is not likely to represent a primary conductive path.
              Minimum requirements for earthing conductors which are provided to create an equipotential
              zone within the substation environment shall be determined by design but shall not be less than
              16 mm² copper.
              If a LV arrester is installed at a substation, the earth side shall be connected to the LV neutral.
              This is because the leads of the arrester should be kept as short as practicable and the nearest
              LV earth is at the supply main switchboard.
              Under no circumstances shall the LV arrester earth side be connected to the transformer tank
              (HV earth) otherwise failure of the HV interturn insulation may occur if there is a lightning strike
              on the HV. This can arise when a strike on the HV causes the tank potential to rise above earth,
              the LV arrester may then operate and discharge surge current through the LV winding to the LV
              earth. This can cause very high voltages to be induced in the HV winding causing its insulation
              to fail between turns. A failure of the LV arrester could also result in the tank being livened at
              240 V.
For bonding of all 1500 V dc cables at 1500 V dc structures, refer to T HR EL 12005 ST.
              The usual practice shall be to supply the auxiliary services in a substation from a transformer
              (designated auxiliary transformer) whose primary winding is supplied from one of the secondary
              windings of the 1500 V dc rectifier transformer. The case of the Auxiliary transformer shall be
              connected directly to the earth grid with a 70 mm2 copper conductor. Refer to
              T HR EL 99002 ST for additional requirements.
              In some situations, the auxiliary supply originates from a supply external to the substation, for
              example, a back-up emergency supply in a single rectifier substation. In these circumstances if
              the external supply is from the local distributor then the external supply shall be connected via
              an isolating transformer. Refer to T HR EL 12004 ST for relevant guidelines.
              Irrespective of the supply source, the neutral bar and the earth bar shall be connected together
              in the ac auxiliary supply switchboard. This shall be the only neutral earth connection in the
              system substation auxiliary supply. The size of the connecting conductor shall be based on the
              size of the active conductors from the auxiliary transformer. The earth bar shall be connected
              directly to the substation earth grid with 70 mm2 copper conductor.
              In the past, several variations of the auxiliary supply design have been used. Some of these
              variations are still in existence, but they should not be used in any new designs. In one variant
              used in traction substations the earth-neutral connection is made at the auxiliary transformer.
              This is undesirable as it can result in circulating currents at two rectifier locations where there
              are two earth-neutral connections, one at each transformer. An older method used in traction
              substations and sectioning huts used a floating three phase 220 V ac system with C phase
              connected to earth via a spark gap and an earthed screen in the auxiliary transformers.
13.5          Batteries
              All system substations require a set of batteries and battery charger to supply power for the
              control circuits of circuit breakers and supervisory control and data acquisition (SCADA)
              equipment. The dc battery system shall not be earthed. For further information relating to
              battery chargers refer to T HR EL 06001 SP and T HR EL 99002 ST.
              An approved sign, as also shown on drawing EL0003147, shall be secured to the fence directly
              above the pipe.
              Any metallic pipes within the substation boundary shall be bonded to the substation earth grid
              by a 70 mm2 copper conductor.
Nearby buried metallic pipes and services shall be assessed for compliance with AS/NZS 4853.
              •     a REC shall remain closed until manually reset on-site and typically has a SCADA
                    indication for the status only
              •     an Auto REC is a smart device that has the ability to auto reset, automatic lockouts and
                    has a SCADA indication for status and SCADA control for remote operation. For a full list of
                    I/O for the REC refer to T HR EL 11001 TI. The SCADA I/O shall conform to
                    T HR EL 11004 ST.
• 400 V instantaneously.
              Certain locations have custom REC settings (up to 120 V with time delay) to address nuisance
              operations of the REC. The any proposed REC settings that vary from this standard.
              The REC and its associated SCADA alarms are required to be commissioned prior to the
              substation being connected to the 1500 V dc traction system.
              The Auto REC has built in voltage-time characteristic curves which comply with EN 50122. The
              settings of the Auto REC shall comply with Table 6 of EN 50122-1:2011 D.C (see Table 1).
              VDLs used outside of substations have different requirements and are required to comply with
              T HR EL 12005 ST.
              At distribution substations, grading conductors are typically installed around the substation
              footprint and are not typically connected to a fence. See Section 11.1 for general arrangements.
A.1           General
              For details of general earthing arrangements refer to the following drawings:
• EL0000930
• EL0000931.
              The earth connection point on the air break switch frame is the connecting point for the earth
              conductors for the surge arrester, earthing switch, transformer tank and also connects to the
              main earthing conductor where a main earth conductor runs down the pole from an overhead
              earth wire. Where no overhead earth wire exists the earthing conductor from the air break
              switch frame becomes the main HV earth conductor.
              The air break switch operating handle shall also be connected to an equipotential mat or buried
              loop located directly below the handle.
              An equipotential mat consists of a non-slip galvanised mesh or steel plate securely fixed above
              the level of the ground to ensure that it is not inadvertently covered by the surface material.
              Although the effectiveness of the mat will not be affected by a layer of dirt, it shall still be visible
              to the operator to ensure it is in good condition. Where the ground level is sloping the operators
              mat may be installed by concreting legs, permanently attached at each corner of the mat, to a
              depth required to effect a permanent stable support (a minimum depth of 300 mm will be
              necessary).
              Alternatively, a buried equipotential loop can be made from a minimum bare 70 mm² copper
              conductor but shall not be formed from the main earthing conductor. The loop is placed around
              the pole so that an operator will stand within the loop when operating the air break switch
              handle. The conductor is typically buried between 100 mm and 150 mm below ground level with
              a diameter of 2500 mm. Where existing equipotential loops are required to be replaced these
              shall be buried 500 mm below ground.
              The equipotential mat or buried loop shall be connected to the air break switch operating
              handle.
• An ultraviolet inhibited fibreglass rod of equal mechanical strength and length to the wood
              •     A post type insulator of the same phase to earth voltage rating as the air break switch. The
                    top of the insulator should be a minimum of 2400 mm above the operating handle.
The following are the two types of earthing switches that are used:
• operating rod
                    Transformer locations connected to the 11 kV system have an earthing operating rod part
                    way up the ladder. It shall be positioned so that the operator cannot easily proceed past the
                    point without earthing the HV supply.
              The connection to the top section of the ladder should be close to the top of the ladder to
              reduce the chance of a touch voltage between the top step of the ladder and the air break
              switch frame, under fault conditions. The connection to the bottom section of the ladder should
              be connected close to the bottom of the ladder, for similar reasons, but shall be higher than the
              earthing test links otherwise the links can be short-circuited by the two earth connections of the
              ladder in the case of a folding style ladder when the ladder is in the unfolded position.
              Fibreglass ladders and other ladders made of non-conductive materials are not required to be
              connected to earth.
A.9           Signs
              All pole mounted transformer installations with a primary side voltage of 33 kV and above
              require a metal notice plate reading “Open air break switch and close earth switch before
              ascending” shall be provided at the bottom of the ladder as, unlike the 11 kV locations, there is
              no physical barrier. For signage requirements for pole mounted transformer installations (33 kV
              and above) refer to drawing EL0008409.
              •     to allow either the low voltage or high voltage earth electrodes to be disconnected from
                    their respective earthing systems for the purpose of periodical testing over the life of the
                    substation. The substation may remain on-line and a link arrangement is typically provided
                    whereby the two systems are temporarily connected. The earth electrode system to be
                    tested may then be disconnected. Both the HV and LV earthing systems are then earthed
                    by the other electrode network. This link arrangement is typically housed in an insulated
                    box (or equivalent) to protect against touch potentials between the two earth systems
              •     such that conductors or metallic parts of the LV earthing system are insulated to at least
                    0.6/1 kV insulation level
              •     to be accessible for test purposes and mounted approximately 2.7 m from ground level.
                    This height allows for clearance above the mechanical protection of the earthing
                    conductors
              Where the LV is an unearthed system then the test links are typically provided for the HV earth
              system. The HV shall be isolated when testing in this situation.
              Existing installations with metallic switchboards may make use of an insulating coating such as
              "Emerclad”. Once correctly applied to the exterior surface of the switchboard the risk of a
              dangerous touch voltage between earthing systems will be reduced to an acceptable level.
              However, an economic assessment is made of the maintainability requirements of each location
              based on local knowledge, such as the likelihood of vandalism, and compared to the option of
              replacing the board with a non-metallic enclosure.