ABSTRACT ESTIMATE
Abstract estimate for the proposed construction of a
Residential building in s no272/7M patta no
369 ,Madavaranpatti village ,Thirupathur taluk
S. Total Total
Description of work Rate Per
No. Qty. Amount
Earth work excavation in hard clay
1. soil including digging and removing 32.00 60.00 M3 640.00
the soil from the site for foundation
River sand filling in foundation
2. including conveyance of sand and 14.00 1300.00 M3 18200.00
consolidation labour charges
Place in cement concrete foundation
1:3:6 mix using hard blue granite
metals 4 mm size including cost and
3. 8.00 2200.00 M3 17600.00
conveyance of materials and labour
charges for concrete mixing
compacting curing etc
Reinforced cement concrete of
column 1:2:4 mix using hard blue
4. 10.00 400.00 M3 4000.00
including cost of conveyance of all
materials, labour charges for mixing
Brick work for the superstructure 1:6 17280.00
5. mix cement mortal including cost 12.00 1440.00 M3
and conveyance of all materials and
labour charges scaffolding etc
Reinforced cement concrete lintel 10.00 1600.00 M3 16000.00
Beam 1:2:4 Mix using hard blue
granite jally 12 mm size including
cost and conveyance of all materials,
6.
centering shuttering works, using
charges cost of steel etc.
Reinforced cement concrete roof
slab 1:2:4 mix 10 cm tk. Using HBG
jally 12 mm size including all
7 6.00 7000.00 M3 42000.00
materials conveyance, scaffolding
steel binding, centering, shuttering
concrete mixing, baring, curing etc.
Brick work for the first floor parapet
wall 1:6 mix cm using chamber
8. bricks, including cost and 4.00 5200.00 M3 20800.00
conveyance of all materials lifting
charges labour charges curing etc.
Reinforced cement structure 1:2:4
mix using hard blue granite jally 12
mm size including all kind of
9. 1.02 1075.00 M3 1096.00
materials, labour charges centering,
shuttering working curing charges
etc.
Brickwork for the tower room on the
second floor 1:6 mix cement mortar
10. 15 2000.00 M3 30000.00
work procedure as above the brick
work
Reinforced cement concrete roof
slab 1:2:4 mix using hard blue
11. 3.20 3750.00 M3 12000.00
granite jally 12 mm size rate, as
above the concrete works
Brick work of parapet wall 1:6 mix
12. 3.00 1800.00 M3 5400.00
cm using chamber bricks
13. Whethering course using 1:3 mix 230.00 17.50 F2 4025.00
brick ballast with lime over laid
onelayer of pressed tiles, pointed
with cement paste. Including cost
and conveyance of all materials and
labour charges.
Ceiling, plastering with 1:3 mix
cement mortar using slaked river
14. sand including cost and conveyance 10.00 3,00 F2 3000.00
of all materials, sea folding labour
charges.
Flooring finishing with 2x2 vertified
15. 30.00 300.00 9000.00
tiles
Joinery items are made up with first
class, well seasoned deek wood,
windows are covered with 12 mm
square rod grill designs including
16. cost and conveyance of all materials
carpenter charges, Hinges, Locks
etc.,
Door 6.00 850.00 M2 5100.00
Window 4.32 850.00 M2 3672.00
Staircase steps provide with 1:4 mix
17. cm with Brickwork plastered with 1:4 18 Nos 210.00 1 No 3780.00
mix
Electric work all are conceiliding into
the wall and roof concrete using ISI
Qty materials including cost and
18. Ls 3000.00
conveyance of materials power
correction charges etc approximate
power points.
Birla white Cement washing the
walls for ceiling two coats one coat
19. LS 12750.00
for wall using white cement (Ceiling
& wall plastering area)
Colour washing the walls two coats
20. using water proof synthetic .L S 7000.00
distember paint wall plastering only
21. Painting the doors and windows one .L S 1800.00
coat of and steel printer and two coat
of enable paints
238143.00
Say Total Amount of R s. 238000.0/-
[Rupees TWO LACKHS THIRTYEIGHT THOUSAND ONLY]