Tender Papers: Mumbai Public Works Region, Mumbai. Mumbai Public Works Circle, Mumbai
Tender Papers: Mumbai Public Works Region, Mumbai. Mumbai Public Works Circle, Mumbai
GOVERNMENT OF MAHARASHTRA
B-1
                TENDER PAPERS
                             e-Tendering System
                            FOR THE WORK OF
http://mahatenders.gov.in
                       EXECUTIVE ENGINEER
               NORTH MUMBAI PUBLIC WORKS DIVISION,
                        ANDHERI, MUMBAI.
                                                       1
                                                  INDEX
     Sr.                              DESCRIPTION                                  PAGES
     No.
                                                                             From          To
    1.       Disclaimer & General information of contract                     1            4
    2.       Brief Tender Notice                                              5            6
    3.       Detailed Tender Notice                                           7            23
    4.       Scope of work                                                    24           24
    5.       Agreement Form B-1 & Conditions of Contract.                     25           59
    6.       Schedule ‘A’                                                     60           60
    7.       Additional Conditions &Additional conditions for Materials to    61           63
             be brought by Contractor.
    8.       Integrity Pact                                                   64           71
    9.       Additional General Conditions                                    72       100
    10.      Technical Conditions & Additional Specifications.               101       119
    11.      Quality Assurance and Maintenance.                              120       120
    12.      Schedule “B” Civil Works                                        121       131
    13.      Schedule “C”, Item wise Specifications.                         132       143
    14.      Model Form of Bank Guarantee Bond for Security Deposit.,        144       146
             Guarantee Bond for Waterproofing Treatment And Anti termite
             treatment & European stone plaster
    15.      Declaration of Contractor                                       147       147
    16.      Drawings.                                                       148       148
Issued to _________________________________________________________
D ISCLAIMER
1.     Detailed Time Table for the various activities to be performed in e-tendering process by the
       Tenderer for quoting their offer is given in this Tender Document under “Tender Schedule”.
       Contractor should carefully note down the cut-off dates for the carrying out each e-tendering
       process / activity.
2.     Every effort is being made to keep the Website upto date and running smoothly 24 x 7 by the
       Government and the Service Provider. However, Government takes no responsibility, and
       will not be liable for, the website being temporarily unavailable due to any technical issue at
       any point of time.
3.     In that event Public Works Department will not be liable or responsible for any damages or
       expenses arising from any difficulty, error, imperfection or inaccuracy with this Website. It
       includes all associated services, or due to such unavailability of the Website or any part
       thereof or any contents or any associated services.
4.     Tenderers must follow the time table of e-tendering process and get their activities of e-
       tendering processes done well in advance so as to avoid any inconvenience due to
       unforeseen technical problem if any.
5.     Public Works Department will not be responsible for any incomplete activity of e-tendering
       process of the tenderer due to technical error/ failure of website and it cannot be challenged
       by way of appeal, arbitration and in the Court of Law. Contractors must get done all the e-
       tendering activities well in advance.
                                  GOVERNMENT OF MAHARASHTRA
                                   PUBLIC WORKS DEPARTMENT
Time stipulated for completion of work       : 300 Days (Including Monsoon) from the date of written order
                                             to start work, which will include the monsoon period.
2) ____________________________
3) ____________________________
                                           DETAILS OF WORK
NAME OF WORK :-         MOW to Labour Commissioner office BKC Bandra Mumbai.
(Repairs & Renovation of Toilet Block) (Gr to 3rd & 5th to 8th floor).
             The EMD applicable amount shall be paid via online mode only. (EMD Exemption Certeficate
will not be accepted) Total Security Deposit 2% (Two percent) Rs, 1,82,000/- (50% in FDR at the time of
Agreement and 50% from R.A. bills).
TENDER SCHEDULE
Cost of Tender Form                                  : Rs. 1180/- (Including GST)
Last date and time for online bid preparation and    : Refer Online schedule on portal
hash submission ( technical and financial )            http://mahatenders.gov.in
Date and time for online bid data decryption and     : Refer Online schedule on portal
Re-encryption ( technical and commercial )             http://mahatenders.gov.in
Receipt of online EMD / stamp paper of Rs.           Document Tender Fee and EMD to be paid
100/- bond Affidavit (Original) in prescribed        via online mode only (EMD Exemption
Format given in Annexure I sworn before Executive Certeficate will not be accepted)
Magistrate / Notary and Tender Document fees,&
EMD to be paid online only via Payment Gateway
mode /TDR of Additional performace Security
Deposit(if required) / Location Map of Hot Mix Plant
Name and signature of contractor / Power of Attorney holder with complete address.
                                                                        .
                pipe, waste water pipe, PVC pipe & water supply pipe line etc. at Gulistan compound, ghatkopar (W.), Mumbai.
                MOW to Gulistan Compound, Bldg. No. 'H' - Repairs to flooring, plaster, painting, WC/bath, door,
        4       window, kitchen platform, waterproofing, external plaster & painting, drainage line & vertical cast Iron, soil   Rs.14025356 /-
                pipe, waste water pipe, PVC pipe & water supply pipe line etc. at Gulistan compound, ghatkopar (W.), Mumbai.
                MOW to Gulistan Compound, Bldg. No. 'D' - Repairs to flooring, plaster, painting, WC/bath, door,
        5       window, kitchen platform, waterproofing, external plaster & painting, drainage line & vertical cast Iron, soil   Rs.9358673 /-
                pipe, waste water pipe, PVC pipe & water supply pipe line etc. at Gulistan compound, ghatkopar (W.), Mumbai.
                MOW to Gulistan Compound, Bldg. No. 'E' - Repairs to flooring, plaster, painting, WC/bath, door, window,
        6       kitchen platform, waterproofing, external plaster & painting, drainage line & vertical cast Iron, soil pipe,     Rs.9730228 /-
                waste water pipe, PVC pipe & water supply pipe line etc. at Gulistan compound, ghatkopar (W.), Mumbai.
                MOW to Gulistan Compound, Bldg. No. 'F' - Repairs to flooring, plaster, painting, WC/bath, door, window,
        7       kitchen platform, waterproofing, external plaster & painting, drainage line & vertical cast Iron, soil pipe,     Rs.9549380 /-
                waste water pipe, PVC pipe & water supply pipe line etc. at Gulistan compound, ghatkopar (W.), Mumbai.
                MOW to Gulistan Compound, Bldg. No. 'G' - Repairs to flooring, plaster, painting, WC/bath, door,
        8       window, kitchen platform, waterproofing, external plaster & painting, drainage line & vertical cast Iron, soil   Rs.9549380/-
                pipe, waste water pipe, PVC pipe & water supply pipe line etc. at Gulistan compound, ghatkopar (W.), Mumbai.
                External & Internal Repairs & Renovation Railway Police Qrts. at Gahtkopar Bldg. No. 13
        9
                                                                                                                                 Rs.11727226/-
                External & Internal Repairs & Renovation Railway Police Qrts. at Gahtkopar Bldg. No. 20
        10
                                                                                                                                 Rs.11724052/-
                MOW Providing Carrying Out Sturctural Repairs Internal/External Reparis. Bldg. No. 143
        11
                                                                                                                                 Rs.8119939 /-
                MOW Providing Carrying Out Sturctural Repairs Internal/External Reparis. Bldg. No. 142
        12
                                                                                                                                 Rs.7588680 /-
                MOW Providing Carrying Out Sturctural Repairs Internal/External Reparis. Bldg. No. 141
        13
                                                                                                                                 Rs.7588690/-
                MOW to Providing & fixing Structural Steel Work & Corrugated G.I. Sheets of Roof on Terrace, Type-V, Bldg.1 at
        14
                ESIS Hospital at Mulund, Mumbai.                                                                                 Rs. 2686700/-
15 Construction of JJ Art Hostel Building and Architecture Hostel Builidng, Kalanagar at Bandra (E) Mumbai. Rs.868910589/-
16 MOW to Renovation and Improvement of Joint Cabin Joint Director Cabin2, Law Officer, O & M Establishment, Rs.11487731/-
Note: - Any changes in the scope / conditions and any other information in the tender document will be intimated on the
same web site.
                                        GOVERNMENT OF MAHARASHTRA
Contractor                          No. of Corrections      Executive Engineer
                                              7
                                    PUBLIC WORKS DEPARTMENT
                                     INVITATION FOR TENDERS
1.1.2 The tender submitted by the tenderer shall be based on the clarification, additional facility offered (if
      any) by the Department, and this tender shall be unconditional. Conditional tenders will be summarily
      REJECTED.
1.1.3 All tenderers are cautioned that tenders containing any deviation from the contractual terms and conditions,
      specifications or other requirements and conditional tenders will be treated as non responsive. The contractor should
      clearly mention in forwarding letter that his offer (in Envelope No.1 & 2) does not contain any condition, deviations
      from terms and conditions stipulated in the tender.
1.1.4 Tenderers should have valid Class III Digital Signature Certificate (DSC) obtained from any Certifying Authorities.
      In case of requirement DSC, Interested Bidders should go to process for new application of DSC Contact to Vinayak
      Agre Mobile No : 8879002344.
1.1.5 For any assistance on the use of Electronic Tendering System, the Users may call the below Toll Free Ph. No. 3000
      3070 2232
      Mob No : 8879002344 – Vinayak Agre
      E-Mail : eproc.maharashtra@gmail.com, cppp-support@nic.in
1.2   Special Instructions to the Contractors / Bidders for the e-submission of the bids online through this tender site:
      https://mahatenders.gov.in
1.2.1 Bidder must register themselves on https://mahatenders.gov.in portal by clicking “Online Bidder
      Enrollment” and then map Digital Signature certificate.
1.2.3 Bidder then login to the site giving User id / Password chosen during registration.
1.2.4 The DSC e-token that is registered should be used by the bidder and should not be misused by others.
1.2.5 The Bidders can update well in advance, the documents such as certificates, purchase order details etc., under My
      Documents option and these can be selected as per tender requirements and then attached along with bid documents
      during bid submission.
1.2.6 After downloading / getting the tender schedules, the Bidder should go through them carefully and then submit the
      documents as asked, otherwise, the bid will be rejected.
1.2.7 If there are any clarifications, this may be obtained online through the tender site, or through the contact details. Bidder
      should take into account of the corrigendum published before submitting the bids online.
1.2.8 Bidder, in advance, should get ready the bid documents to be submitted as indicated in the tender schedule and they
      should be in PDF/XLS/RAR formats. If there is more than one document, they can be clubbed together.
1.2.9 Document Tender Fee and EMD to be paid via SBI MOPS Online Payment Gateway Mode only. and upload successful
      payment receipt in ENVELOPE NO.1 TECHNICAL BID Documents.
1.2.10 The bidder reads the terms & conditions and accepts the same to proceed further to submit the bids.
1.2.11 The bidder has to submit the tender document online well in advance before the prescribed time to avoid any delay or
       problem during the submission process.
1.2.12 After the bid submission, the acknowledgement number, given by the e-tendering system should be printed by the bidder
       and kept as a record of evidence for online submission of bid for the particular tender.
1.2.13    Document Tender Fee and EMD to be paid via SBI MOPS Online Payment Gateway Mode only. And upload
          successful payment receipt in Envelope No.1 Technical Bid Documents. and BOQ in .xls format file to Uploaded in
          ENVELOPE NO.2 FINANCIAL BID Documents.
1.2.15    The bidder may submit the bid documents either by online mode through the site
          (https://mahatenders.gov.in) as indicated in the tender.
1.2.16    The tendering system will give a successful bid updating message after uploading all the bid documents submitted &
          then a bid summary will be shown with the bid no, date & time of submission of the bid with all other relevant details.
          The documents submitted by the bidders will be digitally signed using the DSC e-token of the bidder and then
          submitted.
1.2.16    The bid summary has to be printed and kept as an acknowledgement as a token of the submission of the bid. The bid
          summary will act as a proof of bid submission for a tender floated and will also act as an entry point to participate in
          the bid opening date.
1.2.17    Bidder should log into the site well in advance for bid submission so that he submits the bid in time i.e on or before
          the bid submission end time. If there is any delay, due to other issues, bidder only is responsible.
1.2.18   The bidder should see that the bid documents submitted should be free from virus and if the documents could not be
         opened, due to virus, during tender opening, the bid is liable to be rejected.
1.2.19    The time settings fixed in the server side & displayed at the top of the tender site, will be valid for all actions of
          requesting, bid submission, bid opening etc., in the e-tender system. The bidders should follow this time during bid
          submission.
1.2.20    All the data being entered by the bidders would be encrypted using PKI encryption techniques to ensure the secrecy of
          the data. The data entered will not viewable by unauthorized persons during bid submission & not be viewable by any
          one until the time of bid opening. Overall, the submitted tender documents become readable only after the tender
          opening by the authorized individual.
1.2.21    The confidentiality of the bids is maintained since the secured Socket Layer 128 bit encryption technology is used.
          Data storage encryption of sensitive fields is done.
1.2.22    The bidders are requested to submit the bids through online eTendering System to the TIA well before the bid
          submission end date & time (as per Server System Clock).
1.2.23   The bidder should logout of the tendering system using the normal logout option available at the top right hand corner
         and not by selecting the (X) option in the browser.
1.2.24    The bidder should upload the Technical Bid in .rare format single file to upload in Technical cover and then BOQ in
          .xls format single file to Uploaded in ENVELOPE NO.2 FINANCIAL BID Documents.
1.2.25 For any other queries, the bidders are asked to contact through Mai : etender.maha@nic.in
1.4.7   Scan copy of Abstract of details of list of works in hand and works tendered for (Information to be
        given in proforma of Statement No. I on Page No.20) The Certificates Sr. No. 1.4.6 & 1.4.7 should be
        signed by the Authority with whom the contractor has executed the work not below the rank of
        Exeuctive Engineer.
1.4.8   Scan copy of undertaking /declaration of contractor that he had studied all tender documents,
         Conditions and especialy work methodology (Page no. 147).
1.4.9   Scan copy of Abstract of details of work of similar type and magnitude carried out by the contractor.
        (Information to be given in proforma of Form No. III on Page No. 21) (during last five years)
1.4.10 Scan copy of Abstract of details of Technical Personnel on the rolls of the tenderer.(Information to be
       given in proforma of Statement No. IV on Page No.22
1.4.11 (1) The contractor shall online submit scane copy of an affidavit in original (as per format
       given on Page No.23) to the tender as per tender schedule regarding completeness, correctness and
       truthfulness of documents shall be submitted in Envelope No.1. Separate Affidavit shall be
       submitted for each work in original. Affidavit shall be compulsorily Notarified. Affidavit not
       confirming to these conditions will not be accepted and Envelope No.2 will not be opened.
1.4.12 Certified copy of Registration of Partnership Deed and Power of Attorney or copy
       of Company Registration from the Competent Authority in case of a firm tendering
       for work, Power of attorney shall be submitted in original for all documents.
All the documents from Sr. No. 1.4.1 to 1.4.12 shall be correctly and completely submitted by
contractor online, otherwise his Envelope No.2 will not be opened.
                     2) The form showing the value of existing commitments and ongoing works as well as the stipulated period of
            completion period of completion remaining for each of the works listed should be countersigned by the Officer not below
            the rank of Executive Engineer and Bid capacity statement of the contractor should be got certified from the Chartered
            Accountant. Otherwise, his envelope No.2 will not be opened
            1)        Bidders Shall upload QR based Bid Capacity Certificate downloaded from link "bidcap.emahapwd.com" which
            is provided on portal of www.mahapwd.gov.in on or before two days of bid submission. If this Bid Capacity Certificate
            is not uploaded then tender shall be treated as non-responsive.
            The Bidder should also upload Turnover Details as per Chartered Accountant Certificate and Work Done Details for last
            5 years in proforma of Statement No. IX on Page No. 24)
            2)      Bidders shall fill the relevant information of Key Persons and Technical Staff available with him in the formats
            and specified on link "bidcap.emahapwd.com" of www.mahapwd.gov.in portal.
            Out of the total key persons and Technical staff available with bidder, he shall upload the staff he desires to deploy for
            this work. This statement shall be downloaded from the link "bidcap.emahapwd.com". Bidder shall upload this QR
            based statement downloaded on or before two days of submission of bid. If this certificates is not uploaded then tender
            shall be treated as non responsive.
            Bidder should also uptoad the information of list of key persons and Technical staff available with him in proforma of
            Statement No. X on Page No.25)
              All these statements shall be filled in and signed properly. If these Statements are found incomplete,
1.4.13..2
              incorrect, kept blank or wrongly filled, Contractor’s Envelope No.2 (financial bid) will not be
              opened and his offer will be summarily rejected.
              Misleading or false representations in the Statements attachments submitted in proof of the
              qualification requirements.
                                                              And/ or
              Record of poor performance such as abandoning the works, not properly completing the contract,
              inordinate delays in completion, litigation history or financial failures etc.
1.4.14        The Contractor should submit one hard copy of all the documents required to be submitted in
              Envelope No. 1 in sealed envelope, mentioning name of work. This sealed envelope should be
              addressed to The Executive Engineer, North Mumbai (P.W.) Division, Andheri, Mumbai and should
              be submitted within 72 hours of last date and time of submission of Bid in online form. This sealed
              envelope will be opened ONLY IF any technical difficulty is faced in e-tending procedure.
        a)     This Envelope shall be opened online immediately after opening of Envelope No.1, only if
        contents of Envelope No.1 are found to be acceptable to the Department. The tendered rates in
        Schedule ‘B’ or percentage above/below the estimated rates shall then be read out. in the presence of
        bidders who remain present at the time of opening of Envelope No.2.
        (i)      Earnest money of minimum Rs. 91,000/- shall be paid via online using payment gateway
                 mode. After Tender opening, the EMD of the unsuccessful bidder will be returned to account
                 provided by the bidder during the bid preparation as given in challan under Beneficiary
                 Account Number.
        (ii)     Copy of earnest money exemption certificate will not be accepted Earnest Money in the
                 form of cheques or any other form except above will not be accepted.
        (ii)     The amount will be refunded to the unsuccessful tenderers on deciding about the acceptance
                 or otherwise of the tender. In case of successful tenderer, it will be refunded on his paying
                 intial Security Deposit and completing the tender documents in form B-1.
        The successful tenderer shall have to pay half the security deposit in approved security form
        (preferably in the form of National Saving Certificate) or in cash or in the form of Bank Guarantee
        (in the form as prescribed by Government) from any Schedule Bank or Nationalized Bank and
        balance Security Deposit will be recoverable through the bills at the percentage as shown in item(s)
        of the Memorandum in printed B-1 form or as may be decided by the Executive Engineer during
        course of execution of the work looking to the position and circumstances that may prevail, whose
        orders will be final and binding on the contractor.
         The security deposit for the due performance of the contract shall be as detailed in the Tender
        Documents elsewhere. Fifty percent of the security deposit will have to be deposited within ten days
        (including Government holidays) of the acceptance of the tender and the remaining fifty percent will
        be recovered from the Running Bills at the rate as specified in the tender form, on the cost of work as
        per C.S.R. prevailing at the time of acceptance of tender. Amount of total security
        deposit to be paid shall be 2% of the cost of work, worked out as per S.S.R. 2022-23 for the
        respective District. Initial Security Deposit may be in Bank Guarantee form in format on Page 130 to
        131 of tender document for full period of completion of work and it should be extendable upto expiry
        of valid extension if any, as directed by Engineer-in-charge.
        Payments of Security Deposity By Bankl Guarantee And Online Bank Guaantee Verification :-
        if the Contractor wishesh to deposit security deposit by Bank Guarantee after tender approval then it
        is manditory for contractor to verify the bank guarantee by paying verification fees of rs. 1000 +
        GST through the link provided below
        https://onlinebg.emahapwd.com
1.9.1          If the Bidder quote his offer below by more than 1.00% of the Bid cost of the
               Department and found L-1 then the Bidder should submit Additional Performance
               Security Deposit in the form of Demand Draft/ Fixed Deposit Receipt of any
               Nationalized or Scheduled bank within 8 days after opening of Envelope No. 2. to the
               Employer as mentioned below.
1.9.2          If the Bidder quote his offer below by more than 1.00% upto 10% of the estimated cost
               put to bid then he should submit a Demand Draft or FDR amounting to 1% of the Bid
               Cost of the Employer towards Additional Performance Security.
Contractor                    No. of Corrections                    Executive Engineer
                                                       14
1.9.3            If the Bidder quote his offer below by more than 10.00% upto 15% of the estimated cost
                 put to bid then he should submit Additional Performance Security 1.00% for every
                 additional percentage beyond 10.00% but upto 15% below percentage quoted, in
                 addition to 1.00% Additional Performance Security mentioned in clause 1.10.2 above in
                 the form of Demand Draft or FDR (e.g. if the bidder quotes his offer 14.00% below the
                 estimated cost put to Bid, then he should submit 14.00% - 10.00% = 5.00% amounting of
                 cost put to Bid as total Additional Performance Security).
1.9.4     If the Bidder quote his offer below by more than 15.00% of the estimated cost put to
          tender/bid, then he should submit Additional Performance Security 2.00% for every
          additional percentage beyond 15.00% below percentage quoted, in addition to 1.00% +
          5% Additional Performance Security mentioned in clause 1.10.2 and 1.10.3 above in the
          form of Demand Draft or FDR.
1.9.5     (e.g. if the bidder quotes his offer at 19.00% below the estimated cost put to tender/bid,
          then he should submit (19%-15%)x 2 = 8% + 1% + 5% = 14.00% amounting of cost put
          to bid as Total Additional Performance Security).
1.9.6     If the Additional Performance Security required above is not submitted by the L-1
          Bidder within 8 days to the Employer, then the offer of L-2 Bidder will be considered,
          provided he is agrees to complete the work at less than the cost of L-1 Bidder.
          Note : For calculating amount of Additional Performance Security contractor’s offer
          rounded upto two decimal points shall be considered.
1.9.7     Payments of Security Deposity By Bank Guarantee And Online Bank Guaantee
          Verification :- if the Contractor wishesh to deposit security deposit by Bank Guarantee
          after tender approval then it is manditory for contractor to verify the bank guarantee by
          paying verification fees of rs. 1000 + GST through the link provided below
          https://onlinebg.emahapwd.com
      Refund of Performance Security.
1.9.8            The additional Performance Security shall be returned immediately upon satisfactory
                 completion of work; the certificate of which shall be issued by the Executive Engineer before
                 releasing the additional performance security.
       The tenders which do not fulfill the condition of the notification and the general rules and
       directions for the guidance of contractor in the agreement form or are incomplete in any
       respect are likely to be rejected without assigning any reason therefore.
1.17(a)The Tenderers shall be presumed to have carefully examined the drawings, conditions and
       specifications of the work and have fully acquainted themselves with all details of the site,
       the conditions of rock and its joints, pattern, river, weather characteristics, labour conditions
       and in general with all the necessary information and data pertaining to the work, prior to
       tendering for the work.
1.17(b)The data whatsoever supplied by the Department along with the tender documents are meant
       to serve only as guide for the tenderers while tendering and the Department accepts no
       responsibility whatsoever either for the accuracy of data or for their comprehensiveness.
1.17(c)       The quarries for extraction of metal, murum etc. provided in the sanctioned estimate are as
       per survey conducted by the Department. The Contractor should however examine these quarries and
       see whether full quantity of materials required for execution of the work strictly as per specification
       are available in these sources before quoting the rates. In case the materials are not available due to
       reasons whatsoever, the contractor will have to bring the materials from any other sources with no
       extra cost to Government. The rates quoted, should therefore be for all leads and lifts from
       wherever the materials are brought at site of work and inclusive of royalty to be paid to the Revenue
       Department by the Contractor.
1.18   POWER OF ATTORNEY :
       If the tenderers are a firm or company, they should in their forwarding letter mention the names of all
       the partners together with the name of the person who holds the power of Attorney, authorizing him
       to conduct all transactions on behalf of the body, along with the Tender as per scanned copy
       uploaded in Envelope No.1.
1.19   The tenderer may, in the forwarding letter, mention any points be may wish to make clear but the
       right is reserved to reject the same or the whole of the tenders if the same become conditional tender
       thereby.
1.20   The contractor or the firms tendering for the work shall inform the Department if they appoint their
       authorized Agent on the work.
1.21   No foreign exchange will be released by the Department for the purchase of plants and machinery for
       the work by the Contractor.
1.22   Any dues arising out of contract will be recovered from the contractor as arrears of Land Revenue, if
       not paid amicably. Moreover, recovery of Government dues from the Contractors will be effected
       from the payment due to the Contractor from any other Government works under execution with
       them.
1.23   All scanned pages of tender documents, conditions, specifications, correction slips etc. shall be
       initialed by the tenderer. The tender should bear full signature of the tenderer, or his authorized
       power of Attorney holder in case of a firm.
1.24   The Income Tax at prevailing rate including surcharge or percentage in force from time to time or at
       the rate as intimated by the competent Income Tax authority shall be deducted from bill amount
       whether measured bill, advance payment or secured advance.
1.25   The successful tenderer will be required to produce to the satisfaction of the specified concerned
       authority a valid concurrent license issued in his favour under the provisions of the Contract Labour
       (Regulation and Abolition) Act 1970 for starting the work. On failure to do so, the acceptance of the
       tender shall be liable to be withdrawn and also liable for forfeiture of the earnest money.
1.26   The tenderer shall submit the list of apprentices engaged by the Contractor under Apprentice Act.
1.27   VALIDITY PERIOD :
       The offer shall remain open for acceptance for minimum period of 60 days from the Date of opening
       of Envelope No.2 (Financial Bid) and thereafter until it is withdrawn by the contractor by notice in
       writing duly addressed to the authority opening the tender and sent by Registered Post
       Acknowledgment due. (Ref. to Sr. No 2 memorandum on Page 30 & 32 of B-1 Form Chapter)
1.28   Contractor shall submit the E-Measurements to Engineer in-charge in reference to Clause-10 of tender
       document. Bill will not be sanctioned by the Division Office, unless the contractor submits
       measurements or bill in E-Measurement book only.
1.30.1   कंत्राटदार एकमेकां विरुध्द तक्रार करत असतील अथिा हरकती (Objections) घे त असतील तर रु. 15 कोटी
         ककमतीपर्यंतच्र्या कामांसाठी मुख्र्य अविर्यंता ि रु. 15 कोटी पेक्षा जास्त ककमतीच्र्या कामासाठी विविदा स्स्िकृतीस
         सक्षम अविकारी र्यांचेकडे आिश्र्यक कागदपत्रासह संदिभ करुि विर्भ र्य घ्र्यािा. विविदा स्स्िकृ त प्राविकाऱ्र्याचा विर्भर्य
         दोन्ही बाजूस अंवतम ि बंििकारक राहील.
1.30.2   आर्थथक दे कार उघडल्र्यािंतर, विविदा प्रवक्रर्येत विविदा प्राप्त कंत्राटदारािे अथिा अन्र्य कंत्राटदारांिी खोटी/बिािट
         कागदपत्रे तांवत्रक वलफाफ्र्यास जोडू ि विविदा वमळिण्र्याचे /विविदा प्रवक्रर्येत िाग घे तल्र्याचे विदर्भिास आल्र्यास सदर
                                                            ु त कंपिी ( JV/LLP/Pvt
         कंत्राटदारास/कंत्राटदार िागीदारीस अथिा कंपिीस/संर्यक्                                                Ltd/Public
         Limited Company) संबिीत कंपिीस प्रथम 3 िर्षाचे कालाििीकरीता काळर्या र्यादीत टाकण्र्यात र्येईल ि
         Web Site िर िृत्तपत्रीर्य प्रवसध्दी देण्र्यात र्येईल. तसेच 3 िर्षे सािभजविक बांिकाम वििागाच्र्या विविदा प्रवक्रर्येत
         िाग घे ण्र्यास प्रवतबंि राहील ही अट कंपिीचा मालक/संचालक/िागीदार र्यांिा संर्यक्
                                                                                      ु त ि स्ितंत्र पर्े
         (Combined          & Several Independent liability) लागू राहील.
       1.    The contractor will have to construct shed for storing controlled and valuable materials issued to him under
             Schedule "A" of the agreement at work site, having double locking arrangement. The materials will be taken
             for use in the presence of the Departmental person. No materials will be allowed to be removed from the site
             of works.
       2.    The contractors shall also give a list of machinery in their possession and which they propose to use on the
             work in the form of form No.II
       3.    Successful contractor should produce license/attested copy of license dully attested by Gazetted officer having
             registered with Assistant Commissioner of labour asrequired as per contract labour (Regulation and abolition)
             Act 1973 and the Maharashtra Contract Labour (Regulation and Abolition) Rules 1973.
       4.    The contractor shall comply with the provision of the Apprentices Act 1961 and the rules and orders issued
             there under from time to time if he fails to do so his failure will be breach of contract and Executive Engineer
             may in his discretion cancel the contract. The contractor shall also will be liable for any pecuniary liability
             arising on account of any variation by him of the provisions of the Act.
       5.    The rates of the items in this Schedule of Rates are worked out assuming average lead for Greater Mumbai are
             for all sorts of materials as approved under Government in B & c Department (Now P.W. Department letter
             No. SRS 3870/40773-I, dated 6t' April 1972. The rates are inclusive of octroi charges of M.C.G.M./ Labour
             Cess/ Insurance/ Service Tax/ Labour Amenities/ Toll Charges etc.
       6.    Royalty charges for supply of materials : As per instructions issued vide PWD Govt. of Maharashtra
             Resolution of Revenue and Forest Department No. Gaun Khanij- 10/1009/CR-309/kh dated 11/02/2010 while
             framing the estimates, Royalty charges for the items of supply of material like the rubble, metal, crushed
             metal, soft murum/ hard murum, sand and soil shall be considered in the rate analysis of respective items @
             Rs. 70.68 per Cubic Metre (Rs. 200/- per brass) and shall be recovered.
       7.    The Contractor has to pay these charges directly to Revenue Dept. and original Challans, permission
             documents shall be produced to concerned Executive Engineer. If Contractor fails to produce these original
             documents the Royalty chargesshall be recovered from contractor bill.
       8.    The rates of cement concrete item are based on standard consumption. The mix design shall be carried out for
             concrete Grade of M-20 and above. If the consumption as per approved mix design is less than the standard
             consumption then the difference in the cost of cement shall be reduced according to mix design.
       9.    Testing Charges (0.5%) are deleted from rate analysis, hence all test shall be carried out as per frequency chart
             given by V.Q.C. Circle (Annex-A) and shall form part of tender. The payment against testing charges shall be
             reimbursed by the department to the contractor.
       10.   For Polymer concreting and polymer plaster register should be maintain at site like ghani register, clearly
             mentioning time required per batch, mix of various components with its marking.
       11.   Payment shall be made to the contractor after satisfied executed of work and as per availability of fund.
       12.   No interest shall be demanded by the contractor for delay in payment.
       13.   If the contractor go for litigation for delayed payment or demand any interest he may be debarred from
             submitting bid / tender in future
             .
                                   STATEMENT NO.I
                              (Ref Clouse No.1.4.8 Page No. 12)
                                                                                          Remarks
 No    of     ment    Amount.     of      date     of   of work    Balance     date of
 .     work   No.     (Rs.   in   comm    completio     already    work to     completi
                      lakhs)      encem   n.            done.      be          on.
                                                                   executed
                                  ent.                  (Rs. In
                                                                   (Rs.   In
                                                        lakhs)     lakhs)
  1      2      3        4          5         6           7            8          9            10
SAMPLE FORM
 Sr.      Name   of         No. of        Kind and       Capacity        Age and Present                Remarks
 No       Equipment         Units          make                         condition. Location
                                                                                   .
    1            2            3               4                 5           6         7                      8
SAMPLE FORM
Note :               1) This is only a standard form. Details are to be furnished in this format in the
                        form of type written statements which shall be Enclosed in Envelope No.1 duly
                        singed.
                        2)        List of machinery proposed to be utilized on this work but not
                        immediately available and the manner which it is procured shall be given in
                        above proforma Form No.II.
        (During last Seven years)          (2015-      (2016-       (2017-       (2018-   (2019-       2020-21        2021-22
                                             16)         17)          18)          19)      20)
Sr.     Name       Name and          Place    Agree-       Date of     Tendered       Total     Date of     Principle
No       of      Address of the       and      ment       commen-      cost (Rs.       cost     Comple-     Features
        work      organisation      Country    No.         cement      in lakhs)      work        tion      in brief.
                 for whom the                                                       done (Rs.
                 work was done                                                      in lakhs)
1         2            3              4           5             6            7          8          9             10
Note :        This is only a standard form Details are to be furnished in this format in the form of
              typewritten statements which shall be enclosed in envelop No. 1.
                                                     STATEMENT NO. IV
                                                (Ref Clouse No.1.4.11 Page No. 12)
          STATEMENT SHOWING TECHNICAL PERSONNEL AVAILABLE WITH TENDERER.
NAME OF THE CONTRACTOR :
                                                                                                                       Remarks
                             person                            field or in       similar works.       person is
                                                               office.                                working
                                                                                                      with the
                                                                                                      tenderer.
1 2 3 4 5 6 7 8
SAMPLE FORM
     Note : This is only a standard form. Details are to be furnished in this format in the form of type written
                                      statements, which shall be enclosed in Envelope No.1.
                                                     STATEMENT NO. V
                                                (Ref Clouse No.1.4.6 Page No. 12)
          STATEMENT SHOWING WORK DONE IN ALL CLASSES OF CIVIL ENGINEERING
                            CONSTRUCTION WORKS DURING LAST SEVEN YEARS.
NAME OF THE CONTRACTOR :
                                                              Amount of work done during each of last Five years                 Amount of
                                                                               (Rs. In lakhs)                                    work still
                 Amount
                                                                                                                                 remaining
                                                                                                                                              Remarks
                 put to      Agree-      Date of
Sr.       Name                                                                                                                   to be
                 Tender /    ment        commen-
No        of                                                                                                                     executed
                 Tendered    No.         cement
          work                                        2015-      2016-    2017-     2018-     2019-    2020-       2021-         2022-2023.
                 cost.
                                                       16         17       18        19        20       21          22           (Rs. In
                                                                                                                                 lakhs)
 1         2         3          4           5                                6        7        8                                     9          10
SAMPLE FORM
Grand Total :-
Note :                   This is only a standard form. Details are to be furnished in this format in the form of type
                         written statements, which shall be enclosed in Envelope No.1.
signatory to sign the contract,) hereby submit, vide this asffadavit in truth ,that I am the owner of the
envelope no.1 for the purpose of scrutiny of the contract.I hereby agree to the condition mentioned
below:-
1. I am liable for action under Indian Penal Code for submission of any false / Frudaulent
2. I am liable for action under indian penal code if durimng contract period and defect
liability period ,any false information ,false bill of purchase supporting proof of purchase
,prrof of testing submitted by my staff ,subleting company or by myself,I will be liable for
3. I am liable for action under Indian Penal Code if any paper are found false / fraudulent
duruing contract period and even after the completion of contract (Finalisation of ofgnal
bill).
                                                                                (Signature of Contractor)
                                                                                    (Seal of company)
FORM B-1
      This form will state the work to be carried out as well as the date for submitting and opening tenders,
      and the time allowed for carrying out the work, also the amount of earnest money to be deposited
      with the tender, and the amount of the security deposit to be deposited by the successful tenderer and
      the percentage, if any, to be deducted from bills. It will also state whether quarry fees, royalties and
      ground floor rents will be granted. Copies of the specifications, designs and drawings and estimated
      rates, schedule rates and any other documents required in connection with the work shall be signed
      by the Executive Engineer for the purpose of identification and shall also be open for inspection to
      contractors in the office of Executive Engineer during office hours.
      Where the works are proposed to be executed according to the specifications recommended to a
      contractor and approved by a competent authority on behalf of the Governor of Maharashtra, such
      specifications with designs and drawings shall form part of the accepted tender.
2.     In the event of the tender being submitted by a firm, it must be signed separately by each partner
       thereof, and in the event of the absence of any partner, it shall be signed on his behalf by a person
       holding a power of attorney authorizing him to do so.
2.(A)I) The contractor shall pay alongwith the tender the sum of Rs.91,000/- as and by way of earnest
       money. Earnest money shall be paid via online using payment gateway mode. The said amount of
       earnest money shall not carry any interest whatsoever.
II)    In the event of his tender being accepted, subject to the provisions of sub-clause(iii) below, the said
       amount of earnest money shall be appropriated towards the amount of security deposit payable by
       him under the General Conditions of contract.
III)   If, after submitting the tender, the contractor withdraws his offer or modifies the same, or if, after the
       acceptance of his tender the contractor fails or neglects to furnish the balance of security deposit,
       without prejudice to any other rights and powers of the Government, hereunder, or in law,
       Government shall be entitled to forfeit the full amount of the earnest money deposited by him.
IV)    In the event of the tender not being accepted, the amount of earnest money deposited by the
       contractor shall, unless it is prior thereto forfeited under the provisions of sub-clause (ii) above, be
       refunded to him on online.
3.     Receipts for payments made on account of any work, when executed by a firm, should also be signed
       by all the partners except where the contractors are described in their tender as a firm, in which case
       the receipt shall be signed in the name of the firm by one of the partners, or by some other person
       having authority to give effectual receipts for the firm.
4.     Any person who submits a tender shall fill up the usual printed form including the coloumn of the
       estimated quantities stating at what rate he is willing to undertake all items of the work. Tenders
       which propose any alteration in the work specified in the said form of invitation to tender, or in the
       time allowed for carrying out the work, or which contain any other conditions of any sort, will be
       liable for rejection. No single tender should include more than one work, but contractors who wish to
       tender for two or more works shall submit a separate tender for each. Tenderers shall have the name
       and the number of the work to which they refer written outside the envelope.
5.     The Executive Engineer, North Mumbai (P.W.) Division, Andheri, Mumbai, or his duly
       authorized assistant will open tenders in the presence of any intending contractors who may be
       present at the time and will enter the amount of the several tenders in a comparative statement in a
       suitable form. In the event of a tender being accepted, the contractor shall thereupon, for the purpose
       of identification, sign copies of the specifications and other documents mentioned in Rule 1. In the
       event of tender being rejected, the Divisional officer shall refund the amount of earnest money
       deposited by the contractor online.
6.     The officer competent to dispose of the tenders shall have the right of rejecting all or any of the
       tenders.
7.     No receipt for any payment, alleged to have been made by a contractor in regard to any matter
       relating to this tender or the contract, shall be valid and binding on Government unless it is signed by
       the Executive Engineer.
8.     The memorandum of work to be tendered for and the schedule of materials to be supplied by the
       Public Works Department and their rates shall be filled in and completed by the office of the
       Executive Engineer before the tender form is issued if a form issued to an intending tenderer has not
       been so filled in and completed, he shall request the said office to have this done this before he
       completes and delivers his tender.
9.     All work shall be measured net by standard measures and according to the rules and customs of the
       Public Works Department and their rates shall be without references to any local custom.
10.    Under no circumstances shall any contractor be entitled to claim enhanced rates for any item in this
       contract.
12.    The measurements of work will be taken according to the usual methods in use in the Public Works
       Department and no proposals to adopt alternative methods will be accepted. The Executive
       Engineer’s decision as to what is “the usual method in use in the Public Works Department” will be
       final & binding on all parties.
       (i)    The contractor shall give a list of machinery in their possession and which they propose to
       use on the work.
(i) The contractor will have to construct shed for strong materials procured by him at his own
14.    In view of the difficult position regarding the availability of foreign exchange, no foreign exchange
       would be released by the Department for the purchase of plant and machinery required for the
       execution of the work contracted for.
       (GCD/PWD/CFM/1058/62517 OF 26.5.1959)
15.    The contractor shall have to construct shed for storing controlled and valuable materials brought by
       the contractor at work site having double locking arrangement at contractor’s cost. The materials
       shall then be taken for use in the presence of the Departmental person. No material shall be allowed
       to be removed from the site of works.
16.    The contractors shall also give a list of machinery in their possession, which they propose to use on
       the work.
17.    Successful tenderer shall have to produce to the satisfaction of the accepting authority a valid and
       current     license issued in his favour under the provisions of Contract Labour (Regulation and
       Abolition) Act, 1973 before starting the work. Failing which, acceptance of the tender shall be liable
       for withdrawal and earnest money shall be forfeited to the Government (refere Government of
       Maharashtra, Irrigation and Power Department’s letter No. Lab 1076h181/(666E-17), dated
       8/9/1976.)
18.    The contractor shall comply with the provisions of Apprentices Act,1961 and the rules and orders
       issued thereunder from time to time. If he fails to do so, his failure shall be breach of the contract and
       the Chief Engineer / Superintending Engineer, may in his discretion cancel the contract. The
       contractor shall also be liable for any pecuniary liability arising on account of any violation by him
       of the provisions of the said Act.
MEMORANDUM
                                                                   F) Give schedule
                                                                   where      necessary,
                                                                   showing dates by
                                                                   which the various
                                                                   items are to be
                                                                   completed.
             2.     I/We agree that the offer shall remain open for acceptance for a
             minimum period of 60 days from the date fixed for opening of envelope
             No.2 (Financial Bid) and thereafter until it is withdrawn by me/ us by
             notice in writing duly addressed to the authority opening the tenders and
             sent by registered post A.D. or otherwise delivered at the office of such
             authority . Treasury Bank Challan No. and date or Deposit at Call Receipt
             No.___ and date ________         in respect of the sum of     Rs 91,000/-
             representing the earnest money is herewith forwarded. The amount of
             earnest money shall not bear interest and shall be liable to be forfeited to
             the Government, should I/We fail to (I) abide by the stipulation to keep
             the offer open for the period mentioned above or (II) Sign and complete the
             contract documents as required by the Engineer and furnish the security
             deposit as specified in item      (d)    of the memorandum contained in
             paragraph (1) above within the time limit laid down in clause (1) of the
             annexed General Conditions of contract. The amount of earnest money may
             be adjusted towards the security deposit or refunded to me/us if so, desired
             by me/ us in writing, unless the same or any part thereof has been forfeited
             as aforesaid.
(Occupation) ___________________________
                                    CONDITIONS OF CONTRACT
Security deposit   Clause 1 -       The person/persons whose tender may be accepted
                   (hereinafter called the Contractor, which expression shall unless
PWD. Resolution    excluded by or repugnant to the context include his heirs, executors,
No.CAT/1087/       administrators, and assigns ) shall (A) within 10 days (which may be
CR-94 Bldg 2       extended by Superintending Engineer concerned up to 15 days if
dt. 14-6-89.       Superintending Engineer thinks fit to do so) of the receipt by him of the
                   notification of the acceptance of his tender deposit with the Executive
                   Engineer in cash or Government securities endorsed to the Executive
                   Engineer (if deposited for more than 12 months) of the sum sufficient
                   which will made up the full security deposit specified in the tender or (B)
                   (Permit Government at the time of making any payment to him for work
                   done under the contract to deduct such as will amount to * Two percent
                   of all moneys so payable such deductions to be held by Government by
                   way of security deposit. ) Provided always that in the event of the
                   Contractor depositing a lump sum by way of security deposit as
                   contemplated at above, then and in such case, if the sum so deposited
                   shall not amount to Two percent of the total estimated cost of the work, it
                   shall be lawful for Government at the time of making any payment to the
                   Contractor for work done under the contract to make up the full amount
                   of Two percent by deducting sufficient sum from every such payment as
                   last aforesaid until the full amount of the security deposit is made up. All
                   compensation or other sums of money payable by the Contractor to
                   Government under the terms of his contract may be deducted from or
                   paid by the sale of sufficient part of his security deposit or from the
                   interest arising there form , or from any sums which may be due or may
                   become due by Government to the Contractor under any other contract or
                   transaction of any nature on any account whatsoever and in the event of
                   his security deposit being reduced by reason of any such deduction or
                   sale as aforesaid, the Contractor shall within ten days thereafter, make
                   good in cash or Government securities endorsed as aforesaid any sum or
                   sums which may have been deducted from, or raised by sale of his
                   security deposit or any part thereof. The security deposit referred to,
                   when paid in cash may, at the cost of the depositor, be converted into
                   interest bearing securities provided that the depositor has expressly
                   desired this in writing.
If the amount of the security deposit be paid in a lump sum within the
the Contractor for recovery of the amounts. The amount of the security
payment of the final bill, if the date up to which the Contractor has
agreed to maintain the work in good order is over. If such date is not
the payment of the final bill. The amount of security deposit retained
Compensation for   Clause 2 - “The time allowed for carrying out the work as entered in
    delay          the tender shall be strictly observed by the Contractor and shall be
                   reckoned from the date on which the order to commence the work is
                   given to the Contractor. The work shall through the stipulated period
                   of the contract be proceeded with, with all due diligence (time being
                   deemed to be the essence of the contract on the part of the
                   Contractor) and Contractor shall pay as compensation an amount
                   equal to one percent or such smaller amount as the Superintending
                   Engineer ( whose decision in writing shall be final ) may decide , of
                   the amount of the estimated cost of the whole work as shown by the
                   tender for every day that the work remains uncommenced , or
                   unfinished after the proposed dates . And further to ensure good
                   progress during execution of the work , the contractor shall be bound
                   in all cases in which the time allowed for any work exceeds one
                   month to complete.
Action when         Clause 3 :- In any case in which under any clause of this contract the
whole of security   contractor shall have rendered himself liable to pay compensation
deposit is          amounting to the whole of this security deposit (whether paid in one
forfeited.          sum or deducted by installments) or in the case of abandonment of
                    the work owing to serious illness or death of the contractor or any
                    other cause, the Engineer, on behalf of the Governor of Maharashtra,
                    shall have power to adopt any of the following courses, as he may
                    deem best suited to the interest of Government :-
                    (B) To carry out the work or any part of the work departmentally
                    debiting the contractor with the cost of the work, expenditure
                    incurred on tools and plant, and charges on additional supervisory
                    staff including the cost of work-charged establishment employed for
                    getting unexecuted part of the work completed and crediting him with
                    the value of the work done departmentally in all respects in the same
                    manner and at the same rates as if it had been carried out by the
                    contractor under the terms of his contract. The certificate of the
                    Executive Engineer as to the costs and other allied expenses so
                    incurred and as to the value of the work so done departmentally shall
                    be final and conclusive against the contractor.
                   In case the contract shall be rescinded under clause (a) above the
                   Contractor shall not be entitled to recover or be paid, any sum for any
                   work therefor actually performed by him under this contract unless
                   and until the Executive Engineer shall have certified in writing the
                   performance of such work and the amount payable to him in respect
                   thereof and he shall only be entitled to be paid the amount so certified.
                   In the event of either of the courses referred to in clause (b) or (c)
                   being adopted and the cost of work executed departmentally or
                   through a new contractor and other allied expenses exceeding the
                   value of such work credited to the Contractors, the amount of excess
                   shall be deducted from any money due to the Contractor, by
                   Government under the contract or otherwise howsoever or from his
                   security deposit or the sale proceeds thereof provided, however that
                   the Contractor shall have no claim against Government even if the
                   certified value of the work done departmentally or through a new
                   contractor exceeds the certified cost of such work and allied expenses,
                   provided always that whichever of the three courses mentioned in
                   clauses (a) , (b) or (c) is adopted by the Executive Engineer, the
                   Contractor shall have no claim to compensation for any loss sustained
                   by him by reason of his having purchased, or procured any materials,
                   or entered into any engagements or made any advances on account of,
                   or with a view to the execution of the work or the performance of the
                   contract.
Contractor            Clause 5 :- In any case in which any of the powers conferred upon
remains liable        the Executive Engineer by clause 3 and 4 hereof shall have become
to pay compensation   exercisable and the same shall not have been exercised, the non
if                    exercise thereof shall not constitute a waiving of any of the
action not taken      conditions hereof and such powers shall notwithstanding be
under                 exercisable in the event of any future case of default by the
Clause 3 & 4.         contractor for which under any clause hereof he is declared liable to
                      pay compensation amounting to the whole of his security deposit and
                      the liability of the contractor for past and future compensation shall
                      remain unaffected. In the event of the Executive Engineer taking
                      action under sub - clause (a) or (c) of clause 3, he may, if he so
                      desires, take possession of all or any tools, plant, materials and stores,
                      in or upon the works or the site thereof or belonging to the
Power to take         contractor, or procured by him and intended to be used for the
possession            execution of the work or any part thereof, paying or allowing for the
of or require         same in account at the contract rates, or in the case of contract rates
removal of            not being applicable at current market rates, to be certified by the
or sell               Executive Engineer whose certificate thereof shall be final. In the
contractor’s          alternative, the Executive Engineer may, after giving notice in
plant.                writing to the contractor or his clerk of the work, foreman or other
                      authorized agent require him to remove such tools and plants,
                      materials, or stores from the premises within a time to be specified in
                      such notice, and in the event of the contractor failing to comply with
                      any such requisition, the Executive Engineer may remove them at
                      the contractor’s expenses or sell them by auction or private sale on
                      account of the contractor and at his risk in all respects, and the
                      certificate of the Executive Engineer as to the expenses of any such
                      removal and the amount of the proceeds and expense of any such sale
                      shall be final and conclusive against the Contractor.
Final Certificate   Clause - 7 :- On the completion of the work the Contractor shall be
                    furnished with a certificate by the Executive Engineer ( hereinafter
                    called the Engineer-in-charge ) of such completion, but no such
                    certificate shall be given nor shall the work be considered to be
                    completed until the Contractor shall have remove from the premises
                    on which the work shall have been executed, all scaffolding, surplus
                    materials and rubbish and shall have cleaned off the dirt from all
                    woodwork, doors, windows, walls, floor or other parts of any
                    building in or upon which the work has been executed, or of which he
                    may have had possession for the purpose of executing the wok nor
                    until the work shall have been measured by the Engineer-in-charge or
                    where the measurements have been taken by his subordinates until
                    they have received approval of the Engineer-in-charge, the said
                    measurements being binding and conclusive against the contractor. If
                    the Contractor shall fail to comply with the requirements of this
                    clause as to the removal of scaffolding, surplus materials and rubbish
                    and the cleaning of dirt on or before the date fixed for the completion
                    of the work the Engineer-in-charge may at the expense of the
                    Contractor, remove such scaffolding, surplus materials and rubbish,
                    and dispose off the same as he thinks fit and clean off such dirt as
                    aforesaid and the Contractor shall forthwith pay the amount of all
                    expenses so incurred, but shall have no claim in respect of any such
                    scaffolding or surplus materials as aforesaid except for any sum
                    actually realized by the sale thereof.
Payment on          Clause 8 :- No payment shall be made for any work, estimated to cost
intermediate        less than Rupees One Thousand till after the whole of work shall have
certificate to be   been completed and a certificate of completion given. But in the case
regarded as         of works estimated to cost more than Rupees One Thousand, the
advances.           Contractor shall on submitting a monthly bill therefore, be entitled to
                    receive payment proportionate to the part of the work then approved
                    and passed by the Engineer - in- charge, whose certificate if such
                    approval and passing of the sum so payable shall be final and
                    conclusive against the Contractor. All such intermediate payments
                    shall be regarded as payments by way of advance against the final
                    payments only and not as payments for work actually done and
                    completed, and shall not preclude the Engineer-in-charge from
                    requiring any bad, unsound, imperfect or unskillful work to be
                    removed or taken away and reconstructed or re-erected nor shall any
                    such payment be considered as an admission of the due performance
                    of the Contract or any part thereof in any respect or the occurring of
                    any claim, nor shall it conclude, determine or affect in any other
                    way the powers of the Engineer- in-charge as to the final settlement
                    and adjustment of the accounts or otherwise, or in any other way vary
                    or affect the Contract. The final bill shall be submitted by the
                    Contractor within one month of the date fixed for the completion of
                    the work. otherwise the Engineer-in-charge's certificate of the
                    measurements and of the total amount payable for the work shall be
                    final and binding on all parties.
Payment at           Clause 9 :-The rates for several items of works estimated to cost more
reduced rates on
                     than Rs.1000/- agreed to within shall be valid only when the item
account of items
of work not          concerned is accepted as having been completed fully in accordance
accepted as
                     with the sanctioned specifications. In cases where the items of work
completed to be
at the desecration   are not accepted as so completed, the Engineer-in-charge may make
of the Engineer in
                     payment on account of such items at such reduced rates as he may
charge.
                     consider reasonable in the preparation of final or on-account bills.
               Clause 11 - The Contractor shall submit all bills on the printed forms
Bills to be on
printed form.  to be had on application at the office of the Engineer-in-charge. The
                     charges to be made in the bills shall always be entered at the rates
                     specified in the tender or in the case of any extra work ordered in
                     pursuance of these conditions and not mentioned or provided for in
                     the tender, at the rates hereinafter provided for such work.
Stores supplied   Clause 12 :- If the specification or estimate of the work provides for
by Government.    the use of any special description of material to be supplied from the
                  stores of the Public Works Department store or if it is required that
                  the contractor shall use certain stores to be provided by the Engineer-
                  in-charge (such material and stores and the prices to be charged
                  therefore as hereinafter mentioned being so far as practicable for the
                  convenience of the contractor but not so as in any way to control the
                  meaning or effect of this contract specified in the schedule or
                  memorandum hereto annexed) the contractor shall be supplied with
                  such materials and stores as may be required from time to time to be
                  used by him for the purpose of the contract only, and the value of the
                  full quantity of the materials and stores so supplied shall be set off or
                  deducted from any sums then due or thereafter to become due to the
                  contractor under the contract, or otherwise, or from the security
                  deposit, or the proceeds of the sale thereof, if the security deposit is
                  held in Government securities, the same or a sufficient portion
                  thereof shall in that case be sold for the purpose. All materials
                  supplied to the contractor shall remain the absolute property of
                  Government and shall on no account be removed from the site of the
                  work, and shall at all times be open to inspection by the Engineer-in-
                  charge. Any such materials unused and in perfectly good condition at
                  the time of completion or determination of the contract shall be
                  returned to the Public Works Departmental store, if the Engineer-in-
                  charge so requires by a notice in writing given under his hand, but
                  the contractor shall not be entitled to return any such materials except
                  with consent of the Engineer-in-charge and he shall have no claim for
                  compensation on account of any such material supplied to him as
                  aforesaid but remaining unused by him or for any wastage or damage
                  to any such materials.
Works to be       Clause 13 :- The contractor, shall execute the whole and every part
executed in       of the work in the most substantial and workman like manner, and
accordance with   both as regards materials and every other respect in strict accordance
specifications    with specifications. The contractors shall also conform exactly, fully
drawings,         and faithfully to the designs, drawings and instructions in writing
orders, etc.      relating to the work signed by the Engineer-in-charge and lodged in
                  his office and to which the contractor shall be entitled to have access
                  for the purpose of inspection at such office, or on the site of the work
                  during office hours. The contractor will be entitled to receive three
                  sets of contract drawings and working drawings as well as one
                  certified copy of the accepted tender along with the work order free
                  of cost. Further copies of the contract drawings and working
                  drawings if required by him, shall be supplied at the rate of
                  Rs.300/- per set of contract drawings and Rs.150/- per working
                  drawing except where otherwise specified.
                          The time limit for the completion of the work shall be extended in
                     the proportion that the increase in its cost occasioned by alterations or
                     additions bears to the cost of the original contract work, and the
                     certificate of the Engineer-in-charge as to such proportion shall be
                     conclusive.
                   (3) Where the Engineer requires the Contractor to suspend the work
                   for a period in excess of 30 days at any time or 60 days in the
                   aggregate the Contractor shall be entitled to apply to the Engineer
                   within 30 days of the resumption of work after such suspension for
                   payment of compensation to the extent of pecuniary loss suffered by
                   him in respect of working machinery rendered idle on the site or on
                   account of his having had to pay the salary or wages of labour
                   engaged by him during the said period of suspension, provided
                   always that the contractor shall not be entitled to any claim in respect
                   of any such working machinery, salary or wages for the first 30 days
                   whether consecutive or in the aggregate of such suspension or in
                   respect of any suspension whatsoever occasioned by unsatisfactory
                   work or any other default on his part. The decision of the Engineer in
                   this regard shall be final and conclusive against the Contractor.
OR
No claim to any      Clause 15 (A) - The Contractor shall not be entitled to claim any
payment or           compensation from Government for the loss suffered by him on
compensation for     account of delay by Government in the supply of materials entered in
alteration in or     Schedule A where such delay in caused by -
restriction of
work.                i)     Difficulties relating to the supply of railway wagons.
Notice to be         Clause 19 :- The Contractor shall give not less than five days notice
given before         in writing to the Engineer-in-charge or his subordinate in charge of
work is covered      the work before covering up or otherwise placing beyond the reach of
up.                  measurement any work in order that the same may be measured and
                     correct dimension thereof taken before the same is so covered up or
                     placed beyond the reach of measurement and shall not cover up or
                     place beyond the reach of measurement any work without the
                     consent in writing of the Engineer-in-charge or his subordinate in
                     charge of the work, and if any work shall be covered up or placed
                     beyond the reach of measurement, without such notice having been
                     given or consent obtained the same shall be uncovered at the
                     Contractors expense, and in default thereof no payment or allowance
                     shall be made for such work or for the materials with which the same
                     was executed.
Contractor liable    Clause 20 :- If during the period of 24 (Twenty Four) months from
for damage done,     the date of completion as certified by the Engineer-in-charge pursuant
and for              to clause 7 of the contract, and if in the opinion of the Executive
imperfections.       Engineer the said work is defective in any manner whatsoever, the
                     Contractor shall forthwith on receipt of notice in that behalf from the
P.W.D. Resolution    Executive Engineer, duly commence execution and completely carry
No.CAT-1087/CR-      out at his cost in every respect all the work that may be necessary for
94/Bldg.2.dt.14-6-   rectifying and setting right the defects specified therein including
89.                  dismantling and reconstruction of unsafe portions strictly in
                     accordance with and in the manner prescribed and under the
                     supervision of the Executive Engineer. In the event of the Contractor
                     failing or neglecting to commence execution of the said rectification
                     work within the period prescribed therefor in the said notice and /or to
                     complete the same as aforesaid as required by the said notice, the
                     Executive Engineer may get the same executed and carried out
                     departmentally or by any other agency at the risk, on account and at
                     the cost of the Contractor. The Contractor shall forthwith on demand
                     pay to the Government the amount of such cost, charges and expenses
                     sustained or incurred by the Government of which the certificate of
                     the Executive Engineer shall be final and binding on the Contractor.
                     Such costs, charges and expenses shall be deemed to be arrears of
                     land revenue and in the event of the Contractor failing or neglecting
                     to pay the same on demand as aforesaid without prejudice to any
                     other rights and remedies of the Government, the same may be
                     recovered from the contractor as arrears of land revenue. The
                     Government shall also be entitled to deduct the same from any
                     amount which may then be payable or which may thereafter become
                     payable by the Government to the contractor either in respect of the
                     said work or any other work whatsoever or from the amount of
                     security deposit retained by Government.
Contractor to Clause 21 :- The Contractor shall supply at his own cost all material
                           i)   be of sound material.
                          ii)   be of adequate strength having regard to the loads and strains
                                to which they will be subjected, and
                      iii)      be maintained in proper condition.
             d)      Every chain, ring, hook, shackle, swivel and pulley block used
             in hoisting or lowering materials or as a means of suspension shall be
             periodically examined.
Measure for         Clause 22 :- The Contractor shall not set fire to any standing jungle,
prevention of fire. trees, brushwood or grass without a written permit from the Executive
                    Engineer. When such permit is given, and also in all cases when
                    destroying, cut or dug up trees, brushwood, grass etc. by fire, the
                    Contractor shall take necessary measures to prevent such fire
                    spreading to or otherwise damaging surrounding property.
                   The Contractor shall make his own arrangements for drinking water
                   for the labour employed by him and provide sanitary and other
                   arrangements.
Work on Sunday       Clause 25 :- No work shall be done on a Sunday without the sanction
                     in writing of the Engineer-in-charge.
Work not to be Clause 26 :- The contract shall not be assigned or sublet without the
sublet            written approval of the Engineer-in-charge. And if the Contractor
                  shall assign or sublet his contract, or attempt to do so, or become
                  insolvent or commence any proceedings to get himself adjudicated
Contract may be and insolvent or make any composition with his creditors, or attempt
rescinded and     so to do or if bribe, gratuity, gift loan, perquisite, reward or
security deposit  advantage, pecuniary or otherwise shall either directly or indirectly be
forfeited for     given, promised or offered by the Contractor or any of his servants or
subletting it     agents to any public officer or person in the employ of Government in
without approval any way relating to his office or employment, or if any such officer
or for bribing a  or person shall become in any way directly or indirectly interested in
public officer or the contract, the Engineer-in-charge may thereupon by notice in
if contractor     writing rescind the contract, and the security deposit of the Contractor
becomes           shall thereupon stand forfeited and be absolutely at the disposal of
insolvent.        Government, and the same consequences shall ensure as if the
                  contract had been rescinded under Clause 3 thereof and in addition the
                  Contractor shall not be entitled to recover or be paid for any work
                  therefor actually performed under the contract.
Change in the        Clause 28 :- In the case of tender by partners, any change in the
constitution of      constitution of a firm shall be forthwith notified by the Contractor to
firm to be           the Engineer-in-charge for his information.
notified.
Direction    and     Clause 29 :- All works to be executed under the contract shall be
control of the       executed under the direction and subject to the approval in all respects
Superintending       of the Superintending Engineer of the Circle, for the time being, who
Engineer.            shall be entitled to direct at what point or points and in what manner
                     they are to be commenced, and from time to time carried on.
Direction    and   Clause 30 (1) :- Except where otherwise specified in the contract and
control of the     subject to the powers delegated to him by Government under the
Superintending     code, rules then in the force, the decision of the Superintending
Engineer.          Engineer of the Circle for the time being shall be final, conclusive and
                   binding on all parties of the contract upon all questions relating to the
                   meaning of the specifications, designs, drawings and instruction
                   hereinbefore mentioned and as to the quality of workmanship or
                   materials used on the work, or as to any other question, claim right,
                   matter or things whatsoever, if any way arising out of, or relating to
                   the contract, designs, drawings, specifications, estimates ,
                   instructions, orders, or other conditions, or otherwise concerning the
                   works, or the execution, or failure to execute the same, whether
                   arising during the progress of the work, or after the completion or
                   abandonment thereof.
Action where no Clause 33 :- In the case of any class of work for which there is no
specifications. such specification as is mentioned in Rule 1 of Form B-1 such work
                shall be carried out in accordance with the Divisional specifications,
                and in the event of there being no Divisional specification, then in
                such case the work shall be carried out in all respects in accordance
                with all instructions and requirements of the Engineer-in-charge .
Quarry fees and   Clause 36 :- All quarry fees, royalties, octroi dues and ground rent
royalties.        for stacking materials, if any, should be paid by the contractor.
Compensation      Clause 37 :- The Contractor shall be responsible for and shall pay
under workmen's   any compensation to his workmen payable under the Workmen's
Compensation      Compensation Act.1923 (VIII of 1923), (hereinafter call the said Act)
Act.              for injuries caused to the workmen. If such compensation is
                  payable/paid by the Government as principal under sub-section (1) of
                  Section 12 of the said Act on behalf of the Contractor, it shall be
                  recoverable by the Government from the Contractor under sub-section
                  (2) of the said section. Such Compensation shall be recovered in the
                  manner laid down in Clause 1 above.
                                        Clause 37 (A) :- The Contractor shall be responsible for and shall pay the
                                        expenses of providing medical aid to any workmen who may suffer a bodily
                                        injury as a result of an accident. If such expenses are incurred by
                                        Government the same shall be recoverable from the Contractor forthwith
                                        and be deducted without prejudice to any other remedy of the Government
                                        from any amount due or that may become due to the Contractor .
                                        Clause 37 (B) :- The Contractor shall provide all necessary personal safety
                                        equipment and first aid apparatus available for the use of the persons
                                        employed on the site and shall maintain the same in condition suitable for
                                        immediate use at any time and shall comply with the following regulations
                                        in connection therewith :-
                                        c) Adequate provision shall be made for prompt first aid treatment of all
                                        injuries likely to be sustained during the course of the work.
                                        Clause 37 (C) :- The Contractor shall duly comply with the provisions of
                                        "The Apprentices Act. 1961" (III of 1961) the rules made thereunder and
                                        the orders that may be issued from time to time under the said Act and the
                                        said Rules and on his failure or neglect to do so he shall be subjected to all
                                        the liabilities and penalties provided by the said Act and said Rules.
                                        (Govt. Circular No. CAT-6076/3336/(400)/Bldg.2 dt. 16-8-1985.)
Claim for           Clause 40 - No compensation shall be allowed for any delay caused
compensation for    in the starting of the work on account of acquisition of land or, in the
delay in starting   case of clearance works, on account of any delay in according
of work.            sanction to estimates.
Claim for           Clause 41 - No compensation shall be allowed for any delay in the
compensation for    execution of the work on account of water, standing in borrow pits or
delay in            compartments. The rates are inclusive for hard or cracked soil,
execution of        excavation in mud, sub-soil water or water standing in borrow pits
work.               and no claim for an extra rate shall be entertained unless otherwise
                    expressly specified.
Entering upon or    Clause 42 - The Contractor shall not enter upon or commence any
commencing any      portion of work except with written authority and instructions of the
portion of work.    Engineer-in-charge or his subordinate in charge of the work. Failing
                    such authority the Contractor shall have no claim to ask for
                    measurements of the payment for work.
Minimum age of      Clause 43 (i) :- No contractor shall employ any person who is under
persons             the age of 18 years.
employed, the
employment of         (ii) No contractor shall employ donkeys or other animals with
donkeys and / or         breaching of string or thin ropes. The breaching must be at least
other animals            three inches wide and should be of tape (Nawar).
and the payment
of fair wages.         (iii) No animal suffering from sores, lameness or emaciation or
                         which is immature shall be employed on the work.
                        (v)     The contractor shall pay fair and reasonable wages to the
                        workmen employed by him, in the contract undertaken by him.
                        In the event of any dispute arising between the contractor and his
                        workmen on the grounds that the wages paid are not fair and
                        reasonable, the dispute shall be referred without delay to the
                        Executive Engineer shall be conclusive and binding on the
                        contractor but such decision shall not in any way affect the
                        conditions in the contract regarding the payment to be made by
                        Government at the sanctioned tender rates.
Acceptance of       Clause 45 :- Any contractor who does not accept these conditions
conditions          shall not be allowed to tender for works.
compulsory before
tendering for work.
GST          Finance   Clause 47 :- The Contractor should quote his rate inclusive of all
Department Circular    taxes considering impact of GST etc. (Taxes, rates, cases, and are also
No GST-1017/Case
No. 81/ Karadhanl
                       inclusive of the leviable tax.).
dated 19/09/2017.
                       Clause 47 A :-
C. E. (M) / Tender /   a) The Bidder shall quote his rate considering the provisions Counted
5705.                  under GST Act 2017.
Dt. 30/11/2017.
                       b) Provisional account of GST 2% ie CGST 1% + SGST 1% will be
                       deducted at source (T.D.S.) after the enforcement of section 51 of
                       Maharashtra Goods and Service Act-2017.
                       c) Bidders shall quote his rate excluding GST.
                       d) GST shall be paid on the amount of bill of the work done as per
                       prevalling guidelines rate of GST during the period of work done as
                       applicable.
                        e) The rates quoted by the contractor shall be deemed to be inclusive
                       of the labour welfare cess and other taxes (other than GST) that the
                       contractor will have to pay for the performance of this contract. The
                       Employer will perform such duties in regard to the deduction of such
                       taxes at source as per applicable law.
Clause 56 :
Contractor shall take out necessary Insurance Policy / Policies(viz. Contractors' All Risks Insurance
Policy, Errection All RisksInsurance Policy etc. as decided by the Directorate of Insurance) so as toprovide
adequate insurance cover for execution of the awarded contract work for total contract value and complete
contract period compulsorily from the "Directorate of Insurance, Maharashtra State, Mumbai" only, Its postal
address for correspondence is "264, MHADA, First floor, Opp. Kalanagar, Bandra (E), Mumbai-400051".
(Telephone Nos.26590403 / 26590690 and Fax Nos. 26592461 / 26590403). Similarly all workmen's appointed to
complete the contract work are required to insure under workmen's compensation Insurance Policy, Insurance
Policy / Policies taken out from any Insurance Company, the same will not be accepted and the amount of
premium calculated by the Government Insurance Fund will be recovered directly from the amount payable to the
contractor for the executed contract work and paid to the Directorate of Insurance Fund, Maharashtra State,
Mumbai. The Director of Insurance reserves the right to distribute the risks of insurance among the other insurers.
(As per revised circulate issued by Dy. Directorate of Insurance Maharashtra State vide letter No. |ÉÊ´ÉÊxÉ-
2310/ºÉÉ.¤ÉÉ.Ê´É./ʴɨÉÉ ´ÉºÉÚ±ÉÒ / +ʦÉ-3 dated 8.9.2010 below mentioned percentage for insurance of contract work
shall be added in the recapitulation sheet while framing the estimate as it is not considered in the D.S.R. while
arriving at rates and the amount incurred by contractors for insurance of work shall be reimbursed on production
of documentary evidence and after checking
SCHEDULE 'A'
In figure In words
N I L
7.    The contractor will have to erect temporary shed of approved specifications for storing of above
      materials at work site at his cost having double lock arrangements (By Double lock it is meant that
      godown shall always be locked by two locks, one lock being owned and operated by Contractor and
      other by Engineer-In-charge or his authorised representative and the door shall be openable only after
      both locks are opened.)
8.    If required, the weighment of cement etc. brought by the contractor shall be carried out by the contractor
      at his own cost.
9.           The contractor shall take dated post card size colour photographs at various stages of the work , as
             directed by the Engineer in charge. And submit required nos. of soft & hard copies in separate
             album/C.D. He shall also arranges for the video shooting of important activities of the work during
             execution of items like micro concrete, terrace water proofing, polymer work
10.          The people at site shall be obedient to receive the instruction of Engineers-in-charge. No arrogance
             shall be exerted. In the event that any person not obeying instruction of departmental officers, the
             contractor shall give his substitute to run the site violence free.
12.   INDEMNITY :
      The condition regarding indemnity will apply mutatis mutandis in case of material brought by contractor
      at the site for the execution of the work being executed under this contract.
13.   In case the material brought by the contractor become surplus owing to the change in the design of the
      work, the materials should be taken back by the contractor at his own cost after prior permission of
      Engineer-In-charge.
                                         INTEGRITY PACT
              (सार्णजरनक बांधकाम रर्भाग, क्रमांक:- संकीर्ण-2016/प्र.क्र.183/इमािती-2, रि. 22/07/2019.)
                                                      Between
                   Public Works Department, Maharashtra Governement
                     having its Office at BandhkamBhawan, Fort Mumbai - 4000001.
hereinafter referred to as
and
hereinafter referred to as
"The Bidder/Contractor"
Preamble
PUBLIC WORKS DEPARTMENT intends to award, under laid-down organization procedures, contract
(s) for [Insert the name of the package]
(Signature) (Signature)
(For & On behalf of PUBLIC WORKS DEPARTMENT) (For & On behalf of Bidder / Partner(s) of
                                 Joint Venture / Contractor)
       b)       PUBLIC WORKS DEPARMENT will during the tender process treat all Bidder(s)
                with equity and fairness. PUBLIC WORKS DEPARMENT will in particular,
                before and during the tender process, provide to all Bidder(s) the same information
                through which the Bidder(s) could obtain an advantage in relation to the tender
                process or the contract execution.
       c)       PUBLIC WORKS DEPARMENT will exclude from evaluation of Bids its such
                employee(s) who has any personnel interest in the Companies/Agencies
                participating in the Bidding/Tendering process.
   (2) If Principle Secretary PWD, Maharashtra Government obtains information on the conduct of any
       employee of PUBLIC WORKS DEPARMENT which is a criminal offence under the relevant Anti-
       Corruption Laws of India, or if there be a substantive suspicion in this regard, he will inform its
       Chief Vigilance Officer and in addition can initiate disciplinary actions under its Rules.
   (1) The Bidder/Contractor commits to take all measures necessary to prevent corruption. He commits
       himself to observe the following principles during his participation in the tender process and during
       the contract execution:
(Signature) _                         (Signature) _
(For & On behalf of PUBLIC WORKS DEPARTMENT) (For & On behalf of Bidder / Partner(s) of
Joint Venture / Contractor)
       a)     The Bidder/Contractor will not, directly or through any other person or firm, offer,
              promise or give to PUBLIC WORKS DEPARMENT, Or to any of PUBLIC
              WORKS DEPARMENT's employees involved in the tender process or the
              execution of the contract or to any third person any material or other benefit which
              he/she is not legally entitled to, in order to obtain in exchange an advantage during
              the tender process or the execution of the contract.
       b)     The Bidder/Contractor will not enter into any illegal agreement or understanding,
              whether formal or informal with other Bidder/Contractors. This applies in
              particular to prices, specifications, certifications, subsidiary contracts, submission
              or non-submission of bids or actions to restrict competitiveness or to introduce
              cartelization in the bidding process.
       c)     The Bidder/Contractor will not commit any criminal offence under the relevant
              Anti-corruption Laws of India; further, the Bidder/Contractor will not use for
              illegitimate purposes or for purposes of restrictive competition or personal gain, or
              pass on to others, any information provided by PUBLIC WORKS DEPARMENT
              as part of the business relationship, regarding plans, technical proposals and
              business details, including information contained or transmitted electronically.
       d)     The Bidder/Contractor of foreign origin shall disclose the name and address of the
              Agents/representatives in India, if any, involved directly or indirectly in the
              Bidding. Similarly, the Bidder/Contractor of Indian Nationality shall furnish the
              name and address of the foreign principals, if any, involved directly or indirectly in
              the Bidding.
       e)     The Bidder/Contractor will, when presenting his bed, disclose any and all
              payments he has made, or committed to or intends to make to agents, brokers or
              any other intermediaries in connection with the award of the contract and / or with
              the execution of the contract.
   2) The Bidder/Contractor will not instigate third persons to commit offences outlined above or be an
      accessory to such offences.
(Signature) _                         (Signature) _
(For & On behalf of PUBLIC WORKS DEPARTMENT) (For & On behalf of Bidder / Partner(s) of
Joint Venture / Contractor)
Section III- Disqualification from tender process and exclusion from future contracts.
       1)      If the Bidder, before contract award, has committed a serious transgression through
               a violation of Section II or in any other form such as to put his reliability or
               credibility as Bidder into question, PUBLIC WORKS DEPARMENT may
               disqualify the Bidder from the tender process or terminate the contract, if already
               signed, for such reason.
       (3)     If the Bidder/Contractor can prove that he has restored/recouped the damage
               caused by him and has installed a suitable corruption prevention system, PUBLIC
               WORKS DEPARMENT may revoke the exclusion prematurely.
       (1)     If PUBLIC WORKS DEPARMENT has disqualified the Bidder from the tender
               process prior to the award under Section III, PUBLIC WORKS DEPARMENT
               may forfeit the Bid Guarantee under the Bid.
       (2)     If PUBLIC WORKS DEPARMENT has terminated the contract under Section III,
               PUBLIC WORKS DEPARMENT may forfeit the Contract Performance
               Guarantee of this contract besides resorting to other remedies under the contract.
       (1)     The Bidder shall declare in his Bid that no previous transgressions occurred in the
               last 3 years with any other Public Sector Undertaking or Government Department
               that could justify his exclusion from the tender process.
(Signature) _                         (Signature) _
(For & On behalf of PUBLIC WORKS DEPARTMENT) (For & On behalf of Bidder / Partner(s) of
Joint Venture / Contractor)
       (2)     If the Bidder makes incorrect statement on this subject, he can be disqualified from
               the tender process or the contract, if already awarded, can be terminated for such
               reason.
       (1)     PUBLIC WORKS DEPARMENT will enter into agreements with identical
               conditions as this one with all Bidders.
       (2)     PUBLIC WORKS DEPARMENT will disqualify from the tender process any
               bidder who does not sign this Pact or violate its provisions.
       (2)     The IEM is to review independently and objectively, whether and to what extent
               the parties comply with the obligations under this agreement. He has right of
               access to all project documentation. The IEM may examine any complaint
               received by him and submit a report to Principle Secretary PWD, Maharashtra
               Government, PUBLIC WORKS DEPARMENT, at the earliest. He may also
               submit a report directly to the CVO and the CVC, in case of suspicion of serious
               irregularities attracting the provisions of the PC Act. However, for ensuring the
               desired transparency and objectivity in dealing with the complaint arising out of
               any tendering process, the matter shall be referred to the full panel of IEMs, who
               would examine the records, conduct the investigations and submit report to
               Principle Secretary PWD, Maharashtra Government, PUBLIC WORKS
               DEPARMENT, giving joint findings.
(Signature) _                         (Signature) _
(For & On behalf of PUBLIC WORKS DEPARTMENT) (For & On behalf of Bidder / Partner(s) of
Joint Venture / Contractor)
(3)    The IEM is not subject to instructions by the representative of the parties and performs his
       functions neutrally and independently. He reports to the Principle Secretary PWD,
       Maharashtra Government, PUBLIC WORKS DEPARTMENT.
(4)    The Bidder(s)/Contractor(s) accepts that the IEM has the right to access without restriction
       to all documentation of PUBLIC WORKS DEPARTMENT related to this contract
       including that provided by the Contractor/Bidder. The Bidder/Contractor will also grant
       the IEM, upon his request and demonstration of a valid interest, unrestricted and
       unconditional access to his documentation. the same is applicable to Subcontractors. The
       IEM is under contractual obligation to treat the information and documents of the
       Bidder(s)/Contractor(s)/Subcontractor(s) with confidentiality.
(5)    PUBLIC WORKS DEPARTMENT will provide to the IEM information as sought by him
       which could have an impact on the contractual relations between PUBLIC WORKS
       DEPARTMENT and the Bidder/Contractor related to this contract.
(6)    As soon as the IEM notices, or believes to notice, a violation of this agreement, he will so
       inform the Principle Secretary PWD, Maharashtra Government, PUBLIC WORKS
       DEPARTMENTand request the Principle Secretary PWD, Maharashtra Government,
       PUBLIC WORKS DEPARTMENT to discontinue or take corrective action, or to take
       relevant action. The IEM can in this regard submit non-binding recommendations. Beyond
       this, the IEM has no right to demand from the parties that they act in a specific manner,
       from action or tolerate action. However, the IEM shall give an opportunity to PUBLIC
       WORKS DEPARTMENT and the Bidder/Contractor, as deemed fit, to present its case
       before making its recommendations to PUBLIC WORKS DEPARTMENT.
(7)    The IEM will submit a written report to the Principle Secretary PWD, Maharashtra
       Government, PUBLIC WORKS DEPARTMENT within 8 to 10 weeks from the date of
       reference or intimation to him by PUBLIC WORKS DEPARTMENT and, should the
       occasion arise, submit proposals for correcting problematic situations.
(8)    If the IEM reported to the Principle Secretary PWD, Maharashtra Government, PUBLIC
       WORKS DEPARTMENT, a substantiated suspicion of an offence under relevant Anti-
       Corruption Laws of India, and the Principle Secretary PWD, Maharashtra Government,
       PUBLIC WORKS DEPARTMENT has not, within the reasonable time taken visible
       action to proceed against such offence or reported it to the CVO, the Monitor may also
       transmit this information directly to CVC, Government of India.
(Signature) _                         (Signature) _
(For & On behalf of PUBLIC WORKS DEPARTMENT) (For & On behalf of Bidder / Partner(s) of
Joint Venture / Contractor)
(9) The word ‘IEM’ would include both singular and plural.
(*)          This Section shall be applicable for only those package wherein the IEMs have been
             identified in Section – I : Invitation for Bids and/or Clause ITB 9.3 in Section – III: Bid
             Data Sheets of Conditions of Contract, Volume-I of the Bidding Documents.
This Pact begins when both parties have legally signed it. It expires for the Contractor after the
closure of the contract and for all other Bidder’s six month after the contract has been awarded.
              # CVO shall be applicable for packages wherein IEM are not identified in
              Section IFB/BDS of Condition of Contract, Volume-I. IEM shall be
              applicable for packages wherein IEM are identified in Section IFB/BDS of
              Condition of Contract, Volume-I.
(Signature) _                            (Signature) _
(For & On behalf of PUBLIC WORKS DEPARTMENT) (For & On behalf of Bidder / Partner(s) of
                                 Joint Venture / Contractor)
          (6)           Should one or several provisions of this agreement turn out to be invalid,
                        the remainder of this agreement remains valid. In this case, the parties will
                        strive to come to an agreement to their original intentions.
    (Signature)                                                   (Signature)
    (For & On behalf of the PUBLIC WORKS                          (For & On behalf of the Bidder/ Partner(s) of
    DEPARTMENT)                                                   Joint Venture/ Contractor)
Name: Name:
Designation: Designation:
Witness 1: Witness 1:
----------------------------------------------------------- -----------------------------------------------------------
----------------------------------------------------------- -----------------------------------------------------------
Witness 1: Witness 1:
----------------------------------------------------------- -----------------------------------------------------------
----------------------------------------------------------- -----------------------------------------------------------
1.     COMPETANCY OF TENDER :
       The work will be awarded only to those contractors who are considered to be substantially
       responsive bidders, capable of performing the class of work to be completed. Before passing the
       final award any or all bidders may have to show that they have the necessary experience, facilities,
       ability and financial resources to execute the work in satisfactory manner and also within the
       stipulated time.
2.     PAYMENTS :
      a) RUNNING BILLS
       Two payments in a month will be granted by the Engineer in charge if the progress is satisfactory.
       Contractor should submit bills to the Engineer –in- charge in appropriate forms.
      b) FINAL BILL
       The contractor should submit final bill withen one monthafter complition of the workand the bill
       will be paid withen 5 months if it is in order. Dispute items and claims if any shall be excluded
       from the final billand settled separately later on.
     c) Additional Condition about availability of funds
       The payments of bill will be made as per the availibity of the funds. No claims will be entertained
       for delayed payments” “ If situation arises, the work will be stopped at safe stage and will be
       withdrawn under Clause 15 for which no compensation will be allowed.”
3.     ERASER :
       Persons tendering are informed that no erasers of any alterations by them in the text of the
       documents set herewith will be allowed and any such eraser or an alteration will be disregarded. If
       there is any error in writing, no overwriting should be done but the wrong words or figures should
       be struck out and the correct one written above or near it in an unambiguous way. Such correction
       should be initialed and dated.
4.     ACCEPTANCE :
       Intimation of acceptance of tender will be given by a telegram or a letter sent by Registered Post to
       the address given below the signature of the tenderer in the tenders. The tenders which do not
       fulfill any of the above conditions or those in the form and which are incomplete in any respect
       shall be liable for rejection.
i)        No live electric lines should be allowed to run along the ground in the blasting zone and they
          should be at least about 10 ft. above ground if not more.
ii)       The wiring cable should not be taken near the live electric line and it should be preferably shot
          firing cable as supplied by the supplier of explosives. If such a cable is not available a substitute
          cable recommended by the explosive suppliers should only be used. Under no circumstances
          should cable made up of several pieces jointed and tapped be used.
iii)      The blasting shed from where the exploder is to finally operated should be at least 150 metre away
          from the area to be blasted. It should have a strong roof which can with stand the impact of flying
          stones at this range.
iv) Only trained hands should be allowed to handle explosives, cable detonators etc.
          If he shall have any doubt as to the meaning of any portion of these general conditions or the
          special condition, to the scope of working of the specifications and drawings or any other matter
          concerning the contract, he shall in good time, before submitting his tender, set forth the particulars
          thereof and submit them to the Engineer in writing in order that such doubts may be clarified
          authoritatively before tendering.     Once a tender is submitted, the matter will be decided in
          accordance with tender conditions in the absence of such authentic pre-clarification.
6.2       ERROR, OMISSIONS AND DISCREPANCIES :
       (A) In case of errors, omissions and /or disagreement between written and scaled dimensions in the
          drawing or between the drawings and specifications etc., the following order of preference shall
          apply.
       (I)     Between actual scaled and written dimensions or descriptions on a drawing, the latter shall
               be adopted.
       (II)    Between the written or shown description of dimensions in the drawing and corresponding
               one in the specifications, the latter shall apply.
       (III)   Between the quantities shown in schedule of quantities and those arrived at from the
               drawings, the latter shall be preferred.
(B)    In all cases of omission and / or doubts of discrepancies in the dimensions or description of any
       item or specifications, a reference shall be made to the Engineer, whose elucidation, elaboration or
       decision shall be considered as authentic. The contractor shall be held responsible for any errors
       that may occur in the work through lack of such reference and precaution.
       PROGRESS SCHEDULE
(b)    The Contractor shall furnish within the period stipulated in writing by the Engineer-in-charge of the
       order to start the work, progress schedule using PERT/CPM technique in quadruplicate indicating
       the date of actual start, the monthly progress expected to be achieved and anticipated completion
       date of each major item of work to be done by him, also indicating and setting up materials, plants
       and machinery. The schedule is to be such as is practicable of achievement towards the completion
       of the whole work in the time limit and of the particular items, if any on the due date specified in
Contractor                  No. of Corrections                       Executive Engineer
                                           75
       the contract and shall have the approval of the Engineer-in-charge. No revised schedule shall be
       operative without such acceptance in writing. The Engineer is further empowered to ask for more
       detailed schedule or schedules in weekly form, for any item or items, in any case of urgency of
       work as will be directed by him and the contractor shall supply the same as and when asked for.
(c)    The Contractor shall employ sufficient plant, equipment and labour as may be necessary to
       maintain the progress schedule. The working and shift hours restricted to one shift a day for
       operations to be done under the Government supervision shall be such as may be approved by the
       Engineer-in-charge. They shall not be varied without the prior approval of the Engineer. Night
       work requiring supervision shall not be permitted expect when specifically allowed by Engineer on
       each item, if requested by Contractor. The Contractor shall provide necessary lighting arrangements
       etc. for night work as directed by the Engineer without extra cost to Government.
       Further, the contractor shall submit the progress of work in prescribed forms and charts etc. at
       periodical intervals, as may be specified by the Engineer-in-charge. Schedule shall be in the form of
       progress charts, forms, progress statement and/or reports as may be approved by the Engineer. The
       contractor shall maintain proforma, charts, details regarding machinery, equipment, labour,
       materials, personnel etc. as may be specified by the Engineer and submit periodical returns thereof
       as may be specified by the Engineer-in-charge.
6.5     QUARRIES :
6.5.1   The Contractor (s) shall have to arrange himself / themselves to procure the quarry. However
        necessary assistance without any extra cost to Government will be rendered by the Department for
        procuring the quarries if required by the Contractor.
6.5.2   The quarrying operation shall be carried out by the Contractor with proper equipment such as
        compressor, jack-hammers, drill bits, explosives etc. and sufficient numbers of workmen shall be
        employed so as to get the required out-turn.
6.5.3   The Contractor shall carry out the works in the quarries in conformity with all the rules and
        regulations already laid down or that may be laid down from time to time by the Government .
        Any cost incurred by the Government due to noncompliance of any rules or regulations or due to
        damages by the Contractor shall be the responsibility of the Contractor. The Engineer-in-charge or
        his representative shall be given full facility by the Contractor for inspection at all times of the
        working of the quarry, records maintained, the stocks of the explosives and detonators etc. So as to
        enable him to check that the working records and storage are all in accordance with the relevant
        rules. The Engineer-in-charge or his representative shall at any times be allowed to inspect the
        work, building and equipment at the quarters.
6.5.4   The Contractor shall maintain at his own cost the books, registers etc. required to be maintained
        under the relevant rules and regulations and as directed by the Engineer-in-charge. These books
        shall be open for inspection at all times by the Engineer-in-charge or his representative and the
        Contractor shall furnish the copies or extract of books or registers as and when required.
6.5.5   All quarrying operations shall be carried out by the Contractor in organized and expeditious
        manner, systematically and with proper planning. The Contractor shall engage licensed blasters
        and adopt electric blasting and / or any other approved method which would ensure complete safety
        to all the men engaged in the quarry and its surroundings. The Contractor shall himself provide
        suitable magazines and arrange to procure and store explosives etc. as required under the rules at
        his own cost. The designs and the location of the magazine shall be got approved in advance from
        the Chief Inspector of Explosives and the Rules and Regulations in this connection as laid down by
        the Chief Inspector of Explosives from time to time shall be strictly adhered to by the Contractor. It
        is generally experienced that it takes time to obtain the necessary license for blasting and license for
        storage of materials from the concerned authorities. The Contractor must therefore, take timely
        advance action for procuring all such licenses so that the work progress may not be hampered.
      6.5.6   The approaches to the quarrying place from the existing public roads shall have to be arranged by
              the Contractor at his own cost and the approaches shall be maintained by the Contractor at his own
              cost till the work is over.
      6.5.7   The Quarrying operations shall be carried out by the Contractor to the entire satisfaction of the
              Engineer-in-charge and the development of the quarry shall be made efficiently so as to avoid
              wastage of stones. Only such stones as are of the required quality shall be used on the work. Any
              stone which is in the opinion of the Engineer-in-charge, not in accordance with the specifications or
              of required quality will be rejected at any time, at the quarry or at the site of work. The rejected
              stones shall not be used on the work and such rejected materials shall be removed to the place
              shown at the Contractor's cost.
 i.           Since all stones quarried from Government quarry (if made available) by the Contractor including
              the excavated over burden are the property of the Government , no stones or earth shall be supplied
              by Contractor to any other agencies or works and are not allowed to be taken away for any other
              works. All such surplus quarried materials not required for work under this contract shall be the
              property of the Government and shall be handed over by the Contractor to the Government free of
              cost at the quarry site duly heaped at the spots indicated by the Engineer-in-charge .
ii.           Quarrying permission will have to be directly obtained by the Contractor, from the Collector of the
              District concerned for which purpose the Department will render necessary assistance. All quarry
              fees, royalty charges, Octroi duties, ground rent for staking material etc. if any to be paid, shall be
              paid directly by the contractor as per prevailing rules in force.
      6.5.10 The Contractor will be permitted to erect structures such as stores, office, huts for the labours at his
              own risk and cost at the quarry site, if suitable vacant space in Government area is available for the
              purpose at places approved by the Engineer-in-charge . On completion of the work the Contractor
              shall remove all the structures erected by him and restore the site to its original condition.
      6.5.11 The Contractor shall not use any land in the quarry for cultivation or for any other purpose except,
              that required for breaking or stacking or transporting stones.
      6.5.12 Royalty charges for supply of materials like the rubble, metal crushed metal, soft murum / hard
              murum, sand and soil shall be recovered @ Rs.70.68 per Cubic Metre (Rs.200/- per brass)or as
              per revised rates by Government during course of execution.
      6.5.13 The Contractor has to pay these charges directly to Revenue Dept. and original Challans,
              permission documents shall be produced to Engineer. in charge If Contractor fails to produce these
              original documents the Royalty charges shall be recovered from contractor bill.
      6.5.14 As Royalty charges already paid by the quarry owner, the Royalty charges for the
              bricks (as it is factory product)
      (I)      Where suitable and approved P.W. Department's quarries exist the Contractor or piece worker
      will be allowed if otherwise there is no objection to obtain the materials to the extent required for the
      work from the quarry. He will be, however, liable to pay compensation, if any damage caused to the
      quarry either deliberately or through negligence or for wastage of materials by himself or his staff or
      labour. The Contractor shall pay necessary royalty in advance and claim refund according to rules,
      if admissible and shall submit detailed accounts of materials quarried as directed.
1) Where no suitable P.W. Department's quarries exist or when the quantity of the material required
      cannot be obtained from a P.W. Department quarry, the Contractor or piece worker shall make his own
      arrangements to obtain the material from existing or a new quarry in Government waste land, private
      land or land belonging to other States or Talukas etc. After opening the quarry but before starting
      collection, the quarry shall be got approved from the Engineer-in-charge or his representatives. The
      Contractor or piece worker shall pay all royally charges, compensation etc. No claims or responsibility
      on account of any of obstructions caused to execution of the work by difficulties arising out of private
      owners of the land will be entertained.
2) The rates in the tender, include all incidental charges such as opening of a new quarry, opening out a
      new portion in an existing quarry, removing top soil and the unsuitable material, dewatering, quarry,
      cost of blasting powder and fuse, lift and lead, repairs to existing cart tracks, making new cart tracks,
      control charges, Central/State Government or Municipal Taxes, etc
(IV)        The rates in the tender are for the delivery of the approved material on road side, properly stacked
            at the places specified by the Engineer-in-charge and are inclusive of conveyance charges in respect
            of the leads and lifts. No claims on account of changes in lead will be entertained.
(V)         No material shall be removed from the land within the road boundary or from the land touching it
            without the written permission of the Engineer-in-charge or his authorised agent. If any material is
            unauthorisely obtained from such places, the Contractor or piece worker shall have to make good
            the damages and pay such compensation, in addition as may be decided by the Executive Engineer
            and will have to stop further collection.
       (VI)   Any material that falls on any P.W.D. Road from the cart etc. during conveyance shall be
       immediately picked up and removed by the Contractor or piece worker, failing which it will be got
       removed departmentally at his cost. No heap shall be left prior to stacking even temporarily on the
       road surface or in any way so as to cause any obstruction or danger to the traffic. The Contractor or
       the piece worker shall be liable to pay for any claims of compensation etc. arising out of any
       accident, etc.   Any such materials causing obstruction or danger etc. will be got removed
       departmentally at his cost and no claim for any loss or damage to the material, thus removed will be
       entertained. The Contractor shall also be responsible for the damage or accident etc. arising out of
       any material that falls on the road or track, not in charge of the Department and shall attend to any
       complaints which may be received.
(VII) The materials shall not be stacked in place where it is liable to be damaged or lost due to traffic
       passing over it, to be washed away by rain or floods, to be buried under the land slides etc. or the
       slip down an embankment or hill side etc. No claims for any loss due to these and similar causes
       will be entertained.
(VIII) Before stacking, the materials shall be free from all earth, rubbish, vegetable matter and other
       extraneous substance and in the case of metal, screened to gauge if so directed when ready. It shall
       be stacked entirely clear of the road way on ground which has been cleaned of vegetation and
       levelled. On high banks, ghat roads etc. where it may not be practicable to stack it entirely clear of
       the roadway, it may be stacked with the permission of the Engineer-in-charge on terms in such a
       way as to cause minimum danger and obstruction to the traffic or as may be directed by him.
(IX)   The size of the stack of the materials other than rubble shall be 3 x 1.5 x 0.60 metre or such
       other size as may be directed by the Engineer-in-charge and all but one stack in 200 metres
       shall be of the same uniform size and shall be uniformly distributed over whole lengths.
       One stack (at the end) in each 200 metres may be of length different from the rest in order
       to adjust total quantity to be required but its width and height will be the same as those of
       the rest.
(X)    The Engineer in charge or his authorised representative shall supply the Contractor with
       statement showing 200 metres wise quantities that will be required and the order in which
       the collection is to be done. No materials in excess of requirements in that 200 metres shall
       be stacked. Any excess quantity shall be removed at the expense of the Contractor or piece
       worker to where it is required before the material in that 200 metres is finally measured.
(XI)   All materials shall be examined and measured before it is spread. The labour for
       measurements ( and check measurements wherever carried out ) shall be supplied by the
       Contractor or piece worker. Immediately after the measurements are recorded, the stacks
       shall be marked by the contractor or piece worker by white wash or otherwise as may be
       directed by the Executive Engineer to prevent from any possibility of the same material
       being measured and recorded over again and to prevent any unauthorized tampering with
       the stacks. If the contractor or the piece worker fails to attend the measurements of
       materials after receiving the notice from the Sub Divisional Officer or his subordinate
       stating date and time of the intention to measure the work, the same shall be measured
       nevertheless and no complaint in this respect will be entertained later-on. If the contractor
       or piece worker fails to supply sufficient labour or the materials required at the time
       measurements or check measurements, after due notice has been given to him, the expenses
       incurred on account of employing departmental labour or material etc. shall be charged
       against his account.
6.7    AGENT AND WORK ORDER BOOKS :-
       The contractor shall himself engaged an authorised all time agent on the work capable of managing
       and guiding the work and understand the specifications and contract condition. A qualified and
       experienced, Engineer shall be employed by the contractor as his agent for technical matters in case
       the Engineer-in-charge considers this as essential for the work and so directs contractors. He will
       take orders as will be given by the Executive Engineer or his representative and shall be responsible
       for carrying them out.
       This agent shall not be changed without prior intimation to the Executive Engineer and his
       representative on the work site. The Engineer-in-charge have the unquestionable right to ask for
       change in the quality and strength of contractor’s supervisory staff and to order removal from work
       of any of such staff. The contractor shall comply with such orders and effect replacements to the
       satisfaction of the Engineer-in-charge.
                  A work order book shall be maintained on site and it shall be the property of the
       Government and the contractor shall promptly sign orders given therein by the Executive Engineer
       or his representative and his superior officers and comply with them. The compliance shall be
       reported by the Contractor to the Engineer in good time so that it can be checked. The blank work
       order with machine numbered pages will be provided by the Department free of charge for this
       purpose. The contractor will be allowed to copy out instructions therein from time to time.
       The order issued by the Government in P.W. Department from time to time regarding Construction
       procedure shall be binding on the contractor in addition to the specifications contained in P.W.D.
       hand book Volume I and II and book of standard specification of P.W. Department and the
       specifications enumerated above.
       The Engineer on a written request by Contractor will, if in his opinion the request is reasonable and
       in the interest of work and its progress, assist the Contractor in securing, the priorities for
       deliveries, transport, permits for controlled materials etc. where such are needed. The Department
       will not however be responsible for the non-availability of such facilities or delays on this behalf
       and no claims on account of such failure of delays shall be allowed by the Department.
       The Contractor shall have to make his own arrangement for machinery required for the work.
       However if the same is conveniently available with the Department it may be spared as per the
       rules in force on recovery of necessary Security Deposit and rent at the rate approved from time to
       time by the independent agreement to this contract and the supply or non supply of machinery shall
       not form a ground for any claim or extension of time for this work.
i)     All materials to be used on work, such as cement, lime, aggregates, stone, asphalt, etc. shall be got
       approved in advance from the Engineer-in-charge and shall pass the tests and analysis required by
       him, which will be :
       a) As specified in the specifications of the items concerned and / or
       b) Red book
       c) As specified by the Indian Road Congress Standard Specification and code of practice for Road
       and Bridges or
       d) I.S.I. Specifications (whichever and wherever applicable ) or
       e) As per M.O.R.T. & H specifications for Roads and Bridges latest edition Section 900 quality
       control for road work.
       f) Such recognized specifications acceptable to the Engineer-in-charge as equivalent there to or in
       the absence of such authorised specifications
       g) Such requirements test and/or analysis as may be specified by the Engineer-in-charge in the
       order of procedure given above.
ii)    The Contractor shall at his risk and cost make all arrangement and/or shall provide for all such
       facilities as the Engineer-in-charge may require for collecting, preparing required number of
       samples for test or analysis at such time and to such places as may be directed by Engineer and bear
       all such charges, such samples shall also be deposited with Engineer-in-charge.
iii)   The Contractor shall as and when required submit at his cost the samples of materials to be tested
       or analyzed and if, so directed, shall not make use of or incorporate in the work any material
       represented by the samples until the required test or analysis have been made and after the test of
       the materials, finally accepted by the Engineer-in-charge
iv)    The contractor shall not be eligible for any claim or compensation either rising out of any delay in
       the work or due to any corrective measure required to be taken on account of and as a result of
       testing of the materials.
v)      The contractor or his authorised representative will be allowed to remain present in the Department
        laboratory which testing the samples furnished by him. However the results of all the tests carried
        out in the Departmental laboratory whether in the presence or in absence of the contractor or his
        authorised representative will be binding on the contractor.
vi)     Quality Control Tests :- The contractor shall at his own cost set up Laboratory at site of work to
        carry out the testing of materials which are to be used for the work. This laboratory shall be
        approved by the Engineer-in-charge. The testing shall be done as per frequencies mentioned in the
        specification/additional specification of each item of Schedule 'B'. The 30% of the test included in
        Annexure 'A' (On Page No. 103) shall be carried out in Vigilance and Quality Control Laboratory
        or any NABL approved Labrotary in the victinity area at the cost of contractor and balance 70% in
        the site laboratory. The test which is not included in Annexure 'A' 50% test shall be carried out each
        in Vigilance and Quality Control laboratory or any NABL approved Labrotary in the victinity area
        and site laboratory. The frequency of testing of construction materials is mentioned in Annexure-B
        on Page No. 104
vii)    In case of material procured by the contractor, testing as required by the Codes and Specifications
        shall be arranged by him at his own cost. Testing shall be done in the presence of authorized
        representative of the Engineer in charge, at the nearest approved laboratory. If additional testing
        other than as required by specification is ordered, the testing charges shall be borne by the
        Department, in case the test results are satisfactory and by the contractor if the same are not
        satisfactory.
viii)   In case of materials specified by the Government, if the contractor demands certain testing, the
        charges thereof shall be paid by the contractor if the testing results are satisfactory and the
        Department if the same are not satisfactory.
ix)     Contractor shall have testing machinery/apparatus in his possession as mentioned on Page 120
7.1     QUALITY CONTROL ON WORKS AND MATERIALS :
        The Contractor shall be responsible for the quality of the work in the entire construction work
        within the contract. He shall, therefore, have his own independent and adequate set up for ensuring
        the same. This shall include establishing field laboratory for testing required for works. The
        laboratory shall be equipped with the equipment’s and apparatus required for the testing. The list of
        various equipment’s/apparatus is enclosed on Page 120 for construction works for information and
        guidance of the Contractor. This equipment’s shall be in working condition. The Engineer in
        charge of the work will verify these equipment’s in the laboratory at site. The work shall not be
        started unless and until the laboratory is equipped with equipment’s. (Ref. Page 120)
7.2    CO-ORDINATION :
       When several agencies for different sub-works of the project are to work simultaneously on the
       project site, there must be full coordination between the contractors to ensure timely completion of
       the whole project smoothly. The scheduled dates for completion specified in each contract shall
       therefore, be strictly adhered to. Each contractor may make his independent arrangements for
       water, power, housing etc. if they so desire. On the other hand the Contractor are at liberty to come
       to mutual agreement in this behalf and make joint arrangements with the approval of the Engineer .
       No Contractor shall take or cause to be taken any steps or action that may cause, distruption,
       discontent, or disturbance of work, labour or arrangement etc. of the contractor in the project
       localities. Any action by any Contractor which the Engineer in his unquestioned discretion may
       consider as infringement of the above code, would be considered as a breach of the contract
       conditions and shall be dealt-with accordingly.
       In case of any dispute of disagreement between the Contractors, the Engineer’s decision regarding
       the co-ordination, co-operation and facilities to be provided by any of the Contractor shall be final
       and binding on the contractors concerned and such a decision shall not vitiate any contract nor
       absolve the Contractor of his obligations under the contract nor consider from the grounds for any
       claim or compensation.
7.3    TEMPORARY QUARTER AND SITE OFFICE
I)     The Contractor shall at his own expense maintain sufficient experienced supervisory staff etc.
       required for the work and shall make his own arrangements for housing such staff with all
       necessary amenities. General layout plan for such structures shall be got approved from the
       Engineer-in-charge. It will be the responsibility of the Contractor to get his lay out plan of
       temporary structure approved from the local competent authority.
II)    The contractor shall provide furnish, maintain and remove on completion of the work; a suitable
       office on the work site for the use of Executive Engineer or his representative. The covered area
       exclusive of verandah should not be less than 40.00 sqm. It may have brick walls and asbestos or
       corrugated iron roof, paved floor should be 45 cm. above ground level. He should provide latrines,
       urinals and keep them clean daily. This will be supposed to be included in his offer.
       The Contractor shall make his own arrangements at his own cost for entering into contract with
       concerned authorities for obtaining the connection and carry the water upto the work site as
       required by him. The location of the pipe line with respect to the road shall be decided by
       Engineer-in-charge and shall be binding on the Contractor.
       The Contractor is advised to provide water storage tank of adequate capacity to take care of
       possible shutdown of water supply system.
       The Contractor shall have to supply water required by the Department for its establishment at work
       site. The water consumed by the Department will be metered. For providing the meter permission,
       if necessary will be arranged by the Department.        Charges for the water consumed by the
       Department will be paid to the Contractor at the rates of 125% of the recurring costs or actually
       charged to him by concerned authorities and no other charges would be payable by the Department.
7.6    ELECTRICITY :
       The Contractor will have to make his own arrangement at his own cost for obtaining or providing
       electric supply at work site.
       Electrical supply for the Departments use at work site shall be provided by the contractor. No
       charges would be payable by the Department.
(i)     Providing protective foot-wear to workers, in situations like mixing and placing of mortar or
        concrete, in quarries and place where the work is to be done under too much wet conditions as also
        for movements over surfaces infected with oyster growth etc.
(ii)    Providing protective head wear to workers, working in quarries etc. to protect them against
        accidental fall of materials from above.
(iii)   Taking such normal precautions like providing hand rails to the edges of the floating platform or
        barges, not allowing nails or metal parts or useless timber to spread around etc.
8.2     AMENITIES :
(I)     Supporting workmen with proper belts, ropes etc. when working on any masts, cranes, grabs, hoist,
        dredger etc.
(ii)    Taking necessary steps towards training the workers concerned of the use of machinery before they
        are allowed to handle it independently and taking all necessary precautions in and around the areas
        where machines, hoists and similar units are working.
(iii)   Avoiding bare live-wires etc. as would electrocute workers.
(iv)    Making all platforms, stagings and temporary structures sufficiently strong and not causing the
        workmen and supervisory staff to take undue risks.
(v)     Providing sufficient first aid trained staff and equipment to be available quickly at the work site to
        render immediate first aid treatment in case of accidents due to suffocation, drowning and other
        injuries.
(vi)    Providing full length gum boots, leather hand gloves, leather jackets with fireproof aprons to cover
        the chest and black reaching upto knees plain goggles for the eyes to the labour working with hot
        asphalt handling vibrators in cement concrete and also where use of any or all these items is,
        essential in the interest of health and well being of the labourers in the opinion of the Engineer.
8.3     EXPLOSIVE :
        The Contractor shall at his own expense construct and maintain proper magazines, if such are
        required for the storage of explosives for use in connection with the work and such magazines,
        being situated constructed and maintained in accordance with the Government Rules applicable in
        that behalf. The Contractor shall at his own expenses obtain such license or licenses as may be
        necessary for storing and using explosives. Notwithstanding that the location etc. or storage of
        explosives are approved by the Engineer , the Government , shall not bear any responsibility
        whatsoever in connection with the storage and use of explosives on the site or any accident or
        occurrence what -so-ever in connection, therewith, all operations of the Contractor in or for which
        explosives employed being at the risk of contractor and upon his sole responsibility and the
        Contractor hereby gives to Government an absolute indemnity in respect thereof.
       The contractor shall take all precautions against damage by floods or from accident etc. No
       compensation will be allowed to the Contractor on this account or for correcting and repairing any
       such damage to the work during construction The Contractor shall be liable to make good at his
       cost any plant or materials belonging to the Government lost or damaged by floods or from any
       other cause while is in his charge.
       The Contractor shall comply with all rules, regulations, bye-laws and directions given from time to
       time by any local or public authority in connection with this work and shall himself pay all charges
       which are leviable on him without any extra cost to the Government .
       POLICE PROTECTION:
       For the Special Protection of camp of the Contractor's works, the Department will help the
       Contractor as far as possible to arrange for such protection with the concerned authorities, if so
       required by the contractor in writing. The full cost of such protection shall be borne by the
       Contractor .
      The Contractor Shall deploy following fulltime staff for timely and smooth execution of work at
       the disposal of Engineer-in-charge.
       The Staffer is required for coordination of work and this staff will be at the disposal of Engineer-In-
       Charge from the date of work order up to preparation of final bill of the project and it submission to
      division office.
       The payment to this staff will be responsibility of contractor and not entitle to get additional
       monetary benefits awarded for the same.
        a) Civil Engineer- Diploma with 7 yrs of experience or Degree with 4yrs of experience
        b) Computer Operator/Typist-01No
        c) Multi Task Servants
8.7    INDEMNITY:
       The Contractor shall indemnify the Government against all actions, suits, claims and demands
       brought or made against it in respect of anything done of committed to be done by the contractor in
       execution of or in connection with the work of this contract and against any loss or damage to the
       Government in consequence to any action or suit being brought against the Contractor for anything
       done or committed to be done during the execution of this contract.
       The Government may at its discretion and entirely at the cost of the contractor defend such suit,
       either jointly with the Contractor or single in case the latter chooses not to defend the case.
a)     The Contractor shall provide an adequate supply of pure and wholesome water for the use of
       labourers on work and in camps.
b)     The Contractor shall construct trench or semipermanent latrines for the use of the Labours. Separate
       latrines shall be provided for men and women.
c)     The Contractor shall build sufficient number of huts on a suitable plot of land for use of the
       labourers according to the following specifications:-
       2. A good site not liable to submergence shall be selected on high ground remote from jungle but
       well provided with tress, shall be chosen wherever it is available. The neighborhood of tank,
       jungle, trees or wood should be particularly avoided, Camps should not be established close to large
       cutting of earth work.
       3. The lines of huts shall have open space of atleast ten metres between rows. When a good
       natural site cannot be procured, particular attention should be given to the drainage.
       4. There should be no over crowding. Floor space at the rate of 3 Sq. metre per head shall be
       provided. Care should be taken to see that the huts are kept clean and in good order.
       5. The Contractor must find his own land and if he wants Government land, he should apply for it.
       Assessment for it, if demanded will be payable by Contractor. However the Department does not
       bind itself for making available the required land.
       a)     The Contractor shall construct a sufficient number of bathing places, Washing places should
       also be provided for the purpose of washing cloths.
       b)     The Contractor shall engage a Medical Officer with a travelling dispensary for a Camp
       containing 500 or more persons if there is no Government or other private dispensary situated with
       8 Kms. from the camp. In case of emergency the Contractor shall arrange a this cost of transport
       for quick medical help to his sick worker.
       c)     The Contractor shall provide the necessary staff for effecting satisfactory conservancy and
       cleanliness of the camp to the satisfaction of the Engineer-in-charge. Atleast one sweeper per 200
       persons should be engaged.
       d)     The Assistant Director of Public Health shall be consulted before opening a labour camp
       and his instruction on matters such as water supply, sanitary conveniences, the camp site
       accommodation and food supply shall be followed by the Contractor.
       e)     The Contractor shall make arrangements for all antimalarial measures to provided for the
       labours employed on the work. The antimalarial measures shall be provided as directed by the
       Assistant Director of Public Health.
       f)     The anti-malaria and other health measures shall be as directed by the Joint-Director
       (Malaria and Filaria) Health Services, Pune.
       g)     Contractor shall see that mosquitogenic condition are not created so as to keep vector
       populations to minimum level.
       h)     Contractor shall carry out anti-malaria measures in the area as per guidelines prescribed
       under National Malaria Eradication Programme and as directed by the Joint Director, (M & F) of
       Health Services Pune.
       j)       The Contractor shall make sufficient arrangements for draining away the surface and
       sullage water as well as water coming from the bathing and washing places and shall dispose off
       this waste water in such way as not to cause any nuisance. He shall also keep the premise clean by
       employing sufficient number of sweepers.
       k)       The Contractor shall comply with all rules, regulation bye-law and directions given from
       time to time by any local or public authority in connection with this work and shall pay fees or
       charges which are leviable on him without any extra cost to Government.
       l)       In addition to above all provisions of the relevant labour act pertaining to basic amenities to
       be provided to the labourer shall be applicable which will be arranged by the Contractor.
9.     MISCELLANEOUS :
9.1    For providing electric wiring or water lines ete. recesses shall be provided if necessary through
       walls, slabs, beams etc. and later on refilled it with bricks or stones, chipping cement mortar
       without any extra cost.
9.2    In case it becomes necessary for the due fulfillment of contract for the Contractor to occupy land
       outside the Department limits, the Contractor will have to make his own arrangements with the land
       owners and pay such rents, if any, are payable as mutually agreed between them.
9.3    The Contractor shall duly comply with the provision of the Apprentices Act 1961 (iii of 1961) and
       the rules and orders made thereunder from time to time under the said Rules and on his failure or
       neglect to do so he shall be subject to all the liabilities and penalties provided by the said Act and
       Rules.
9.4    It is presumed that the Contractor has gone carefully through the Standard Specification (Vol. I & II
       1981 Edition) and Schedule of Rate of the division, and studied the site conditions before arriving
       at rates quoted by him. The special provisions and detailed specification of wording of any item
       shall gain precedence over the corresponding contrary provisions (if any) in the standard
       specification given without reproducing the details in contract. Decision of Engineer-in-charge
       shall be final in case of interpretation of specification.
9.5    The stacking and storage of building materials at site shall be in such a manner as to prevent
       deterioration or inclusion of foreign materials and to ensure the preservation of the quantity,
       properties and fitness of the work. Suitable precautions shall be taken by Contractor to protect the
       materials against atmospheric action fire and other hazards. The materials likely to be carried away
       by wind shall be stored in suitable stores or with suitable barricades and where there is likelihood of
       subsidence of soil, heavy materials shall be stored on paved platforms.           Suitable separating
       barricades and enclosure as directed shall be provided to separate materials brought by contractor
       and from different sources of supply.
10.    DEFINITIONS :
       Unless excluding by or repugnant to the context :-
       a)     The expression "Government" as used in the tender documents shall mean the Public Works
       Department of the Government of Maharashtra.
       b)     The expression "The Chief Engineer" as used anywhere in the tender papers shall mean
       officer for the time being of the Government of Maharashtra who is designated as such.
       c)     The expression "Superintending Engineer" as used in the tender papers shall mean the
       officer of Superintending Engineer rank (by whatever designation he may be known) under whose
       control the work lies for the time being.
       d)     The expression “Engineer” or “Engineer-In-Charge” as used in the tender papers shall mean
       the Executive Engineer-in-charge of the work.
       e)     The expression "Contractor" as used in the tender papers shall mean the successful tenderer
       that is the tenderer whose tender has been accepted, and who has been authorised to proceed with
       the work.
       f)     The expression "Contract" as used in the tender papers shall mean the deed of contract
       together with or its original accompaniment and those later incorporated in it by mutual consent.
       g)     The expression "Plant" as used in the tender papers shall mean very temporary and
       necessary means necessary or considered necessary by the Engineer to execute, construct, complete
       and maintain the works and used in altered, modified, substituted and additional works ordered in
       the time and in the manner herein provided and all temporary materials and special and other
       articles of appliances of every sort, kind and description whatsoever intended or used therefor.
       h)     The expression “Department” as used in the tender papers shall means Public Works
       Department of Government of Maharashtra.
       i)     The “Accepting authority” shall mean the officer competent to accept the tender.
       j)     The “Site” shall mean the land and/or other places where the work is to be executed under
       the contract including any other land or places which may be allotted by the Government or use for
       the purpose of contract.
Contractor                  No. of Corrections                      Executive Engineer
                                            92
       The Contractor shall be responsible for the quality of the work in the entire construction work
       within the contract. He shall, therefore, have his own independent and adequate setup for ensuring
       the same. This shall include establishing field laboratory for testing required for concrete works.
12.    AUTHORITIES OF THE ENGINEER IN CHARGE :
       Save in so far as it is legally or physically impossible the Contractor shall execute, complete and
       maintain the works in strict accordance with the contract under the directions and to the entire
       satisfaction of the Engineer in charge and shall comply with and adhere strictly to the Engineer-in-
       charge’s instructions and directions on any matter (Whether mentioned in the contract or not)
       pertaining to this works.
       The Engineer in charge shall decide all questions which may arise as to quality and acceptability of
       materials furnished and work executed, manner of execution, rate of progress of the works,
       interpretation of the plans and specifications and acceptability of fulfillment of the contract on the
       part of the Contractor . He shall determine the amount and quantity of work performed and
       materials furnished and his decision shall be final. In all such matters, and in any technical
       questions which may arise touching the contract, his decision shall be binding on the Contractor.
       The Engineer in charge shall have the power to enforce such decisions and orders if the Contractor
       fails to carry them out promptly. If the Contractor fails to execute the work ordered by the
       Engineer-in-charge . The Engineer in charge may give notice to Contractor specifying a reasonable
       period therein and on the expiry of that period proceed to execute such work as may be deemed
       necessary and recover the cost there of from the Contractor.
       The duties of the representative of the Engineer-in-charge are to watch and supervise the work and
       to test and examine any material to be used for workmanship employed in connection with the
       works.
12.2   The Engineer-in-charge may from time to time, in writing delegate to his representative any of the
       powers and authorities vested in the Engineer-in-charge and shall furnish to the Contractor a copy
       of all such delegations of powers and authorities. Any written instruction or approval given by the
       representative of the Engineer-in-charge to the Contractor within the terms of such delegations (but
       not otherwise) shall bind the Contractor and the Department as though it had been given by the
       Engineer-in-charge, provided always as follows.
       b)     If the Contractor is dissatisfied with any decision of the Representative of the Engineer-in-
              charge he shall be entitle to refer the matter to the Engineer-in-charge, who shall there upon
              confirm/reverse or vary such decision.
       The Engineer-in-charge shall furnish the contractor with only the four corners of the works site and
       a level bench mark and the contractor shall set out the works and shall provide an efficient staff for
       the purpose and shall be solely responsible for the accuracy of such setting out.
       The contractor shall provide, fix and be responsible for the maintenance of all stacks, templates,
       level marks, profile and other similar things and shall take all necessary precautions to prevent their
       removal or disturbance and shall be responsible for the consequence of such removal or
       disturbance, should the same take place and for their efficient and timely reinstatement. The
       contractor shall also be responsible for the maintenance of all existing survey marks, boundary
       marks distance marks and center line marks, either existing or supplied and fixed by the contractor.
       The work shall be set out to the satisfaction of the Engineer-in-charge. The approval thereof or
       joining with the contractor by the Engineer-in-charge in setting out the work, shall not relive the
       contractor of any of his responsibilities.
       Before beginning the work, the contractor shall at his own cost provide all necessary reference and
       level posts, pegs, bamboos, flags, ranging rods, strings and other materials for proper layout of
       the work in accordance with the scheme for bearing
         marks acceptable to the Engineer-in-charge. The center, longitudinal or face lines and cross lines
         shall be marked by means of small masonry pillars. Each pillar shall have distinct mark at the
         center to enable the theodolite to be set over it. No work shall be started until all these ponts are
         checked and approved by the Engineer-in-charge in writing but such approval shall not relieve the
         contractor of any of his responsibilities. The contractor shall also provide all labour, material and
         other facilities, as necessary, for the proper checking of layout and inspection of the points during
         construction.
         Pillars bearing geodetic marks located at the sites of units of works under construction should be
         protected and fenced by the contractor.
         On completion of works, the contractor must submit the geodetic documents according to which the
         work was carried out.
         The contractor shall be entirely and exclusively responsible for the horizontal and vertical alignment,
         the levels and correctness of every part of the work and shall rectify effectually any errors or
         imperfections therein, such rectifications shall be carried out by the contractor, at his own cost, when
         instructions are issued to that effect by the Engineer in charge.
16.1     The stacking and storage of material at site shall be in such a manner as to prevent deterioration or
      intrusion of foreign matter and to ensure the preservation of their quality, properties and fitness for the
      work. Suitable precautions shall be taken by the Contractor to protect the materials against atmospheric
      action, fire and other hazards. The materials likely to be carried away by wind shall be stored in suitable
      stores or with suitable barricades and where there is likely hood of subsidence of soil, heavy materials shall
      be stored on paved platforms.
       Suitable separating barricades and enclosures as directed shall be provided to separate materials brought
       by Contractor and materials issued by Government to Contractor under Schedule "A" Same applies for
       the material obtained from different sources of supply.
16.2   The Contractor shall at his own expense engage watchman for guarding the materials and plant and
       machinery and the work during day and night against any pilferage or damage and also for prohibiting
       trespassers.
16.3   No materials brought to the site shall be removed from the site without the prior approval of the
       Engineer-in-charge.
18.2   The Contractor shall provide at his cost necessary ladders and such arrangements as are considered safe
       by the Engineer-in-charge for proper inspection of all parts of the work.
17.3   Contractor shall extend his full co-operation and make all necessary arrangements when needed for
       carrying out inspection of the work or any part of the work by the local representatives, M.L.As,
       M.Ps and officers and dignitories / delegates of various Government departments, local bodies,
       private sectors etc. No compensation shall be paid to the contractor on this account.
17.4   The work shall be carried out by the Contractor without causing damage to the existing
       Government property and / or private property. If any such damage are caused, the Contractor shall
       pay for restoration of the property to the original conditions, and any other consequent damages.
17.5   In the event of the occurrence of an accident involving serious injuries or death of any person, at
       site of work or quarry or at any place in connection with the work the same shall be reported in
       writing within twenty four hours of the occurrence to the Engineer-in-charge and Commissioner of
       Workmen's compensation.
17.6   The Contractor after completion of work shall clean the site of all debris and remove all unused
       materials other than those supplied by the department and all plant and machinery, equipment, tools
       etc. belonging to him within one month form the date of completion of the work, or otherwise the
       same will be removed by the department at his cost or disposed off as per departmental procedure.
       In case the material is disposed off by the department, the sale proceeds will be credited to the
       Contractor’s account after deducting the cost of sale incurred. However, no claim of Contractor
       regarding the price or amount credited will entertained afterwards.
17.7   All constructional plant, provided by the Contractor shall when brought on to the site be deemed to
       be exclusively intended for the construction and the contractor shall not remove the same or any
       part thereof (save for the purpose of moving it from one part of the site to another) without the
       consent in writing of the Engineer-in-charge who shall record the reasons for withholding the
       consent.
       As there is local traffic by the side of construction during construction for the bilding, the
       Contractor will have to take proper precautions such as proper barricading, fencing, lighting,
       information and cautionary boards for safe and smooth flow of traffic, and keeping the concerned
       authorities informed about the work in progress.
19.1   The work shall not be considered to have been completed in accordance with the terms of the
       contract until the Engineer-in-charge shall have certified in writing to that effect. No approval of
       material or workmanship or approval of part of work during the progress of execution shall bind the
       Engineer-in-charge or in any way prevent him from even rejecting the work which is claimed to be
       complete and to suspend the issue of his certificate of completion until such alteration and
       modifications or reconstruction have been effected at the cost of the Contractor as shall enable him
       to certify that the work has been completed to his satisfaction.
19.2   After the work is completed the Contractor shall give notice of such completion to the Engineer-in-
       charge and within 30 days of receipt of such a notice the Engineer-in-charge shall inspect the work
       and if there is no defect in the work shall furnish the Contractor with a certificate indicating the
       date of completion. However, if there are any defects which in the opinion of the Engineer-in-
       charge are rectifiable he shall inform the Contractor the defects noticed. The Contractor after
       rectification of such defects shall then inform the Engineer-in-charge and Engineer-in-charge on his
       part shall inspect the work and issue the necessary completion certificate within 30 days if , the
       defects are rectified to his satisfaction, and if not, he shall inform the Contractor indicating defects
       yet to be rectified. The time cycle as above, shall continue.
19.3   In case defects noticed by the Engineer-in-charge which in his opinion are not rectifiable but
       otherwise work is acceptable at reduced payment, work shall be treated as completed. In such
       cases completion certificate shall be issued by the Engineer-in-charge within 30 days indicating the
       un-rectifiable defects for which reduction in payment is being made by him.
19.4   The issued of completion certificate shall not be linked up with the site clearance on completion of
       the work.
21 SPECIAL CONDITIONS:
21.1   The Contractor should ensure that all safety precautions are observed by their laboures, working
       closed to the State Highway and while closing the State Highway precautions are taken including
       insurance etc., for their labour at the cost of the contractor and the contractor will bear all the
       expenses, compensation etc. if any accident occurs to the labour etc. No claim in this regard on
       whatsoever account shall be entertained and this decision of the Department will be final and
       conclusive.
21.2   The Contractor shall observe the rules and regulation imposed by traffic police for smooth flow of
       traffic on the diversion road and shall not be entitled for claims any compensation arising thereof.
21.3   In case of delay in handing over the land required for the work, due to unforeseen cause, the
       Contractor shall not be entitled for any compensation what-so-ever form the Government on ground
       that the machinery or labour was idle for certain period. Contractor may, however apply for
       extension of time limit which may be granted on the merit of the case.
       The Contractor shall arrange to take dated post card size coloured photographs at various
       stages/facts of the work including interesting and novel features of the work as desired by the
       Engineer-in-charge and supply them in five copies each in separate albums of appropriate size. He
       shall also arrange for the Video Filming of important activities of the work during the currency of
       the contract and edit it to a video film of 60 to 300 minutes playing time.
       It shall contain narration of the various activities in English/Marathi by a competent narrator. The
       cassette shall be of acceptable quality and the film shall be capable of producing color pictures.
       This shall be considered as incidental to the work and no additional payment whatsoever will be
       made for the same.
       Approval of all materials for the work shall be obtained in writing from Engineer-in-charge or his
       representative before its use in the Project.
       Before taking up of any construction activity the construction work done earlier shall be got
       approved in writing. Any failure on this account may result in the work for which the Contractor
       will be solely responsible.
       Materials and job mix, etc. shall be got approved in writing atleast 15 days in advanced of the
       commencement of the corresponding activity. The testing charges shall be borne by the Contractor
       .Besides the prescribed tests and frequencies any other test of tests over the prescribed frequency
       shall also be carried out by the Contractor at his own cost if so directed by Engineer-in-charge or
       his authorised representative.
              Building and other construction worker welfare cess at 1% or at the rates awarded from
      time to time as intimated by the competent authority of building and other construction worker
      welfare Act 1996 shall be deducted fro bill amount. Whether bill advance payment or secured
      advance.
30.    Goods and Service Tax (GST) as preveling rates on the contract amount will be recovered from the
       Bill of the Contractor who are registered under GST, as per provisions made in the GST Act 2017.
31.     DIARY :
      Contractor shall maintain, throughout the construction period, a diary in the from of a register
regarding the following :-
        i) Daily presence of all categories of labours. ii) Daily availability and use of machinery and
equipment’s on work. iii) Daily procurement, Consumption and balance of materials on site. iv) Daily
record of various visiting authorities alongwith name of the officers visited and timing. v) Details of work
executed per day. The register shall be closed on daily basis and signature of Engineers in charge or his
representative should be taken over it.
32.1     Payment shall be made to the contractor after satisfied executed of work and as per availability
         of fund.
32.2     No interest shall be demanded by the contractor for delay in payment.
32.3     If the contractor go for litigation for delayed payment or demand any interest he may be debarred
         from submitting bid / tender in future.
 1.    The work shall be carried out in the best workmanship like manner and strict accordance with
       P.W.D. hand book volume I and II 1960. Edition supplemented by specification attached and as per
       Standard Specifications Book of Govt. of Maharashtra of 1979 and as per specific order of the
       Executive Engineer or his representative from time to time.
 2.    The orders issued by the Government in P.W. Department and the Superintending Engineer,
       Mumbai (P.W.) Circle, Mumbai form time to time regarding construction procedure shall be binding
       on the contractor in addition to the specification contained in P.W.D. hand book volume I and II and
       book of standard specification of P.W. Department and the specifications enumerated above.
 3.    The contractor shall submit day to day account of the materials issued to him and its use and also
       monthly progress and programme of work.
 4.    a) The maximum size of aggregate permissible would be as per A-7 page-8 of Standard
       specifications book 1979 edition.
 5.    The items provided with watering for curing include continuous watering operations through out the
       day including lunch hours and also during holidays. For this purpose contractor shall have to bring
       or construct tank of approx. 3000 litres capacity near each building and provide necessary Booster
       Pumps etc. to ensure adequate curing and wetting. Hold fasts coming in contact with R.C.C.
       columns shall be of sizes 30 cm x 4 cm to be fitted with two rows, nails fixed properly in concrete.
 6.    Material testing requirement frequency and type of testing is enclosed separately. Material to be used
       shall be tested accordingly and cost shall be borne by contractor.
 7.    The execution of any work form external side of the building Steel scaffolding/Double Bamboo
       scaffolding shall be used. No separate payment for claims in this regard shall be entertained.
 8.    Photographs / video shooting shall be taken during the execution of work to verify qualities of
       polymer and micro concrete.
 9.    Working hours for carring out the site work is from 9.00 AM to 18.00 PM only and No work shall
       be executed after the sunset as to control the quality of the work.
                                     Annexure 'A'
                                QUALITY CONTROL TESTS
                                (Refer Condition No.7 (vi) on Page No.84)
Annexure 'B'
ADDITIONAL SPECIFICATIONS
       The contractor shall achieve that following requirements in respect of quantity of work and his
contract rate shall provided for the same.
1.1    ADMIXTURES :-
       Whenever necessary the admixture should be used to achieve the required workability. The type of
       admixture should be got approved from Engineer-in-charge. The rate is inclusive of all admixtures
       etc. if found necessary.
1.7    BAR SPACING : As per relevant I.S. codes and as detailed design drawing or as directed by
       Engineer-in-charge.
1.8    HOLLOWS IN CONCRETE : After concreting is complete the concrete surface articularly
       where there is congestion of reinforcement, shall be tested by light hammering or if possible by
       Schmidtz hammer. Any portion showing signs of hollowness should be grouted immediately.
1.2    Design of Formwork :- Formwork including complete false work shall be designed by the
       contractor in accordance with I.S.: 2750 (1964), 4041 (1987) and all other relevant I.S. codes
       without any extra cost to the Government and these shall be got approved from Engineer before any
       formwork is taken up.
1.3    The contractor shall entirely be responsible for the adequancy and safety for false work not-
       withstanding any approval or review by the Engineer of his drawing and design. Proprietary system
       of formwork if used a detailed information shall be furnished to the Engineer for approval.
2.     QUALITY OF SHUTTERING : The shuttering shall have smooth and even surface and its joints
       shall not permit leakage of cement slurry.
2.1    Shuttering materials to be used shall be steel shuttering/marine ply well seasoned free from projecting
       nails, splits or other defects that may mark on the surface of concrete. It shall not be so dry as to absorb
       water from concrete, or so green or wet as to shrink after erection. Mild steel plates or plywood shall be
       used for slab and beam bottoms.
2.2    The timber shall be accurately spawned planed on the sides and the surface coming in contact with
       concrete.
2.3      So far as practicable, clamps shall be used to hold the forms together. Where use of nails is unavoidable
         minimum number of nails shall be used and these shall be left projecting so that they can be easily with
         drawn. use of double headed nails shall be prefered.
3.       TOLERANCE :-
3.1      The formwork shall be made so as to produce finished concrete true to shape, lines, levels plumb
         and dimensions as shown on the drawings, subject to the following tolerance unless otherwise
         specified in these documents or drawings or as directed by the Engineer :
         a)      Section dimension        =       5 mm
         b)      Plumb                    =       1 in 1000 of height
         c)      Levels                   =       3 mm before any deflection takes place.
3.2      Tolerance given above are specified for local aberrations in the finished concrete surface and should not
         be taken as tolerance for the entire structure taken as a whole or for the setting and alignment of
         formwork which should be as accurate as possible to the entire satisfaction of the Engineer, Errors if
         noticed in any lift/ tilt of the structure after stripping of forms, shall be corrected in the subsequent work
         to bring back the surface of the structure to its true alignment.
4.       SPECIAL PROVISION :- Whenever the concreting of thinner members in required to be carried out
         within shutters of considerable depth, temporary openings in the side of the shutters shall, if so directed
         by the Engineer be provided to facilitate the puring and consolidation of the concrete. Small temporary
         openings shall be provided as necessary at the bottom of shutters of walls and deep beams to permit the
         expulsion of rubbish etc.
      1) REMOVAL OF FORMWORK :- The formwork shall be so removed that it shall not cause
        damage to concrete. Centering shall be gradually and uniformly lowered in such a manner as to
        avoid any shock or vibrations. Supports shall be removed in such a manner as to permit the concrete
        to take stresses due to its own weight uniformly and gradually.
         The whole of the formwork removal should be planned and definite scheme of operation shall be
         worked out. Under no circumstances forms be struck until the concrete reaches a strength of at least
         twice the stress to which the concrete may be subjected at the time of striking but not before the
         period as mentioned in IS:456-2000 where ordinary portland cement is used.
      fastenings etc complete for R.C.C. member like beams slabs and canopy including its removal after
       the specified period, stacking making good the damaged parts / its replacement before its next use
       with all leads and lift (all centering material shall be contractor.)
2.     For R.C.C. works formwork shall be of mild steel plates/ marine plywood of adequate thickness
       and grade only. The centering & supporting arrangement such as standard steel trusses/ joists/ spans
       standards adjustable/fixed props. H-type frames etc shall be designed by the Contractor and
       approved from the Engineer before commencement of its erection. The Contractor with the prior
       approval of the Engineer shall use standard steel centering arrangement which may be
       manufactured by the reputed firm.
3.     The supporting arrangement designed by the contractor shall conform to the relevant I.S. code and
       Standard practice adopted in this type of work. The centering arrangement shall be adequately
       braced and properly secured by using appropriate type of fastenings and fixtures to ensure stability
       and rigidity of the centering to withstand all loads coming on it. The entire responsibility for
       design, erection, maintenance and safety etc. will exclusively rest with the contractor. The Engineer
       reserves right to call detailed design calculations of the entire centering or part there of to verify its
       stability and also reserve tight to reject entire centering arrangement or part there of and any
       material used for the centering in the event of which the contractor shall have to arrange for its
       replacemnet at his own cost.
b)     The design of concrete mixes for various concrete items in the work shall be obtained by the
       contractor at his cost from and approved laboratory. The contractor shall submit in advance details
       of such design to the Engineer-in-charge for his prior approval.
d)     The concrete mix design shall give target strength of 1.33 times the working strength.
e)     The minimum size of aggregate permissible shall be as per para A-7 of Page - 8 f of standard
       specification book of 1979 Edition Vol. 1.
f)     The provision of the specification No. B-7 at page - 38 to 40 of Vol. 1 1979 Edition of standard
       specification book for controlled concrete shall be applicable for all the structural concrete items.
       The maximum water cement ratio shall be 0.45. The mix design shall be done accordingly.
g)     All the expenses of preliminary mix design, subsequent field/ laboratory mix design, work tests,
       shall be borne by the contractor.
2.     FROMWORK FOR CONCRETE WORK :- The forms of concrete shall be of the materials as
       directly by the Executive Engineer-in-charge and shall preferably be of steel or waterproof
       plywood, Forms shall be of the required shape, profile and lines. Suitable devices shall be used to
       hold corners, adjacent ends, edges of panel or other forms together in accurante alignment. The
       forms and joints shall tight enough. Forms used for circular curved or structures of unusual shape,
       petal dome etc. shall be of such a character that will result in smooth concrete surface and exact
       shape. They shall be prepared such that they will not warp or distort during erection or while
       placing concrete. Their design and layout shall be got approved form the Executive Engineer-in-
       charge in advance.
3.     ERECTION AND REMOVAL OF FORM WORK :- The centering and strutting shall be of
       steel or plywood board exclusively for concreting. The design and drawing should be got approved
       in advance from the Department. For minor members the Engineer-in-charge may, at his discretion,
       permit use of wooden shuttering. The centering and shuttering shall be close and tight to prevent
       leakage of cement slurry. The centering shall have the necessary props, bracing and edges
       sufficiently strong and stable which shall not yield or displace while or after laying of concrete.
       They shall be made in such way that they can be slackened and removed gradually and slowly
       without distributing the concrete. Centering and shuttering shall not be removed before the design
       strength is achieved.
4.     MIXTURE OF CONCRETE :- Design mix concrete as well as nominal mix concrete shall be
       mixed by following the provision in Standard specification at B. 6.4 unless otherwise directed by
       the Engineer. Unless otherwise agreed by the Engineer concrete shall be mixed in a batch type
       mixer of such other type of mixer as the Engineer’s approval.
       During hot weather the Contractor shall ensure that the constituent materials are sufficiently cool to
       prevent the concrete from stiffening in the intervals between its discharge from the mixer and its
       final position.
       No concreting shall be carried out during period of continuous heavy rains unless, it is completely
       covered during mixing, transporting and placing, In extreme hot weather, concreting shall be
       restricted to morning and evenings The time between mixing and placing of concrete shall be kept
       to the minimum and formwork shall be cooled by sprinkling with water.
8.     FINISHING : Finishing work shall comply with requirement of section B.6.10 of Standard
       Specification unless otherwise specified herein below :
       Immediately on removal of forms, the R.C.C. work shall be examined by the Engineer before any
       defects are made good
a)     The work that has sagged or contains honey combing to an extent detrimental to structural safety or
       architectural concept shall be rejected.
b)     Surface defects of a minor nature shall be rectified generally as indicated below by the contractor.
       i)     Surface defects which require rectification when forms are removed usually consist of
              bulges due to movement of forms, ridges at form joints, honeycombed areas, damage
              resulting from the stripping of forms and bolt hole. Bulges and ridges shall be removed by
              careful chipping or tooling and the surface is then rubbed with a grinding stone. Honey
              combed and other areas shall be chipped out, the edges being cut as straight as possible and
              perpendicular to the surface, or preferably slightly under cut to provide a key at the edge, of
              the patch. Bolt holes shall be closed by cement mortar to ensure thorough filling.
       ii)    Shallow patches shall be treated with a coat of thin grout composed of one part of cement
              and one part of sand and then filled with mortar similar to that used in concrete. The mortar
              is placed in layers not more than 10 mm thick and each layer shall be given a scratch finish
              to secure bond with the succeeding layer. The last layer shall be finished to match the
              surrounding concrete by floating, rubbing or tooling on formed surfaces by pressing the
              form material against the patch while the mortar is still plastic.
       iii)   Large and deep patches requires filling up with concrete held in place by forms. Such
              patches shall be reinforced and carefully dowelled to the hardened concrete.
       iv)    The same amount of care to cure the material in the patches shall be taken for the whole
              structure. Curing shall be started, as soon as possible after the patch is finished to prevent
              early drying. Damp Hessian cloth may be used. But in some locations it may be difficult to
              hold it in place, a membrane curing R.C.C. Compound in these cases will be most
              convenient.
9.     CONSTRUCTIONS JOINTS : Construction joints shall be provided and treated following the
       provisions of Specification and as directed by the Engineer-in-charge.
10.    DURABILITY :- Minimum cement contents for different exposures and sulphate attack are given
       in Tables 4 and 5 o I.S. 456, 2000 shall be followed for design mix.
11.2   DEFECTIVE CONCRETE : Any concrete which gives substandard results, or is severely
       damaged due to cracking or shows excessive honey combing and exposure of reinforcement, if
       exhibits any fault which in the opinion of the Engineer, seriously impairs its function, may be
       declared as defective concrete. Such non acceptable concrete shall be removed from the site and
       replaced by fresh concrete of the specified quality by the contractor at his own expenses.
       Alternatively in case of acceptable concrete, the Contractor shall carry out whatever other remedy
       the Engineer may reasonably suggest "Small rendering shall be done by the Contractor without
       extra cost."
12     KEEPING RECORDS : The record of mix design, mixing, slum, testing of C.C. cubes etc. shall
       be maintained in accordance with Section B-6.13 of the Standard Specification.
0.1    This standard covers the code of practice for corrosion protection of reinforcing steel using cement
       polymer composite coating system. In this preparation assistance has been derived from the
       following.
(A)    ASTM A775 / A775M -94 d Standard specification for Epoxy coated reinforcing steel bars.
(B)    Test methods specified by Central Electrochemical Research Institute Karaikudi - 630006.
0.2    This practice covers the various test procedures required to ensure the quality of coated product.
1. SCOPE
This specification covers the code of practice for cement-polymer composite coating system which will be
applicable to reinforcing bars conforming to :      BIS 432 ( Part 1 ) 1982 - Specification for mild steel
and medium tensile steel bars and hard drawn steel wire for concrete reinforcement - Part 1 Mild steel and
Medium Tensile steel bars. BIS 432 ( Part 2 ) 1982 - Specification for mild steel and medium tensile steel
bars and hard drawn steel wire for concrete reinforcement - Part 2 Hard Drawn steel. BIS 1139 (Part 1)
1966 - Specification for hot rolled mild steel and medium tensile steel and high yield strength deformed
bars for concrete reinforcement.
This standard specifies the recommended practice for surface preparation, method of application, testing,
inspection, handling and stacking of coated reinforcing bars.
2. SURFACE PREPARATION
2.1    Prior to blast cleaning visible deposits of oil, grease or paint shall be removed by suitable alkaline
cleaner ( soak cleaning R.C.C. Compound ) as per SSPC - SPCOM, clause 11.1.2
2.2    The surface of the steel reinforcing bars to be cleaned by abrasive blast cleaning using either sand
or grit to the near white metal finish in accordance with SSPC - SP 10 - / NACE No.2.1994.
2.3 The prepared surface shall meet the visual standards of comparisons as in SSPC-VIS 2
2.4    As per SSPC - VIS 2. The cleaned surface shall conform to the rust grading scale 9-10 ( i.e. % of
area rusted 0.03 % ). 0.2 - 1994.
3. APPLICATION OF COATING
3.1    The application of the coating shall not be unduly delayed and commence immediately after
completion of surface preparation.
3.2    The coating shall be applied by an appropriate method and fully cured in accordance with the
recommendations of the supplier of the coating material.
3.3    It is advisable that severely rusted and heavily pitted reinforcements are not accepted for treatment.
5. ACCEPTANCE / INSPECTION.
5.1    The coated rods that do not meet the requirements of the above specification shall be rejected.
5.2    The manufacturer of the coated rebar, shall submit a certificate from an appropriate testing agency
that the coated rebars meet the requirements of the specification.
6. PROCEDURE FOR HANDLING, STACKING AND TRANSPORTING
OF COATED REINFORCING BARS.
The durability of the coated rebars is related to the coating quality. The more damage is to the coating, it is
more prone to corrosion. Good jobs site practices can minimise the coating damage. For this reason,
standards, such as ASTM, JSCE, NACE (USA) have laid down specific procedures for stacking and
transporting coated bars. Some important guidelines are referred here.
6.1      Stacking :
6.1 a) It is preferable to store the coated bars on buffer material placed at suitable intervals instead of
placing them directly on the ground.
6.1 b) It is nor desirable to store coated bars by piling them on top of one another. If they are to be stored
by piling, buffer materials such as wood, rubber, jute sack etc. , should be used to separate the layers.
However, the number of layers allowed shall be limited to a maximum of five.
6.1 c) The coated rods shall be stored in an enclosed yard.
6.1 d) If any damage had accured during stacking it should be repaired immediately before any rusting
could occur by using the same coating formulation.
6.2      Handling and Transporting
6.2.a) The coated bars shall be securely bound together using a buffer material ( Padding ) and it is
desirable that the best bars shall be supplied with some canvas cover.
6.2.b) When loading and unloading bundles of coated bars, it shall be preferable to lift them, with a strong
back, spreader bar multiple supports etc. To avoid extreme bending, nylon slings at 2 or 3 points shall be
used.
7. SPECIFICATIONS FOR PATCH REPAIRING OF COATING DAMAGES.
.1       Coating repair is required when peeling off and other damages accur during fabrication or handling.
7.2      The patch repair shall be done at site using the same coating material as per the manufacturer’s
recommendations.
7.3      It is essential to ensure a minimum coating thickness of 150 microns at all the repaired portions
         before embedding in concrete
 REFERENCE DOCUMENTS.
1.       ASTM G8 -90 Standard test methods for cathodic disbonding of pipeline coatings
( Method A )
2.       ASTM G20-88 Standard test method for chemical resistance of pipeline coating.
3.       ASTM G12-83 Standard test method for non-destructive measurement of film thickness of pipeline
coating on steel.
4.       ASTM D-4060-90 Standard test method for abrasion resistance of organic coating by the Taber
Abraser.
5.       ASTM -G14-88 Standard test method for impact resistance of pipeline coating ( falling - weight
test )
6.       BIS - 2770 Part - I 1967 Method of testing bond in Reinforced Concrete part 1 Pullout Test ( 1967 )
7.       SSPC - SP 10-NACE No.2 1994 Near White Blast Cleaning.
8.       SSPC - VIS 2 Guide to standard method of evaluating degree of rusting on painted steel surfaces.
9.       SSPC-SP-COM - Surface Preparation Specifications.
ANNEXURE
                                          TEST PROCEDURE A.
Determination of adhesion of the coating :
Adhesion of the coating is to be tested as per ASTM-A-775/775 M 94 d. 10 mm Dia coated rods of length
1 m. shall be used in this test. The coated rods shall be padded with sponge and bend to 300 degree around
a 75 mm diameter mandrel. The bending shall be done at an uniform rate and not suddenly. No cracking of
the coating shall be visible to the unaided eye on the outside radius of the bar. If the test is to be conducted
on other than 10 mm diameter rod, then the diameter of the mandrel has to be changed accordingly as
tabulated below :
8 mm and 10 mm 75
12 100
16 125
25 200
32 250
TEST PROCEDURE B.
Two identical coated bars of same size and length shall be used in the test. 14 mm gauge copper wire shall
be soldered to the one end of the each bar. The other end of the bars shall be sealed with an insulating
material to a length of 2.5 cm. The exposed area on which test is to be conducted shall not be less than 240
sqcms, if 10 mm. diameter rods are used, then the length exposed shall not be less than 80 n             cm. A
non-conductive plastic container of size not less than 150 x 150 mm x 850 mm is filled with 7 % NaCl
solution (70 gms./litre) up to the height of 800 mm. The coated rebars shall be suspended vertically so as to
have a clearance of 25 mm from the bottom, 40 mm from the sides and 40 mm in between the rods. A
potential of 2 V in between the coated rods shall be impressed for a period of 60 minutes using suitable DC
power source. The voltage and current shall be measured by using a high resistance voltmeter having an
internal resistance of not less than 10 Mega Ohms and having a range upto 5 V (minimum) Storage
batteries may also be used for impressing the voltage.
During this 60 minutes of testing, there shall not be any coating failure as evidenced by evolution of
hydrogen gas at the cathode or by appearance of corrosion products of iron at the anode.
                                        TEST PROCEDURE C.
Determination of abrasion resistance of the coating :
Test shall be conducted as per ASTM D 4060 using Taber Abraser using CS-19 wheel under 1 kg. load per
wheel. Abrasion resistance of the coating shall be conducted on panel of size 100 mm x 100 mm in which 8
mm Dia hole shall be drilled. The panel shall be coated as per specified procedure. After curing, thickness
of the coating shall be measured to the nearest 0.1 mg. Then the coated panel shall be mounted on the turn
table. The abrading heads shall placed on the panel and the vacuum pickup nozzle kept in position. The
counter shall be set in position. The vacuum pickup and turn table of the abrader shall be fixed for 1000
cycles. After 1000 cycles loose abradings remaining on the test specimen shall be removed by light
brushing. The final weight of the specimen shall be measured for finding the loss in weight. The weight
loss shall not exceed 100 mg. The test shall be conducted on duplicate specimens.
TEST PROCEDURE D.
Choride tolerable limit :
10 mm Dia cement polymer coated rod of length 10 cm. shall be used. Bottom edge of the coated rod shall
be sealed using lacquer. Then test specimen is kept immersed in 0.04N NaOH + 10,000 PPM Chloride and
potential is monitored using high impedance Multimeter against suitable reference electrode such as
saturated calomel electrode. After getting stabilized potential, using appropriate current regulator (0-100
mA), the test specimen is anodically polarized at a constant current density of 290 uA/sqcm. using a
Platinum/Stainless Steel/TSIA/Polished mild steel as cathode. Potential with time is followed for 5
minutes. At the end of 5 minutes, no rust spots shall be observed on the coated rod.
TEST PROCEDURE E.
Chemical Resistance of the coating :
The coated rods ( any diameter ) of length 30 cm. shall be used in this test. The bottom edge of the coated
rods are to be sealed using lacquer. Transparent PVC cylindrical container shall be use. 3M Cacl2 3M
NaOH Saturated Ca(oh)2 and distilled water are prepared as individual test solution and filled in the
separate container up to the half of its height. Then the coated rods are kept partially immersed in the test
solution so that they are in term contact with both the liquid and vapour phase of the test solution. The test
shall be conducted for 45 days. The coating should not blister, soften or disbond during this period.
TEST PROCEDURE F.
200 mm diameter
      2.36 mm, 2.0 mm, 1.18 mm, 600 micron, 425 micron,
                                                                                                  2 Sets
      300 micron, 150 micron, and 75 micron
14.   Water testing Kit                                                                            1 Set
15.   Atterbergs Limits (liquid and plastic limits) Determination apparatus                        1 Set
16.   Dry Bulk Density Test apparatus (sand pouring cylinder, tray, can etc.).
                                                                                                   1 Set
17.   Speedy Moisture Meter complete with chemicals                                                1 Set
18.   Aggregate Impact Value Test apparatus/
      Los Angles Abrasion Test apparatus.                                                         1 Set
19.   Flakiness and Elongation Test Gauges                                                        1 Set
20.   Vicat apparatus for testing setting times                                                   1 Set
21.   Slump testing apparatus                                                                     4 Sets
22.   Compression and Flexural strength testing machine, 200 tonne capacity
      with additional dial for flexural testing.                                                  1 No.
       To ensure the specified quality of work which shall also include necessary surveys, temporary
works etc., the contractor shall prepare a quality assurance plan and get the same approved from the
Engineer in charge within eight days from the date of work order. For this, contractor shall submit an
organization chart of his technical personnel to be deployed on the work along with their qualification, job
descriptions defining the functions of reporting, supervising inspecting and approving. The contractor shall
also submit a list of tools, equipment’s and the machinery and instrumentation which he proposes to use
for the construction and for testing in the field and/or in the laboratory and monitoring. The contractor shall
modify/supplement the organization chart and the list of machinery, equipment etc. as per the direction of
the Superintending Engineer and shall deploy the personnel and equipment on the field as per the approved
chart and list respectively. The contractor shall submit written method statements detailing his exact
proposals of execution of the work in accordance with the specifications. He shall get these approved from
the Engineer in charge. The quality of the work shall be properly documented through certificates,
records, check-lists and logbooks of results etc. Such records shall be complied from the beginning of the
work and be continuously updated and supplemented and this shall be the responsibility of the contractor.
The forms should be got approved from the Executive Engineer-in-charge.
       The contractor shall prepare detailed completion drawings after completion of the work. He shall
also prepare and submit a maintenance manual giving procedure for maintenance, with the period of
maintenance works including inspections, tools and equipment to be used, means of accessibility for all
parts of the structure. He shall also include in the manual, the specifications for maintenance work that
would be appropriate for his design and technique of construction. This manual shall be submitted within
the contract period.
    Name of work : MOW to Labour Commissioner office BKC Bandra Mumbai. (Repairs & Renovation of Toilet
                   Block) (Gr to 3rd & 5th to 8th floor).
Quantity                                 Description of Item                      Rate in         Rate in Words      Unit      Amount    Ref. to Std.          Additional
                                                                                Figure(Rs.)                                     (Rs.)    Spn. Book       Specifications if any
713.54       1 . Removing cement tiles, or marble or polished shahabad floor or       47.25 Rupees Forty Seven And   Per One    33714.77        --      The work shall be
Square           dado without bed concrete including stacking the materials as              Paise Twenty Five Only   Square                     --      carried as per wording
Metres          directed with all leads, lifts etc. complete                                                         Metre                              of the item and as
                                                                                                                                                        directed by the
                                                                                                                                                        Engineer in-charge.
238.00       2 . Dismantling the R.C.C. Work 1:2:4 and sorting out the              1523.55 Rupees One Thousand      Per One   362604.90        --      The work shall be
Cubic           materials such as steel etc. as directed and stacking them within           Five Hundred Twenty      Cubic                      --      carried as per wording
Metres           the specified lead as directed etc. complete.                              Three And Paise Fifty    Metre                              of the item and as
                                                                                            Five Only                                                   directed by the
                                                                                                                                                        Engineer in-charge.
63.00        3 . Removing urinal pans or wash hand basins with frame                 100.80 Rupees One Hundred And   Per One      6350.40       --      The work shall be
Numbers         including disconnecting the sanitary and water supply                        Paise Eighty Only       Number                     --      carried as per wording
                connections, removing the same carefully and stacking the                                                                               of the item and as
                serviceable materials as and where directed including throwing                                                                          directed by the
                the unserviceable materials outside etc complete.                                                                                       Engineer in-charge.
35.00        4 . Removing W.C. pans including disconnecting the sanitary and         217.35 Rupees Two Hundred       Per One      7607.25       --      The work shall be
Numbers         water supply connections, removing and breaking flooring and                Seventeen And Paise      Number                     --      carried as per wording
                bed con-crete around pan removing the same carefully and                    Thirty Five Only                                            of the item and as
                stacking the serviceable materials as adn where directed                                                                                directed by the
                including throwing the unserviceable materiasls out side etc.                                                                           Engineer in-charge.
                carefully and throwing out the refusal outside etc. complete.
6.69         5 . Removing brick bat coba including stacking the spoils as            664.65 Rupees Six Hundred Sixty Per One      4446.51       --      The work shall be
Cubic           directed with all leads, lifts etc, complete.                               Four And Paise Sixty     Cubic                      --      carried as per wording
Metres                                                                                      Five Only                Metre                              of the item and as
                                                                                                                                                        directed by the
                                                                                                                                                        Engineer in-charge.
Name of work : MOW to Labour Commissioner office BKC Bandra Mumbai. (Repairs & Renovation of
               Toilet Block) (Gr to 3rd & 5th to 8th floor).
 Item                                   Description                                           Ref. to Std. Spn. Book                Additional Specification if any
  No.                                                                                         Item No and Page No.
        1 . Removing cement tiles, or marble or polished shahabad floor or dado                           --           The work shall be carried as per wording of the
          without bed concrete including stacking the materials as directed with all                      --           item and as directed by the Engineer in-charge.
          leads, lifts etc. complete
        2 . Dismantling the R.C.C. Work 1:2:4 and sorting out the materials such as                      --            The work shall be carried as per wording of the
          steel etc. as directed and stacking them within the specified lead as                          --            item and as directed by the Engineer in-charge.
          directed etc. complete.
        3 . Removing urinal pans or wash hand basins with frame including                                --            The work shall be carried as per wording of the
          disconnecting the sanitary and water supply connections, removing the                          --            item and as directed by the Engineer in-charge.
          same carefully and stacking the serviceable materials as and where
          directed including throwing the unserviceable materials outside etc
          complete.
        4 . Removing W.C. pans including disconnecting the sanitary and water                            --            The work shall be carried as per wording of the
          supply connections, removing and breaking flooring and bed con-crete                           --            item and as directed by the Engineer in-charge.
          around pan removing the same carefully and stacking the serviceable
          materials as adn where directed including throwing the unserviceable
          materiasls out side etc. carefully and throwing out the refusal outside etc.
          complete.
        5 . Removing brick bat coba including stacking the spoils as directed with all                   --            The work shall be carried as per wording of the
           leads, lifts etc, complete.                                                                   --            item and as directed by the Engineer in-charge.
(a)    Due performance and observance by the Contractor of the terms, covenants and
       conditions on the part of the contractor contained in the said Agreement and
(b)    Due and punctual payment by the Contractor to the Government of all sums of
       money, losses, damages, costs, charges, penalties and expenses payable to the
       Government by the contractor under or in respect of the said Agreement.
3.(a)   The guarantee herein contained shall remain in full force and effect during the
        subsistence of the said Agreement and that the same will continue to be enforceable
        till all the dues of the Government under or by virtue of the said Agreement have been
        duly paid and its claims satisfied or discharged and till the Government certifies that
        the terms and conditions of the said Agreement have been fully and properly carried
        out by the Contractor.
(b)     We shall not be discharged or released from liability under this Guarantee by reasons
        of
(c)     Our liability herein under shall be joint and several with that of the Contractor as if we
        were the principal debtors in respect of the said sum of Rs. ________________
        (Rupees _____________________________________ only.) and
(d)     We shall not revoke this guarantee during its currency except with the previous
        consent in writing of the Government.
(1) __________________________
(2) __________________________
Name of work :
Name of Agency :
Agreement No. :
The contractor hereby declares that the water proofing work carried out under this contract
shall be of the best quality and workmanship and shall strictly in accordance with the
specifications and particulars contained/mentioned in the clause hereof and the contractor
hereby guarantee that the said work should continue to conform to the description and quality
aforesaid for a period of Ten years from the date of handing over the said work to the
Department and notwithstanding the fact that the Department may have inspected and or
approved the said work. If during the aforesaid period of Ten years, the said work be
discovered not to conform to the description and quality aforesaid for a period of Ten years
from the date of handling over the said work to the Department and notwithstanding the fact
that Department may have inspected and or approved the said work. If during the aforesaid
period of Ten years, the said work be discovered not to conform to the description and quality
aforesaid or have deteriorated (and the decision of the Engineer in charge in that behalf will
be final and conclusive) the department will be entitled to reject the said work or such portion
thereof as may be discovered not to conform to the said description and quality. On such
rejection, the work will be at the contractor’s risk and all the provisions herein contained
relating to rejection of work etc. shall apply. The contractor shall, if so called upon, have to
make good the work etc. or such portion thereof, as is rejected by the Engineer in charge,
otherwise the contractor shall pay to the Department, such damages, as may arise by the
reason of the breach of the condition herein contained. Nothing herein contained shall
prejudice any other right of the Department in that behalf under this contract or otherwise.
Date :
Place : Contractor
Name of Work :-
I/We hereby declare that I/we have made myself / ourselves thoroughly
conversant with the local conditions regarding all materials and labour on
which I/we have based my/our rates for this tender. The specifications, and lead
of materials on this work have been carefully studied and understood by me/us
before submitting this tender. I/we undertake to use only the best materials
Andheri Mumbai or his duly authorised representative before starting the work
I/We hereby undertake to pay the labourers engaged on the work as per
Signature of Contractor
DRAWINGS
CONTRACT DRAWINGS :-
              The Contract Drawings provided for tendering purpose with the tender documents shall
       be used as a reference only.      Contractor should     visualize the nature and type of work
       contemplated and to ensure that the rates and prices quoted by him in the bill of quantities take
       due consideration of the complexities of work involved during actual execution / construction
       as experienced contractors in the field.
              The tendered rates / prices for the work shall be deemed to include the cost of
       preparation, supply and delivery of all necessary drawings, prints, tracings and negatives which
       the contractor is required to provide in accordance with the contract.
DOCUMENTATION :
              If so ordered by the Engineer-in-charge, the contractor will prepare drawings of the work
       as constructed and will supply original and three copies to the Engineer who will verify and
       certify these drawings.
              Final as constructed drawings shall then be prepared by the contractor and applied in
       triplicate alongwith a micro-film of the same to Engineer for record and reference purpose at
       the contractors cost.