Eur24 14-1
Eur24 14-1
Abstract - Several installations include synchronous users (e.g. medium voltage induction motors). This is
generators and, in some cases, synchronous motors. the typical case of a mid-size industry.
Under short-circuit conditions, the fault currents generated • Island power system where generator/s is directly
from the synchronous machine are characterized by a high connected to a medium voltage switchgear (e.g. at
level of asymmetry that requires suitable circuit breaker 11 kV level) where are derived the distribution
performances to ensure safe interruption of fault current. transformers (for load supply) and the users (e.g.
To calculate such interrupting performances, which are medium voltage induction motors). This is the typical
important for effective circuit breaker selection (IEC case of a mid-size industry not linked to the National
Standard discussed in this paper), it is necessary to grid, and is also the typical case of large offshore
properly consider: short-circuit current calculation installations, FPSOs, cruise & operating vessels,
Standards that vary depending on installation type etc…
(onshore and offshore), network topology and IEC circuit • Large synchronous motor/s connected to a medium
breaker Standards. voltage switchgear, where commonly other feeders
A systematic steps approach is discussed referring to a (distribution transformers and/or motors) are
real case study, investigating the symmetrical and connected. This is the typical case of a large industrial
asymmetrical components of the fault current and delayed complex such as LNG plants, etc…
zero crossing phenomena. Additionally, a set of sensitivity
analysis is proposed to give the reader an overall feeling All the above-listed types of installations, characterized
about potential critical conditions. by the proximity to the synchronous machine/s, are
potentially exposed to short-circuit currents with a high
Index Terms — Synchronous machine, circuit breaker, degree of asymmetry and delayed current zero crossing
short-circuit breaking capacity, delayed current zero phenomenon. Therefore, the investigation discussed in this
crossing. report is required.
I. INTRODUCTION
B. Analysis objective
It is well known from technical literature that in proximity
of a medium voltage synchronous machine, the short- The aim of the analysis is to accurately predict the short-
circuit current is characterized by a high degree of circuit current that the circuit breaker is required to interrupt,
asymmetry and potential delayed current zero crossing. to qualify its performances adequacy in respect of:
Therefore, special care is required in “near-to-generator • Rated short-circuit breaking current (Isc).
circuit breaker” selection process, to ensure suitable • DC time constant of the rated short-circuit breaking
performances to effectively and safely interrupt the short- current.
circuit current. • Rated short-circuit making current.
Transient recovery voltage (TRV) and out-of-phase • Delayed current zero crossing phenomenon.
current are not discussed in this paper.
C. Theoretical background of a synchronous machine
under short-circuit condition
A. System architecture and Electrical topology
A widely established fact from technical literature is that
The common architecture of an electrical system that the equation below defines the natural asymmetrical short-
includes medium voltage synchronous machine is typically circuit current behaviour of a synchronous machine at no-
one or a combination of the followings: load (here specifically for a turbo generator):
• Generator/s connected to the National grid system
through unit step-up transformer/s. This is the typical 𝑡
√2 ∙ 𝑉𝑚𝑔 ∙ 𝑆𝑛 1 1 − 1 1 −𝑡
case of conventional power plant, synchronous 𝐼𝑎𝑠𝑦𝑚 = − ) 𝑒 𝑇"𝑑 + ( − ) 𝑒 𝑇′𝑑
{[(
3 𝑥" 𝑥′ 𝑥′ 𝑥
compensator plants, and industrial complex with √3 ∙ 𝑉𝑛 𝑑 𝑑 𝑑 𝑑
1 1 𝑡
internal generation capacity. −
𝑇
+ ] cos(𝜔𝑡) − ( ) 𝑒 𝑎 }
• Generator/s directly connected to a medium-voltage 𝑥𝑑 𝑥"𝑑
switchgear (e.g. at 11 kV level) where at the same
voltage level are connected: the incomer from high- Where:
voltage grid (via step-down transformer), the Sn rated generator apparent power.
distribution transformers (for load supply) and the Vmg / Vn maximum and rated generator line-to-
line voltage. D. Reference IEC Standards
x"d, x’d, xd saturated direct axis subtransient,
transient and synchronous reactance’s. The following IEC Standards define the short-circuit
T"d, T’d short-circuit subtransient and transient current calculation procedure and the circuit breaker
time constants. performances.
Ta armature time constant. • IEC 60909-0 defines the procedure for calculating the
short-circuit currents in high-voltage and low-voltage
The equation describes the behaviour of both the three-phase a.c. systems with a rated frequency of
symmetrical and the DC components, which together 50 Hz or 60 Hz, excluding the installations on board
define the asymmetrical fault current that varies for each of ships and aeroplanes [1].
the three phases as illustrated in the next figure (Fig. 1). • IEC 61363-1 defines a procedure for calculating the
three-phase short-circuit currents of a.c. electrical
installations of ships and mobile and fixed offshore
units with a rated frequency of 50 Hz or 60 Hz [2].
• IEC 62271-100 defines the requirements applicable
to three-phase a.c. circuit-breakers designed for
indoor or outdoor installation and for operation at
frequencies of 50 Hz and/or 60 Hz on systems having
voltages above 1 kV [3].
• IEC/IEEE 62271-37-013 defines the requirements
applicable to three-phase a.c. generator circuit-
Fig. 1: asymmetrical fault current of the three phases breakers (defined as a circuit-breaker installed
between generator and associated step-up
The main factor that causes the high degree of transformer) designed for indoor or outdoor
asymmetry in proximity of a synchronous machine is installation and for operation at frequencies of 50 Hz
displayed in the following figure (Fig. 2). From the envelop and 60 Hz on systems having voltages above 1 kV
of the upper / lower waveform, the combined effect of the and up to 38 kV. It is applicable to generator circuit-
DC current component and the current amplitude reduction breakers that are installed between the generator and
can be observed. The first is the point of wave condition, the transformer terminals with rating equal to or
which is essentially the voltage phase angle at the fault greater than 10 MVA [4]. This Standard defines both
occurrence (in real-life it’s a random and uncontrollable the short-circuit current calculation procedure and the
phenomenon) while the second is determined by the circuit breaker performances.
subtransient and transient (and after a long time by the
synchronous) behaviour of the machine. Summarizing the above, two main types of high-voltage
Those two factors lead to high peak short-circuit current circuit breakers are defined: “circuit breaker” (in the
values and possible delayed current zero crossing (as following named “CB”) and “generator circuit breaker” (in
shown in example of below Fig. 2 not earlier than 5 cycles) the following named “GCB”) that comply with different
by shifting away from the zero value the current waveform. Standards, respectively [3] and [4].
At the same time, three short-circuit current calculation
methods are available. IEC 60909-0 specific for fixed
onshore installations, IEC 61363-1 specific for ships and
offshore installations, IEC/IEEE 62271-37-013 specific for
circuit breaker installed between generator and
transformer. Those methods, even if the physics are the
same and the electrotechnical concepts are invariable,
apply different mathematical equation and process.
TABLE II
RATINGS AND OVERALL SHORT-CIRCUIT RESULTS
Rated Rated Calculated initial
Calculated
short-time peak symmetrical
peak short-
withstand withstand short-circuit
circuit current
current current current
40 kA 100 kA 36.6 kA 94.7 kA
TABLE XIII
RESULTS FOR “CB-AUX” with CPT = 50 ms
%
Fault Isym Iasym Fig. 6: National grid only
Scenario Gen. deg.
pos. [kA] [kA]
Asym.
no-load 28.6 44.7 85% OK
Point 5 Normal PF lead 28.7 44.7 85% OK
PF lag 28.5 44.5 85% OK
TABLE XIV
INVESTIGATED DELAYED CURRENT ZERO CROSSING Fig. 10: National grid + Synchronous motor
Figure Description of short-circuit current sources
Fig. 6 National grid only
Fig. 7 Generator only
Fig. 8 Synchronous motor only
Fig. 9 National grid + Generator
Fig. 10 National grid + Synchronous motor
Fig. 11 Generator + Synchronous motor
Fig. 12 National grid + Generator + Synchronous motor
Fig. 13: National grid + Generator + Synchronous motor, Fig. 14: simplified protection single line diagram
sensitivity analysis
Summarizing, for this specific case, the following fault
Vice versa, in all the cases where the fault current is clearance times are expected:
composed by the synchronous machines only (generator
or the synchronous motor or the combination of the two), TABLE XIX
the short-circuit current zero crossing occurs in a range PROTECTION TRIP COMMAND TIME
from 80 ms to 140 ms. For delayed current zero crossing, Fault position Trip by Trip command
Point 1, 11 kV transf. terminals 87T 30 ms
the “CB-AUX” is the less critical one as there are no
Point 2, 11 kV switchgear 50 300 ms
restrictions to use a standard circuit breaker “CB” while, for
Point 3, generator terminals 87G 30 ms
all the others, needs to be verified the effective opening
Point 4, motor terminal 87M 30 ms
time by adding the protection trip time: if it will be lower than Point 5, aux. transformer terminals 50 20 ms
the calculated 80-140 ms, the installation of a generator
circuit breaker “GCB” may be required.
For Point 2, 11 kV switchgear, the considered trip
As a general note, the calculated delayed current zero
command time of 300 ms for the operation of transformer
crossing refers to the worst-case for one phase only based
on point of wave. Therefore, is a “random” phenomenon
incomer and generator phase overcurrent protection (50) III. SENSITIVITY ANALYSIS
ensure coordination with the other protections.
On breaker performance evaluation, is not intentionally The following additional technical consideration and
listed above the arc-detection system (that’s effectively sensitivity analysis are discussed.
installed on busbar compartment of the switchgear) even if
are even faster than a differential protection. However, A. Impact of armature resistance
since the trip command results where arc is released in air,
being the arc-plasma is characterized by high-resistivity One of the key factors determining the degree of
component, the level of asymmetry and delayed zero asymmetry and delayed current zero crossing is the
crossing are naturally mitigated. armature time constant of a synchronous machine.
With the target to provide a sensitivity analysis on this
parameter, sets of results (plots) are provided for a range
G. Final results of values of armature time constant from 50 ms to 300 ms,
by considering the same electrical parameters of the
In this case study, are investigated the current breaking generator.
capacity and the delayed current zero crossing condition The first plot provides the DC short-circuit current profiles
for the four circuit breakers investigated, with following that determine the increase of both the peak value of the
results: short-circuit current and the related zero crossing.
“CB-TR”: Symmetrical, asymmetrical, and making
currents are within the circuit breaker ratings in all the
cases, at time 40 ms. Delayed current zero crossing exists
for source side fault (Point 1, TR terminal 11 kV), where the
current crosses zero in approx. 140 ms (worst-case).
Differential protection 87T is expected to operate in this
case and send the trip command in 30 ms. The following
two alternative solutions can be applied:
1. select a circuit breaker “CB” type with performance
as per TABLE II and impose to the protection setting
a minimum intentional delay time of 120 ms.
2. select a generator circuit breaker “GCB” type, Fig. 15: DC short-circuit current [kA]
without any extra delay requirement.
“CB-GEN”: Symmetrical, asymmetrical, and making The following plot shows the profile of the degree of
currents are within the circuit breaker ratings in all the asymmetry (as a percentage) where is evident that a higher
cases, at 40 ms. Delayed current zero crossing exists for a values of armature time constants determine a level of
system side fault (Point 2, 11 kV switchgear), where the asymmetry above 100%.
current crosses zero in approx. 80 ms. In this case, the
protection system will not act before 300 ms and thus, a
circuit breaker “CB” type with performance as per TABLE
II is adequate and there is no need to install a generator
circuit breaker “GCB”.
“CB-MOT”: Symmetrical, asymmetrical, and making
currents are within the circuit breaker ratings in all the
cases, at 40 ms. Delayed current zero crossing exists for a
source side fault (Point 2, 11 kV switchgear), where the
current crosses zero in approx. 140 ms but in this case, the
protection relay of the synchronous motor will not directly
operate on it (eventual intertrip in long time ≥300 ms). Fig. 16: Degree of asymmetry of short-circuit current [%]
Consequently, also in this case, a circuit breaker “CB” type
with performance as per TABLE II is adequate and there is The last plot describes the instantaneous current profile
no need to install a generator circuit breaker “GCB”. on the worst-case phase, with relevant impact in term of
“CB-AUX”: Symmetrical, asymmetrical, and making delayed zero crossing. Higher values of armature time
currents are within the circuit breaker ratings in all the constant postpone the zero crossing: 20 ms (1 cycle) for a
cases, at 50 ms (for 40 ms the requirements are not Ta = 50/100 ms, 40 ms (2 cycle) for a Ta = 150 ms, 60 ms
satisfied). No delayed zero crossing condition subsists, and (3 cycle) for a Ta = 200 ms, 100 ms (5 cycle) for a Ta =
thus, a circuit breaker “CB” type with performance as per 250 ms, 140 ms (7 cycle) for a Ta = 300 ms.
TABLE II is adequate with a minimum trip time of 50 ms.
The proximity (near-to) of a synchronous machine [1] IEC 60909-0 “Short-circuit currents in three-phase
requires careful selection of the circuit breaker a.c. systems – Part 0: Calculation of currents”, 2016.
performances. [2] IEC 61363-1 “Electrical installations of ships and
Such verification requires several analyses discussed mobile and fixed offshore unit – Part 1: Procedures
step-by-step in this paper, where the electrical system was for calculating short-circuit currents in three-phase
modelled and studied in ETAP software. a.c.”, 1998.
The investigation of the short-circuit current magnitude [3] IEC 62271-100 “High-voltage switchgear and
compared with the target circuit breaker performances, the controlgear – Part 100: Alternating-current circuit-
delayed current zero crossing phenomena and the breakers”, 2021.
required circuit breaker opening time for the various [4] IEC/IEEE 62271-37-013 “High-voltage switchgear
locations of a fault, leads to a non-intuitive result. and controlgear – Part 37-013: Alternating current
In the studied network (Fig. 4 on page 3), for the circuit generator circuit-breakers”, 2021.
breakers located at the generator incomer and at the [5] IEC 62271-1 “High-voltage switchgear and
synchronous motor feeder, a circuit breaker “CB” controlgear – Part 1: Common specifications for
responding to the requirement of IEC 62271-100 is alternating current switchgear and controlgear”,
adequate. On the contrary, the outgoing feeder to the 2017.
auxiliary transformer is the one with the highest short-circuit
current breaking performance request and is II. VITA
recommended to apply an extra delay time to the protection
settings to prevent the needs of increase the circuit breaker Giovanni Gambirasio, M.Eng., P.Eng., is the Director of
rating. However, also in this case and with this additional SELECTY, a consulting company with worldwide business
delay (minor) a circuit breaker “CB” responding to the specializing in Power System studies and protection relay
requirement of IEC 62271-100 is adequate. The incomer coordination, across all the energy sectors. He has +10
from the transformer (from National grid) requires more years of professional experience in conducting and
performances in term of delayed zero crossing, up to reviewing different types of electrical power system studies
require a minimum delay to be applied to the transformer such as Load Flow, Short-circuit, Motor acceleration,
differential protection of 120 ms (to allow the use of circuit Transient Stability, Load Shedding, Generator Dynamic
breaker “CB” responding to the requirement of IEC 62271- model validation, Power Harmonics, Protection relay
100), or to select a generator circuit breaker “GCB” Coordination, CT & VT verification, and Arc-Flash hazard.
responding to the requirement of IEC 62271-C37-13. Since 2018, ETAP Representative for Italy and certified
Under this specific case study, the presence of the ETAP instructor for advanced class.
National grid connection (for which a sensitivity analysis gambirasio.giovanni@selecty.it
has been done) and the not-allowed island operation,
significantly simplify the calculation process and provide Mauro Giuseppe Codoni is a Senior Electrical Engineer
many benefits in term of results. In this sense, it is obvious focused on Power System Studies part of SELECTY’s
that any system operating in electrical island, is normally team, based in Bergamo, Italy. He has 15 years of
more subjected to this phenomenon, and for example in a professional experience in electrical engineering of
case like this one, will require special performances and industrial plants (oil & gas, cement, and power generation
potentially the requirement of a “GCB” an all the circuit application). Before joining Selecty he worked for an EPC
breakers, with a potential exception of the generator Company active in the oil & gas industry and thermal power
incomer circuit breaker “CB_GEN” only. plant, a major cement Company and an ORC power
This paper also includes a sensitivity analysis of the main generation unit Manufacturer. Mr. Codoni received his
parameters affecting the circuit breaker selection, along M.Sc degree (Electrical Engineering, 2006) at the
with the discussion of the concept of “near-to-generator” Polytechnic University of Milan and Certified professional
with a more scientific approach. Engineer for the State of Italy since 2007.
codoni.mauro@selecty.it