METHOD STATEMENT
FOR
CONSTRUCTION OF WATERPAN
         Method Statement   Page 1
      METHOD STATEMENT FOR THE WATERPAN CONSTRUCTION WORKS
1.0 INTRODUCTION
1.1   General
The purpose of this waterpan method statement is to describe the activities, sequence and
methods that are mandatory for carrying out this assignment which is waterpan construction
works. The activities described here under covers the scope of works for the
CONSTRUCTION OF KOSITEI WATERPAN IN BARINGO COUNTY. Since Inception, we
have carried out numerous waterpan projects and this forms the basis of this method
statement applicable in these projects.
As an ambitious Construction Company, we have adopted the best practice over time to
ensure we deliver our projects to the Clients’ satisfaction and beyond.
1.2   Components of Method Statement
In the execution of the works as spelt out in the program of works, the Contractor intends to
take the following basic steps in order to achieve his objectives:
     Mobilization.
     Publicity Sign Boards
     Setting Out
     Excavation And Construction Of The Water Pan.
        - Embankment
     Spillway.
             i. Concrete Sill
             ii. Riprap
     Silt Trap
     Quality Control
     Demobilization.
2.0 MOBILIZATION
2.1   General
The contractor shall, upon being given notice of Order to Commence, make necessary
arrangements to mobilize plant/machinery, site staff and any other persons connected to the
project.
2.2   Mobilization of Key Personnel
We shall deploy personnel to site as soon as the site has been handed over. Contractor
shall comply fully with the personnel requirements of the Contract and comply with all the
labour laws of the Country as well as providing all the necessary evidence of personnel
qualification an experience. The Contractor before deployment seek an approval from the
Client on the suitability of the Key Personnel. The three main key staff on site are:
      Site Agent (1)
      Foreman (1)
      Plant operator (2)
      Surveyor
Other site staff to be deployed for this assignement shall include are;
      Drivers
                                     Method Statement                               Page 2
     Watchmen
     Plant operators
     Surveyor
     Chainmen
     Casual workers
     Hired park security personnel as and when needed
Gender equality as well as compliance with Water 2000 strategy shall be fully ensured. The
Contractor shall make daily returns to the Client for concurrence with gender balance being
adopted by the Contractor.
The Contractor will mobilize the following key personnel in executing the activities in the
program of works;
   Position               Assigned Tasks
   Project Director        Coordinate project activities
                           Coordinate cash flow
                           Coordinate human resource
                           Coordinate machines and equipment
   Site Agent              Liaising with clients and reporting on progress
                           Supervising construction workers and hiring subcontractors
                              (if any).
                           Buying materials for each phase of the project
                           Monitoring build costs and project progress
                           Conducting quality and safety inspections
                           Checking and preparing site reports, designs and drawings
                           Maintaining quality control checks
                           Motivating the workforce
                           Day to day problem solving and dealing with any issues that
                              arise
                           Using specialist project management computer programmes
                           Working on-site in all weathers, at clients’ businesses or in a
                              site office.
   Foreman                 Supervise key activities like excavation,concrete works and
                              otherwaterpan construction activities.
                           Supervise waterpan construction crew daily and assist a
                              team of heavy equipment operators to build water projects
                           Provide hands-on training as required
                           Manage project start-up, one calls, utility locates and sub-
                              contractors
                           Manage and coordinate activities with the landowners,
                              contractors, other consultants and the approving authority
                           Read, interpret, and understand construction drawings and
                              specifications
                           Monitor expenditures to ensure projects remain within budget
   Surveyor                Produce waterpanlayouts using surveying instruments and
                              tools.
                           Supervise setting out of carious items
                           Levelling
                           Establish lines and grades within the construction site by
                              performing construction surveys.
                           Perform daily record keeping of work performed on a daily
                              basis and share the records with the Site Agent
   Plant operator          Operating heavy machinery and equipments on site
                                     Method Statement                               Page 3
The contractor will also mobilize support staff which include and not limited to driver (s),
secretary and unskilled labour.
            As part of the Contractor’s tradition, unskilled labour will be sourced            2.3
                   from the locals where the project will be implemented.                      Si
        te organisation
            Projects manager/Engineer – Headquarter Based
                        Site agent                                 Foreman & Surveyor
                                                      Machineries               Semi-Skilled
                                                      Operator / Driver         Staff
2.4     Mobilization of Machines and Equipment
Well-operated equipment are essential ingredient in successfully implementing a road
construction project. The contractor will mobilize the following equipment where applicable
to ensure successful completion of works;
Equipment       Function
Dozer D6        Dozer will be used for preparation of formation, levelling of tipped
                material, processing of fills in layers. Level to desired pre-compaction
                thickness and where practicable shall be used for top soil stripping.
Drum Roller     For compaction
Excavator       For Excavation of gravel material and load it onto the tippers. This will
                also be used for demolishing, stock piling materials and to be used
                where dozer cannot be used.
Pickups         For transport of light construction material
Tippers         It will be used to haul fill material/gravel material to the required
                sections and to haul cleared and grabbed material and top soil material
                to the designated spool areas.
Poker vibrator  For compacting concrete
Concrete mixer For batching
Other    simple Wheelbarrows, spades etc for simple tasks on site
tools
Mobilization of this equipment will include hiring of equipment not owned by the contractor.
2.4.1    Equipment Ownership
The contractor owns some of the basic equipment necessary for execution of works as
indicated and evidenced in standard forms of tender however at instances where the
Contractor lacks the equipment the Contractor has already established an agreement with
Mechanical and Transport Department in Nairobi – MTF to hire these equipments.
                                        Method Statement                              Page 4
2.4.2     Equipment Management Plan:
We shall provide a well-resourced equipment return schedule that clearly indicates
equipment usage and operation i.e. idle time, break down and operation to ensure optimal
use of and accountability of equipment engagement. The Plan shall also include preventive
maintenance schedule of the equipment and vehicles for the project.
2.5     Publicity Board
The Contractor shall provide Sign Boards as specified on the Drawings or as directed by the
Engineer. The Sign Boards shall be placed at the beginning and end of the road or road
section covered by this Contract. Sign Boards shall be maintained for the duration of the
Works, and retained on site upon completion of the works.
2.6     Sources of Materials
At mobilization stage, the contractor shall at the same time, establish potential borrow pits
for gravel from the area adjoining the project road.
Sources of materials like bitumen, chippings etc. will also be identified at this stage.
2.7     Setting Out.
The Contractor shall also use this time to acquaint himself with the existing service lines as
well as structures.
The Contractor intends to use the available space and alignment with minimum disturbance
to the existing Structures.
3.0      CONSTRUCTION OF THE WATER PAN METHODOLOGY
3.1     Excavation
We shall mobilize the necessary excavation equipment to the site and proceed to
excavate the reservoir area to the specified depth of 2-3 meters, ensuring proper
compaction of the excavated area. Following excavation, we will begin the
construction of the embankment, placing and compacting suitable materials in layers
to form the embankment with a width of 4 meters and side slopes of 3:1 upstream
and downstream
3.2     Spill-way installation
         To begin the spillway construction, we will excavate the designated area to the
         specified dimensions of 8 meters wide at the bottom and a length of 72
         meters, with side slopes of 1:1. Following this, we will proceed with the
         construction of a concrete sill, measuring 12 meters in length, 0.3 meters in
         width, and 0.8 meters in depth, utilizing concrete of class 25 (mix 1:2:4).
         Subsequently, selected materials will be placed and compacted in layers of
         150mm spillway riprap, ensuring proper stability and functionality. Finally,
         riprap will be positioned to cover one-third of the upstream face embankment
         from the crest top, completing the spillway installation process.
                                       Method Statement                                    Page 5
3.3   Silt-trap construction
To initiate the construction of the silt trap, we will excavate the designated area to the
specified dimensions of 30 meters in length, 20 meters in width, with side slopes of 2:5:1.
Subsequently, we will proceed with the construction of the silt trap basin, which will measure
20 meters in length and 10 meters in width at the bottom. Following this, the installation of
stone pitching will be carried out to direct sediment-laden water from the collection channel
into the silt trap and then out into the main pan. This process will involve using 250mm
hardcore for reinforcement to ensure the structural integrity and effectiveness of the stone
pitching system.
4.0       QUALITY CONTROL
The compliance testing required to approve the compaction will be performed using the
recognized standard procedures as defined both in General specification AASHTO and
British Standards. However, where possible, it is intended that Sand Replacement Tests be
carried out in sufficient number to realistically assess the insitu density pertaining to the
number of passes of the rollers.
Where such testing is shown to be difficult to perform it may be necessary to prove the
effectiveness of the compaction by proof rolling each section separately.
To support the results of the field testing, samples of the fill material shall be taken for
determination of the parameters listed as follows:
         Particle size Analyses
         Soils Classification Tests MDD/OMC
         CBR
         Natural Moisture Content.
The contractor will ensure that the best standards of workmanship and materials are
obtained for the Employer within the terms of the contract including controlling over what will
be accepted into the works. This may include:-
     Assessing the suitability of the methods proposed by the Contractor (not instructing
         him on method).
     Accepting materials to be incorporated into the permanent works.
     Approving the Contractor's workmanship.
Contractor will ensure that materials quality controls is adhered to as per the specification to
ensure that materials used and all working areas comply with the project plans and
specifications.
The contractor will adopt standard construction procedures and quality controls to ensure
that the methods used for executing the work will produce the end results intended by the
plans and specifications.
5.0       MEASUREMENTS AND CERTIFICATION
Computations for quantities will be carried out in accordance with the methods specified in
the construction specifications. The verification of actual work output will be achieved by joint
survey and measurement of completed works carried out by both the Engineers
Representative and the contractor's surveyor as indicted in the document and within the
tolerances specified in the construction documents. The contractor will ensure that the
specified tolerance is not exceeded. Certificates and Payments shall be based on actual
measured quantities of work performed not on billed quantities.
                                      Method Statement                                 Page 6
6.0     PHOTOGRAPH PLAN.
We shall provide a photograph plan to record the condition of the road before and after
works have been done and progress as proof of quality control and measurement or any
event that may arise that affects progress or quality.
The photos will be taken during material testing, before start of the process and completion
of a process, during monthly inspections and at measurement.
7.0     WORKS SAFETY MANAGEMENT AND ENVIRONMENTAL CONSIDERATIONS
7.1   Work Safety Management
a) Work Safety
Safety meeting shall be conducted weekly to induct new staff of the safety requirements.
Staffs will be -provided with safety gears e.g. Safety boots, Helmet, Dust must, gloves and
dust coat, including provision of high visibility clothing or vests for the workforce
b) Accident prevention
To reduce cases of accident on site to individual staffs or animals, the dos and don’ts while
on site shall be explained to the staff.
In addition the contractor shall liaise with the park management for provision of security to
his workers
The Contractor shall be responsible for the provision of all equipment, tools, material, and
temporary stores.
The contractor shall also maintain first aid kits with a minimum of the following items:-
     Crepe bandages
     Gauze and cotton wool Antiseptic solution (washing wounds)
     Antiseptic cream
     Pain killers
     Anti diarrhoea
     Anti nausea Antibiotic
     Eye ointment
     Oral re-hydration sachets
     Surgical gloves
7.2   Environmental Considerations
During the construction period, the Contractor's proposes to take into account environmental
considerations and compliance with stipulations and or mitigation measures for
environmental protection as presented in the Contract Documentation.
The contractor will monitor closely the environmental and safety aspects during construction,
with regards to all mitigation and environmental protection measures. The Environmentalist
will therefore visit the project area on a regular basis. This will also ensure that should any
unforeseen environmental problems arise, recommendations for their aversion or mitigation,
as the case may be, can be made before the problems become intractable.
Quality control procedures for material sites play an important role in environmental
protection, and in addition, will expedite the rehabilitation of the quarries and borrow pits.
The Contractor shall observe the following measures with a view to reducing or elimination
adverse environmental effects by the site works:
                                      Method Statement                                 Page 7
       All quarries and borrow pits shall be filled and landscaped to their original state after
        extraction of construction material
       Spillage of oils, fuels and lubricants shall be avoided and if spilt, shall be collected
        and disposed off in such a way as not to adversely affect the environment
       Rock blasting near settlement areas shall be properly coordinated with the relevant
        officers of the Government so as to minimize noise pollution and community
        interference
8.0      FIELD (SITE) DIARY
The contractor shall maintain a daily diary to record the operation(s) being inspected and
record (but not be limited to) the following details
     Weather conditions
     Equipment conditions, hours of work, hours idle or broken down giving reason(s)
        why equipment was not productive at any particular time.
     Employees on the section he was in charge of.
     Narrative discussion on the type of work completed by the Contractor by location
        compliance with the specifications and directives given concerning amendments or
        interpretation of plans detailed structural drawings and specifications.
     Short summary of tests taken indicating actual locations.
     Source of materials used and quantities used when possible.
     Short summary of tests taken indicating actual locations.
     Source of materials used and quantities used when possible.
     Potential disputes.
9.0      SITE MEETINGS
There will be site meetings as regularly as required, with Engineer's Representative. The
meetings will deal, inter alia, with the following matters:
     Approval on rejection of executed work elements
     Work schedule
     Work methods
     Temporary works
10.0    DEMOBILIZATION
Upon substantial completion of works, the contractor shall write to the engineer to request
for substantial inspection of works to allow for processing for payment.
                                       Method Statement                                Page 8