Earthquake Contingency Plan 2024
Earthquake Contingency Plan 2024
PEREZ MEMORIAL
TECHNICAL-VOCATIONAL HIGH SCHOOL
Contingency Plan
for
EARTHQUAKE
As of April 2024
1
TABLE OF CONTENTS
CHAPTER I. BACKGROUND
A. Introduction ………………………………………………..………………….... 3
B. Hazard Analysis CP Form 1……………………………….……………………. 5
C. Anatomy of the Hazard CP Form 2……………………….……………………. 6
D. Scenario CP Form 3A……………………………………….……………………. 7-8
CP Form 4A.1 (affected learners) …………………………………….. 9
CP Form 4A..2 (affected personnel)……………………………………… 10
CP Form 4B.1 (Breakdown of Affected Learners) ……………………….. 11
ANNEXES
2
CHAPTER I. BACKGROUND
A. Introduction
3
As of history, fortunately, the school has no recorded major damages due to
earthquakes. However, the school must make a contingency plan for this calamity.
This contingency plan should be done collaboratively among the school community,
PTA Officers, and Local Officials headed by the School Head.
LOCATION MAP
AERIAL VIEW
4
B. Hazard Analysis
Earthquake 2 The Central Cebu Fault systems 3 Last major earthquake, the school has 2.5 3
runs through the mountain minor damages of school facilities
ridges of Danao City in the
north.
Typhoon 5 Tropical cyclone and other 3 Previous tropical cyclone brought heavy 4 1
weather disturbances frequently rainfall with windspeed ranging from 185
pass through the area kph to 215 kph. The tropical cyclone
caused major floods in the area
Hot weather 3 Due to new classes schedule, 1 For the month of March to May, the 2 4
the school experienced hot school experienced heat wave which
weather especially during the resulted to suspension of face to face
month of March to May. classes.
Landslides 4 Based on the assessment from 2 It may cause damages to the school 3 2
Mines and Geoscience Bureau facilities.
department.
The table above shows that there are 5 possible hazards that might struck to our school. Among of these hazards are typhoon which is
most likely to occur due to the geographical locations of the school. It followed by a landslide on which the school is prone to landslides. Third, the
school usually experience typhoon for every year. One of the strongest typhoons that brought a major damages of school facilities was the typhoon
Odette. Fourth is the hot weather on which recently by month of April 2024, there was a suspension of face to face classes. Finally, the last hazard
which are likely to occur is the fire. All of these identified hazards need to craft a contingency plan.
5
C. Hazard to Plan for: EARTHQUAKE
Based on the result that these Hazards is caused and triggered by Natural Phenomena. Early warning signs should be
monitored to lessen the impact of the disaster as well as prevent the increasing number of casualties. The mitigating measures must
be followed.
6
D. Scenario (Earthquake)
7
No. of Missing Non-Teaching Personnel (Male, 1 2
0
Female)**
Infrastructure*
- Classrooms 0 1-2 14
- WASH facilities 0 1 3
- Other infrastructures and ancillary facilities 0 1-2 5
(e.g., laboratories, clinic, library)
Non-infrastructure*
- Furniture and fixtures 1-4 5 and above
- Learning resources and self-learning modules 0 1-10 10 and above
- Information and Communication Technology 0 1 2 and above
(ICT) equipment 0
Other non-infrastructures (e.g., laboratory
equipment, medical and dental equipment and
supplies, technical-vocational supplies and
equipment)
Communication is Interrupted No communication
Communication**
still available
Power/ Electricity** 10 Partial Partial
Transportation 0 Partial Partial
Response Capabilities 100% 90% 80%
Based on the projected table, every scenario has its value as well as measures to undertake when happens. Classification into
bad, worse, and worse scenarios is also reflected so that it would be clear for the team to come up with desirable decisions.
Data for both human and non-human resources affected are also shown to design specific measures and interventions for
quick recovery.
8
CP Form 4A.1: Affected Learners Inside and Outside Isolation/Quarantine and Healthcare Facility
Grade 8 78 0 0 0
Grade 9 74 0 0 0
Grade 10 78 0 0 0
Grade 11 113 0 0 0
Grade 12 129 0 0 0
TOTAL 526 0 0 0
There are 526 affected learners every time an incident happened. Based on the report, nothing was reported to be inside and
outside in the evacuation facility.
CP Form 4A.2: Affected Personnel (Inside and Outside Isolation/Quarantine and Healthcare Facility)
9
NO. OF NO. OF
NO. OF NO. OF NON- NO. OF NON-
TEACHING TEACHING NO. OF NON-
TEACHING TEACHING TEACHING
PERSONNEL PERSONNEL TEACHING
PERSONNEL PERSONNEL PERSONNEL
INSIDE HOME-BASED PERSONNEL
NO. OF INSIDE Reasons INSIDE INSIDE
AREA/ EVACUATION EVACUATION EVACUATION
TEACHING EVACUATIONFA for EVACUATION EVACUATION Reasons for
LOCATION FACILITY FACILITY FACILITY
PERSONNEL CILITY Displace FACILITY FACILITY
LOCATION (Diasaggregat (Diasaggregate (Diasaggregate Displacemen
AFFECTED (Diasaggregate ment (Diasaggregate (Diasaggregate
e data as to data as to data as to t
data as to data as to data as to
female, male, female, male, female, male, IP,
female, male, IP, female, male, IP, female, male, IP,
IP, muslim, IP, muslim, muslim, PWD)
muslim, PWD) muslim, PWD) muslim, PWD)
PWD) PWD)
0 0 0 0 0 0
ELPIDIO H.
PEREZ 25
MTVHS
TOTAL 25 0 0 0 0 0 0
There are 25 affected teaching personnel and 2 non-teaching personnel every time an incident happens. Based on the report,
nothing was reported to be inside and outside the evacuation facility.
There are 526 affected learners every time an incident happened. Based on the report, nothing was reported to be inside and outside
in the evacuation facility
11
CHAPTER II. GOALS AND OBJECTIVES
A. Goal
The goal of the contingency plan is to provide effective, efficient, timely, and well-
coordinated response mechanisms in the event of the occurrence of an earthquake in
barangay Masaba, Danao City specifically in ELPIDIO H. PEREZ MEMORIAL
TECHNICAL NATIONAL HIGH SCHOOL. Such mechanisms shall help to protect lives,
properties, and the environment, and restore the immediate needs of the affected
communities.
B. General Objective(s)
12
CP FORM NO. 5: IMPLEMENTATION PLAN
Response Clusters
Lead: Members
2. ALDRIN B. PEREZ
3. JENNYLOU M. TITO
4. ERIC L. MANZO
7. JANREY J. SENCIO
8. IKE Q. BULAGSAC
9. LEIZEL O. PEÑAS
Scenario: (Describe the specific scenario that will be faced by the Response Cluster. The said scenario must be
consistent with the worst-case):
Occurrence of earthquake magnitude scale of 6.1 to 7.9 May cause a lot of damage in very populated areas and major
serious earthquake damages
Objectives: (Enumerate the specific objectives for the response Cluster. These should be in accordance with the CP
goal ang general objectives):
1. To ensure the safety and well-being of Elpidio H. Perez MTVHS learners and, teaching and non-teaching
13
personnel by applying mitigating measures on damage to office infrastructure and equipment
2. To promote personnel resilience
3. To implement strong emergency responses, protocol, efficient risk assessment, accounting of lives and
properties, public education and awareness, and infrastructure reinforcement through creating a
comprehensive plan for earthquake preparedness
Roles and Responsibilities: (Enumerate the roles and responsibilities of the head and members of the Response
Clusters. Protocols may be added as well):
Participate in training sessions and drills to prepare for earthquake mitigating measure responses.
Developing and updating emergency response plans and procedures.
Conducting risk assessments and identifying vulnerable areas or structures.
Coordinate with relevant authorities, agencies, and stakeholders to ensure response efforts.
Communicate, and update instructions and information.
Deploy trained personnel to locate and rescue individuals trapped in collapsed buildings.
Coordinate agencies responsible for inspecting buildings, infrastructure, and utilities to assess structural
14
integrity and identify hazards.
Documenting damage and compiling reports for use in recovery efforts.
Collaboration with engineers and building inspectors to prioritize repairs and restoration
Providing information and guidance to the public regarding earthquake safety measures and evacuation
procedures.
Communicating with media outlets to disseminate updates and advisories
Addressing public concerns and inquiries related to earthquake response efforts
Collaborating with local, regional, and national authorities to coordinate response efforts
Participating in multi-agency task forces and committees focused on disaster preparedness and response
Facilitating communication and cooperation between different response teams and organizations
15
CHAPTER III. RESPONSE ARRANGEMENTS
A. Response Activities
TIMEFRAME RESPONSIBLE
SCENARIOS (after the RESPONSE ACTIVITIES COMMITTEE/
trigger) PERSONNEL
Scenario 1 Within 24 Perform the basic process (sound alarm, drop, cover and hold, SCHOOL DRRM
BAD hours proceed to evacuation center, and do head counting) TEAM
Conduct triaging (separation for dead, injured, etc.)
Follow the reunification procedure
Coordinate with the Division DRRM Coordinators on the
status of the preparedness and/or response measures and
update on the impact of the hazard
Conduct assessment of infrastructure
Certificate of no damages
Within 48 to 72 Start ADM SCHOOL DRRM
hours Functionalize the quick and response team TEAM,
Comply with the D.O 65 s. 2017 BDRRMO &
Send RADAR report to C.O CDRRMO
Send incident or damage report to the division office
Ready the RLS (temporary learning space) either in barangay
covered court or request the TLS to C.O
Always initiate a Memorandum of agreement for TLS
After 72 hours Continue Monitoring of all damages, status of facilities SCHOOL DRRM
and onwards Conduct psychological first aid TEAM,
Conduct mental health psychological support BDRRMO &
CDRRMO
16
TIMEFRAME RESPONSIBLE
SCENARIO
(after the RESPONSE ACTIVITIES COMMITTEE/
S
trigger) PERSONNEL
Scenario 2 Within 24 Perform the basic process (sound alarm, drop, cover and hold, SCHOOL DRRM
WORSE hours proceed to evacuation center, and do head counting) TEAM
Conduct triaging (separation for dead, injured, etc.)
Search and rescue
Follow the reunification procedure
Coordinate with the Division DRRM Coordinators on the
status of the preparedness and/or response measures and
update on the impact of the hazard
Use the contingency plan
Conduct psychological first aid
Conduct mental health psychological support
Within 48 to 72 Functionalize the quick and response team and let them SCHOOL DRRM
hours assess the damages. TEAM,
Comply with the D.O 65 s. 2017 BDRRMO &
Send RADAR report to C.O CDRRMO
Send incident or damage report to the division office
Ready the TLS (temporary learning space) either in barangay
covered court or request the TLS to C.O
After 72 hours Continue Monitoring of all damages, status of facilities SCHOOL DRRM
and onwards Make TLS and tap into potential stakeholders TEAM,
BDRRMO &
CDRRMO
17
TIMEFRAME RESPONSIBLE
SCENARIOS (after the RESPONSE ACTIVITIES COMMITTEE/
trigger) PERSONNEL
Scenario 3 Within 24 Perform the basic process (sound alarm, drop, cover, and SCHOOL DRRM
WORST hours hold, and proceed to evacuation center) TEAM
Conduct triaging (separation for dead, injured, etc.)
Search and rescue
Follow the reunification procedure
Coordinate with the Division DRRM Coordinators on the
status of the preparedness and/or response measures and
update on the impact of the hazard
Within 48 to 72 Start ADM SCHOOL DRRM
hours Assessment of physical damages TEAM,
report BDRRMO &
Functionalize the quick response team CDRRMO
Comply with the D.O 65 s. 2017
Send RADAR report to C.O
Send incident or damage report to the division office
Ready the RLS (temporary learning space) either in barangay
covered court or request the TLS to C.O. Note MOA is
required
After 72 hours Continue Monitoring of all damages, status of facilities SCHOOL DRRM
and onwards Conduct psychological first aid TEAM,
Conduct mental health psychological support BDRRMO &
Tap potential stakeholders for TLS CDRRMO
Note: Refer also to existing policies such as DepEd Order No. 33 s. 2021 (Enclosure 2), OM-OSEC 2021-002
It is practical to exercise response activities only within 72 hours onwards for this particular incident. Within the
period of the incident until the day it ends, it is obvious that the activities stipulated are measurable and specific.
Thus, this will lead to proper channeling and response protocols.
18
B. Resource Inventory
RESPONSE CLUSTER
Megaphone 1 Serviceable
SDRRM TEAM
The school has established an Emergency Response Team equipped with basic communication and emergency
response facility. Trained in basic life support, Emergency Rescue and Transport, Radio Handling, and Fire Fighting.
In their chaste to support the team, additional equipment is still needed to maximize the response.
On the other hand, grade leaders and security personnel also need an additional communication facility to
facilitate not only in emergencies but in everyday situations as well.
C. Resource Projection
19
CP Form 8: Resource Projection
RESPONSE
CLUSTER
COST ESTIMATES SOURCE OF FUNDS
GAPS ACTIVITIES/ SOURCES TO FILL
RESOURCES NEEDS HAVE (FILL UP ONLY WHEN (FILL UP ONLY WHEN
(NEED - HAVE) THE GAPS
APPROPRIATE) APPROPRIATE)
Hard Plastic Craft an activity design
6 0 6 14946 School MOOE/Other sources
Spine Board Tapping stakeholders
Dual Fuel Portable Craft an activity design
3 0 3 57240 School MOOE/Other sources
Generator Tapping stakeholders
Craft an activity design
First Aid Kit FA-12 14 4 10 17066 School MOOE/Other sources
Tapping stakeholders
Craft an activity design
Mega Phone 6 0 6 28000 School MOOE/Other sources
Tapping stakeholders
Walkie-talkies two-way Craft an activity design
20 20 0 - School MOOE/Other sources
radio Tapping stakeholders
4200w gasoline Chain Craft an activity design
1 0 1 2500 School MOOE/Other sources
Saw Tapping stakeholders
Craft an activity design
Hydraulic jack 1 0 1 1500 School MOOE/Other sources
Tapping stakeholders
Craft an activity design
Hard Hat set with strap 30 0 30 63600 School MOOE/Other sources
Tapping stakeholders
Outdoor dolphin Craft an activity design
20 0 20 1600 School MOOE/Other sources
Whistle Tapping stakeholders
Firefly powerful led
Craft an activity design
torch Emergency 14 0 14 13356 School MOOE/Other sources
Tapping stakeholders
flashlights
Solar panel (dual glass Craft an activity design
3 0 3 25000 School MOOE/Other sources
590 watts) Tapping stakeholders
Tigronyx Green fire Craft an activity design
4 0 4 34000 School MOOE/Other sources
extinguisher 20 lbs Tapping stakeholders
Based on the table presented, it is evident that there is an insufficient supply of disaster preparedness
equipment. Stakeholders and other means may be employed to supplement the immediate needs to avoid further and
massive damages
Search, rescue, and retrieval Hard plastic spine board, generator, 450000.00
first aid kit, megaphone, chain saw,
hydraulic jack, hard hat, whistle,
emergency flashlights, solar panel,
and green fire extinguisher
Emergency response equipment is vital in all emergent situations. This is to prevent learners and school
personnel from getting hurt and minimize damage. In our case, School MOOE and tapping our Stakeholders is
enough to cater to the procurement bills, thus, procurement of disaster preparedness equipment is rarely prioritized.
With this, large numbers or quantities are still needed to standardize the needs of the school. PTA subsidy and other
Local stakeholders are needed to immediately fill the Gap. More so, members of our Emergency Response Team have
purchased their equipment.
Ideally, each school should have adequate and complete disaster preparedness equipment. We always remember
that a well-planned and prepared community is always a safe community.
21
E. Directory of School Disaster Risk Reduction and Management Team
(SDRRMT)
Others:
RDRRM TEAM
POSITION NAMES AND ADDRESS CONTACT INFORMATION
(CUSTOMIZE AS APPROPRIATE) (PRIMARY AND ALTERNATE) (PRIMARY AND ALTERNATE)
School Head ALVIN B. CAMBAYA 09054055642
Guinsay, Danao City
School DRRM Coordinator FLORA MAE S. MAHILUM 099223059229
Taytay, Danao City
Alternate: ALDRIN B. 09995238395
PEREZ
Purok 4, Masaba, Danao
City
Medical team Grace G. Lendio 09232872398
Poblacion,Danao City
GPTA President Rhea Mea M. Hermosada 09226170981
Masaba, Danao City
Punong Barangay Sulpicio E. Perez 09295247338
Purok 4, Masaba, Danao
City
Others___________
23
COMPOSITION OF QUICK RESPONSE AND RECOVERY TEAM
(QRRT)
ALVIN B. CAMBAYA
Responsible Officer
CONCEPCION C. ENTERO
Assistant RO FLORA MAE S. MAHILUM
Incident Commander
CHARIFE G. GUNGOB
Communication
24
CHAPTER IV. ACTIVATION, DEACTIVATION, AND NON-ACTIVATION OF
CONTINGENCY PLAN
A. Activation
B. Deactivation
The deactivation of this school contingency plan is contingent only upon the
state of the community as a whole, as determined by the evaluations of our city health
office, city DRRM office, and barangay local government. After the deactivation of the
contingency plan, the field will receive a school memorandum. Any of the following
triggers are included in this:
When earthquake and aftershock ceases.
When school facilities and amenities are intact and take no damage due to
typhoon
When everyone (Teaching and non-teaching staff, Students and Parents and
the community is safe and at peace.
C. Non-activation
This School Contingency Plan will not be triggered unless further evaluation is
completed with the assistance of the City DRRM Office, particularly in cases where a
scenario calls for specialist skill, particularly in the field of seismology. Any further
actions pertaining to this strategy must be consistent with the current command
structure that the City has chosen.
Below is the school CP activation, deactivation, and non-activation chart for plan
event.
23
CP Activation Flow Chart for Earthquake
START
PhiVocs
Advisory
DRRMC
conducts
PDRA
Earthquake strikes,
DRRMC will conducts
PDANA
1
2
RO mobilizes and
deploys IMT Clusters provide
continuous support
to responders
Clusters and IMT
operate based on
contingency plan
No
Situation
3
normalize
No d?
Situation
1 Yes
improved?
IC recommends
Yes demobilization
IMT recommends
deactivation of RO approves recommendation
contingency plan for demobilization
END
24
ELPIDIO H. PEREZ MTVHS CP Activation and De-Activation chart for Earthquake
START
DRRMC activates
contingency plan
RO convenes the
clusters at EOC
Planned
event ended?
IMT recommends
deactivation of
contingency plan
RO directs deactivation of
contingency plan
END
23
ANNEXES
Working Group
Purpose:
RO mobilizes and
deploys IMT
The Working Group will be responsible for the refinement, finalization, testing,
evaluation, packaging, updating and improvement of the Contingency Plan.
Clusters and IMT
operate based on
contingency plan
Duties and responsibilities
1. Facilitate the refinement and finalization of the Elpidio H. Perez Memorial
No
Technical Vocational High School Contingency Plan to include testing,
evaluation, packaging, updating and improvement;
Yes
2. Develop work plan for the completion and updating of the Elpidio H. Perez
Memorial Technical Vocational High School Contingency Plan;
3. Organize consultation meetings with the planners and relevant technical experts
regarding the development of the Elpidio H. Perez Memorial Technical Vocational
High School and
4. Facilitate the presentation and endorsement of the Elpidio H. Perez Memorial
Technical Vocational High School Contingency Plan to the authorities for
comments and approval.
24
TECHNICAL WORKING GROUP
Purpose:
The Working Group will be responsible for the refinement, finalization, testing,
evaluation, packaging, updating, and improvement of the CP.
WINONA L. JOPIA
ROSEMARIE HERMOSO
23
Members:
Search & Rescue: ……………………..Aldrin B. Perez and Janrey Sencio
Damage Assessment: ………………...Vicente M. Gomez Jr. & Adonis Restie Ochia
Public Safety & Communication: .... Jennylou M. Tito
Logistic & Support: …………………… Eric L. Manzo & Leizel O. Peñas
Coordination & Collaboration: …….. Ike Bulagsac
Post-Event Recovery: ………………… Grace G. Lendio
24