Ongc Training Report
Ongc Training Report
By
Sumit Mandal
Certificate
1
This is to certify that the training
report titled “Processes at
ONGC and available firefighting facilities and
equipment” is being submitted by below listed
student, is in line with requirements for the award
of completion of training certificate for the training
at IPSHEM, ONGC GOA campus during the two-
week period from 16th August – 29th August in
the academic year 2020-21.
List of Students MR. Alok Kumar
Deepak Kumar 20618028
Gaurav Kumar 20618031 Manager, Fire Services,
Pawan Singh Bisht 20618047 ONGC
Pawan Yadav 20618048
Saurabh Chaubey
20618056
Shubham Sinha
20618058
Sumit Mandal 20618062
A Adhithya 20618001
Abdul Razak P S
20618003
Ashish A S 20618019
Beebi Nuamana Khaleel P P
20618026
K S Sreehari 20618038
Sneha Joseph 20618059
2
Declaration
3
Table of Contents
1 Cover Page 1
2 Certificate 2
3 Declaration 3
4 Acknowledgments 5
5 Abstract 6
6 About ONGC 7
7 Processes and Associated 9
Hazards in ONGC
8 Fire-fighting facilities and 27
methodologies adopted in ONGC
9 Recommendation as per OISD 47
STD 189
10 Conclusion 51
4
Acknowledgements
5
Abstract
The upstream industry is arguably the most complex of
all the oil and gas business sectors. Since it is highly
capital-intensive and highly risky business by its nature,
early Hazard Identification and their mitigation becomes
very crucial.
This project is an attempt to recognize major processes
happening at ONGC India’s largest PSU and accident
hazards & their control measures as taken by the
organization. Major accident hazards are those that have
the potential to cause multiple fatalities, ecological
imbalance and may necessitate the evacuation of
facilities. The potential for escalation of the initial events
is primarily determined by the design of the facility and
the protection systems provided.
The project puts forth a comprehensive analysis of all the
norms and methodologies at place in ONGC through a
comparative study with the adopted policies and
requirements as per the Standard (OISD 189).
6
ABOUT ONGC
7
two are subsidiaries of ONGC) to produce petroleum products
like Petrol, Diesel, Kerosene, Naphtha, and Cooking Gas LPG.
Oil and Natural Gas Corporation Limited (ONGC) is a global
energy holding company, engaged in the oil exploration,
development, and production of crude oil and natural gas. Its
segments include Exploration & Production (E&P), and
Refining.
ONGC's on-going upstream exploratory efforts are an
important segment of its core E&P Business in India with the
responsibility of finding and accreting oil and gas reserves. It
has three facets of hydrocarbon exploration activities viz.
Deep Water, Shallow Water, and Onshore exploration
activities.
ONGC ranked 4th in India in 2021 ranking of Fortune Global
500 list.
ONGC Group of Companies comprises of:
8
Processes and associated
Hazards in ONGC
9
A Hazard is a situation that poses a level of threat to Life,
Health, Property or Environment. Most hazards are dormant
or potential, with only a theoretical risk of harm; however,
once a hazard becomes "active", it can create an emergency
situation. Hazard and possibility interact together to create
risk.
Oil & Gas continues to be the major source of energy and
dependency has grown too high since majority of energy
needs are met by this sector. This has necessitated the
adoption of new technologies in exploration, refining &
storage of the hydrocarbon in Oil & Gas Industry.
Thus, a lot of technological improvements have taken place
both in upstream & downstream sectors of Oil & Gas to
enhance oil recoveries in upstream and make environment
friendly products in downstream.
ONGC is committed to the idea that all the incidents
(including fire) are preventable; hence every fire incident can
be classified by the place of work of its occurrence. In ONGC,
working areas can be classified as: -
1. Exploration
a) Geophysical drill site on land
b) Seismic vessel at offshore
2. Drilling
a) Drill site on land
b) Work Over Rig on land
c) Jack-up drilling rig at Offshore
d) Drill Ship/Floater at Offshore
e) Workover Rig at Offshore
10
3. Production
a) Well on land
b) Well Platform at Offshore
c) Well Head Installation (WHI) on land
d) Early Production System (EPS)
e) Group Gathering Station (GGS)
f) Production Platform – Unmanned
4. Transportation
a) Oil Pipeline on Land
b) Gas Pipeline on Land
d) Pumping Station of Pipeline on Land
e) Submarine Pipeline
11
f) Rail and Road Loading Gantries
g) Land Fall Points
h) Offshore Support Vessel (OSV) & Multipurpose Support
Vessel (MSV)
5. General Services
i. Workshops
ii. Laboratories
iii. Electrical Substations
iv. Stock Yards
v. Central Stores
vi. Explosive Magazines
vii. Multi-storeyed Office Buildings
viii. Residential Colonies, etc.
The major hazards associated with the oil industry are fire,
explosion, sudden pressure release and toxic release. Of
these, fire is the most common, but explosion is particularly
significant in terms of fatality and losses. ONGC has been
engaged in oil and natural gas exploration and production
since its inception. Since exploration, production, refining and
marketing of hydrocarbons are the multidisciplinary task and
are spread on land and sea, hence one has to be extremely
cautious and safe in each operation being performed.
Therefore, ONGC encounters all types of common fire
hazards known in the industrial operations, besides some
special types of fire hazards specific to oil industry only.
Some of the major hazards are listed below:
12
Activity Hazards/ Risk Controls
Tested BOP
Drilling Mud System
Drilling / Kick / Blowout Cement Integrity test
Testing/
Well Control System
Completion
/ Operational Drills
Fluid weight control
Surface Line Test
Analysis of sampling during
Cementing
Communication System
Training & Competency
Loss Prevention Program
Well Shut-in & Control Procedures
13
Production/ Active Secondary Containment
ProcessingHazards/
Activity Causes PassiveControls
Secondary
Storage/ Risks Containment
Spillage of
transportati harmful/Gas from Gas
Sealing Test
Detection
Deterioration of System (fixed &
on of Well Synthetic /Bulk
Stored Mud, Slip JointPortable)
Certification
fluid materials to the
Toxic/
environmentGas from
Monitoringor ofConfined Space
Process Control
OR Flammable
present in confined Entry Permit
Equipment
Gas Release
Handling spaces
Drilling / Such as Buddy work in
Fuels for H2S,CH4, H2, Spill Kit
confined
Completio
EquipmentCO, etc. Overfill Protection System
n Loss of Choke Manifold
Culverting/ Drainage
atmospheric Tests System
separator hydraulic
Seal Sumps & Collection System
14
Completion/ Explosion Fire Fighting Equipment
Production Training & Mock Drills
Financial loss SOP /JSA/ MOC/ PTW
(downtime,
Fire Alarms/ PPEs/ BAs
asset &
Reputation loss Identification of Ignition
Sources
Emergency Shower
First Aid Facilities
Emergency Rescue Plan
15
4. Mud gunning pump 1no. 10kg DCP type extinguisher
5. Electrical Control Room 1no. 6.8 kg CO2 type extinguisher
for each unit
6. Mud mixing tank area 1no. 10kg DCP type extinguisher
7. Diesel storage area 1no. 50 lit mechanical foam
1no. 50kg DCP type extinguisher
2nos. 10kg DCP type extinguisher
2nos. sand bucket or ½ sand drum
with spade
8. Lube Storage Area 1no. 10kg DCP type extinguisher
1no. sand bucket
9. Air Compressor area 1no. 10kg DCP type extinguisher
10. Fire pump area 1no. 10kg DCP type extinguisher
11. Near Dill in charge One fire extinguisher/shed with 3
Office nos. 10kg DCP type extinguisher
and 2 sand buckets.
12. Fire bell near bunk 1no. 10kg DCP type extinguisher
house
16
etc. (Collision of Operational No mobile phones
Vehicles, Failure while driving
Fuel Spillage
Night Journey
etc.)
Management plan
Equipment
Failure Vehicle
Maintenance &
Periodic Inspection
Vehicle Road
Worthiness
Certificate
17
– Extreme Pilot Helideck
weather Operational
Environmental
– Helicopter Experience
/ Damage
equipmen
Helicopte t failure Airworthiness
r – Pilot error Structure
of Helicopter
operatio – Obstructio Failure
ns n in
landing /
Competent
takeoff People Injury
Personnel –
Path
– Helideck Crew/ HLO
structure Loss of Rig
failure
– Ditching HUET
Downtime
Fire Fighting
Loss of Site Training
18
❖ Occupational Rig Movement Plan
hazards such as:
Defensive Driving
a. Dropped Object
b. Fall of person from Trained Drivers
monkey board.
c. Electrocution
d. Personnel getting New Location Planned
Rig Movement
entangled in lines & Inspect Pre-
Onshore during raising of movement
mast
e. Being struck by
(Drilling / swinging objects. Maintain safe
Completion) f. Chemical Hazard due distance from
to mud splash overhead lines
g. Swinging block/ pipe
hitting the derrick
h. Pinch points at pipe, Selection of vehicles,
elevator links, & slip cranes and lifting
handles. gear (such as wire
i. Road Accident
rope slings, lifting
eye, lifting rope for
mast etc.).
19
❖ In case of offshore
rigs, hazards
include:
Working at height –
a. Change in weather use of fall prevention
conditions – wind devices, man
speed, current, wave overboard
height Seabed precautions for
/conditions/ stability offshore operations.
b. Punch through (in
case of jack up rigs)
c. Water depth Shut down of wells on
d. Mooring / station platform (offshore)
keeping systems during rig move &
e. Other nearby assets proper preloading
Rig Movement such as platform guidelines to be
structure, piping at
Offshore adhered to.
platform, pipelines at
seabed and flowing
wells at platform etc.
(Drilling / f. Dynamic loading Pre move meetings
Completion) g. Towing operation –
fitness of tug boat
and anchor handling Competent personnel
equipment, vessel
collision
h. Lack of marine Inspection of Tug
competence Boats and their
i. Inadequate towing lines
procedures
j. Coordination failure –
communication Towing wires
failure,
accountability not Designed as per load
defined of rig.
20
Activit Hazards Controls
y
Installation, Maintenance &
Inspection of well control
equipment.
Competent personnel
CO Hazards from P
erforation during Use of specified PPEs
Perfora P&A Operations
tion
Switching off wireless
communication equipment
(Drillin Occupational
g/ hazards during the Electrical Isolation & Protection
Comple handling of for lightening
tion) explosives due to :-
& - Uncontrolled
Proper Gun Design
Plug - Detonation
and
abando - Surface
Perforating operations involving
nment Detonation electrical detonators should not
- Explosion be carried out during electrical or
static-generating dust storms
21
Adding an oxidizer (e.g., perchlor
ate) inside the gun system is
to reduce CO a maximum of 25%.
22
chamber.
(Production) Direct ignition sources Remote ignition system
and excess fuel in firing
PTW / JSA / SOP
chamber in case of fired
component: Flame in the firing
chamber is monitored by
a. Explosion
BSL or TSL sensor. Flame
b. Backfire arrestor in natural draft
burner.
23
OISD- 118
Fire Protection System
Dikes & Bunds
24
Activity Hazards Controls
25
(Production) to : start up
– Over Sufficient Stack Height
pressure
Competent Personnel
– Carryover of
SOP
liquid with
gas.
– Failure due to PTW
corrosion
– Mechanical
JSA
failure
26
27
Fire Fighting facilities and
methodologies adopted in
ONGC
28
Fire Protection Philosophy
The Fire Protection Philosophy in oil and gas industry is based
on Fire safety, Loss Prevention and Control. It considers that
in the hydrocarbon industry, the risk of fire is omnipresent at
all levels of operational activities like exploration, drilling,
production, processing and distribution, critical operations
requirement and large inventories stored at facilities. A fire in
one part of these operational areas can endanger other
part/section of the area, if not controlled or extinguished as
quickly as possible to minimize the loss of life and property
and prevent further spread of fire.
Considering the above philosophy, the basic fire protection
requirement depends on various factors like area of
operations, size of storage tanks, layout of facilities like GGS,
CTF, Oil & Gas Processing installation, pipeline installation,
disposal system of blow down, drainage from equipment
handling petroleum product, pressure & temperature
conditions in the process, terrain, etc. Material of
construction for infrastructure facilities shall conform to
various statutory regulations like National Building Code
(NBC), Oil Industry Safety Directorate (OISD), National Fire
Protection Association (NFPA), American Petroleum Institute
(API), etc.
Depending on the nature and size of installation and
risks involved, appropriate fire protection facilities out
of following shall be provided
i) Water Spray System.
ii) Foam System.
iii) Hydrants and Monitors.
iv) Fire Extinguishers.
v) Portable/mobile firefighting equipment
29
vi) Clean Agent system
Design Criteria for Fire Protection System
AS per OISD 189 the following shall be the design criteria for
a fire protection system
The fire protection facilities shall be designed considering
that city fire water supply is not available close to the
installation.
30
Further, fixed water spray system shall be provided on all the
tanks, where inter
distances between tanks in dyke and/or within dykes are not
meeting the
requirements of OISD-STD-118.
Fixed foam system or Semi-fixed foam system shall be
provided for all tanks (floating roof or fixed roof) and storing
Class A or Class B petroleum.
Fire Station
31
A fire station is the basic operational Centre of ONGC Fire
Service in the Asset / Plant/Installation. In major Work Centers
the main, centrally located fire station is designated as
“Main Fire Station” for coordinating the activities of other
fire stations. Main Fire Station has minimum two authorized
manned fire tenders for initial emergency response. All other
fire stations in the Work Centers are called as “Sub-Fire
Station”. In smaller Work Centers sub – Fire Stations can
perform the role of the Main Fire Station of the Work Centre.
Functions of Fire Station
(a) Co-ordinate all activities in connection with fire safety,
fire protection and firefighting operations within the
operational jurisdiction.
(b) To respond to any emergency call.
(c) To organize maintenance of firefighting equipment
available in the field and also which are available at the Fire
Station itself.
(d) Checking and testing of fixed firefighting equipment.
(e) To perform standby duties during hot jobs, hot oil
circulation, well stimulation, Helicopter landing and take-off
etc.
(f) Conducting onsite training programmes, mock drills etc.
(g) Provide mutual aid assistance to sister industries
and assist civil administration in firefighting & rescue
operations, when so required.
32
environmental treatment necessary for proper functioning of
the Hydrocarbon Processing and Handling Installation. The
control room could either be blast-resistant or non-blast
resistant as applicable to the type of installation”
Functions
To attend and respond all emergency situations calls (like-
Gas leakage, blow out situation, Fire call, disaster)
Keep a record of all the employees attendance.
Maintain records of Daily activities in situ of fire station
Maintain a log book and location tracking (GPS) of every fire
tender and its movement
Conduct Mock drill, one day training programmers to ONGC
as well as people in the vicinity of installations.
Communication
A. Line Communication: -
B. Wireless Communication:
33
I. All Main / Sub Fire Stations are equipped with VHF sets of
required capacity as Base Station to communicate among
themselves as well as with the fire appliances of the station.
II. All fire tenders/fire vehicles are fitted with VHF sets of
sufficient capacity as Mobile Stations to be in constant
contact with their respective fire stations.
III. Each fire vehicle is are equipped with 4 walkie – talkie sets
of 5 watt capacity for use by the crew on firefighting duty
away from the tender.
34
FIRE TENDERS
Specifications for fabricating a fire vehicle commonly used in
petroleum industry are given here
1. FOAM TENDER
35
system of 24 V type. An alternator and rectifier capable of
delivering a minimum of 50 A at 24 V should be provided.
(vii) Batteries: Ordinary lead acid batteries. Master isolation
switch should be provided in dashboard panel.
(viii) Radio suppression of the electrical system, which is
sufficient to ensure positive operation of radio equipment
without interference, should be provided.
(ix)Braking distance should not be more than 9m at 32 km/hr.
when fully loaded.
1.2 PUMP
(i) The foam tender should be mounted with one centrifugal
type, single /double stage pump.
(ii) The pump should be capable of discharging minimum
4000 lpm at 8.5 Kg/cm2. The suction side of the pump should
be connected to water tank independently.
(iii) The pump should be capable of discharging not less than
150% of the rated capacity at a head not less than 65% of
the rated head. The shut off head of the pump should not
exceed 120% of the rated head for the pumps.
(iv) Pump should be suitably mounted on the rear / midship
on the chassis and should be accessible and readily
removable for repair and maintenance. The pump should
have its control panel installed suitably.
(v) The pump should be of rigid construction and should be
made of gunmetal/ any suitable light alloy, compatible with
firefighting water and foam compound with stainless steel
grade 304 shaft should be suitable for use with saline water.
(vi) The pump impeller shaft should be fitted with antifriction
bearings. (vii) The pump impeller neck rings and impeller
rings should be renewable types and the gland should be
self-adjusting type. A drain plug should be provided at the
bottom of the casing.
36
(viii) Primer: The pump should be fitted with an automatic
water ring /reciprocating primer. It should be capable of
lifting water at least from a depth of 7.0 m at a rate of not
less than 30 cm per second.
(ix) The delivery outlet of the pump should be connected to
the monitor and 4/6/8 numbers of screwed 63 mm female
instantaneous couplings in accordance with IS:903 – 1975.
The monitor and other 63 mm female coupling outlets should
be fitted with lever operated ball valves.
(x) Suction lines should be provided with strainers which
should be removable easily.
1.3 WATER TANK
Water tank of 1800 to 3000 liters capacity should be suitably
mounted on the chassis. It should be fabricated out of Mild
Steel / stainless steel grade 304/316 sheets; of minimum 5
mm thickness for bottom and 4 mm for sides and top. The
gas tungsten arc welding (GTAW) with ER 309 MOL electrode
or equivalent and 100% radiography should be followed. 150
mm / 200 mm water filling pipe on each side of
the vehicle should be provided for water tank filling, fitted
with 2/3 numbers of 63 mm instantaneous male couplings
incorporating a strainer, NRV.
1.4 FOAM TANK
Foam Compound tank of 3000 to 4500 liters capacity should
be mounted on the chassis. It should be fabricated out of
stainless-steel grade 304/316 plates 11 of minimum 5 mm
thickness for bottom and 4 mm thickness for sides & top. All
external surface should be suitably treated to resist
atmospheric corrosion and painted. The foam tank should be
of rigid type rectangular / elliptical in shape with welded
construction. The gas tungsten arc welding (GTAW) with ER
37
309 MOL electrode or equivalent 100% radiography is
required. The foam tank should be suitably baffled to prevent
the surges while the vehicle is accelerating, cornering and
braking and should be so designed and mounted as to bring
the centre of gravity as low as possible in the chassis. The
baffles should have flanged man ways of 450 mm dia. The
tank should have minimum 1 no. of 450 mm dia inspection
manhole with hinged or removable covers. The manhole
cover should be marked ‘FOAM’ at the top. The tank should
be provided with a breather valve to enable automatic
venting of the foam compound tank when the foam
compound is drawn from it or when the tank in being filled.
38
A power take-off unit of suitable gear ratio to match the
engine & pump characteristics should be provided. A
separate lever in the main cabin should engage the PTO.
Necessary supports for PTO units, propeller shaft couplings,
universal joints etc. for power input to and output from PTO
unit should be provided. The drive assembly components
(shaft, couplings etc.) should be dynamically balanced.
1.7 WATER / FOAM MONITORS
There should be one roof mounted water-cum-foam
aspirating / non aspirating monitor of minimum 2580 lpm
capacity and 60 m horizontal water throw at 7.0 Kg/sq.cm.
The monitor should be capable of traversing through 360o in
a horizontal plane and 90o up and 15o down in the vertical
plane. The monitor and hand-lines should be tested
separately and in combination for delivering foam and water
throw at rated capacity and range; within the pump capacity.
2. FOAM NURSER
The Foam Nurser including all accessories should be designed
and manufactured as per relevant Indian Standards and TAC
requirements wherever applicable and should be as per
sound engineering practice. The specifications given here are
guidelines for material, design, construction and accessories
etc. for Foam Nurser. All the equipment and accessories
should be fixed on the appliance in a compact and neat
manner and should be so placed that each part is easily and
readily accessible for 17 use and maintenance. The centre of
gravity should be kept as low as possible.
2.1 CHASSIS
The foam nurser should be fabricated on a suitable chassis of
pay load capacity 10 tonnes or 16.8 tonnes or 19.0 tonnes.
39
The spare wheel assembly (supplied along with chassis)
should be fitted at a suitable place on the appliance. Rest
same as foam tender.
2.2 FOAM TANK
The net capacity of the foam tank should be 7000 to 12000
liters. The tank should have 2% expansion space over and
above foam compound capacity. The materials of
construction of foam tank and fittings should be SS-304 / SS-
316. The foam tank of rectangular / elliptical shape and
should be made of 5 mm. (minimum) for bottom and 4 mm
minimum thick plates for sides and top. The tank should be
welded in construction and should have adequate SS angle
reinforcement. Suitable baffles should be provided inside the
tank, made out of 5mm. SS-304 / SS- 316 plates to prevent
surging, when vehicle is in motion. The baffle plates should
be placed at every 900mm (max.) interval. Hooks should be
provided on roof of the tank for lifting purpose.
2.3 FOAM PUMP
The pump to handle foam compound should be rotary gear
type. The pump should be driven by chassis engine through
PTO and should meet following specifications:
Capacity: Minimum 400 lpm at 7 kg. /CM2 (g) discharge
pressure.
40
o Type of Gears: Double helical, hardened and profile ground.
o Bearings: GM and Teflon bush bearing (replaceable type).
o Shaft Seal: Mechanical seal.
41
should not exceed 120% of the rated head for the pumps.
The pump impeller shaft should be fitted with antifriction
bearings.
Primer: Pump should be fitted with an automatic water ring
/reciprocating primer. It should be capable of lifting water at-
least through 7.0 m at a rate of not less than 30
cm per second. The delivery outlet of the pump should be
connected to the monitor and 4/6/8 numbers of screwed 63
mm female instantaneous couplings should be in accordance
with IS:903 – 1975. The monitor and other 63 mm female
coupling outlets should be fitted with lever operated ball
valves. Suction lines should be provided with strainers which
should be removable easily.
3.3 WATER TANK
Water tank of minimum 6000 liters capacity should be
suitably mounted on the chassis. It should be fabricated out
of MS/Grade 304/316 Stainless Steel sheets; of minimum 5
mm thickness for bottom and 4 mm for sides and top. The
Gas Tungsten Arc Welding (GTAW) with ER 309 MOL
electrode or equivalent and 100% radiography should be
followed. Tank made of MS should be epoxy coated. The tank
should have adequate MS / SS angle reinforcement
3.4 WATER MONITORS
There should be one roof mounted water monitor of minimum
2580 lpm capacity and minimum 60 m horizontal throw at 7.0
Kg/sq.cm. The monitor should be capable of traversing
through 360o in a horizontal plane and 90o up and 15o down
in the vertical plane. The monitor and hand-lines should be
tested separately and in combination for delivering water
throw at rated capacity and range; within the pump capacity.
4. EMERGENCY RESCUE TENDER
42
The Emergency Rescue Tender (ERT) including all accessories
should be designed and manufactured as per relevant Indian
Standards and TAC’s requirements wherever applicable and
should be as per sound engineering practice. The
specifications mentioned hereunder lays down the
requirements regarding material, design, construction,
workmanship and finish, accessories and acceptance tests
emergency rescue vehicle. All the equipment and accessories
should be fixed on the appliance in a compact and neat
manner and should be so placed that each part is easily and
readily accessible for use and maintenance. The centre of
gravity should be kept as low as possible. This specification
covers the general requirements regarding materials,
performance and acceptance tests for Emergency Rescue
Tender to be used for Rescue Operations including handling
LPG Emergencies
The scope of supply should be inclusive of, but not limited to
the following:
Diesel generator set of 5 KVA fitted with CCE approved
spark arrestor & Flood lighting arrangement.
A battery-operated amplifier system.
An extension ladders.
Pneumatic lifting equipment.
43
Fire proximity suit
Hydraulic spreader and cutter
Portable gas detectors
LPG transfer equipment
Traffic control equipment
other accessories.
44
ONGC NORMS FOR FIRE FIGHTING
EQUIPMENT AT FIRE STATIONS
45
Recommendation as per OISD 189
46
47
48
49
Conclusion
The thorough study of the processes and the related hazards
was helpful to understand the operations of ONGC and the
ways in which it tackles the hazards to ensure safe operation
at minimal loss of human lives, property and damage to
environment.
Only through earnest effort to follow the safest possible path
under the guidance of the standards laid down by the
industry regulators has ONGC been able to rise to such a
height in both quantity produced and quality of safety and
fire standard.
The study showed that the organization has adopted ‘no-
compromise’ attitude towards the implementation of various
requirements. Yet the company is aware that the ultimate
goal off zero incidents is far to ahead in the future and
requires tireless efforts.
50