Issue Date: 19 April
2010
Rev 3
BRICKWORK CHECKLIST
Project : Contract Start :
Package :
Package Contractor : Contract Finish :
Area : Date :
Location :
Sl. No. Description Comments Contractor MASTERS
A BRICKWORK
1 Check for clean area
Check whether the customer
2
choice is in place
Check for hacking at the column
3
edge, floor & beam soffit
4 Check for brick test report
Check the layout in plumb with
5
the beams
Check the cement used :
6 (a) Brand the Cement
of
(b) Lot no. of the Cement
7 Check for mortar making platform
Check for mortar mix (cement :
8
sand) for diff. thickness of wall
Check for cube taken of the bed
9
mortar
Check door, window, AC
10
cutout openings
Check the R.C.C. band plumb of
11
A.C. cutout
Check the holes left at the
12
brickwall above A.C. band
Check for chicken wire mesh at
13
90mm thick & 75mm thick wall
Check for pointing, jointing and
14
level of the Brickwall
Check for soffit of loft, lintel &
15 900mm outside peripherial beam
at same level
16 Check for plumb of brickwall
17 Check for bed mortar thickness
Check dates are written in the
18
walls
19 Check for PCC at window sills
20 Check for RCC band shuttering
21 Check for RCC band R.I.
Check for RCC Jali, Golu &
22
Precast Lintels
Page 1 of
Issue Date: 19 April
2010
Rev 3
23 Check bricks used in diff. walls
Check for vertical joints &
24
bonding of brickwork at rt. Angles
Check the different bricks used at
25 the junction of external and
partition wall
Check for brick used for break
26
joints at every alternate layers
Check for top layer of brick work
27 touching beam & slab soffit is a
full brick
Check brickwork done above and
28 below window of A type and C
type living room (240 mm wall)
Check the lintel projections till the
29 end to support the above point in
A and C type flat
Check the toilet lintel rods are
30 hooked properly from the beam in
both A & C type Master toilet
Check for fabricated elements in
31
balconys and at AC cutouts
Check for effloresence while
32 doing the curing of Brickwall
Check the snag repot is ready &
33
attended simultaneously
Check the waste management
34
plan is followed
Check for floor cleaning from all
35
loose materials
Page 2 of