Contract N°006
Contract N°006
p. 1
p. 2
Chapter I: General
The subject of this contract shall be the construction of Work of the council road
kinding (MISAJE)-AKWETO-MBANDE-(AKO) ROAD AND CONSTRUCTION OF TWO
BRIDGE 12M AND 9M SPANS) ALONG THE MBESSA-AKWETO –MBANDA ROAD IN
DONGA MANTUNG MARKET (AKO) LENTH-12.000KM
p. 3
- The authority in charge of the clearance of expenditures shall be the
Controller of Finance Boyo
- The body or official in charge of payment shall be the Paymaster General
Bamenda
- The official competent to furnish information within the context of execution of
this contract shall be the Project Owner (Mayor OF MISAJE); Contracting
Authority/ Divisional Delegate of territorial Administration &
Decentralisation.
3.3 Duties of the Control Mission, Project Manager
3.3.1 Missions [to be completed, where need be]
3.3.2 Means put at the disposal of the Control Mission and the other stake holders of the
project:
In accordance with the provisions of article 153 paragraphs 1 and 2 of the Public
contract Code (Decree No. 2018/366 OF 20 June 2018), the Contract Manager, the
Contract Engineer as well as the other persons in charge of the control and follow up
of the project shall perceive indemnities as well as logistics support for the realisation
of the project from that shall be fixed by a decision of the Project Owner or delegated
Project Owner.
Article 4: Language, applicable law and regulation
2) The bidder’s tender and its annexes in all provisions not contrary to the Special
Administrative Conditions (GAC) and the Special Technical Conditions (STC)
hereunder;
5) The particular elements necessary for the determination of the contract price, such as, in
order of priority: the unit price schedule, the statement of all-in prices, detailed
estimates, the breakdown of all-in prices and the sub-details of unit prices;
p. 4
6) Plans, calculation notes, trial documents, geotechnical documents [insert and indicate,
where need be, names and references].
7) The General Administrative Conditions applicable on public works contracts that went
into effect by Order No. 033/CAB/PM of 13 February 2007;
8) The General Technical Condition(s) applicable on the services forming the subject of the
contract [insert and indicate, where need be, names and references].
This contract shall be governed by the following general instruments [to be adapted
according to the case]:
1. Framework Law No. 96/12 of 5 August 1996 on the management of the environment;
2. The Mining Code;
3. Instruments governing the various professional bodies;
4. Decree No. 2001/048 of 23 February 2001 relating to the setting up, organization
and functioning of the Public Contracts Regulatory Agency
5. Decree No. 2003/651/PM of 16 April 2003 to lay down the procedure for
implementing the tax and customs system applicable to public contracts;
6. Decree No. 2018/366 OF 20 June 2018, to institute the Public Contracts Code;
7. Decree No. 2012/075 of 8 March 2012 to organise the Ministry in charge of Public
Contracts;
8. Circular No. 001/CAB/PR of 19 June 2012 relating to the award and control of
execution of Public Contracts;
9. Letter No; 00908/MINTP/DR of 1997 to publish guidelines for the consideration of
environmental impact of road maintenance;
10. Circular [to be indicated as applicable] relating to the execution, and control of
execution of the budget of the State, Public Administrative Establishments and
Regional and Local Authorities and other bodies receiving government subsidies
11. Unified Technical Documents (DTU) for building works;
12. Applicable standards;
13. Other instruments specific to the domain concerned with the contract.
1.1 All communications within the framework of this contract shall be written and
notifications sent to the following address:
a) In the case where the contractor is the addressee: Sir NOPOLE NILES
FRANCK
p. 5
Beyond the time-limit of 15 days fixed in article 6(1) of the GAC to make his
domicile known to the Project Owner and Contract Manager, correspondences
shall be validly addressed to the [to the specified] council, chief town of the
8.1 The Administrative Order to start execution of works shall be signed by the
Contracting Authority and notified to the contractor by the Project Owner with a copy
to the Contracting Authority, the Contract Manager, Contract Engineer, the Paying
Body and the Project Manager, where applicable.
8.2 Upon proposal by the Project Owner, Administrative Orders with an incidence on the
objective, the amount and execution deadline shall be signed by Contracting
Authority and notified by the Project Owner to the Contractor with a copy to the
Contracting Authority, the Contract Manager, the Contract Engineer, the Project
Manager and the Paying Body. The prior endorsement of the Paying Body shall
possibly be required before the signature of those that have an incidence on the
amount.
8.3 Administrative Orders of a technical nature linked to the normal progress of the work
and without financial incidence shall be signed directly by Contract Manager and
notified to the contractor by the Contract Engineer or Project Manager (where
applicable) with a copy to the Contracting Authority and Contract Manager.
8.4 Administrative Orders serving as warnings shall be signed by the Project Owner and
notified to the contractor by the Contract Manager with a copy to the Contracting
Authority, the Contract Engineer and Project Manager.
8.5 Administrative Orders for suspension or resumption of work as a result of the weather
or any other case of force majeure shall be signed by the Contracting Authority and
notified by his services to the contractor with a copy to the Project Owner, Contract
Manager, Contract Engineer and Project Manager.
p. 6
8.6 Administrative Orders prescribing works necessary to remedy disorders which could
appear on structures during the guarantee period and not related to normal usage
shall be signed by the Contract Manager upon the proposal of the Contract Engineer
and notified to the contractor by the Contract Engineer.
8.7 The contractor has a time-limit of fifteen (15) days to issue reservations on any
Administrative Order received. Having reservations shall not free the enterprise of
executing the Administrative Orders received.
8.8 Concerning Administrative Order signed by the Contracting Authority and notified by
the Project Owner, the notification must be done within a maximum of 30 days from
the date of transmission by the Contracting Authority to the Project Manager.
Beyond this deadline, the Contracting Authority shall establish the default of
the Project Owner, take over from him and carry out the said notification.
9.2 The time-limit granted for notification of the Administrative Order to start execution of a
conditional phase shall be five (5) days.
10.1 Any modification, even partial, made to the technical bid shall only occur after the
written approval of the Contract Manager. In case of modification, the contractor shall
have himself replaced by a member of staff of equal competence (qualifications and
experiences).
10.2 In any case, the lists of supervisory staff to be used shall be subject to the approval
of the Project Owner in the days following notification of the Administrative Order to
start execution. The Project Manager has 5 (five) days to notify his opinion in writing
with a copy sent to the Contract Manager. Beyond this time-limit, the staff list shall be
considered as approved.
10.3 Any unilateral modification on the supervisory staff made in the technical bid prior to
and during the works shall be a reason for termination of the contract as mentioned
in article 45 below or the application of penalties [to be specified where need be].
The final bond shall be set at 2 % of the amount of the contract, inclusive of all taxes.
The bond shall be returned or the guarantee released within one month following the date of
provisional acceptance of the works, following a release issued by the Contracting Authority
upon request by the contractor.
The return or release of the retention fund or security shall be done within one month after
final acceptance by release issued by the Contracting Authority upon request by the
contractor.
The amount of this contract as indicated by the attached [detail or estimates] is two
hundred and ninety-two million, two hundred and ten thousand eight hundred and
tweny-two (292 210 822) CFA francs Inclusive of All Taxes; that is:
Amount exclusive of VAT: (245 040 522) two hundred and forty-five million forty
thousand five hundred and twenty-two CFA F
Amount of VAT: Fourthly seven million one hundred and seventy thousand, trois
hundred thousand (47 170 300) CFA F.
Amount of TSR and/or two hundred and thirty-nine million six hundred and forty-nine
thousand, six hundred and thirty-one (239 649 631) CFA F
Net to be paid= EVAT-TSR and/or AIR five million three thoudans and ninety, eight
hundred and twenty-two (5 390 981)
p. 8
The Project Owner shall release the sums due in the following manner:
For payments in CFA francs (amount in figures and letters exclusive of taxes) by
credit to account No.10025 00030 16401014333 19 opened in the name of the
contractor in the NFC bank.
The Project Owner shall release the sums due in the following manner:
a. For payments in CFA francs (amount in figures and letters exclusive of taxes) by
credit to account No._________ opened in the name of the contractor in the
___________bank.
b. For payments in foreign currencies (amount in figures and letters exclusive of
taxes) by credit to account No._________ opened in the name of the contractor in
________bank.
(not applicable)
(not applicable)
p. 9
- The hours put in by the heavy equipment shall be counted at the rate featuring in
the sub-detail of prices;
- Building materials and materials shall be reimbursed at cost price duly justified at
the place of use, marked up by ten percent for loss, stocking and handling;
- The amount for services thus calculated, including the hours put by heavy
equipment shall be marked up by 25 % to take into account the overheads, profits
and the contractor’s unforeseen.
20.2 This advance whose value cannot exceed twenty (20) percent of the initial amount
inclusive of all taxes shall be guaranteed at one hundred (100) percent by a banking
establishment governed by Cameroon law or a first-rate financial institution in
accordance with the instruments in force and reimbursed by deduction of the payments
on accounts to be paid to the contractor during the execution of the contract according
to the modalities laid down in the Special Administrative Conditions.
20.3 The total amount of the advance must be reimbursed not later than when the value
in basic price of the works reaches eighty (80) percent of the amount of the contract.
20.4 As the reimbursement advances, the Project Owner shall issue the release of the
corresponding part of the guarantee upon the express request by the contractor.
20.5 The possibility of granting start-off advance or advance for supplies must be
expressly stipulated in the Tender File.
Article 21: Payment for works (articles 26, 27 and 30 of the GAC supplemented)
21.1 Establishment of works executed
Before the 30th of each month, the contractor and the Engineer shall jointly establish a job
cost sheet which summarises and fixes the quantities executed and established for each
item on the schedule during the month and capable of giving entitlement to payment. This
sheet shall be based on the certification of the various tasks jointly established by the
contractor and the Project Manager
p. 10
Every month of during a periodic sequence established by contractor and representative of
the project owner, the contractor shall hand over to the Contract Engineer two draft
provisional monthly detailed accounts in seven copies (one detailed account exclusive of
VAT and the other inclusive of taxes), according to the agreed model and establishing the
total amount of the sums to which he may lay claim as a result of the execution of the
contract since the start of the contract.
Only the detailed account exclusive of VAT shall be paid to the contractor. The detailed
account of the amount of the taxes shall be the subject of an entry into the budgets of the
Ministry in charge of Finance
Only the amount exclusive of VAT shall be paid to the contractor as follows:
- [100-2.2 and/or – (5.5 or 15%)] paid directly into the account of the contractor;
- 2.2 % paid to the public treasury as AIR due by the contractor.
- 7.5% or 15% paid into the public treasury as TSR due by the contractor.
The Project Manager has a time-limit of seven (7) days to forward to the Contract Manager
the detailed accounts he has approved.
The Contract Engineer has a maximum time-limit of twenty-one (21) days to forward the
detailed accounts he approved such that they are in his possession not later than the
twelfth of the month.
The Contract Manager has a deadline of fourteen (14) days maximum to sign the detailed
accounts.
Payments shall be done by the Municipal Treasurer Bangem Council within a maximum
deadline of _______ calendar days from the date of submission of the approved detailed
accounts.
21.3 Detailed account of start-off account (if applicable).
Article 26: General and final detailed account (article 35 of the GAC)
26.1 The Contract Manager or the Project Manager has up to thirty (30) days to establish
the general detailed account and forward to the contractor after final acceptance.
At the end of the guarantee period which results in the final acceptance of the works, the
Contract Manager draws up the general and final detailed accounts of the contract which he
has had signed jointly by the contractor and the Contracting Authority. This detailed account
includes:
- the final detailed account,
- the balance
- the summary of monthly payments on account.
The signing of the general and final detailed account without reservation by the contractor
definitely binds the two parties, puts an end to the contract, except with regard to interest on
overdue payments.
26.2 The contractor has up to thirty (30) days to return the signed final detailed account.
p. 12
Article 27: Tax and customs regulations (article 36 of the GAC)
Decree No. 2003/651/PM of 16 April 2003 lays down the terms and conditions for
implementing the tax regulations and customs procedures applicable to public contracts.
The taxes applicable to this contract include notably:
- Taxes and dues relating to industrial and commercial profits, including the IAR which is a
deduction on company taxes;
- Registration dues in accordance with the Tax Code;
- Dues and taxes attached to the execution of services provided for in the contract;
o Duties and taxes of entry into Cameroonian territory (customs duties, VAT,
computer tax);
o Council dues and taxes;
o Dues and taxes relating to the extraction of building materials and water.
These elements must be included in the costs which the undertaking imputes on its running
costs and constitute one of the elements of the sub-details of prices exclusive of taxes.
Seven (7) original copies of the contract shall be stamped by and at the cost of the
contractor, in accordance with the applicable regulations.
Article 30: Role and responsibilities of the Project Owner (GAC supplemented)
30.1 The Project Owner shall be bound to furnish the contractor with information necessary
for the execution of his mission and to guarantee, at the cost of the contractor, access to
sites of projects.
30.2 The Project Owner shall ensure the contractor of protection against threats, insults,
violence, assault and battery, slander or defamation of which he could be victim by reason
of or during the exercise of his mission.
p. 13
31.1 The time-limit for the execution of the works forming the subject of this contract shall
be Three (03) calendar months.
31.2 This time-limit shall run from the date of notification of the Administrative Order to
commence execution of the works [or that fixed in this Administrative Order- to be
specified].
Article 32: Role and responsibilities of the contractor (article 40 of the CAG)
The detailed and general plan of progress of the works shall be communicated to the
Project Manager in five (05) copies at the beginning of each.
p. 14
comments. Delay in approving the draft execution schedule shall stay the execution
deadline.
The approval given by the Contract Manager or Project Manager does not in any way
release the contractor of his responsibilities. Meanwhile, works executed before the
approval of the programme shall neither be ascertained nor paid for. The updated and
approved schedule will become the contractual schedule.
The contractor shall constantly update on site, a schedule that will take account of real
progress of the site. Significant modifications may only be made on the contractual
programme upon receiving the approval of the Project Manager. After approval of the
execution schedule by the Contract Manager, the latter shall transmit it within five (5) days
to the Contracting Authority without staying its execution. However, if important
modifications alter the objective of the contract or the nature of the works, the Contracting
Authority shall return the execution schedule accompanied by reservations to be lifted within
fifteen (15) days of the date of reception.
b) The Environment Management Plan should bring out notably the choice technical
conditions of the site and basic life, conditions of the backfill of the extraction sites and
conditions for reinstating the works and installation sites.
c) The contractor shall indicate in this schedule the equipment and methods which he
intends to use as well as the personnel he intends to employ.
d) The approval granted by the Contract Manager or Project Manager shall in no way
diminish the responsibility of the contractor with regard to the harmful consequences
which their implementation may cause both towards third parties and the respect of
clauses of the contract.
35.2 Execution draft
a) The execution plan documents (calculations and drawings) necessary for the
realisation of all the parts of the structure must be submitted for the endorsement of
the [Contract Manager or Project Manager] at most fifteen (15) days prior to the date
provided for the commencement of execution of the corresponding part of the
structure.
b) The [Contract Manager or Project Manager] has a deadline of [five (05) days] to
examine and make known his observations. The contractor then has a deadline of
[04) four days] to present a new file including the said observations.
35.3 In case of the non-observance of the approval deadlines of the above documents by
the Administration, these documents shall be deemed to have been approved.
Before the acceptance of the works the contractor shall ask in writing to the Contract
Engineer, to organize a technical visit for pre-acceptance. This visit shall include the
following operations.
Qualitative and quantitative evaluations of the different works that have been
executed.
p. 16
Findings and statement of the unexecuted task envisaged in the present jobbing
order.
Findings relative to the completion of the work
Findings on the quantity of works that have been effectively realized
These operations shall be subject to a site report drawn up on the field, signed by the
following.
-Contract Engineer,
-Contractor.
During this pre-acceptance, the Contract Engineer shall eventually specify the
reserves to be lifted and the corresponding works to be effected before the acceptance. The
Contract Engineer shall fix the acceptance date in collaboration with the chief of service for
the contract.
42.2 Acceptance
However, the report (process - verbal) shall be valid if two third (2/3) of the members
including the chairperson append their signatures.
The chairperson can only convene the acceptance of works when he must have received
from the Contract Engineer the report (process - verbal) of the technical acceptance of
works with no reserves pending clearance.
This report (process - verbal) of the technical acceptance of works shall be an integral part
of the acceptance of works’ report (attached to acceptance of works report) and shall
accompany the bills for settlement
p. 17
In accordance with the provisions of article 153 paragraphs 1 and 2 of the Public
contracts Code (Decree No. 2018/366 OF 20 June 2018), an indemnity to be fixed by the
project Owner shall be perceived by the members.
The guarantee period is one (01) year from the date of the provisional reception for
the section of new civil Engineering works.
p. 18
Where no amicable solution can be found for a disagreement, it is brought before the
competent Cameroonian jurisdiction, subject to the following provisions: [to be filled, where
need be].
Article 48: Production and dissemination of this contract
In accordance with the provisions of article 125 of Decree No. 2018/366 OF 20 June 2018
of the Public Contract Code, [Ten (10)] copies of this contract shall be produced by the
Delegated Project Owner. Seven of which shall be notified to the contractor for registration.
In case of conflicts of terms or issues in these technical specifications with the GCC and/or
Contract Data the terms or issues in the GCC and/or Contract Data shall prevail.
The various works to be executed are detailed in the bill of quantities and the execution
drawings conform to the typical drawings for model plans in the tender present document.
The necessary borrow sites shall be indicated by the Project Manager after running
identification tests on the materials.
If need be, the contractor may choose other borrow sites and submit their identification tests
for the approval of the Project Manager whose refusal will warrant that the contractor look for
new borrow sites without claiming any compensation or using those indicated.
When a borrow site chosen by a contractor has been approved, he shall run the necessary
identification tests prescribed, and shall compile these in single document which shall be
submitted to the Project Manager for approval. This document shall include:
Quarries
p. 20
The contractor may start exploiting an identified quarry only if the supervising Project
Manager has carried out quality control and given his authorization.
In case of contradictory test results, the Project Manager may ask the contractor to run
further tests at his own cost.
The Project Manager may withdraw the authorization at any time once the quarry no
longer provides good quality material. In that case, the contractor cannot claim any
compensation.
Bush clearing, top soil removal and tree felling required for the exploitation of borrow
sites shall be at the expense of the contractor and shall not be paid for as of right.
The fill required for the road section generally come from excavations of satisfactory
quality. In case of insufficient quantity or poor quality, they will be taken from deposits
situated out of the right-of-way.
Fill should be free of organic debris and should be well graded in order to facilitate
compaction. This material should have the following minimum characteristics:
- 2 Atterbergs limits
- 2 granulometric analysis
- 2 modified proctor
- 1 CBR
4.2 Material for substitution fill in swampy zones
- 2 Atterbergs limits
- 2 granulometric analysis
- 2 modified proctor
- 1 CBR
4.3 Fill Adjacent to Structures
Material for backfilling or block technique of structures should meet the following
specifications:
- 2 Atterbergs limits
- 2 granulometric analysis
- 2 modified proctor
- 1 CBR
4.4 Laterite and Scoria (Pouzzolana)
The laterite or Pouzzolana required to refill the road shall be of selected material. It
should be free of organic material and should meet the following characteristics
Qualities of the laterite or Pouzzolana shall be specified on the works site by the
Project Manager who may immediately accept or refuse exploitation of a deposit, a
deposit area, or a heap of laterite or Pouzzolana that has bulked. If the contractor
objects, the Project Manager may conduct control tests and/or ask an approved
p. 22
Laboratory to conduct the density and plasticity index tests mentioned above. And
where the material does not conform to specifications, the contractor shall bear the
cost. Otherwise, the Employer will take charge of it
Culvert rings
Metallic culvert rings used should meet the LCPC SETRA September 1981 standards.
Sheets will be in Carbon steel, resistant to temperature changes, meet NFA - 35-556
standards on HR bolts intended for the construction of structures.
The Project Manager, however, reserves the right to request control tests and reject all
the materials which do not meet the standards even if they had already been accepted
by virtue of the guarantee certificate.
Cement: They should be of CPA 325 class and be obtained from an approved
factory.
Water : Water to be used for mortar and concrete should be clean and
free of organic matter or chemicals that may impair the properties
of cement. Water to be used must be approved by the Project
Manager
4.7 Gabions
They shall be made up of cages of galvanized wire netting, with hexagonal mesh, filled
with hard water - resistant stones of appropriate sizes (the stones in contact with the
wire netting should be 1.5 times larger than the links).
They shall be obtained from a quarry or deposit approved by the Project Manager and
none should be smaller than 20 cm.
p. 23
The blocks should be as regular in shape as possible and have a
diameter of between 30 and 40 cm.
5.1 Security
The contractor shall be required to place at the entrance to the works site
and in its vicinity, signboards indicating that work is underway and he shall be
responsible for any accident that occur on the works site and/or suffered by a
third party, his staff and employees and officials of the Administration as a result
of their presence on the works site. Organisation of work and security on the
works site shall be the responsibility of the contractor.
5.2 Traffic
5.3 Laboratory
The Contractor shall provide, use and maintain a laboratory on the Site for the
use of both Project Manager and Contractor throughout the period of execution of
the Works and until such time as a Taking-Over Certificate for
p. 24
Materials shall be selected and set up according to the prescriptions of these Technical
Specifications and price schedule. If the Project Manager feels that the
working registers;
drawings and execution plans for each structure and drainage system to
the scale of 1/20 or 1/10 as the case may be;
p. 25
quantities corresponding to works.
The register shall show:
the width from where top soil has been removed as well as the areas and
thickness of cuts and fill;
ditches to be dug or reshaped;
proposals for discharge ditches;
proposals for structures and drainage systems;
location of base layer.
The amount of earthworks to be performed shall be calculated by the Contractor
in alongside with the Project Manager by taking down the rectangular
coordinates, the distances on the centre line x, and height from the natural
ground level at the right angles of each horizontal point Y of the characteristic
points of the cross-section after bush clearing.
Special attention should be paid to the slope which should not be less
than 4% on both sides of the centre line of the cross section and could reach 8%
in the curves.
In such a case, laboratory expenses shall be borne by the contractor. Just as defined in
Article 9 above, a patch shall be carried out before the works.
In sites with god bearing capacity soil, the contractor shall choose
between mounting before or after earth works.
However, the Project Manager should prescribe elementary rules for the
placing of culverts.
1.3.11 GABIONS
Gabions may only be fitted after the contractor is notified that the quality
of wire netting has been approved.
Any gabion received on site shall during use, be laid out such that all its
faces lie flat on the ground. The four lateral faces will be lifted to form a box
with an open lid, and then the gabion will be thus placed on its appropriate
position.
Where the gabion is being placed next to others already in place, the faces in
contact should be firmly placed against adjoining gabions
The four vertical edges shall be tied with an approved wire; for gabions
which are in contact, the edges of gabion being assembled shall be tied
together with the edges of gabion already in place. Horizontal edges for
gabions in contact, including the joint line of the lid of the gabion being placed
shall be tied together before the gabion starts to be filled.
All tying shall be done with well stretched out wire, with at least a
complete round of tying on each length of the gabion mesh.
p. 28
1.3.12 STONE MASONRY
The stone masonry required for the construction of structures should be
aesthetical and according to structure type (shape, size of stones, joints etc…)
in accordance with engineering rules.
Binding mortar shall contain 300 (three hundred) kg of cement per m3 of sand.
The visible sides of the stone masonry must be regular. The minimal sizes of
the sides must not be less than 15 (fifteen) cm.
M450 mortar shall be used for the finishing of the external joints.
M450 mortar shall be mixed with 450 (four hundred and fifty) kilogrammes of
cement per cubic metre of dry sand.
17.2 Concrete
The volume of average and big size aggregates in the C150 concrete should
double that of the volume of sand. The test on grading of the aggregate must
p. 29
be performed for the concrete structures. Also sand equivalence test as well
as any other test deemed necessary to be required by the Project Manager.
The rock facing should be at least 1.5 times the average diameter of
rocks used and at least 60 cm thick under the structure and in the bank
protection.
After completion of the site clearance and setting-out the contractor shall
survey all the new and replacement structures (bridges, retaining ,culverts, etc
) sites and confirm the setting out details of the new and replacement bridges
with the Project Manager.
The Contractor will be provided with drawings showing indicative details of the
proposed new and replacement bridges. The Contractor shall survey each
bridge site prior to commencing work at the bridge. The survey shall extend for
a distance as directed by the Project Manager, each side of the proposed
centreline of the structure. The features at the site shall be accurately
recorded. The survey shall record the heights, slopes and other relevant
details of the embankments and slopes at the site of the structure. He shall
record the maximum known highest flood level. The alignment, levels and the
other relevant details of the river channel crossed by the structures in case of
bridges , culverts, box culverts, etc shall also be recorded. At the sites of
replacement structures, the survey shall record the dimensions and the levels
of the exiting superstructure structure and substructure and the location and
p. 30
dimensions of auxiliary items including handrails, guardrails etc. The survey
details shall be recorded on drawings, which shall include fully dimensioned
plans, elevations and sections at appropriate scales.
The Contractor shall submit to the Project Manager for his approval two sets
of bridge survey drawings. The Project Manager shall give comment or
approval within 15 days from the date of receipt of the drawings. The
Contractor shall make any amendments to the bridge survey drawings as
required by the Project Manager. Following the approval of the survey
drawings, the Contractor shall supply to the Project Manager a further four
copies of each drawing for the Project Manager.
p. 31
any of his responsibilities or liabilities under the Contract. Following approval
of the bridge working drawings the Contractor shall supply to the Project
Manager a further four copies of each drawing for the use of the Project
Manager.
The final bridge arrangements agreed with the Project Manager may be
different from those shown on the indicative contract drawings. The Contractor
shall be deemed to have taken the requirements of this Clause into
consideration for the submission of his tender and preparation of his
programme.
1.3.17 PRICES
The unit prices quoted by the Contractor are defined under price determination
and works evaluation
The Contractor shall be paid for work done on the basis of the price schedule
corresponding to the quantity of work evaluated as provided for by Article 7 of
these technical specifications.
Where it is observed that there are additional works whose unit prices are not
determined in the price schedule, the Project Manager shall reserve the right
to apply his reference unit prices.
1.3.19 PROTECTION OF THE ENVIRONMENT
23.1 SITE INSTALLATIONS
The contractor shall propose to the project manager, before the start of works,
the places of his site installation and solicits by a verbal notification (with it
mentioned on the report) the authorization of site installation.
The location of the installations should be situated out of sensitive areas to
avoid, too much grass cutting, off rooting and cutting of trees. In the installation
zone, pruning and cutting down of trees whose diameter above 1m from the
ground level is greater than 20cm should be done with an authorization from the
Supervisor.
The site should preview adequate drainage of water in its total surface area.
The areas where machines are washed and repaired should be concreted with
a pit to collect the oily ad greasy waters. This repair and cleaning area should
have a slope towards the pit and towards the center of the platform to avoid
polluted water from reaching bare ground.
At the end of works, the contractor will take all the necessary measures to keep
the area in good state. The contractor should pack all his equipment including
machines. He should demolish any fix installation, like foundation, concrete or
p. 32
metallic supports etc, demolishes the concreted area, disinfect the soil if it was
contaminated. In general, he should put it back or near its original state. He is
not permitted to abandon any equipment or machines on site or its environs.
Concerning where to deposit the demolished materials, the contractor should
seek the authorization of the delegated project manager. These demolished
materials will be covered by a layer of soil and protected from erosion:
After packing of equipment from the site, minutes will be established under the
confirmations of the control mission, this will be joined to the minutes of works
reception. The payment of the rest of 30% of site installation will be done only
after the presentation of these minutes.
The required compaction of the surfacing shall be 95% of the dry modified
optimum Proctor density. To obtain this result, the Contractor shall use laterite or
volcanic scoria bulked, reserved and approved according to the requirements of
these technical specifications and at least four passes of compaction equipment
p. 33
previously approved by the Project Manager on the entire surface of the
surfacing course and water this surface whenever necessary during compaction.
Geotechnical test at an interval of every 200m shall be conducted to determine
this density
Where the Project Manager is dissatisfied with the job done or doubts the
compaction results, he shall at his own expense conduct control tests and where
necessary ask an approved laboratory to do so. If on a section, more than 20%
of compaction tests are below standards, the contractor will repeat compaction
and new tests will be conducted before acceptance of the section. Expenses for
such laboratory tests shall be borne by the contractor. The Project Manager shall
check the thickness of the layer.
In such a case, laboratory expenses shall be borne by the contractor. Just as defined in
Article 9 above, a patch shall be carried out before the works.
p. 34
1.3.22 REHABILITATION OF EXISTING STRUCTURES
p. 35
III-PRICE LIST
B: BILL OF QUANTITIES AND ESTIMATE
UP in
Unit Qty UP in letters
figures
LOT 100 : SITE
100 INSTALLATIONS AND
STUDIES
Site installation including
7 000
101 transportation of equipment Ft 1 Seven million
000
and tools to and from
Preparation of works
7 000
102 performance program and Ft 1 Seven million
000
as built plans
Geotechnical Studies by an
approved Laboratory
(Identification of Borrow
3 500 Three million cinq
102 pits, in-situ density after Item 1
000 hundred thousand
compaction, quality of sand,
quality of gravel, quality of
rocks quality of concrete)
LOT 200 : EARTH
200
MOVEMENT WORKS
5
201 Grass cutting m² 2000 Five thousand
000
Cut to dump (opening of the 7 seven
202 km 6,5
road) 000 thousand
Back filling with laterite from 5
203 m3 1000 Five thousand
borrow pit 000
Cleaning and reshaping of 5
204 ml 220 Five thousand
ditches and off shuts 000
Road camber, reshaping Two thousand two
2
205 and compacting which m2 14000 hundred and
277
include ditches and offshots seventy-seven
Llot 300 DRAINAGE
300
STRUCTURES
Supply and placing of 400 Four hundred
301 ml 19,2
metallic Culvert dia 800mm 000 thousand
Masonry Culvert Chambers 350 Three hundred
302 U 2
dia 800mm 000 and fifty thousand
p. 36
Masonry Culvert Heads dia 350 Three hundred
303 U 2
800mm 000 and fifty thousand
p. 37
SUB TOTAL LOT 000 : 48 017 549
Llot 300 DRAINAGE
300
STRUCTURES
Supply and placing of metallic 400
301 ml 19,2 7 680 000
Culvert dia 800mm 000
Masonry Culvert Chambers dia 350
302 U 2 700 000
800mm 000
Masonry Culvert Heads dia 350
303 U 2 700 000
800mm 000
9 080
SUB TOTAL LOT 300 :
000
SUMMARY
TOTAL WITHOUT TAX 245 040 522
TVA (19,25%) 47 170 300
TOTAL ALL TAXES INCLUSIVE 292 210 822
AIR (2.2%) 1 604 249
NET RECEIVABLE 71 316 151
p. 38