Ref.: MTCPL/SWSM/TPI-Cluster 17/2024-25/                                    Date:
18.10.2024
To,
The Executive Engineer,
Division office (E&M),
U.P Jal Nigam (Rural)
Varanasi, Uttar Pradesh
Sub: Third Party Inspection and Monitoring of Physical and Financial Progress
of various Rural Water Supply Projects for Cluster-17 – Varanasi (Revenue
Division),          Uttar           Pradesh:             Checking          of
RA16_EnM_MACHHLISHAHR_CHITAWAN_SolarInstallation dated 08.10.2024. of Chitwan
water supply scheme of Jaunpur district under JJM project (New scheme) -Reg.
References:
   1. 2710/W-23/NIT/2020-21 dated 05.03.2021
Dear Sir,
With       reference   to   the   above     cited       subject,   it   is   to   inform   that
RA16_EnM_MACHHLISHAHR_CHITAWAN_SolarInstallation dated 08.10.2024. of Chitwan
water supply scheme amounting to Rs 3,33,832.8 (without        GST) by TKC On
Completion of Installation of Solar power plant (for complete plant ) including solar
panels , VFD , Structure, earthing of all electrical items , Balance of system with auxiliary
load arrangements for Field monitoring devices , Cleaning arrangements for solar
panals , Interlocking Pavement below solar panels and Installation and commissioning
with civil works etc. complete, & deduction of 0.06KW solar power plant, submitted by
contractor M/s. Afcons. Infrastructures Ltd. Online on 16.08.2024 & forwarded to TPIA
for verification. The checked bill is being submitted along with the observations made
during inspection.
The Bill Observation report with observation is herewith enclosed as Annexure-A.
Thanking You
Yours Faithfully
Medhaj Techno Concept Pvt. Ltd.
 Nafees Baig
Dharmendra Upadhaya
(Deputy Project Manager)
Electrical Engineer
CC:
      1.   Executive Director, State Water and Sanitation Mission Department, Lucknow.
      2.   Unit Coordinator, State Water and Sanitation Mission Department, Lucknow.
      3.   Chief Development Officer (CDO), Vikas Bhawan, Jaunpur, Uttar Pradesh.
      4.   Project Manager M/s. Afcons Jaunpur, Uttar Pradesh
                                          Page 1 of 6
                            Bill Inspection Report (Annexure-A)
TPI for Monitoring and Supervision of various Rural Water Supply Projects un-
der Jal Jeevan Mission – Inspection of “Jaunpur-Tube Well WSS”
 S. No.            Particulars                               Information
   1      Name of District/Block             Jaunpur
   2      Name of Scheme                     Chitwan water supply scheme
   3      Name of Contractor                 M/S Afcons Infrastructure Limited
                                             125/ED/PHASE-3/2022-23/II/20030802 Dated
   4      Agreement No. & Date
                                             29 .09.2023
                                             RA16_EnM_MACHHLISHAHR_CHITAWAN_SolarIn-
   5      Bill No. & Date                    stallation dated 08.10.2024
   6      Amount of Bill (In Rs.)            Rs 3,33,832.8 (without GST)
                                              On Completion of Installation of Solar
                                             power plant (for complete plant ) including
                                             solar panels , VFD , Structure, earthing of all
                                             electrical items , Balance of system with
                                             auxiliary load arrangements for Field
          Type of Bill (Supply/ Laying/
   7                                         monitoring devices , Cleaning arrangements
          Construction/other)
                                             for solar panals , Interlocking Pavement
                                             below solar panels and Installation and
                                             commissioning with civil works etc. complete,
                                             deduction of 0.06 KW solar power plant,
                                             supply of
   8      Date of Bill Received              16.10.2024
          Details of Inspecting
   9
          Persons-
  9.1     Name of Representatives UPJN       Mr. Aditya Singh (JE)
                                             Mr. Vinay Shanker (Mechanical Engineer)
          Name & Designation of TPIA         Mr. Dharmendra Upadhyay (Electrical
  9.2
          Representatives                    Engineer)
          Name & Designation of
  9.3                                        Mr. Kripa Shankar Singh (Project Manager)
          Contractor’s Representatives
A. Details of documents
 S. No.   Name of Document                          Remark (Provided/ Not Provided)
    1)    Cover Agreement                         Provided
    2)    BOQ & Price Schedule                    Provided
          Payment terms &
    3)                                            Provided
          Conditions/breakup
                                          Page 2 of 6
        S. No.       Name of Document                            Remark (Provided/ Not Provided)
             4)      Form-27 (B)                               Not Provided
             5)      Tax Invoice No and Date                   Provided
             6)      E-MB                                       Provided
             7)      Previous claimed bill ( if any)            provided
                     Certification from TKC that all
             8)      these items are not claimed               Provided
                     previously.
             9)      SOR (Schedule of Rate)                    Provided
                     JMR                                       Provided.
       10)
      B. Details of supply documents
       S. No. Name of Document                                         Remark (Provided/ Not Provided)
      SITC of solar Power plant
      (for complete plant) in-
      cluding solar panel, struc-
18.01 ture, inverter etc. com-
      plete in all respect with
      required materials, T&P
      labour
                                        Provided 1. Solar Panel- M/s Sova solars –
                                         SWSM Q.A.P. No-592/SE/QAP/P-2/2022-23 dated02.12.2022
      QAP of Solar Panel                2. Structure- QAP of structure is not provided.
                                         3. Inverter- Inverter is in built with automation system.
                                        1) Solar PV Module- Pre-Delivery Material Testing Certificate (MTC) is pro-
      Pre-Delivery MTC                  vided- Crown agents. (Certificate No. IN/23/0525 date 13 &14 March 2023
                                        quantity 1738 Nos. (947.21 KW)
      Post Delivery MTC                 Not Provided
      C. Work status details
      SOR         Description of
                                      SITC of pumping plant (Defects/ General Observations /
      item            items
                                                      Remedial Measures)
       No.
       18b.       20% of item
                  code
                  18Erection,         DP       Qty            Variat       Remark         for
                  Laying, Fixing,     R        execu          ion          deduction
                  Jointing SITC of    Qt       ted at
                  Solar power         y        site
                  plant (for          (K       (KW
                  complete            W)       includ
                  plant )                      ing 2
                  including solar              KW)
                                                       Page 3 of 6
SOR     Description of
                          SITC of pumping plant (Defects/ General Observations /
item        items
                                          Remedial Measures)
 No.
       panals , VFD ,
       Structure,          19    19.44        0.06          1. Cleaning
       earthing of all     .5                                  arrangem
       electrical items                                        ent    for
       , Balance of                                            solar
       system with                                             panels
       auxillary load                                          not
       arrangements                                            done .
       for Field
       monitoring                                           2. Interlocki
       devices ,                                               ng
       Cleaning                                                Pavemen
       arrangements                                            t   below
       for solar panels                                        solar
       , Interlocking                                          panels
       Pavement                                                not done
       below solar
       panals and                                           3. Few     PV
       Installation and                                        modules
       commisioning                                            found
       with civil works                                        loose
       etc. complete                                           fitted.
       in all respect
       with required                                        4. Earth pit
       material T&P                                            chamber
       labour                                                  not
                                                               construct
                                                               ed.
                   Table-1- GP wise claimed supply items details
                                                               Current
                                                     Previ-                 Cumula-
                                                               claimed                Bal-
  SOR                                        BOQ       ous                    tive
             Item Name          UOM                              Qty.-                ance
   No                                        Qty.    claime                 Claimed
                                                                in this               Qty.
                                                     d Qty.                   Qty.
                                                                GP bill
           70% of item code
 18.01.a   18.01 Solar power     KW          19.5    19.5        -0.06       19.44     0
                 plant
                                      Page 4 of 6
C.        Other Observations and Note for Appropriate Deduction Amount –
     1. In Abstract Item No. 18.01a     is deduction     for 0.06 KW solar power
        plant    is proposed against previous claimed quantity with 70% of
        supply which is installed at site.
     2. Guidelines given by SWSM for earthing system as mentioned in point 8.1 & 8.1.4
        to 8.1.13 of RFP are not followed by TKC (TPIA Comm. Letter No-
        MTCPL/SWSM/TPIA-Cluster 09/2023-24/113952 Dated 28.02.2024). So appropriate
        amount may be deducted by SWSM/UPJN before release the payment.
     3. Appropriate amount may be withheld/Deducted by UPJN/SWSM as per the
        observations in remark for deduction column of report.
The reviewed bill is being submitted along with the observations attached as per
ANNEXURE –A above made during checking. Also, adherence of Payment terms and
conditions as per contract agreement done between SWSM and TKC may be referred
before releasing the payment.
Bill Status- Verified (with observations)
 Nafees Baig
Dharmendra Upadhaya
(Deputy Project Manager)
Electrical Engineer
                                  Snapshot of Items
                Snapshot-01 (Solar Power Plant _Front & Rear side)
                             Snapshot-02 ( VFD &MMS)
                                       Page 5 of 6
Page 6 of 6