                                                                                                       ABSTRACT
Item                                                                                             Previous Bill    This Bill    Total
                                          Item Description                                Unit                                             Rate     Previous Bill Amount   This Bill Amount   Total Amount
code                                                                                              Quantity        Quantity    Quantity
        1      EXCAVATION AND REFILLING WORK
       1(a)    Earth work in excavation in trench. Footing etc not exceeding in
               depth 3.0 mtrs. Including disposal of excavated earth lead up to cum                                 554.399     554.40     200.00                              110,879.82         110,879.82
               30.00mtrs.
       2 (b)   Refilling of excavated earth or earth supplied by client, Spreading
in trench in layers not exceeding 300mm in depth, consoliddating cum 636.139 636.14 110.00 69,975.24 69,975.24
               Providing and laying first class Brick Masonry in CM 1:5 in Super Structure (above FFL)
               level using approved quality Chamber bricks or locally available good quality burnt stock
       5 (a)   bricks having Min. Compressive Strength of 5 N/Sqmm or 50 Kg /sqcm and as approved            cum                       121.574     121.57   7500.00                              911,802.05         911,802.05
               by Consultant / Client including raking the joints, curing, scaffolding etc. complete.
               (excluding cement)
6 Plaster work - - -
               Prepare the surfaces of all internal & External walls at all heights and plaster in cm 1:4,
               15mm thick, finished smooth with trowel and sponge and providing 6 mm x 6mm
       6 (a)   recessed grooves at the junction of all RCC surfaces and brickwork including and              sqm                     1,343.085   1,343.08   550.00                               738,696.72         738,696.72
               scaffolding, curing, etc complete. (excluding cement)
        RCC in Footing
        Grid A, B/1-7, 1,7/A-D                                cum            17            -1         3.000          3.000    0.300    -45.900
        Tapper part                                           cum            17            -1         3.583                   0.550    -33.504
        Column up to Plinth                                   cum            17            -1         0.400          0.400    0.825     -2.244
        Grid 1A/B,C,D                                         cum            3             -1         1.500          1.500    0.300     -2.025
        Lift Raft                                             cum            1             -1         4.280          2.760    0.300     -3.544
                                                              cum            1             -1         0.400          0.400    1.375     -0.220
        Column up to Plinth                                   cum            3             -1         0.300          0.300    1.375     -0.371
        Lift RCC Long wall up to Plinth Top                   cum            2             -1         2.300          0.230    1.375     -1.455
        outer side RCC Wall of Lift up to Plinth Top          cum            1             -1         1.800          0.230    1.375     -0.569
        Inner side RCC Wall of Lift up to Plinth Top          cum            1             -1         1.860          0.230    1.375     -0.588
        Inner side Lift                                       cum            -1            1          2.070          1.800    1.375     -5.123
        Back Filling above NGL to Plinth Beam                 cum            1             1         24.496         12.217    0.700    209.487
                                                              cum            1             1          8.217          3.100    0.700     17.831
        Plinth Beam
        Grid A, B/1-7,                                        cum            2             -1        24.496          0.400    0.400     -7.839
        Grid 1,7/A-D                                          cum            2             -1        11.417          0.400    0.400     -3.653
        Staircase Beam                                        cum            1             -1         8.217          0.300    0.400     -0.986
        Staircase Beam D, B/1A-1                              cum            2             -1         2.800          0.300    0.400     -0.672
                                                                                                              TOTAL Qty                636.139
 2      CEMENT CONCRETE WORK
        Providing and laying in position cement concrete
2 (a)   1:4:8(PCC), Excluding cost of shuttering
        (stoneaggregate 40mm nominal size)
        PCC Below Footing
        Grid A,D/1-7                                          cum            2             1         27.996          3.000    0.125     20.997
        Grid 1,7/A-D                                          cum            2             1          9.500          3.000    0.125     7.125
        Staircase 1A/B-D                                      cum            1             1         10.817          3.000    0.125     4.056
        Lift area offset                                      cum            1             1          1.800          4.260    0.125     0.958
        Grid A, B/1-7,                                        cum            2             1         21.696          0.500    0.100     2.170
        Grid 1,7/A-D                                          cum            2             1         10.617          0.500    0.100     1.062
                                                                                  Page No. 3 of 14                                                         MB
      Detail of Measurment and Calculated of Quantities
  Item                                                                                       L             B         D
                       Item Description                     Unit   No.         No.                                          Quantity   Remark
  code                                                                                    (meter)       (meter)   (meter)
        Staircase Beam                                      cum    1            1          7.317         0.400     0.100     0.293
          Staircase Beam D, B/1A-1                          cum    2           1           2.800          0.400    0.100     0.224
                                                                             TOTAL
                                                                                                                            36.885
                                                                              Qty
   2b     Floor PCC
          Grid 1-7/A-D                                      cum    1           1          24.036         11.757    0.100    28.259
          staircase area                                    cum    1           1           7.297          2.87     0.100     2.094
                                                                             TOTAL
                                                                                                                            30.353
                                                                              Qty
    2     RCC
  2 (b)   Providing and laying in position reinforcement
          cement concrete 1:1:2 (M25) in footing, Retaing
          wall, lintel beam, slab , stair cases, shelves,
          Fascia, louvers etc complet using 20mm stone
          aggrigate and down size ( the above excludes
          shuttering , Reinforce ment )
          RCC in Footing
          Grid A, B/1-7, 1,7/A-D                            cum    17           1          3.000          3.000    0.300     45.900
          Tapper part                                       cum    17           1          3.583                   0.550     33.504
          Column up to Plinth                               cum    17           1          0.400          0.400    1.225     3.332
          Grid 1A/B,C,D                                     cum    3            1          1.500          1.500    0.300     2.025
          Lift Raft                                         cum    1            1          4.280          2.760    0.300     3.544
                                                            cum    1            1          0.400          0.400    2.175     0.348
          Column up to Plinth                               cum    3            1          0.300          0.300    2.175     0.587
          Lift RCC Long wall up to Plinth Top               cum    2            1          2.300          0.230    2.175     2.301
          outer side RCC Wall of Lift up to Plinth Top      cum    1            1          1.800          0.230    2.175     0.900
          Inner side RCC Wall of Lift up to Plinth Top      cum    1            1          1.860          0.230    2.175     0.930
          Plinth Beam
          Grid A, B/1-7,                                    cum    2            1         24.496          0.400    0.400     7.839
          Grid 1,7/A-D                                      cum    2            1         11.417          0.400    0.400     3.653
          Staircase Beam                                    cum    1            1          8.217          0.300    0.400     0.986
          Staircase Beam D, B/1A-1                          cum    2            1          2.800          0.300    0.400     0.672
          Column from Plinth Beam to GF                     cum    14           1          0.400          0.400    4.600     10.304
                                                            cum    3            1          0.300          0.300    4.600     1.242
          Staircase Beam 1st Landing level                  cum    1            1          7.317          0.230    0.300     0.505
                                                            cum    2            1          2.800          0.230    0.300     0.386
          Lintel Beam
          Grid A, B/1-7,                                    cum    8            1          3.616          0.230    0.300     1.996
          Lift Column up to Slab                            cum    2            1          0.230          0.230    4.600     0.487
          Staircse waist slab up to 1st landing             cum    1            1          4.430          1.500    0.125     0.831
          1st Landing                                       cum    1            1          3.100          1.800    0.125     0.698
          1st Landing to 2nd Landing                        cum    1            1          4.430          1.500    0.125     0.831
          2nd Landing                                       cum    1            1          3.100          1.800    0.125     0.698
          First Floor                                                                                                        0.000
          Column up to slab                                 cum    14           1          0.400          0.400    3.600     8.064
                                                            cum    3            1          0.300          0.300    3.750     1.013
          Lift Column up to 2nd Floor level                 cum    2            1          0.230          0.230    3.750     0.397
          RMC Concrete in Slab
          Ground Floor
          Beam Grid A, D/1-7                                cum    2            1         21.696          0.300    0.450     5.858
          Beam Grid 1,7/A-D                                 cum    2            1         10.617          0.300    0.450     2.867
          Beam Grid B,C/1-7                                 cum    2            1         23.696          0.300    0.450     6.398
          Beam Grid 2,3,4,5,6/A-D                           cum    5            1         11.417          0.300    0.450     7.706
          Lift Beam                                         cum    2            1          2.300          0.230    0.230     0.243
                                                            cum    1            1          1.800          0.230    0.230     0.095
          slab Grid 1-7/A-D                                 cum    1            1         24.496         14.217    0.150    52.239
          First Floor
          Beam Grid A, D/1-7                                cum    2            1         21.696          0.300    0.450     5.858
          Beam Grid 1,7/A-D                                 cum    2            1         10.617          0.300    0.450     2.867
          Beam Grid B,C/1-7                                 cum    2            1         23.696          0.300    0.450     6.398
          Beam Grid 2,3,4,5,6/A-D                           cum    5            1         11.417          0.300    0.450     7.706
          Lift Beam                                         cum    2            1          2.300          0.230    0.230     0.243
                                                            cum    1            1          1.800          0.230    0.230     0.095
          slab Grid 1-7/A-D                                 cum    1            1         24.496         14.217    0.150    52.239
                                                                                                   TOTAL Qty                284.785
2 (c )    DPC Work
          Grid A, B/1-7,                                    sqm    2            1         24.496          0.230              11.268
                                                                       Page No. 4 of 14                                                         MB
    Detail of Measurment and Calculated of Quantities
Item                                                                                               L             B       D
                      Item Description                           Unit   No.         No.                                          Quantity   Remark
code                                                                                           (meter)       (meter)   (meter)
      Grid 1,7/A-D                                               sqm    2            1          11.417         0.230               5.252
      Staircase Beam                                             sqm    1            1           8.217         0.230               1.890
      Staircase Beam D, B/1A-1                                   sqm    2            1           2.800         0.230               1.288
                                                                                                         TOTAL                    19.698
                                                                            Page No. 5 of 14                                                         MB
    Detail of Measurment and Calculated of Quantities
Item                                                                                                                  L             B          D
                       Item Description                                         Unit      No.           No.                                              Quantity    Remark
code                                                                                                               (meter)       (meter)     (meter)
      slab Grid 1-7/A-D, Bootom                                                  sqm       1             1          24.496        14.217                  348.260
                                                                                 sqm       1             2          24.496                    0.150        7.349
                                                                                 sqm       1             2          14.217                    0.150        4.265
                                                                                 sqm                                         TOTAL                        1580.614
 4      Reinforcement
5 Brick Work
        Ground Floor
        Brick work Below DPC
        Grid A, B/1-7,                                                           cum       2             1         21.696            0.230    0.400        3.992
        Grid 1,/A-D                                                              cum       2             1         10.617            0.230    0.400        1.954
        Staircase Brick work                                                     cum       1             1          8.217            0.230    0.400        0.756
        Staircase Beam D, B/1A-1                                                 cum       2             1          2.800            0.230    0.400        0.515
        Brick work above Floor                                                   cum
        Grid A, B/1-7,                                                           cum       2             1         21.696            0.230    4.150        41.418
        Grid 1,/A-D                                                              cum       1             1         10.617            0.230    4.150        10.134
        Staircase wall                                                           cum       1             1          7.317            0.230    4.300         7.237
        Lift wall                                                                cum       1             2          2.070            0.230    4.600         4.380
                                                                                 cum       1             1          1.800            0.230    4.600         1.904
        Deduction Lift Opening wall                                              cum       -1            1          1.630            0.230    4.150        -1.556
        Staircase Door                                                           cum       -1            1          1.500            0.230    2.100        -0.725
        First Floor
        Grid A, B/1-7,                                                           cum       2             1         21.696            0.230    3.150        31.438
        Grid 1,/A-D                                                              cum       1             1         10.617            0.230    3.150         7.692
        Staircase wall                                                           cum       1             1          7.317            0.230    3.300         5.554
        Lift wall                                                                cum       1             2          2.070            0.230    3.300         3.142
                                                                                 cum       1             1          1.800            0.230    3.300         1.366
        Deduction Lift Opening wall                                              cum       -1            1          1.630            0.230    3.150        -1.181
        Staircase Door                                                           cum       -1            1          1.500            0.230    2.100        -0.725
        Deduction Door for Chajja                                                cum       -2            1          0.750            0.230    2.100        -0.725
        Parapit wall                                                             cum       2             1         24.496            0.230    0.300         3.380
                                                                                 cum       2             1         11.757            0.230    0.300         1.622
                                                                                 sqm                                         TOTAL                        121.574
 6      Plaster Work
        Prepare the surfaces of all internal & External walls at all heights
        and plaster in cm 1:4, 15mm thick, finished smooth with trowel
6 (a)   and sponge and providing 6 mm x 6mm recessed grooves at the
        junction of all RCC surfaces and brickwork including and
        scaffolding, curing, etc complete. (excluding cement)
        Ground Floor
        Plaster work (Internal )
        Grid A, B/1-7, , Long wall                                               sqm       2             1         24.036                     4.600       221.131
        Grid 1,/A-D, short wall                                                  sqm       1             1         11.757                     4.600        54.082
        Column offset                                                            sqm       2            12          0.170                     4.600        18.768
        Beam offset, Long Beam                                                   sqm       2             1         24.036            0.070                  3.365
        Beam offset, Short Beam                                                  sqm       1             1         11.757            0.070                  0.823
        Deduction staircase Door                                                 sqm       1            -1          1.500                     2.100        -3.150
        Door for wall opening for Toilet                                         sqm       1            -1          0.750                     2.100        -1.575
        Deduction Lift Door                                                      sqm       1            -1          1.630                     4.150        -6.765
        Plaster Lift area                                                        sqm       1             2          2.300                     4.750        21.850
                                                                                 sqm       1             2          1.800                     4.750        17.100
        Plaster work (External)
        Grid A, B/1-7, , Long wall                                               sqm       2             1         24.496                     4.750       232.712
        Grid 1,/A-D, short wall                                                  sqm       1             1         12.217                     4.750        58.031
        staircase wall                                                           sqm       1             2          8.217                     4.750        78.062
        side                                                                     sqm       1             2          0.300                     4.750         2.850
        Lift wall side                                                           sqm       1             2          2.300                     4.750        21.850
                                                                                                Page No. 6 of 14                                                              MB
    Detail of Measurment and Calculated of Quantities
Item                                                                                    L             B           D
                     Item Description                   Unit   No.         No.                                            Quantity   Remark
code                                                                                  (meter)       (meter)     (meter)
      First Floor
      Plaster work (Internal )
      Grid A, B/1-7, , Long wall                        sqm    2            1         24.036                     3.600    173.059
      Grid 1,/A-D, short wall                           sqm    1            1         11.757                     3.600     42.325
      Column offset                                     sqm    2           12          0.170                     3.600     14.688
      Beam offset, Long Beam                            sqm    2            1         24.036            0.070               3.365
      Beam offset, Short Beam                           sqm    1            1         11.757            0.070               0.823
      Deduction staircase Door                          sqm    1           -1          1.500                     2.100     -3.150
      Deduction Door for chajja                         sqm    1           -2          0.750                     2.100     -3.150
      Deduction Lift Door                               sqm    1           -1          1.630                     3.150     -5.135
      Plaster Lift area                                 sqm    1            2          2.300                     3.600     16.560
                                                        sqm    1            2          1.800                     3.600     12.960
      Plaster work (External)
      Grid A, B/1-7, , Long wall                        sqm    2            1         24.496                     3.750     183.720
      Grid 1,/A-D, short wall                           sqm    1            1         12.217                     3.750      45.814
      staircase wall                                    sqm    1            2          8.217                     3.750      61.628
      side                                              sqm    1            2          0.300                     3.750       2.250
      Lift wall side                                    sqm    1            2          2.300                     3.750      17.250
      Parapit wall                                                                                                           0.000
      Long wall                                         sqm    2            1         24.496                     0.830      40.663
      short wall                                        sqm    2            1         12.217                     0.830      20.280
                                                                                                TOTAL                     1343.085
                                                                   Page No. 7 of 14                                                           MB
NAME OF CLIENT             :
NAME OF CONSULTANT :
NAME OF LOCATION :
Foundation
          Footing (3000x3000x850) 18
          Nos.
          Main Bars Bottom Long                              10         100 c/c         28          18       504        0.150    2.900    0.150                                             3.200               1612.8
          Distribution Bars                                  10         100 c/c         28          18       504        0.150    2.900    0.150                                             3.200               1612.8
          Footing (1500x1500x300),
          3 Nos.
          Main Bars Bottom Long                              10         100 c/c         14          3         42        0.150    1.400    0.150                                             1.700                 71.4
          Distribution Bars                                  10         100 c/c         14          3         42        0.150    1.400    0.150                                             1.700                 71.4
          Lift Raft
          (4280x2760x300),
          Main Bars Bottom & Top                             10         100 c/c         41          2         82        0.150    2.660    0.150                                             2.960                242.7
          Distribution Bars                                   8         100 c/c         26          2         52        0.150    4.180    0.150                                             4.480    232.96
          Chair bars                                         10                         10          1         10        0.300    0.172    0.600        0.172            0.300               1.544                 15.4
          Retaining wall Main Bars                           10         150 c/c         55          2        110        0.300    2.600                                                      2.900                319.0
          Binder Long wall                                    8         150 c/c         14          2         28        0.300    2.450    0.300                                             3.050      85.4
                                                              8         150 c/c         14          2         28        0.300    2.180    0.300                                             2.780     77.84
          U Bars                                             10                         24          1         24        0.300    0.130    0.300                                             0.730                 17.5
          Column from foundation
          to GF
          C1 (400x400) 18 nos.                                                                                                                                                              0.000
          Main Bars                                          20                         12          18       216        0.300    7.175                 1.000                                8.475                                                   1830.6
          Stirrups Bars                                       8         150 c/c         47          18      846         0.320    0.320    0.320        0.320            0.160               1.440   1218.24
          Stirrups Bars                                       8         150 c/c         94          18      1692        0.180    0.320    0.180        0.320            0.160               1.160   1962.72
          C2 (300x300) 3 nos.                                                                                                                                                               0.000
          Main Bars                                          16                          6          3         18        0.300    7.175                 1.000                                8.475                                       152.55
          Stirrups Bars                                       8         150 c/c         47          3        141        0.220    0.220    0.220        0.220            0.160               1.040    146.64
          Column (230x230) 2 Nos.
          Main Bars                                          16                          6          2         12        0.300    7.175                 1.000                                8.475                                         101.7
          Stirrups Bars                                       8         150c/c          47          2         94        0.150    0.150    0.150        0.150            0.160               0.760     71.44
          Plinth Beam                                                                                                                                                                       0.000
          Grid A,D/1-7                                                                                                                                                                      0.000
          Main Bars Bottom                                   20                         4           2         8         0.300   24.446    0.300                         2.000              27.046                                                  216.368
          Main Bars Top                                      20                         4           2         8         0.300   24.446    0.300                         2.000              27.046                                                  216.368
          Stirrups Bars                                      8          150 c/c        144          2        288        0.350    0.350    0.350        0.350            0.160               1.560    449.28
          Grid 1,7/A-D                                                                                                                                                                      0.000
          Main Bars Bottom                                   20                          4          2          8        0.300   12.167    0.300                         1.000              13.767                                                  110.136
          Main Bars Top                                      20                          4          2          8        0.300   12.167    0.300                         1.000              13.767                                                  110.136
                                                                                                                                                         Page 8 of 14
NAME OF CLIENT          :
NAME OF CONSULTANT :
NAME OF LOCATION :
                                                                                                                                                         Page 9 of 14
NAME OF CLIENT          :
NAME OF CONSULTANT :
NAME OF LOCATION :
                                                                                                                                                       Page 10 of 14
NAME OF CLIENT          :
NAME OF CONSULTANT :
NAME OF LOCATION :
                                                                                                                                                       Page 11 of 14
NAME OF CLIENT          :
NAME OF CONSULTANT :
NAME OF LOCATION :
                                                                                                                                                   Page 12 of 14
                                 SARASWATI CONSTRUCTION COMPANY
PROJECT :
CLIENT :
CONTRACTOR:- Saraswati Construction Company
                                          Cement Consumption
Sr. No                 Material Description        Unit    Quantity      Per Bags Cement   Cement Qty.   Remark
A CEMENT :
  2      Cement Consumption in RCC - M25 Grade    Cum          134.785          7.000             943.49 Bags
          kg /cum 350kg