CLIENT:
MSHEIREB
PROPERTIES Procurement Status Log (974 OFFICE)
Lead Time Material Submittal Status
Activity ID
Purchase Order Actual delivery
Sr. No (As per approved Description Supplier /Manufacturer Details Country of Origin Material on Site Submittal Approval REF: NO Code Status 974 (Stakeholder) Plan Delivery Date Remarks
REF: NO. date
BL)
Planned Actual Planned Actual
A. FIT-OUT
1 Gypsum & Painting Q-Gyps Qatar Local - Stock available 16-Oct-24 16-Oct-24
2 Raised Flooring Total Flooring/Kehua China 5-6 weeks 20-Nov-24
4 Doors & Ironmongeries 1 -2 weeks 19-Dec-24
Joinery Works-Reception Desk, Feature Walls, Counters and
6 Qatar 1 -2 weeks 15-Dec-24
Cabinetries,
Wooden Cladding Interior Plastic Composite Fluted Covering Board
7 1 -2 weeks 19-Dec-24
Decorative WPC Wall Panel "behind TV unit"
Timber Ceiling Vic Ash finish natural oil Batten size 40mm x 40mm
8 1 -2 weeks 4-Dec-24
"WC-01"
9 Marble polished treshold and Marble/Corian Counter tops Sinmar Qatar 1 week 27-Nov-24
10 Waterproofing to wet areas Sika Qatar Local - Stock available 24-Nov-24
11 Blockworks and accessories Qatar Local - Stock available 17-Nov-24 10-Oct-24
12 MDF Skirting Qatar Local - Stock available 15-Dec-24
13 Glass Partition and Glass Door 1 -2 weeks 1-Dec-24
14 Double Sliding Glass Door (Fire Rated to confirm upon issuance of FLS) 1 -2 weeks 19-Dec-24
15 Carpet & Vinyl Flooring Decoproject China Local - Stock available 11-Dec-24
16 Porcelain Tiles Nabina Ceramics Qatar Local - Stock available 27-Nov-24
17 Branding Works -Wall Art in Black with LED Light & Stickers Qatar Neon/Gulfcrafts Qatar to confirm upon design freeze 19-Dec-24
5 Signage / graphics (Room Signage & Identifications) Qatar Neon/Gulfcrafts Qatar to confirm upon design freeze 19-Dec-24
18 Manual Curtain/Blinds Supply Master Qatar 1 week ` 11-Dec-24
19 Lighting Fixtures Qatar 5 -6 weeks 9-Dec-24
20 Sanitary Fixtures Qatar Local - Stock available 19-Dec-24
B. MECHANICAL
1 FCU FINPOWER UAE 6 weeks 6-Nov-24
2 Hangers and supports WILTZ/TEMBO INDIA Delivered 7-Oct-24 30-Oct-24
3 Chilled water pipe and fittings AQUATHERM GERMANY Delivered 7-Oct-24 24-Oct-24
4 Rubber insualtion Gulfoflex UAE Delivered 7-Oct-24 24-Oct-24
5 Fire pipe and fittings FLOWCON&BIS ROMANIA&THAILAND Delivered 14-Oct-24 23-Oct-24
CLIENT:
MSHEIREB
PROPERTIES Procurement Status Log (974 OFFICE)
Lead Time Material Submittal Status
Activity ID
Purchase Order Actual delivery
Sr. No (As per approved Description Supplier /Manufacturer Details Country of Origin Material on Site Submittal Approval REF: NO Code Status 974 (Stakeholder) Plan Delivery Date Remarks
REF: NO. date
BL)
Planned Actual Planned Actual
6 Sprinklers Rapidrop UK Delivered 7-Oct-24 23-Oct-24
7 GI & PI Duct JINDAL INDIA Delivered 7-Oct-24 23-Oct-24
8 Grill and diffuser HAWA QATAR 2 weeks 11-Dec-24 18-Nov-24
9 Duct accessories HAWA CHINA Delivered 7-Oct-24 23-Oct-24
11 Thermostat HONEYWELL CHINA 2 weeks 11-Dec-24 4-Nov-24
12 Condenstae drain pipe QADDCO QATAR Delivered 7-Oct-24 23-Oct-24
13 Water supply PPR pipe and fittings QADDCO QATAR Delivered 7-Oct-24 23-Oct-24
14 Water supply Valves and fittings PEX UK 2 weeks 19-Dec-24 23-Oct-24
15 UPVC pipe and fittings QADDCO QATAR Delivered 7-Oct-24 23-Oct-24
C. ELECTRICAL
1 Fire alarm system SIEMENS/EXISTING SYSTEM USA 6 weeks 20-Nov-24 13-Nov-24
2 PVC conduits and accessories QADDCO QATAR Delivered 10-Oct-24 10-Oct-24
3 GI conduit and accessories ALTAIR INDIA Delivered 14-Oct-24 10-Oct-24
4 Fire alarm cables NORDEN UK Delivered 14-Oct-24 10-Oct-24
5 Electrical wires and cables DOHA CABLES QATAR Delivered 9-Oct-24 10-Oct-24
6 Data cables /NORDEN/ULTIMA/TMT EUROPE/ASIA 2 weeks 27-Nov-24
7 Floor box DAVIS/ALTAIR MALAYSIA/INDA 2 weeks 2-Dec-24
8 Wiring accessories CLICK/MK/SCHNEIDER EUROPE/CHINA/ASIA 2 weeks 9-Oct-24
TRANSGLOBEL/TRANSPOWER/
9 Cable tray and trunking WILTZ
QATAR Delivered 9-Oct-24 10-Oct-24
10 Ceiling rose SCAME VIETNAM Not required 9-Oct-24
11 Isolators SCAME ITALY 2 weeks 11-Dec-24 10-Nov-24
12 Smdp and dp panel Panduit USA 1 Week 4-Dec-24