0% found this document useful (0 votes)
248 views1 page

Mep Rooms Handover Tracker: Project: Parsons Regional Headquarters

The document is a tracker of mechanical, electrical, and plumbing (MEP) room handovers for the Parsons Regional Headquarters project. It lists 51 MEP rooms across various floors that need to be handed over, along with planned and actual handover dates. Many of the rooms are behind schedule, with delays ranging from 12 to 124 days. The tracker will be used to monitor progress and ensure all MEP rooms are handed over per schedule.

Uploaded by

ShivarajJadhav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
248 views1 page

Mep Rooms Handover Tracker: Project: Parsons Regional Headquarters

The document is a tracker of mechanical, electrical, and plumbing (MEP) room handovers for the Parsons Regional Headquarters project. It lists 51 MEP rooms across various floors that need to be handed over, along with planned and actual handover dates. Many of the rooms are behind schedule, with delays ranging from 12 to 124 days. The tracker will be used to monitor progress and ensure all MEP rooms are handed over per schedule.

Uploaded by

ShivarajJadhav
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PROJECT : PARSONS REGIONAL HEADQUARTERS

MEP ROOMS HANDOVER TRACKER 3-Nov-18


Actual/
SL MEP Works Plan Finish based
ROOM DESCRIPTION ROOM NO FLOOR Forecast* Hand Over reference Delay Remarks
NO Status Duration on Access
Handover
1 ELECTRICAL ROOM B03.16 B03 14-Aug-18 BM-AD-SUBCONLET-001118 In progress 60 13-Oct-18 -21
2 ELECTRICAL ROOM B03.04 B03 14-Aug-18 BM-AD-SUBCONLET-001118 In progress 60 13-Oct-18 -21
3 TELECOMS B03.05 B03 14-Aug-18 BM-AD-SUBCONLET-001118 In progress 60 13-Oct-18 -21
4 TELECOMS B03.15 B03 14-Aug-18 BM-AD-SUBCONLET-001118 In progress 60 13-Oct-18 -21
5 DOMESTIC WATER TANK B03.19 B03 17-Sep-18 BM-AD-SUBCONLET-001273 In progress 60 16-Nov-18 13
6 PUMP ROOM B03.20 B03 17-Sep-18 BM-AD-SUBCONLET-001273 In progress 60 16-Nov-18 13
7 ELECTRICAL ROOM B02.04 B02 14-Aug-18 BM-AD-SUBCONLET-001118 In progress 60 13-Oct-18 -21
8 TELECOMS B02.05 B02 14-Aug-18 BM-AD-SUBCONLET-001118 In progress 60 13-Oct-18 -21
9 TELECOMS B02.15 B02 14-Aug-18 BM-AD-SUBCONLET-001118 In progress 60 13-Oct-18 -21
10 ELECTRICAL ROOM B02.16 B02 14-Aug-18 BM-AD-SUBCONLET-001118 In progress 60 13-Oct-18 -21
11 WATER TANK B01.08 B01 28-Oct-18 60 27-Dec-18 54
12 ELECTRICAL ROOM B01.04 B01 23-Aug-18 BM-AD-SUBCONLET-001150 In progress 60 22-Oct-18 -12
13 TELECOMS B01.05 B01 23-Aug-18 BM-AD-SUBCONLET-001150 In progress 60 22-Oct-18 -12
14 TELECOMS B01.15 B01 23-Aug-18 BM-AD-SUBCONLET-001150 In progress 60 22-Oct-18 -12
15 ELECTRICAL ROOM B01.16 B01 23-Aug-18 BM-AD-SUBCONLET-001150 In progress 60 22-Oct-18 -12
16 L.V ROOM-1 GF.72 GRD 08-Oct-18 BM-AD-SUBCONLET-001359 In progress 60 07-Dec-18 34
17 ELECTRICAL ROOM GF.04 GRD 06-Nov-18 BM-AD-SUBCONLET-001541 60 05-Jan-19 63
18 TELECOMS GF.05 GRD 06-Nov-18 BM-AD-SUBCONLET-001541 60 05-Jan-19 63
19 TELECOMS GF.15 GRD 24-Oct-18 60 23-Dec-18 50
20 ELECTRICAL ROOM GF.16 GRD 05-Nov-18 BM-AD-SUBCONLET-001536 60 04-Jan-19 62
21 ELECTRICAL ROOM GF.48 GRD 28-Oct-18 BM-AD-SUBCONLET-001487 60 27-Dec-18 54
22 GENERATOR ROOM GF.70 GRD 20-Oct-18 BM-AD-SUBCONLET-001433 In progress 60 19-Dec-18 46
23 TRANSFORMER ROOM GF.71 GRD 20-Oct-18 BM-AD-SUBCONLET-001433 In progress 60 19-Dec-18 46
24 L.V ROOM GF.19 GRD 20-Oct-18 BM-AD-SUBCONLET-001433 In progress 60 19-Dec-18 46
25 ELECTRICAL ROOM GF.40 GRD 28-Oct-18 BM-AD-SUBCONLET-001487 60 27-Dec-18 54
26 SECURITY CONTROL & BMS ROOM GF.56 GRD 25-Oct-18 60 24-Dec-18 51
27 ODF ETISALAT GF.74 GRD 25-Oct-18 60 24-Dec-18 51
28 FIRE COMMAND CENTRE GF.81 GRD 10-Nov-18 60 09-Jan-19 67
29 H.V ROOM GF.88 GRD 10-Nov-18 60 09-Jan-19 67
30 ELECTRICAL ROOM P01.04 P01 05-Nov-18 60 04-Jan-19 62
31 TELECOMS P01.05 P01 05-Nov-18 60 04-Jan-19 62
32 TELECOMS P01.15 P01 05-Nov-18 60 04-Jan-19 62
33 ELECTRICAL ROOM P01.16 P01 05-Nov-18 60 04-Jan-19 62
34 ELECTRICAL ROOM P02.04 P02 12-Nov-18 60 11-Jan-19 69
35 TELECOMS P02.05 P02 12-Nov-18 60 11-Jan-19 69
36 MEP P02.08 P02 08-Dec-18 60 06-Feb-19 95
37 MEP P02.12 P02 12-Dec-18 60 10-Feb-19 99
38 TELECOMS P02.15 P02 12-Nov-18 60 11-Jan-19 69
39 ELECTRICAL ROOM P02.16 P02 12-Nov-18 60 11-Jan-19 69
40 ELECTRICAL ROOM L01.04 L01 07-Nov-18 BM-AD-SUBCONLET-001545 60 06-Jan-19 64
41 TELECOMS L01.05 L01 07-Nov-18 BM-AD-SUBCONLET-001545 60 06-Jan-19 64
41A WATER METER ROOM L01.06 L01 07-Nov-18 BM-AD-SUBCONLET-001545
41B WASTE ROOM L01.07 L01
42 TELECOMS L01.32 L01 01-Dec-18 60 30-Jan-19 88
43 ELECTRICAL ROOM L01.33 L01 05-Dec-18 60 03-Feb-19 92
43A WATER METER ROOM L01.31 L01
43B WASTE ROOM L01.30 L01
44 ELECTRICAL ROOM L02.04 L02 09-Dec-18 60 07-Feb-19 96
45 TELECOMS L02.05 L02 13-Dec-18 60 11-Feb-19 100
46 TELECOMS L02.33 L02 17-Dec-18 60 15-Feb-19 104
47 ELECTRICAL ROOM L02.34 L02 21-Dec-18 60 19-Feb-19 108
48 ELECTRICAL ROOM L03.09 L03 25-Dec-18 60 23-Feb-19 112
49 TELECOMS L03.10 L03 29-Dec-18 60 27-Feb-19 116
50 TELECOMS L03.20 L03 02-Jan-19 60 03-Mar-19 120
51 ELECTRICAL ROOM L03.21 L03 06-Jan-19 60 07-Mar-19 124
52 ELECTRICAL ROOM L04.09 L04 02-Jan-19 60 03-Mar-19 120
53 TELECOMS L04.10 L04 05-Jan-19 60 06-Mar-19 123
54 TELECOMS L04.20 L04 09-Jan-19 60 10-Mar-19 127
55 ELECTRICAL ROOM L04.21 L04 13-Jan-19 60 14-Mar-19 131
56 ELECTRICAL ROOM L05.09 L05 09-Jan-19 60 10-Mar-19 127
57 TELECOMS L05.10 L05 12-Jan-19 60 13-Mar-19 130
58 TELECOMS L05.20 L05 16-Jan-19 60 17-Mar-19 134
59 ELECTRICAL ROOM L05.21 L05 20-Jan-19 60 21-Mar-19 138
60 ELECTRICAL ROOM L06.09 L06 16-Jan-19 60 17-Mar-19 134
61 TELECOMS L06.10 L06 16-Jan-19 60 17-Mar-19 134
62 TELECOMS L06.20 L06 16-Jan-19 60 17-Mar-19 134
63 ELECTRICAL ROOM L06.21 L06 16-Jan-19 60 17-Mar-19 134
64 ELECTRICAL ROOM L07.05 L07 23-Jan-19 60 24-Mar-19 141
65 TELECOMS L07.07 L07 23-Jan-19 60 24-Mar-19 141
66 TELECOMS L07.21 L07 23-Jan-19 60 24-Mar-19 141
67 ELECTRICAL ROOM L07.22 L07 23-Jan-19 60 24-Mar-19 141
68 ELECTRICAL ROOM L08.04 L08 30-Jan-19 60 31-Mar-19 148
69 TELECOMS L08.05 L08 30-Jan-19 60 31-Mar-19 148
70 TELECOMS L08.21 L08 30-Jan-19 60 31-Mar-19 148
71 ELECTRICAL ROOM L08.22 L08 30-Jan-19 60 31-Mar-19 148
72 CHILLED WATER PUMP ROOM RF.06 RF 06-Feb-19 60 07-Apr-19 155
73 PUMP ROOM FOR DOMESTIC WATER PUMPS RF.03 RF 06-Feb-19 60 07-Apr-19 155
74 CALORIFIER ROOM RF.05 RF 06-Feb-19 60 07-Apr-19 155
75 PUMP ROOM FOR DOMESTIC WATER PUMPS RF.11 RF 06-Feb-19 60 07-Apr-19 155
76 CHILLED WATER PUMP ROOM RF.13 RF 06-Feb-19 60 07-Apr-19 155
77 CALORIFIER ROOM RF.08 RF 06-Feb-19 60 07-Apr-19
78 MCC Room RF.04 RF 06-Feb-19 60 07-Apr-19
79 MCC Room RF.12 RF 06-Feb-19 60 07-Apr-19 155
*Forecast dates based on area hadndover after blowckwork & Painting. Subject to confirmation from Construction team.