ASSIUT HYDROCRACKING COMPLEX PROJECT (AHC)
Emergency Team Daily Report
Date: 19.11.2024
Man Power
SN Name Title
1 MAHMOUD SAID Rescue Team Supervisor
2 RAGHEB ABD ELMAGEED Rescue Team Supervisor
3 HOZIFA ABDULLAH Rescue Team Technician
4 AHMED ELTAHAWY Rescue Team Technician
5 MOHAMMED HASAN Rescue Team Technician
6 MOHAMED MAGDY Rescue Team Technician
7 ABDULLAH MAHMOUD Rescue Team Technician
8 ABDULAZIZ GAMAL Rescue Team Technician
Page 1 of 7
ASSIUT HYDROCRACKING COMPLEX PROJECT (AHC)
Emergency Team Daily Report
Permits Signed:
SN Area PTW No Activity / Description
B03
1. 22299 Confined Space ( installation )
H021
B04
2. 22741 Confined Space ( Grating Removal )
H001
B04
3. 22774 Working at height (Man basket)
H001 Roof Cladding
B04
4. 22390 Confined Space ( Scaffolding )
H001
B04
5. 22826 Confined Space ( Isolation )
H001
B03
6. 22647 Working at height (Man basket)
T021 Sec Steel
B03
7. 22648 Working at height (Man basket)
T021 Grating
B03
8. 22373 Confined Space (Alignment)
E012
B03
9. 22341 Confined Space (Construction)
Trench Line
B03
10. 22948 Working at Height ( PWHT )
STR100
B03
11. 22938 Working at Height ( Piping )
PR300
B03
12. 22342 Confined Space (test)
Manhole
Page 2 of 7
ASSIUT HYDROCRACKING COMPLEX PROJECT (AHC)
Emergency Team Daily Report
B03
13. 22960 Working at Height ( Piping )
K001A,B,C
B03
14. 22909 Confined Space (Ladder )
Manhole
B03
15. 22944 Working at Height ( Growled )
K002
B03
16. 22937 Working at Height ( Piping )
PR105-106
B03
17. 22949 Working at Height ( Piping )
STR200
B03
18. 22344 Working at Height (Chipping)
Manhole
B03
19. 22540 Working at Height (installation)
PR500
B04
20. 22628 Confined Space (Chipping )
Manhole
B04
21. 22928 Working at Height ( Man Lift)
H001
B04
22. 22864 Confined Space (Ladder )
Manhole
Q
23. 22358 Confined Space (Hydro test)
BA001
Q
24. 22752 Working at Height ( Grating Removal )
PR101-102
Q
25. 22827 Confined Space (Construction)
BA701 Pump 702 ABC
Q
26. 22946 Confined Space (Installation)
BA001
Page 3 of 7
ASSIUT HYDROCRACKING COMPLEX PROJECT (AHC)
Emergency Team Daily Report
Q
27. 22945 Confined Space (Installation)
BA002
Q
28. 22947 Working at Height (Installation)
Colling Tawas
Q
29. 22336 Confined Space ( Hydro-Test )
Cooling Tower
Q
30. 22964 Confined Space ( Hydro-Test )
BA001
Q
31. 22933 Work at Height ( Scaffolding )
PR 102
Q
32. 22934 Confined Space ( Scaffolding )
BA001
Q
33. 22931 Confined Space ( Scaffolding )
BA002
Q
34. 22932 Work at Height ( Scaffolding )
PR 101
Q
35. 22494 Confined Space (concrete)
Manholes
M58
36. 22510 Confined Space ( HDBE )
Trench
M50
37. 22872 Confined Space (Chipping )
Man hole
M50
38. 22769 Confined Space ( Construction )
Trench Line
M50
39. 22868 Confined Space ( Scaffolding )
BA601
M
40. 22930 Work at Height ( Scaffolding )
PR 1100
Page 4 of 7
ASSIUT HYDROCRACKING COMPLEX PROJECT (AHC)
Emergency Team Daily Report
M
41. 22929 Work at Height ( Scaffolding )
PR 1000
M
42. 22927 Work at Height ( Scaffolding )
PR 900
M
43. 22926 Work at Height ( Scaffolding )
PR 900
DHTU
44. Air cooler E-005 A/B/C/D 13058 Confined Space (Alignment)
– E007A/B
DHTU
45. 13240 Working at Height ( Piping )
K001A,B,C
DHTU
46. 13095 Confined Space ( Hydro-Test )
BA002
DHTU
47. 13193 Confined Space ( Piping )
BA002
VDU
48. 13239 Confined Space ( Touch up )
BA002
VDU
49. 13004 Confined Space ( House Keeping )
Man hole
VDU
50. 13136 Working at Height ( Piping )
T001
VDU
51. 13204 Working at Height ( Tray )
T001
Page 5 of 7
ASSIUT HYDROCRACKING COMPLEX PROJECT (AHC)
Emergency Team Daily Report
Rescue team activity drill
Confined Space – B04 – H001
Scenario: a worker had been tired Inside H001 Scaffolds.
IMG_202410 31_122 018
Page 6 of 7
ASSIUT HYDROCRACKING COMPLEX PROJECT (AHC)
Emergency Team Daily Report
1. Observations / Notes (If any):
2. Signed a rescue plan for T001 Piping Area VDU.
3. Signed a rescue plan for PR100 Piping Area VDU.
4. Signed a rescue plan for PR200 Piping Area VDU.
5. Signed a rescue plan for H001 Cutting WAH Area VDU.
6. Signed a rescue plan for H001 Isolation CONF Area VDU.
7. Signed a rescue plan for H001 Preservation Area VDU.
8. Signed a rescue plan for STR 200 Steel at Area DHTU.
9. Signed a rescue plan for PR101-102-103 Piping at Area DHTU.
10. Signed a rescue plan for STR 100 Piping at Area B03.
11. Signed a rescue plan for H021 Piping at Area B03.
12. Signed a rescue plan for H002 Installation at Area B03.
13. Signed a rescue plan for H001 Installation at Area B03.
14. Signed a rescue plan for H021 Installation at Area B03.
15. Signed a rescue plan for H021 welding at Area B03.
16. Signed a rescue plan for H021 PWHT at Area B03.
17. Signed a rescue plan for H002 Installation at Area B03.
18. Signed a rescue plan for H001 Installation WAH at Area B03.
19. Signed a rescue plan for H021 Installation WAH at Area B03.
20. Signed a rescue plan for H001 Bent house Grating at Area B04.
21. Signed a rescue plan for PR1200 TO 1800 Hydro test at Area M.
22. Signed a rescue plan for PR100 Steel man lift at Area M50.
23. Signed a rescue plan for Trench Hydro test at Area M50.
24. Signed a rescue plan for BA002 Scaffolding Space at Area Q.
Page 7 of 7