Performance Management (PM)
Performance Management (PM)
MANCE MANAGEMEN
ACCA
EMENT
A REVISION TO M
Particulars Amount
Direct material 212
Direct labour
Bonding department 120
finishing department 72
Prime cost 404
Variable production cost
Bonding department 36
finishing department 15
Total variableProduction cost 455
Fixed production OH 40
Total production cost 495 Let Sp be X , Therefore profit is 25% of sp i.e. 0.
Non production OH 30 = 0.75x = 525 , X = 525/0.75 = 70
Total Cost 525
Profit 175
Selling price 700
Particulars Minutes
Total time 100%
idle time (8%) 0.08
Productive time 92%
92 32 min
100 34.8 min
Add on: non productive time 2 min
Total time 36.8 min
For 60 min =4.50
For 1 min=4.50/60
for 36.8 min 2.76 for 20 sandwitch
for 1 sandwitch 0.138
Illustratiion - 1
Particulars SKY BAR MOON EGG
Direct labour cost per unit ($) 0.07 0.14
Direct material cost per unit ($) 0.17 0.19
Sales/ production 500000 150000
Direct labour hours per unit 0.001 0.01
Direct machine hours per unit 0.01 0.04
Selling price per unit 0.5 0.45
Actual production OH 80000
OAR PER MACHINE HOUR 5
Calculation of cost card
Particulars SKY BAR MOON EGG
Direct labour cost per unit ($) 0.07 0.14
Direct material cost per unit ($) 0.17 0.19
(Production) OH Absorbed per unit 5000.00 20000.00
Full cost of production per unit 5000.24 20000.33
Selling price per unit 0.5 0.45
Profit/ loss per unit -4999.74 -19999.88
Illustratiion - 2
Calculation of under/over absorption
Particulars $
Direct cost (per unit) 17
Fixed overheads (per unit) 9
Total cost (per unit) 26
Budgeted fixed OH 27000
Fixed OH absorbed 28800
Actual fixed OH [27000+(27000*5%)] 28350
Over-absorption 450
Illustratiion
Calculation of under/over absorption
Particulars $ Units
Budgeted production - 5000
Actual production - 5200
Direct cost (per unit) 25 -
Fixed overheads (per unit) 10 -
Total cost (per unit) 35 -
The actual fixed overhead expenditure was 8% higher than budgeted.
Note
During the period, 200 defective units had to
be scrapped, the cost of scrapped units is to be
absorbed into the remaining good units.
Practice Question
Particulars Twix bar Mars bite
Direct labour cost per unit ($) 0.10 0.15
Direct Material cost per unit ($) 0.22 0.2
Actual production/ sales 400000 100000
Direct labour hours per unit 0.003 0.006
Direct machine hours per unit 0.02 0.03
Selling price per unit ($) 0.55 0.48
Annual production overhead = $95000
Cost Sheet
Particulars Twix bar Mars bite
Direct labour cost per unit ($) 0.10 0.15
Direct Material cost per unit ($) 0.22 0.2
Overhead Absorbed 0.09 0.14
Full cost of production 0.41 0.49
Selling price per unit ($) 0.55 0.48
Profit/loss per unit 0.14 -0.01
OAR per machine hour 4.52
ILLUSTRATION -3
Level of activity 2500 units 5000 units
Revenue 50000 100000
Variable cost 30000 60000
Total contribution 20000 40000
fixed cost 25000 25000
Total profit / (loss) -5000 15000
Contribution per unit 8 8
fixed cost Per unit 10 5
Profit/(loss) per unit -2 3
ON TO MANAGEMENT ACCOUNT
Sp Let 100
Profit 25% of sp
Therefore 25
cp 75
75 525
1
100 700
X , Therefore profit is 25% of sp i.e. 0.25x therefore cost = sp - profit = 0.75X Therefore Cost
= 0.75x = 525 , X = 525/0.75 = 700 , Therefore profit = 700 X 0.25 = 175
SUN BAR
0.12
0.16
250000
0.005
0.02
0.43
SUN BAR
0.12
0.16
10000.00
10000.28
0.43
-9999.85
Illustratiion
Calculation of under/over absorption
Particulars $
Direct cost (per unit) 20
Fixed overheads (per unit) 8
Total cost (per unit) 28
Snickers chunk
0.18
0.25
0.23
0.66
0.5
-0.16
52
3
7500 units 10000 units
150000 200000
90000 120000
60000 80000
25000 25000
35000 55000
8 8
3 2.5
4.67 5.5
ACCOUNTING
SPECIALIST COST AND MANAGEM
TYU- 2 Theor
Step -1 Idenification of constraint (bottl
PROCESS A B
Capacity per week (Current) 400 300
New machine for C - -
New capacity 400 300
New machine for B 300
New capacity 400 600
New machine for A 150
New capacity 550 600
Throughput calculation
Information $
Profit 120000
Fixed cost 300000
Material cost 10% of sale value
contribution/ sale ratio 75%
Throughput = sale price - direct material cost
Workings
Sale (revenue) (100%)...(420000/75)*100 560000 WORKINGS
less: All variable cost (25%) 56000 75
contribution (75%) 420000 1
less: fixed cost 300000 100
Profit / loss 120000
Throughput 504000
Test your understadning -3
TPAR & RETURN PER FACTORY HOUR
production time ( machine hour ) 1.5
Availability of machine 10
Machine maximum time 40 hour each per week
Total machine time 400 hours per week
sale price of product ($) per unit 85
Direct material cost per unit ($) 42.5
total factory cost 8000 each week
Workings
Throughput = sale price -direct material cost 42.5
Throughtput per unit 42.5
Retur per factory hour = TP per unit / production
time on bottleneck 28.33
TPAR = Return per factory hour/ cost per factory hour
Cost per factory hour = total factory cost
/bottlneck Maximum time available 20.00
TPAR 1.417
Calculation of TPAR
Selling price per unit ($) 10
WORKINGS
420000
5600
560000
Test your
Particulars Alpha
sale price per unit($) 2
Less: direct material cost per unit($) 0.50
Throughput per unit 1.50
Machine time per unit (min)
Assembly (min) 2
quality control(min) 3
pacakaging (min) 4
Sp 182.93
Profit 16.63
Target price 166.3
quite reasonable
at $8 per unit
of the product. he
M Prodcuing 20M products
nly and selling it for $8
to sell but also making
OUNTING TECHNIQUE
d interelated with each other . All the options must be opt in order to maximize
profitability
1250000 2 -750000
1
6250000 4.5 1750000
10200
10200
0
Decline
-
0.9
0.5
4
esource
hour
hour Bottleneck
hour
COST VOLUME
Test your understandings - 1
Selling price ($) 25 per unit
Variable cost ($) 20 per unit
Contribution per unit 5
less: fixed cost 50000
Profit 0
A) No of units (breakeven) 10000 Selling price ($) 25
B)Total Contribution 90000 Variable cost ($) 20
Level of activity to earn profit 18000 Contribution per unit 5
less: fixed cost 50000
C) No of sales budgeted 13000 Profit 40000
Contribution 65000
less: fixed cost 50000
Profit 15000
breakeven 10000
margin of safety (units) 3000
margin of safety (%) 23%
per unit
per unit
ADVANCE V
Calculation of material M
Material Grade Actual Qty consumed Standard Mix
A 14000 12600
B 5500 5040
C 5500 7560
Total 25000 25200
our understandings - 10
our understandings - 13
f sales mix and sales quantity
standard mix (kgs) Sales Mix(kgs)
std contribution per
Sales
unitMix($)
8200 1300 5 6500 F
12300 -1300 6 -7800 A
20500 0 11 -1300 A
arket share
Test your understanding - 6
Recouncilation Statement - AC
Variance $
Budgeted profit
Sale volume variance A
Standard profit on actual sales
TEST YO
FOAR 1.75
Fixed OH exp variance 1240
Fixed OH capacity variance 520.00
The labour works less hour than it was budgeted for here ther
Test y
Material grade Actual mix
A 14000
B 5500
C 5500
25000
Operational variance
Planning variance
Total sale quantity variance
Addition
Original budget
Flexed budget
-6
AC
$ Working
37500 Actual Q X Actual price
2500 Sale price variance
35000 Actual Q X Standard pric
F
hour
Less hours worked than expected as a r
A utilised optimumly
Working
Sale price variance per cy
Effect therefore sale price varia
Contribution per cylinder
F Sale volume variance
Material price variance pe
A Material price variance
F Material usage variance
A standard Q for actual pro
A Labour rate variance per
F Labour rate variance
Standard hour for actual
Labour efficiency varianc
A Fixed OH Expenditure var
understandings - 9
Output Material used cost per unit
14000 1.10
5500 2.40
5500 1.50
1000 25000
20833
167 F
1.78
296 F
nderstandings - 14
R K Total
6750 8500 20000
F F F
1500 2500 -3000
F A A
3.00 5.00
4.1 4.85
5.2 4.55
2.70 3.60
SQ STD MIX Std mix(%) AQ STD MIX Sale quantity variance (units)
400 20% 440 40
600 30% 660 60
1000 50% 1100 100
2000 2200
SQ STD MIX Std mix(%) AQ STD MIX Sale mix variance (units)
400 20% 440 -140
600 30% 660 40
1000 50% 1100 100
2000 2200
SQ STD MIX Revised sales budget
Planning variance (units) Std profit per unit
400 360 -40 8
600 540 -60 6
1000 900 -100 4
2000 1800 200
Actual sales
Revised sales budget Std profit per unit Operational variance ($)
300 360 8 -480
700 540 6 960
1200 900 4 1200
2200 1800 1680
r understandings - 18
5.20 per unit
5.00 per unit
5.18 per unit
10000
1800 ADV
2000 FAV
200 FAV
r understandings - 19
28 7kg per unit @$4 per kg
30 8 kg per unit@$3.80 per kg
1400 units
11000kg at $41500
3.77
2500 F
4800 A
9800 kg
300 F 11200
2200 F
2500 F
r understandings - 20
5 per unit
250
1450
10
20%
500 F
1500 1250
250 15000
2500 A 14500
2000 A
1499.99999999999 A
2800 A
6000 A
3500 F
Working Note -1
0.06
599.999999999998 A
1.7
1020 F
0.001
60.000000000001 F
160 A
53000
-0.02
-39.9999999999999 A
2120
120 F
200 A