0% found this document useful (0 votes)
62 views11 pages

Direct Pipe vs HDD: Method & Case Studies

Uploaded by

maa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
62 views11 pages

Direct Pipe vs HDD: Method & Case Studies

Uploaded by

maa
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

DIRECT PIPE AS AN ALTERNATIVE TO HDD,

METHOD AND CASE STUDIES


Authors : Dr Gerhard Lang, Business Development Manager, Herrenknecht AG
Diana Pfeff, Product Manger, Herrenknecht AG
Presenter : Ben Hayes, Sales Manager, Herrenknecht Asia

ABSTRACT
This paper provides an overview of the multiple case histories of the Direct Pipe technology worldwide.
Thereby illustrating the benefits for the owner, engineer and contractor in comparison to HDD in permeable soil
conditions.

The Direct Pipe method has been first used in 2007 at the Rhine river crossing in Worms, Germany. Since then,
more than 18 crossings have been installed in Europe and the US with great success. The longest installation so
far had a total length of 4,600ft (1,400m) and a pipeline diameter of 48”. The peak performance during that
installation was 756ft (232m) per day (24hrs).

Since its inception Direct Pipe has been adopted for the installation of over 30 crossings in numerous European
countries and further afield such as America, Canada and Thailand.

To date all attempted installations have been successful.

The largest pipeline currently installed is a 56” steel pipe in Preston, England with a total length of 2,820ft,
serving as casing pipe for a post installed 36” potable water pipeline (HDPE).

The combination of the well established Microtunneling technique with the Pipe Thruster technology makes it
ideal for difficult (permeable) soil conditions which pose a certain risk for frack-outs using the HDD method,
and this paper intends to highlight the benefits from operational, construction programme and risk mitigation
aspects.

KEYWORDS

Pipeline Installation, Geology, Safety, Environment, Innovation

1 INTRODUCTION
In pipe and pipeline construction, safe passageways through sensitive areas are a matter of course and only
rarely a major challenge. But in every project the question is which of the available construction methods is the
most economical and less risky from an engineering point of view.
Apart from characteristics such as the pipeline diameter and drive length, the choice of a suitable method
mainly depends on other project-specific parameters like geological, environmental and other boundary
conditions.
The Direct Pipe method opens up new application options by combining the benefits of the well established
microtunneling technology and the HDD. The key innovation is the Pipe Thruster which grips the pipeline
circumferentially and pushes it into the ground. This means that the pre-fabricated pipeline can be installed in
the ground simultaneously with the excavation process, thus permanently supporting the bore hole.
The Direct Pipe method, which was developed in the scope of a research project sponsored by the German
Federal Ministry of Education and Research (BMBF), was successfully deployed for the first time in 2007 for a
Rhine crossing in Worms. Since then, the individual process components have been continuously improved
and adapted to reflect increasing requirements. Beginning of 2014 36 projects with a total of more than 18
kilometers of laid pipeline have been realized in Europe and the USA. The pipeline diameters vary between 30"
(Outer Diameter: OD=762 mm) and 56" (OD=1,422 mm) with a maximum drive length of 4,600ft (1,400m).
The new established process is characterized by the fact that it is suitable for direct laying of larger diameter
product pipes. In specific project conditions, Direct Pipe offers benefits compared with older established
installation methods, and is thus a useful alternative.
The following pages provide an introduction to the machine technology and design parameters. Based on
reference projects, a differentiation between Direct Pipe and the alternative methods, Horizontal Directional
Drilling (HDD) and Pipe Jacking / Microtunnelling follows.

Figure 1: River crossing using the Direct Pipe method from left to right

2 MAIN COMPONENTS
2.1 DIRECT PIPE MACHINE
The slurry supported Direct Pipe machine works roughly in a similar way like a conventional slurry supported
microtunnelling machine (AVN), but differs in length. To allow for a curved movement of the machine and the
trailing pipeline in the curved path, the machine is equipped with two backup pipes. The fact that all of the
joints in the individual backup pipes are articulated and connected by tension rods, ensures optimum steering
capability of the machine. An additional benefit is that the machine together with the pipeline can be retracted,
in the case it is needed, with the aid of the Pipe Thruster.

AVN-Machine │ Power Pack │ Telesc. Station │ Conical │ Slurry Discharge Pump │Pipeline
│Transition Piece│

Figure 2: Longitudinal section through a Direct Pipe machine (AVN1000XC for a 48” pipeline)

The scope of project planning, includes the machine's cutterhead, which is adjusted to the geological
conditions. In case boulders or rock are anticipated along the route, disc cutters can be deployed in addition to
the cutting knives. Disc cutters crush the rock ahead of the machine until the fragments are small enough to
pass through the cutting wheel openings and enter into the crusher chamber which is also called excavation
chamber.

With the cone crusher inside the crusher chamber a wide geological range can be handled from coarse gravel,
cobbles and boulders to hard rock. The crusher basically uses the same principle as a coffee grinder. Stones are
ground until they pass through the predetermined openings on the inner cone of the excavation chamber, the
last stage where the maximum grain size before entering into the slurry lines is limited. This prevents blockages
in the following slurry lines.

With pipe diameter of 40" (OD=1,016mm) an greater, Direct Pipe machines are equipped with an integrated
Power Pack. The unit generates the hydraulic pressure required to rotate the cutterhead and power the steering
cylinders. It is located in the backup pipe behind the cutterhead and the steering cylinders. The advantage of
generating energy locally in this way is that longer drive lengths can be achieved. However, due to the lack of
space, smaller machines with a pipe diameters of 28"- 38" (OD= 711-965mm) cannot be equipped with a Power
Pack. They need to be driven by hydraulic lines from a power pack on the surface. The hydraulic losses
resulting from a therewith necessary hydraulic supply through pipes and hoses from the control container on
the surface limit the drive length to approx. 1,000ft. (300m).

A telescopic station can be assembled between the backup pipe with the power pack and the conical transition
piece connecting the pipeline with the micromachine. Thereby it is possible to thrust the machine forward
independently from the pipeline, e.g. after a longer period of standstill where frictional forces tend to be higher.
Additionally, there is more control of excavating obstacles such as e.g. boulders or rock formations. In contrast
to the telescopic station deployed in Pipe Jacking with concrete pipes, the telescopic cylinders on the Direct
Pipe machine can act in both directions. If it becomes necessary to withdraw the machine with the pipeline, the
frictional forces between the ground and the machine can be handled by the telescopic cylinders and the friction
between the ground and the pipeline by the Pipe Thruster. This can be useful if the machine is "locked" in the
ground. The telescopic station thus acts as a safety tool which can be deployed under certain conditions.

The transition piece onto which the pipeline is welded has a conical shape. It reduces the larger diameter of the
machine to the smaller pipeline diameter. The conical transition piece contains a backwards facing bentonite
lubritacation ring from which the main volume of bentonite lubricant is pumped into the annulus. The whole
operation is volume controlled in order to make sure that the annulus is not over pressurized. The built in rear
bulkhead seals off the machine from the pipeline and the intrinsic slurry lines.

2.2 PUSH UNIT PIPE THRUSTER


The Pipe Thruster was originally designed as an auxiliary assist tool for the pipe pull-in with the HDD method
(installed on the pipe-side). The Pipe Thruster's applications are as follows:
 Pushing or pulling pipelines into the excavated open bore holes (e.g. created by HDD) or existing
tunnels. This has already been implemented in several projects worldwide. The maximum length of a
pipe pushed in like this is currently at 13,000ft (4,000m).
 Pulling out previously laid steel pipes from the ground. This is also established in the USA and Europe.
 Direct Pipe method for laying pipelines (with coating if needed). Thus far, 35 projects have been
successfully completed. Chapter 4 briefly describes some of them.

Figure 3: The Pipe Thruster HK500PT exhibited at the Hannover Fair in 2006 clamping a 48" steel pipe.

The maximum pipeline diameter that the biggest Pipe Thruster version can clamp is 60" (OD=1,524 mm). The
clamping unit is mainly adapted by changing the clamping inserts to match the pipeline diameter. It was
designed to avoid damaging the coating of the product pipes, such as gas or oil pipelines. In extensive tests at
the Herrenknecht workshop in Germany, it was demonstrated in cooperation with various gas suppliers that no
damage is caused to the coating. PE (polyethylene), PP (polypropylene) and Glasfibre Reinforced Plastic (GRP
on PE) coated pipes were tested at full clamping force of the clamping unit and at full thrust force. The contact
surface between the pipe and the clamping inserts is covered with hot-vulcanized rubber. It is designed to be
large enough to minimize the pressure (3.5 N/mm²) and shear forces (1.2 N/mm²) on the coating.

Table 1: Characteristics of the three different Pipe Thruster models

Pipe Thruster Models HK300PT HK500PT HK750PT


Max. push and pull force (in kN /
3,000 / 300 5,000 / 500 7,500 / 750
tons)
Clamping diameter (in inches = " ) Max. 36 Max. 48 Max. 60
Attack angle ( in °) 0 to 15
Weight (in tons) 40 53 78

3 ACCESSORIES AND SET UP AT CONSTRUCTION SITE


3.1 LAUNCH AND TARGET PITS
By using the Direct Pipe method, the drilling route is typically a curve from the surface of the terrain,
underneath the obstacle (river) to be drilled under, to the opposite surface, like in HDD. The benefit here is the
simplicity of the required launch and target pits. The Pipe Thruster can either be set up and anchored in a
shallow launch pit, or right on the surface.

Figure 4: Force components to be anchored on pushing the pipe with the Pipe Thruster

The machine connected to the pipeline is set up at the required entrance angle in front of the launch seal. The
overbend of the outlaid pipeline is held in place with side booms or roller supports as well as launch tracks
with rollers on the surface. The horizontal and vertical forces to be anchored depend on the entrance angle and
the maximum push or pull force to be applied. The forces can, for example, be held by an anchoring frame and
sheet piling or foundation piles with a depth sufficient for the geology. The following table shows the values
for the resulting forces with a corresponding entrance angle.
Table 2: Vertical and horizontal forces for three Pipe Thruster models - computed for maximum push and pull
force in corresponding entrance angles (figures in kN)

HK 300 PT HK 500 PT HK 750 PT


Launch angle
FV1 FV2 FH FV1 FV2 FH FV1 FV2 FH

0° 986 986 3000 1532 1532 5000 2998 2298 7500

1° 1020 967 3000 1577 1490 4999 2366 2235 7499

5° 1153 891 2989 1751 1315 4981 2627 1973 7471

7° 1217 852 2978 1835 1226 4963 2753 1839 7444

10° 1311 790 2954 1957 1089 4924 2935 1633 7386

12° 1372 748 2934 2035 996 4891 3053 1493 7336

15° 1459 683 2898 2148 854 4830 3222 1280 7244

Similar to Microtunnelling with concrete pipes, penetration of groundwater, soil, slurry or lubricating bentonite
out of the annulus into the launch pit must be prevented by the use of a launch seal. The overcut is sealed with
a neoprene rubber. To be able to compensate for movements in the pipeline, the launch seal for Direct Pipe
comprises of two steel structures which are supported by a U-shaped Neoprene rubber to allow for relative
movement. Guide rollers on the front part of the seal ensure the required clearance between the pipeline coating
and the structure of the seal. To ensure the best possible sealing effect, the launch seal is mounted to the pit wall
at the selected entrance angle. The soil coverage over the launch seal should be at least one or two times the
machine diameter.

Figure 5: Direct Pipe Launch Seal

3.2 OPERATION CONTAINER


All of the process components involved in drilling and lying, such as the machine, the Pipe Thruster, pumps
and navigation systems are remotely controlled from the control container. The important functions and
measured values are visualized for the machine operator on multiple displays located in the control cabin. One
screen displays e.g. the navigation system, another one the pictures from the cameras built inside the machine.
The control container is installed next to the launch pit. The hydraulic power supply to the Pipe Thruster is
provided by a power unit built into the container.
Figure 5: The control container Figure 6: Machine operator's workplace

3.3 NAVIGATION SYSTEM


To allow the machine to drill precisely along the required route, and thus lay the pipeline exactly at the desired
location, a suitable surveying system is needed to locate the machine. The horizontal position is determined by a
fibre-optic gyroscope. The latest generation of gyroscopes measures continuously, thus removing the need for
interruptions, as previously dictated by the mechanical gyroscope. The vertical position is determined by an
electronic hydraulic water level, a simple and proven system. The navigation system is accurate within a few
centimeters (in some cases even only a few millimeters).
Before drilling begins, the coordinates for the route (start and/or end points) are entered in the surveying
software. The machine operator sees a visualization of where the machine is located compared to the target
route during drilling. By extending the three steering cylinders appropriately, the steering head can be
articulated. The machine moves in the desired direction, with the entire pipeline following.

3.4 PREPARATION OF THE PIPELINE


The pipeline is laid out at the predetermined launch angle so that it can be easily moved in the direction of the
launch pit when drilling starts. Depending on local conditions and the launch angle, it is supported either by
rollers or side booms.

Figure 7: Pipeline (48") laid out on roller supports in the direction of the launch pit.

The feed and discharge lines are connected from the machine through the whole pipeline to the separation unit
on the surface. All lines are placed on steel hangers which are equipped with rubber coated rollers for easy
assembly and disassembly. None of the service lines are thereby touching the pipe wall and therefore there is no
risk of damaging the coating from inside. At the end of the pipeline flexible hoses for the slurry and the
bentonite lubrication are laid next to the pipeline and connected to the separation plant which is half way back
to the shaft. The power and data cables are installed on top of the pipe and connected to the control container.
Figure 8 and 9: View into and cross-section of a 48" pipeline with supply lines placed on movable
support structures

4 PROJECT CASE STUDIES


4.1 PROJECTS TO DATE
To date 35 projects have been completed using the Direct Pipe method with a total of approximately 18km of
pipeline installed. Case studies of selected projects are given below.

4.2 PILOT PROJECT 2007 IN WORMS, GERMANY


The development of the Direct Pipe method was supported by the Germany's Federal Ministry of Education and
Research (BMBF). The pilot project was successfully completed in Worms in 2007. A 464 m, (1522 ft) 48" steel
pipe was laid under the river Rhine (48” casing pipe for various lines). The reasons for choosing this method
were the partly difficult geology (sands, gravels, cobbles) on the one hand and the confined space conditions
on the exit side on the other hand. In addition it was impossible to lay out the pipe in a single section on either
bank of the river, thus making HDD extremely difficult.
The crossing was completed in 13 days with only five days of microtunneling. The remaining days were needed
for pipe extension. The limited easement area only allowed for pipe strings of 90m. The fact that the machine
including the pipeline was thrust into the small target pit in Worms with a thrust force of just 80 tons (500to
Pipe Thruster installed) has shown the enormous capabilities of the new system and laid the foundation for
further installations.

4.3 48" GAS PIPELINES IN THE NETHERLANDS


The first gas pipe job in the Netherlands opened the market outside Germany. In the years 2010 and 2011, a
total of six projects were realized. Drive length between 1,200ft and 4,600ft, thereby crossing rivers, rail tracks
and archeological sites were part of the 310miles (500km) North-South route which distributes gas in a 48”
pipeline throughout Holland.
One example is the 1,800ft (540m) crossing below the very deep Hartelkanaal in Rotterdam. It was required to
install the pipeline at a depth of 100ft (30m) below the surface. The limited space available on both sides of the
crossing, resulted in steep launch and exit angles of 10° and 12°. The pipeline was split up into 10 pipe sections
of each 177ft (54m) which have been installed within 2 weeks. The Dutch Society for Trenchless Tunneling
"NSTT" awarded the client and the construction company the No-Dig Prize 2010 for the successful use of the
innovative system.

Another remarkable project was the installation of a 4,600ft (1,400m) 48" gas pipeline on the same pipeline
project. It has been chosen as test to evaluate the capacity of the Direct Pipe system. It is currently the record in
terms of drive length. The pipeline was laid out in three pipe sections of 1,640ft (500m) each. With two pipe
changes, the thrust duration from launch to arrival of the machine at the target was just 16 days. The maximum
advance rate in 24 hours was 760ft (232m).
Figure 13: Advance rates in laying a 4,600ft (1,400m) gas pipeline (48") in sand

The 16 days included setting up a second Pipe Thruster (HK500PT), which was installed after advancing
approx. 3,000ft (900m). The thrust force of 500 tons was insufficient at approx. the 3,000ft mark. After
installing the second Pipe Thruster, the remaining pipe section was pushed into the target pit within just four
days by the two Pipe Thrusters. This is equivalent (with an effective working period of 11 days) with an
average advance rate of around 410ft (125m) per day.

Figure 14: Two HK500PT Pipe Thrusters in line laying a 4,600ft (1,400m) 48" gas pipeline

4.4 42” CASING PIPE INSTALLED IN NEW YORK


In May 2011 Empire Pipeline Inc., a subsidiary of National Fuel Gas Company received approval to build a
natural gas pipeline in Steuben County (N.Y.) and Tioga County (P.A.) with a connection to Empire´s existing
network at the northern end of the project. The new, 15-mile pipeline will bring further supplies of domestic,
clean-burning natural gas from locally produced Marcellus Shale and Trenton-Black River gas wells to
consumers in this region and beyond. This Tioga County Extension Project demanded installation of a new 24-
inch pipeline on a length of 15 miles. One challenging section on this route was the crossing of State Highway
382 and the adjacent river in Corning, N.Y.

On a length of 2,900 feet the pipeline was installed by Michels Directional Crossings Inc. using the HDD
method. To excavate through the initial layer of cobbles and gravels, where HDD is not suited, the construction
company decided to install a 420ft (130m) long 42” casing pipe by the use of the Direct Pipe system. An
AVN800 Direct Pipe machine with a Pipe Thruster HK750PT installed the casing within 5 days, with an entry
angle of 11°.
Figure 16 and 17: Pipe Thruster HK750PT anchored on the surface with deployed machine AVN800A and 42”
pipeline

4.5 AQUASHICOLA AND WETLANDS CROSSING


Laney Directional Drilling out of Houston utilized the Direct Pipe technology in 2013 on the ‘Aquashicola Creek
and Wetlands Crossing’ in Monroe County Pennsylvania. It is a segment of the Williams Northeast Supply Link
project and represents the longest Direct Pipe installation in North America to date, with a total installation
length of 1,358ft (410 m).
One of the primary reasons why Direct Pipe had been chosen over HDD is the minimum frac-out risk of Direct
Pipe. The Aquashicola Creek flows through a valley with steep ridges on either side. An HDD design would
have been significantly longer and most importantly sufficiently deeper than Direct Pipe in order to have
enough safety against hydraulic fractures and inadvertent returns within the permeable soil conditions under the
river bed. The subsurface conditions included rock, shale with layers of gravel and cobbles. Especially the
gravel and cobbles posed an additional challenge for the alternative HDD method. An average of 4ft per hour
had been achieved in the challenging soil conditions. A special launch pipe configuration has been chosen by
the contractor to minimize installation time of the equipment.
The pipeline has been split in 2 sections and could be installed on roller supports. The topography benefited the
stinging of the pipeline close to the surface.

Figure 18 and 19: HK 750PT installed on the launch side in front of the launch pipe – pipe layout section with
service lines.

The project was completed on 21st of June in time and budget and laid the foundation for Laney Directional
Drilling to use the technology on future projects in North America.

4.6 DEBUT IN CANADA FOR THE BEAVER RIVER CROSSING


Sept. 2013 Michels Canada Co. completed the first unground pipeline installation in Canada using the Direct
Pipe method. The project was part of the Inter Pipeline Cold Lake and Polaris Expansion Program and involved
the installation of 1,122 ft (342 m) of a 42-inch pipe across the Beaver River near Bonnyville, Alberta.
Michels Canada is a wholly owned subsidiary of Michels Corporation who has already used the Technology in
the U.S. in previous years.

The Direct Pipe method was selected for the Beaver River project to accommodate geotechnical and routing
challenges as well as the specific environmental and cultural sensitivities associated with this particular
watershed. The project was located in a rural area about 12.4 miles (20km) north east of Bonnyville, Alberta.

Michels decided to use a 750to Pipe Thruster (HK750PT) together with a 42” Direct Pipe machine. The
installation had an entry angle of 4 degrees and an exit angle of 8 degrees. The depth of cover under the Beaver
River bed was 16.4 ft (5 m).

The owner Inter Pipeline Ltd., together with the design engineer Complete Crossings Solutions and Michels
Canada Co. began preliminary design on the oil pipeline crossing almost a year before it started. In early
August, crews and equipment were mobilized and set-up was completed within two weeks of arrival. The entire
project was supported by the mainline pipeline contractor which prepared the entry and exit locations and pipe
sections.

Michels finished the crossing on Labor Day weekend and was off the site mid-September.

Figure 20: Side booms supporting during pipe extension

4.7 56” CASING PIPE FOR WASTEWATER CASING PIPE IN ENGLAND


The Direct Pipe method has been chosen as alternative to an EPBM (2,8m ID) which had been trapped after
only 70m. In order to maintain the same hydraulic capacity a twin tube with each 56” in diameter have been
chosen. Due to the anticipated galcial deposits, the use of the HDD method was assessed to be too difficult and
too risky. The 850m long alignment led through constantly changing layers of clay, sands, gravel and also
cobbles and bolders had to be excavated in the galcial deposits.From a shared launch pit, the two parallel 56"
pipelines (OD=1,422 mm) were laid at a distance of just 3.5 m (11.5ft) . The two pipes acted as a casing for two
waste water lines (DN900) which had been installed later. In contrast to most of the projects realized previously,
whose target pits were near to the surface, the machine had to be recovered from a 15 m deep target shaft. The
navigation system deployed (gyroscope and water leveling system) allowed for precise steering of the machine
up to only a few mm into the seal installed in the reception shaft. Drive progress averaged 20m a day with a
new UK pipe-jacking record of 72m in a single 12 hour shift.
Figure 21: Direct Pipe Equipment set up in the launch pit in front of the launch seal (HK750PT with
AVN1200TB) with 56” pipeline.

5 BENEFITS COMPARED WITH OTHER TRENCHLESS METHODS


The benefits which have been discussed throughout the paper are briefly summarized in the following Figure.

Figure 22: Direct Pipe vs. HDD and Direct Pipe vs. Microtunneling

6 CONCLUSION AND OUTLOOK


The first 35 projects have shown, that Direct Pipe achieves fast pipe installation performance. This makes the
method an alternative to HDD and microtunnelling in terms of both installation safety and economics. The
drives completed so far show the feasibility of increasingly long distances, given the right geology, which are
only restricted by the smaller defined diameters of the product pipes and thus the limited accessibility of the
machine for cutting tool changes. With the records of 4,600ft (1,400m) length of a 48” pipeline and the largest
diameter of 56” installed by Direct Pipe, it was possible to set another milestone in innovative pipeline
construction. Improved installation safety in difficult terrain - compared with HDD – and the economic benefits
compared with standard Microtunnelling, makes the method very competitive. Direct Pipe is at its best when
installing pipe through mixed soil conditions or unconsolidated rock formations non-conducive to HDD, or
when performing installations with minimum cover. Since the equipment is only required on one side of the
crossing, Direct Pipe can be ideal in applications with restricted areas on the exit side.

You might also like