Ismaillia Project ITP - Check List

Uploaded by

KAREEM NADER
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views2 pages

Ismaillia Project ITP - Check List

Uploaded by

KAREEM NADER
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Inspection and Test Plan

Ismaillia Road Lighting

Inspection Code: 1- Madkour(Q.C) 2- 3- 4-

H : Hold Point W: Witness R: Review M: Monitor

Inspection Code
Item Activity Characteristic to be Verified Reference Document Acceptance Criteria/Tolerance Verifying Document Device/tools Freq.
1 2 3 4

1 Submission

Technical Specification & Egyptian Compliance to Egyptian code Approved Document Prior to start
1.1 Approval of shop drawings Document N/A H
code & specifications Submittal work

Approval of method of Technical Specification & Egyptian Signed Masonry MS by PM & Approved Document Prior to start
1.2 Document N/A H
statement code QC and approved Submittal work

Technical Specification & Egyptian Compliance to Project Approved Document Prior to start
1.3 Approval for material Document N/A H
code specifications Submittal work

2 Materials

2.1 Conduits Conduit Sizes Shop Drawing Project Specs MIR Visual Per Plot H

2.2 Cables Cables Structure / Sizing Contract Specifications Project Specs MIR Visual Per Plot H

2.3 High Masts Structure / Dimensions Shop Drawing Project Specs MIR Visual Per Plot H

2.4 Brackets Structure / Dimensions Shop Drawing Project Specs MIR Visual Per Plot H

2.5 Fixtures Structure / Dimensions Shop Drawing Project Specs MIR Visual Per Plot H

2.6 Transformers Structure / Ratings Contract Specifications Project Specs MIR Visual Per Plot H

3 Work Activities

Conduit sizes Shop Drawing Project Specs Visual Per Plot

Conduit upper and bottom


3.1 Conduit Fixation Shop Drawing Project Specs Visual Per Plot
levels

Conduit bending radius Shop Drawing Project Specs Visual Per Plot
IR H

Cable list Shop Drawing / AC Load List Project Specs Visual Per Plot
3.2 Cables Pulling
Cables Structure Contract Specifications Project Specs Visual Per Plot

Structure, Dimensions and


3.3 High Masts Installation Shop Drawing Project Specs IR Visual Every Time H
Over Lap

Cables Phase Sequence Shop Drawing Project Specs Visual Every Time

Shop Drawing / Contract


3.4 Cables Termination Cables and Wires Accessories Project Specs IR Visual Every Time H
Specifications

Wires Tightness Contract Specifications Project Specs Visual Every Time

Transformers location Prior to start


Shop Drawing Document Transmittal Visual
(Coordinates) work
3.5 Transformers Installation IR H
Terminal lugs tightness Contract Specifications Document Transmittal Visual Per Plot

Fixures Structure Shop Drawing Project Specs Visual Every Time


3.6 Fixures Installation IR H

Fixures Wiring Shop Drawing Project Specs Visual Every Time

3.7 High Masts Earthing Earthing Wiring Shop Drawing Project Specs IR Visual Per Plot H

3.8 Kiosiks Earthing Earthing Wiring Shop Drawing Project Specs IR Visual Per Plot H

Inspection Code: 1: 2: 3: 4:

H: HOLD POINT Official notification and next step will not proceed till the satisfactory pass

W: WITNESS Official notification and next step will proceed automatically

R: REVIEW Review of submitted Documents/Report/certificate

M: MONITOR NO Official notification Required and next step will proceed automatically
Ismaillia Road Lighting Project

General Check List

Status
Item Material / Activity Check Points Total Issued Remarks
Ok Not Ok Not Accessible

1.1 Verify conduit sizes are ok

1.2 Conduits / Conduits Installation Verify conduit Structure are ok

1.3 Verify Conduit upper and bottom levels are ok

2.1 Verify cables Structure and sizing are ok

2.2 Verify cables Meggering Test is ok

2.3 Verify cables Pulled as per AC Load list

2.4 Cables / Cable Pulling Verify cables Phase Sequence is ok

2.5 Verify cables and wires Accessories are ok

2.6 Verify wires Tightness is ok

3.1 Verify High Mast Structure and Dimensions are ok

High Masts / High Masts


3.2 Installation Verify High Mast Over Lap is ok

3.3 Verify High Mast Earthing is ok

4.1 Brackets Verify Brackets Structure and Dimensions are ok

5.1 Verify Fixtures Structure is ok

5.2 Fixtures / Fixtures Wiring Verify Fixtures Opreation is ok

5.3 Verify Fixtures Alignment is ok

6.1 Verify Transformer Location is ok

6.2 Transformers / Transformers Verify Tansformer Termination and Tightness are ok


Terminaton

6.3 Verify Tansformer Earthing is ok

Site Engineer
Name Signature Date

QC Engineer

Name Signature Date