Urs Cda
Urs Cda
Document
INS_00000371972 Version: 1.0
Number:
Name Role
1 Revision History
Version Revision Reason / Change Request Number Revised by
1.0 Initial version
TABLE OF CONTENTS
1 REVISION HISTORY............................................................................................................... 1
2 INTRODUCTION ..................................................................................................................... 4
2.1 Purpose ............................................................................................................................ 4
2.2 Scope ............................................................................................................................... 4
2.2 Reference Documents ...................................................................................................... 4
3 OVERVIEW .............................................................................................................................. 5
3.1 Project Overview............................................................................................................... 5
3.2 Operational Overview ....................................................................................................... 7
4 SCOPE OF SUPPLY ............................................................................................................... 8
4.1 Main components/Description........................................................................................... 8
5 REQUIREMENTS.................................................................................................................... 9
5.1 Functionality Requirements .............................................................................................. 9
5.2 Operating Environment ................................................................................................... 13
5.3 Interfaces........................................................................................................................ 13
5.4 Computing Environment ................................................................................................. 13
5.5 System Security.............................................................................................................. 13
5.6 Data Recording and Storage .......................................................................................... 14
5.7 Environmental Health and Safety.................................................................................... 14
5.8 Supplier Support ............................................................................................................. 15
5.9 Documentation ............................................................................................................... 17
6 SYSTEM DESIGN INSTALLATION ...................................................................................... 18
6.1 Sequence of Events for Installation................................................................................. 18
6.2 Critical Pipe Work ........................................................................................................... 19
6.3 Utility Pipe Work ............................................................................................................. 20
7 COMMISSIONING................................................................................................................. 20
7.1 Factory Acceptance Test (FAT) ...................................................................................... 20
7.2 Site Acceptance Test (SAT)............................................................................................ 21
8 TRAINING ............................................................................................................................. 22
9 HEALTH AND SAFETY ........................................................................................................ 22
10 TIME SCHEDULE ................................................................................................................. 22
11 VALIDATION ACTIVITIES .................................................................................................... 22
12 VALIDATION......................................................................................................................... 23
13 FUNCTIONAL DESIGN SPECIFICATION............................................................................. 23
14 DOCUMENTATION ............................................................................................................... 24
14.1 Before Installation Qualification....................................................................................... 24
14.2 After Installation Qualification.......................................................................................... 25
14.3 After Operation Qualification........................................................................................... 25
14.4 Before Delivery for Current Use ...................................................................................... 25
15 CHANGE CONTROL............................................................................................................. 25
16 ABBREVIATION ................................................................................................................... 25
17 APPENDIX SUMMARY ......................................................................................................... 27
APPENDIX 1: CONTROL/ALARM SIGNALS TO BE AVAILABLE ON THE SYSTEM ............. 27
APPENDIX 2: CONSUMERS POSITIONS................................................................................. 28
APPENDIX 3: LOAD PROFILE TABLE ..................................................................................... 31
2.1 Purpose
The purpose of this User Requirements Specification is to define clearly and precisely, what
the user wants the system to do. It defines the functions to be carried out, the data on which
the system will operate, and the operating environment. It also defines any non-functional
requirements, constraints such as time and costs, and what deliverables are to be supplied.
This User Requirement Specification (URS) specifies the design parameters and lays down
the acceptance criteria, which the defined equipment is expected to meet. Any part of the
supply that does not conform to the requirements expressed in this document must be brought
to the attention of GlaxoSmithKline.
2.2 Scope
All compressed air system starting from Compressors & Dryers and Distribution Network.
This document describes user requirements for Compressed air generation and distribution to
users/consumers of the facility. The plant will serve outlets in the rooms within the Production
Plant and Lab areas in accordance with the consumer point of use table. The purpose of this
document is to provide a clear and complete statement of the user requirement for the
Compressed Air system covering the following:
The system shall be designed to generate compressed air complying to below quality-
Pressure dew point- -40deg C, Class 2 (in order to achieve -25 deg C PDP) Oil < 0.01
mg/m3, Class 1.
Particles – Class 3
GQP REQUIREMENTS FOR COMPRESSED GASES AND FORCED AIR SUPPLIES
Products Particles Particles Viable Oil Moisture g/kg of
0.5 5.0 mg/m
m/m3 m/m3 Micro- 3
dry air at
organis atmospheric
ms pressure, (%RH
cfu/m3 at 15 C)
Large volume forced air nmt nmt
(LVFA) 350,000 nmt 2000 nmt 100 0.5*** Controlled as
or compressed gas
supplies
coming into direct appropriate at point
contact
of use
during processing with
secondary product or
final stage
of non-sterile API.
Examples
include fluid bed driers,
tablet
coating machines, filter
cake
driers etc.
Typical value referred to in ISPE Good Practice Guide: Process Gases (2011)
The compressed dry air system shall be design to supply process & instrument air for following
equipment.
Packaging lines
Process equipment
Service outlet plates
Laboratories
Instrument air for utilities
3.2 Operational Overview
The system shall comprise of oil-free (non-lubricated), Air cooled screw type compressors.
Oil free air cooled screw compressors, Non Lubricated Air/water cooled compressor (VFD
based) both working and stand by.
Heat of compression desiccant type drier equipped with pre-final filter, receivers, oil/water
removal sterile air filters on the distribution line. Necessary redundancy for
compressors/dryers/filters is considered in the design.
Suitable oil removal filter to maintain oil content < 0.01 mg/m3 shall be considered along the
main header.
Pressure reducing valve on the header line shall be considered to achieve required
pressure of 7.0 – 8.0 bar g at POU.
Receiver tank will be installed after drier to maintain the compressor header at
required pressures if any bulk usage at any point of production schedule.
Receiver tank with Pressure safety valve, auto drain valve, Pressure gauge and
service door etc.
Flow meter to measure the consumption
The compressed air header shall be designed for 8 barg pressure in order to achieve
8-7barg at POU. Necessary pressure reducing valves near the process equipment
shall be considered.
Interconnecting piping between compressor/dryer/receiver up to oil removal filter &
further up to Production building shall be of SS ASTM 269 dairy tube descaled and
degreased.
Further distribution piping from inside production building shall be in SS304 up to
sterile filter (0.22 um size) at POU outlets.
Post sterile filter till process equipment shall be in SS 316 L ASME BPE 2009 .
The compressed dry air system shall be located in second floor (+ 8.0 m lvl) of production
building which shall house compressors, dryers, filters & receiver.
4 SCOPE OF SUPPLY
This document defines the requirements for Compressed air system, storage and distribution
system for Production and lab areas at the GSK Vemgal site.
This document represents a first stage of validation activities, and is the starting point in
achieving the validation status of any equipment.
Based on this document, validation documents that support the activity will be developed by
the assessment of each specification requirements expressed in user requirements (protocols
for installation qualification, operational qualification and performance qualification).The scope
of the work to be provided by the installer shall include delivery and handover of a complete
system that has undergone client witnessed functional tests and is fully supported by
document dossiers. The installer will be responsible for preparation of an FDS, Equipment
schedules, IQ and OQ documentation to a format agreed by GSK, and execution thereof with
GSK or agent as a witness. GSK will prepare documentation and execute phases relating to
PQ. The installer shall demonstrate the performance of the system to the required quality
standards.
1- Three variable speed compressors provide at least 1322 m3/hr , oil free type
2- Two heated adsorption dryers , each of them with inlet flow not less than 2662 m3/hr,
with pressure dew point -40
3- Compressed air particle filters to remove particles down to 1 Micron and 0.01 Micron
at system flow remove particles down to at system flow
4- Compressed air filters to remove oil aerosol & liquid water down to 0.01 PPM at
system flow
5- Compressed air network pipes St.St 304 L orbital welding to guarantee pressure
looses at end point not more than 0.3 bar , or any other GSK approved pipe type
6- Connecting the compressor and dryers to the nearest electric panel
5 Requirements
Compressed air system requirements are documented in the following tables. The
requirements are rated according to the following categories:
5.1.9 The Command and Control system shall be the central point for E
the starting and stopping of the systems. The design shall allow
the independent operation of the Air compressors and Driers. The
system will be designed such that an individual system can be
safely isolated and maintained without interruption to the other
system.
5.1.10 The whole system must be provided with a central control system E
for the supply and distribution of electrical power to items of
equipment and packaged systems within the plant room. The
system should be designed to control the equipment automatically
with the minimum of operator intervention. Table from Appendix A
outlines the minimum controls and alarms to be available on the
system
5.1.11 The control system construction should be based upon a multi- E
compartment control centre with a dedicated instrument section to
the fascia of which will be mounted operator switches, alarm
indication and monitoring instrumentation.
5.1.12 The control centre must be provided with a main isolator that will E
isolate the whole of the system from a single supply but also
provide separate isolation for the each compressor to allow the
loop distribution system to remain operational.
5.1.13 Visual indication must be provided of the operating status of the E
systems.
5.1 Functionality Requirements
This section defines detailed equipment user requirements. These requirements are provided
below with references as applicable.
5.1.26 The system will be fully welded with the exception of process E
connections which will be hygienic tri-clamp with PTFE faced
seals.
5.1.27 The system must be able to operate in the temperature below 40 E
°C
5.1.28 The HMI screens shall be in English together with parameter E
settings and menus.
5.1.29 All visual indication/labels with be in English. E
5.1.30 All main branded components will selected for quality and easy of E
maintenance serviceability locally where available, a proposed list
will be presented for GSK’s approval.
5.1.31 Electric cables to the nearest panel to connect dryers and E
compressor
5.2 Operating Environment
This section defines any special requirements for the physical environment related to
operation such as temperature, vibration, humidity, physical layout and required utilities such
as compressed air and power supply requirements.
Req. Requirement Essential (E) /
No. Desirable (D) /
GMP Critical
(GMP)
5.2.1 Electricity supply 400 V / 50 Hz for dryers and compressors E
5.2.2 Compressors room should be well ventilated E
5.3 Interfaces
This section defines any requirements for how the system components, e.g. machine, is to be
interfaced with Operator/other equipment.
Req. Requirement Essential (E) /
No. Desirable (D) /
GMP Critical
(GMP)
5.3.1 On line dew point detector should be installed after drying phase E
5.3.2 Pressure sensor on the o outlet of compressed air generation E
system
6.1.1 The detailed design project will be delivered to GSK for acceptance prior to start the
work.
6.1.2 The provider will describe the functions for the project based on the tender package.
6.1.3 The Compressed Air vessel complete with all equipment required for the distribution
loop will be purchased at the same stage. It is expected that the complete loop will be installed
before the water treatment equipment is installed. The Distribution system will be pressure
tested, then connected to the vessel,
6.1.4 The entire installed Generation and Distribution system will undergo IQ/OQ, fully
documented and handed over for PQ
Note: The sequence of installation will be subject to change due to the site execution
schedule. A site programme to be issued.
6.2.2 Pipe work will be installed to ensure adequate support throughout to prevent undue
stress or forces on the pipe work installation. Consideration will by made for thermal
expansion. Ref: ANSI B31.3
6.2.4 Calculation will be made for stresses due to pipe work expansion. Where necessary the
stresses will be relieved by changes in direction.
6.2.5 Particular attention should be made to any external piping that will be subjected to the
local environmental conditions.
6.2.6 The system will be fully welded with the exception of process connections which will be
hygienic tri-clamp with PTFE faced seals.
6.2.7 All hygienic pipe work used in fabrication of the distribution will be Orbital Tig welded.
Where this is impractical, manual welds utilising a pulse welder may be used in consultation
with the GSK.
6.2.8 The distribution system must be pressure tested to 1.5 times working pressure after
completion.
6.2.9 All welded stainless steel pipe work must be cleaned and passivated.
6.2.10 All equipment and pipeline components must be identified with a pre-approved tagging
system.
6.3 Utility Pipe Work
6.3.1 Utility pipe work must be installed to the local site standard
6.3.2 The utility requirement must be sized by the supplier with due consideration to the utility
available at the plant room.
6.3.3 All pipe work must be identified with a pre-approved pipe line marker system
6.3.4 All equipment and pipeline components must be identified with a pre-approved tagging
system.
7 COMMISSIONING
7.1 Factory Acceptance Test (Fat)
7.1.1 The Generation system will be tested at the supplier’s factory for acceptance before it is
released for shipment. This acceptance testing ensures that the equipment is constructed
and finished and works correctly before shipment to site. This is done to minimise any
problems that can occur when the equipment is installed on site and is in both the Supplier
and GSKs’ interest.
7.1.2 The Factory Acceptance Test (FAT) should be carried out to the supplier’s standard and
documentation. This is subject to the approval by GSK, and may be modified to include
supplementary testing that is considered necessary to demonstrate the equipment functions
as specified. The test plan should be similar to the IQ and OQ test plans that the Supplier will
produce for execution.
7.1.3 Typical test and inspection that will be included but will not be limited to: -
Documentation
Mechanical inspection
FAD and Efficiency of Air Compressor
Pressure and Temperature of Air at discharge of compressor
Calibration status of instruments and their control loops
Checking of control panel and external finishes & internal standards
Checks on accessibility operability
Functional tests against simulated probe signals with alert and alarm conditions. The
test protocol will be required as part of the FAT protocol, and must be based upon the
system functional design specification.
Wet run tests to check all aspects of system function where possible.
Pressure hold test to demonstrate system integrity.
7.1.4 Satisfactory performance at the FAT and complete documented resolution of all
action items is a pre-requisite for FAT acceptance and acceptance for packaging and
delivery.
7.2.2 The Site Acceptance Test (SAT) should be carried out to the supplier’s standard and
documentation. This is subject to the approval by GSK, and may be modified to include
supplementary testing that is considered necessary to demonstrate the equipment
functions as specified. The test plan should be similar to the IQ and OQ test plans that the
Supplier will produce for execution.
7.2.3 The site acceptance test will only be considered as complete when the total
functionality of the system has been proved. The system must be seen to operate without
intervention for a GSK approved time interval.
7.2.4 Typical test and inspection that will be included but will not be limited to: -
Documentation and certification.
Mechanical inspection
Materials and Finish Inspection.
Check list on accessibility operability
FAD and Efficiency of Air Compressor
Quality test of air at each POU, which shall include Particle count, Moisture content,
Oil content, Pressure, PDP, Temperature and Air Quantity.
8 TRAINING
A minimum of 1 day training will be required for all GSK staff in the safe operation and
maintenance of the system as part of the handover. Procedures will be demonstrated in real
time and not by simulation.
The training will include but not be limited to Log book and maintenance procedures.
10 TIME SCHEDULE
The Compressed Air Generation and Distribution Systems shall be installed commissioned
and validated in accordance with the approved project validation plan and agreed timetable.
11 VALIDATION ACTIVITIES
11.1 Validation activities will be handled by the equipment supplier according to approved
documentation.
11.2 Qualification includes the following:
Design Qualification (DQ)
Installation Qualification (IQ)
Operation Qualification (OQ)
Performance Qualification (PQ) – this stage is exclusively the responsibility of GSK
Vemgal
11.3 All qualification activities must be completed in the presence of an authorized person
from GSK
11.4 Finalising validation activities that involve supplier responsibilities
11.5 Final report of every stage needs to be handed over to GSK for approval
11.6 Approval of qualification documentation is the responsibility of the Quality department at
GSK Vemgal
11.7 Any deviation from approved specification need to be authorized by GSK Vemgal. This
sort of authorization may only be obtained in written paperwork and signed by both parties
11.8 GSK Vemgal representatives will gain access to equipment installation during the
qualification process. They also are authorized to shut down any operation that is not meeting
the required specifications.
11.9 Payment according to signed contract.
12 VALIDATION
12.1 If the equipment has its own documentation for qualification, this documentation will be
forwarded in order to be approved by GSK Vemgal. In case GSK Vemgal does not consider
the forwarded documentation as valid, GSK Vemgal review documents to improve them.
Implementations will start only after approval of this documentation.
12.2 Full validation (DQ, IQ, OQ and PQ) will be handled according to Vemgal requirements.
Extra details will be offered upon request.
12.4 IQ/OQ/PQ shall be done by suppliers according to GSK Vemgal own protocols.
12.5 The validation plan will be completed by the validation team of GSK Vemgal and it shall
be based upon supplier documentation.
Installation Details
14 DOCUMENTATION
14.1 Before Installation Qualification
Any deviation from this document needs justifying and details shall be put down in
hard copy.
Scheduling activities (with deadlines). Programme of Works.
Standard procedures for equipment qualification:
Fabrication and installation Method Statement and Risk Assessment
Pressure Test Pneumatic
Compliance Certificate.
Qualification report completed before delivery to the Site (FAT). This report must
contain primary data, results, documentation, mechanical work documentation
(welds, joints, quality certificates for materials used for equipment assembly).
Components and accessories list.
Spare parts list estimated for a minimum of 2 years, list that will contain the
recommended spare parts and delivery deadline for each module.
Approved validation report for Design Qualification (DQ).
Approved validation protocol for Installation Qualification (IQ).
14.2 After Installation Qualification
Approved validation report for Installation Qualification phase (IQ).
Operational and checking procedure for the equipment (at least a draft form).
Training report.
15 CHANGE CONTROL
Any change occurred during commissioning must be approved by GSK personnel. Any
deviation from approved specifications must be authorized in hard copy by management
with the approval of the Quality Department, before implementation.
16 ABBREVIATION
The following definitions apply to the corresponding terms within this user requirement
specification:
Abbreviation Term
DQ Design Qualification
GSK GlaxoSmithKline
IQ Installation Qualification
OQ Operational Qualification
PQ Performance Qualification
PROCESS AIR
A Loedige Blender Loedige-Loss-in-Weight-Feeder 0 0.5 0.5 0.00 0.00 1.00 0.0 0.0 -
3 Fette Tableting, Zinetac suite Tablet Press 1 1 18 18 18.00 18.00 1.00 18.0 18.0 6
4 Fette Tableting, Zinetac suite Tablet Press 2 1 18 18 18.00 18.00 1.00 18.0 18.0 6
5 Fette Tableting, Zinetac suite Tablet Press 3 1 18 18 18.00 18.00 1.00 18.0 18.0 6
6 Thomos Flex coating,Zinetac suite Tablet Coater 1 306 306 306.00 306.00 1.00 306.0 306.0 7
8 Thomos Flex coating, Zinetac suite Tablet Coater 1 306 306 306.00 306.00 1.00 306.0 306.0 7
4 Fette Tableting, Zinetac suite Tablet Press 2 1 0.00 0.00 1.00 0.00 0.00 6
5 Fette Tableting, Zinetac suite Tablet Press 3 1 0.00 0.00 1.00 0.00 0.00 6
28 Fette Granulation suite Tablet Press 2 1 0.00 0.00 0.10 0.0 0.0 6
17 GEA Capsule blending Area Hoist 1 10.8 10.8 10.8 10.8 0.10 1.08 1.08 6
10 GEA IBC Wash Room IBC Washer 1 2 20 20 40 40 0.80 32.00 32.00 6
19 GEA blender room IBC Blender 1 25 25 25 25 0.60 15.00 15.00 6
10 GEA IBC washer CIP 2 20 20 40 40 0.00 0.00 0.00 6
11 Alpha Phonix WASH BAY 2 Parts Washer 2 72.4 72.4 144.8 144.8 0.50 72.40 72.40 5-10
IMA Primary packing Blister Machine-Thermo/Cold Former 7 20 39 140.00 273.00 1.00 140.00 273.00 7
IMA Secondary packing Packaging (50 cartons/mc)-Cartoner 7 3 3 21.00 21.00 1.00 21.00 21.00 7
IMA Secondary packing Casepacker (2 outers/min) 7 3 20 21.00 140.00 1.00 21.00 140.00 7
WTP, PW ACTUATED VALVES 40 5.00 5.00 185.00 185.00 0.50 92.50 92.50 6
TOTAL 1333.00 1376.80 1732.00 1991.80 1245.48 1502.58
GRAND TOTAL 2668 2863 3144 3556 2410 2793