S-04 SECTION 1:100: Plan As On Top of Septic Tank
S-04 SECTION 1:100: Plan As On Top of Septic Tank
650
CEILING JOISTS AT
600mm C/C.
200
200
WALL NOTES
ALL WALLS IN THE
2,908
FOUNDATION AND THE
SUPER STRUCTURE
2,100
ARE 225mm THICK
42
FOUNDATION NOTES
OVERSITE CONCRETE OF 1:3:6 MIX
Scale 1:100
900
ON A WELL RAMMED MURRAM.
FOUNDATION DEPTH TO BE
257
DETERMINED ON SITE.
330
12,500
2,428
2,127
E-02 1:100 E-03 1:100
IC
IC
IC
425
8
41
IC
3,774
94
6
3,900
1,097
556 IC
600x450mm
SITE NOTES
1. ALL DIMENSIONS TO BE CHECKED ON SITE , WRITTEN DIMENSIONS TO BE FOLLOWED IN PREFERENCE TO THE SCALED 450x450mm cast Iron cover
DIMENSIONS.
2. ALL WALLS TO BE REINFORCED WITH HOOP IRON AT EERY ALTERNATE COURSE cast Iron cover (56LBWT)
3. ALL REINFORCED CONCRETE WORK IS TO BE IN ACCORDANCE WITH STRUCTURAL ENGINEER'S DETAILS.
4. ALL SANITARY WORK TO BE IN ACCORDANCE WITH M.O.H RULES AND REGULATIONS.
(56LBWT) determined by slope of grad.,fall & length of drain
5. WHERE DRAINS PASSES UNDER THE BUILDING OR DRIVE WAY AREA , PIPE TO BE OF CAST IRON OR ENCASED IN 150mm
PROPOSED
OF CONCRETE.
6. ALL WASTE PIPES AND SOIL PIPES ARE TO BE IN DUCTS AND THE BENDS TO HAVE THE CLEANING EYES ACCESSIBLE 810
FROM OUTSIDE.
7. ALL WINDOWS AND EXTERNAL GLAZED DOORS TO HAVE BURGLAR PROOFINGS TO THE ARCHITECTS DETAILS.
8. ALL DOOR FRAMED TO BE REBATED AND MOULDED AND BE FULL WIDTH OF WALL WITH MOULDED ARCHITRAVES TO
IC
BUILDING
DETAIL. PROVIDE RUBBER STOPS TO ALL DOORS
g/l I.C I.C I.C I.C g/l
150
9.ALL INTERNAL PLASTER TO BE TWO COATS AND FINISHED WITH STEEL FLOAT.
10. ALL MANHOLES WITH IN THE BUILDING AREA, DRIVEWAY AND PARKING TO HAVE HEAVY DUTY AIR TIGHT CIVERS AND
DOUBLE SEALED.
3,920
11. PROVIDE G1 150*100mm WATER PIPES AND 125*100mm RAIN GUTTER WITH BRACKETS.
150
150
12.ALL PAINTING TO BE 3 COATS.
13. SPLASH APRONE OF 500mm ALOND THE PERIMETER OF THEBUILDING.
to soak pit
75
14. SAMPLES OF FIITINGS , MATERIALS etc TO BE PRODUCED AND APPROVED BEFORE COMENCING WORK.
15. ALL WINDOWS HAVE PRECAST CONCRETE SILLS BUILT IN THE WALL.
P
17. TIMBER TRUSSES TO BE PAINTED WITH BURNT OIL TO PROTECT THEM FROM TERMITES.
150
18. THESE ARCHITECTURAL DRAWINGS TO BE READ IN CONJUCTION WITHTHE STRUCTURAL DRAWINGS,ELECTRICAL,
MECHANICAL DRAWINGS, BILLLS OF QUANTITY AND THE TECHNICAL SPECIFICATIONS.
( ANY DISCIPANCY SHALL BE REPORTED IMMEDIATELY TO THEARCHITECT)
810 Working Level
IC
150
100
150mm thick concrete
U
16,000
base 1:3: 6
4,782
450
1,923
15,000
R
MH
218
SEPTIC
TANK
precast r.c base 1:3: 6
E-01 1:100 conc. baffle 150 230 S T 230
865
E-04 1:100 MH
at inlet 150
599
LONGITUDINAL SECTION THROUGH SEPTIC TANK
SOAK
PIT
1,245
7,128
7,174
Paved
Compound No. of U V
P O R S T Diameter Eff. Depth Capacity,L
users
4,726
6 350 350 450 1200 900
E-03
15 495 655 2400 1200 1250 1200 1830 3500 5400
10,204 500
15
15
11,500 NB: Assumed 45.46 litres/person/24hrs & absorption rate of average soil (22.73) per 300
3,000
2,663 3,994 1,997 1,543 run percolation trench lengths subject to site soil formation
Access Road
W1
225
717
1,355
MASTER BEDROOM
1,829
BATHROOM
590
W3
D4 SCALE : 1:100
225
4,267
4,717
W1
D1 01
1,610
1,359
DINNIG
W1
225
E-04
D3
10,429
10,429
966
BEDROOM
DOWN
5
D2
1,500
3,505
2,152
W2
4
3,730
RE 3
W3 01 600 600
225
1
UP
1,265
D2
VENTILATOR SHEDULE
225
1,993
3,128
Remarks
386
W2 Location
5
1,981
LIVING ROOM
DOWN
D1
5R x 160
UP
4G x 330
225
W1
373
1,702 1,997 1,702 750 1,500 802 850 526
21/U/VTD/367/GV