The document outlines multiple amendment slips to the Accident Manual - 2012 for the South Central Railway, detailing changes in procedures for testing points on lines with ART/MRT cranes, accident inquiry protocols, and compensation scales for injuries and fatalities. Key amendments include weekly testing requirements for crane lines, revised inquiry processes for accidents, and updated compensation amounts for various injuries and deaths. All amendments are to be implemented and communicated to the relevant personnel.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
31 views7 pages

Accident Manual AS - 2 To 5

The document outlines multiple amendment slips to the Accident Manual - 2012 for the South Central Railway, detailing changes in procedures for testing points on lines with ART/MRT cranes, accident inquiry protocols, and compensation scales for injuries and fatalities. Key amendments include weekly testing requirements for crane lines, revised inquiry processes for accidents, and updated compensation amounts for various injuries and deaths. All amendments are to be implemented and communicated to the relevant personnel.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

SOUTH CENTRAL RAILWAY

Headquarters office,
Transportation Branch,
Rules section,
Secunderabad.

No.T.157/ASNo2-AM/Vol.I Date: 09.03.2015

DRMs/SC, BZA, GTL, HYB, GNT & NED

Sub:- Amendment Slip No.2 to Accident Manual – 2012 – Testing of points of


the lines on which ART/MRT/140 T crane stabled and change in
***

The following amendments to Accident manual – 2012 have been given for
implementation proforma
of track measurements.

Ref: i) CSO/SC Lr. No.157/ART & MRT/Vol.III dtd. 02.12.2014


ii) CSO/SC Lr. No. 157 G&SR,AM,BWM/Vol.III dtd. 21.01.2015
.
Item No.1: Add the following as 603.2 (f) below para No.603.2 (e)

(f) For dispatching ART in time, the points of the line on which ART/140T crane
stabled are to be tested once in a week and the results to be noted in the station
diary of the concerned station. Any malfunctioning to be got rectified by
concerned maintenance staff. SS of the station is responsible for ensuring
regular testing as above.

Item No.2: Add the following as 605.3 (v) below para No.605. (iv)

(v) The points of the line on which MRT stabled are to be tested once in a week and
the results to be noted in the station diary of the concerned station. Any
malfunctioning to be got rectified by concerned maintenance staff. SS of the station
is responsible for ensuring regular testing as above.

Item No.3: Replace the proforma under 504.2 – Track measurements with the
following proforma.

Proforma after amendment

504.2 Track Measurements

STN No. Distance apart Gauge slack Cross level Marks on Grinding or
in metres or tight in (mm) Under no sleeper or rail rubbing marks
exact mm load condition top on rails
1 2 3 4 5 6

Cont...2
(2)

Versine in mm
Examination of Sub- On 20 M. or 10 M. On 10 M. or such Remarks Longitudinal
alignment for sidence of chord depending shorter Chords as regarding length level to be
perceptible kinds track on practice considered of transition, recorded in the
of track distortion prevalent on the necessary for degree of curve case of M.G.
in the vicinity of Railway for flat sharp curves (less and specified and N.G. in
the point of curves more than than 600 M. super elevation case of sags
derailment. 600 M. radius. radius on B.G. general and curves.
and M.G. alignment etc.
7 8 9 10 11 12

To be jointly signed by
Supervisor (P.Way) Supervisor (Traffic) Supervisor (C&W)

All concerned may please be notified.

Sd/-
Chief Operations Manager
SOUTH CENTRAL RAILWAY

मुख्य प्रबन्धक कायााऱय/Headquarters Office


ऩररचऱन विभाग/Transportation Branch
सिककिं द्राबाद/Secunderabad.

ििंख्य./No. टी.T. 157/AM/AS/03 ददनािंक/Date: 28.10.2017.

DRMs/SC, BZA, GTL, HYB, GNT & NED

विषय/Sub: Amendment Slip no.03 to Accident Manual - 2012


***
The following amendments to Accident Manual have been given for implementation.

Item no. 1: Sub-rule i) of (a) of Rule no. 906 in Chapter IX (at page no. 103) is
amended as follows:

In case of Commissioner of Railway Safety or Chief Commissioner of Railway


Safety is not in a position to into serious accident cases involving coaching train,
notified to him under section 113 of Railway Act, the inquiry shall be carried out by
a Committee of SA Grade Officers and CSO of the Railway shall be convenor of
such Committee. The General Manager of the Zonal Railway will be the
accepting authority of the Accident Inquiry Report of the Committee.

Item no. 2: Sub-rule (b) of Rule no. 906 in Chapter IX (at page no. 103) is
amended as follows:

All other consequential train accidents shall be inquired by Dy. CSOs from Safety
Department to be nominated by GM, with the GM as accepting authority. The
Inquiry Officer can co-opt any other officer as necessary. The investigating team
would be assisted by the Divisional Officers.

Item no. 3: Sub-rule (c) of Rule no. 906 of Chapter IX (at page no. 103) is
amended as follows:

All other accidents shall be inquired into by a Committee of Senior Scale or Junior
Scale Officers as decided by respective DRMs with DRM as the accepting
authority.

Item no. 4: Sub-rule (g) of Rule no. 906 of Chapter IX (at page no. 103) is
amended as follows:
In accident cases where the Inquiry Committee determines the responsibility on
the staff of Foreign Railway, the Inquiry Report should be put upto Principal Head
of the concerned department of the Railway on which the accident took place
through CSO after which such enquiry report shall be accepted by the AGM
(instead of DRM). Finalisation of Inter Railway DAR cases arising out of such
inquiry report be followed up by the Principal Head of the Department of the
concerned department of the Railway on which on which the accident took place.
If suitable response is not received from the respondent Railway at General
Manager’s level, then the case should be referred to Railway Board.
Contd….2.

-2-

Item no. 5: Sub-rule (i) of Rule no. 906 of Chapter IX (at page no. 103) is
amended as follows:

All inquiries will be ordered by the concerned DRM except for inquiries falling
under items (a) & (b).

Please note and notify all concerned.

Sd/-
प्रमुख मुख्य यतायात प्रबन्धक/
Principal Chief Operations Manager
SOUTH CENTRAL RAILWAY

प्रधान कायााऱय/Headquarters Office,


ऩररिाहन शाखा/Transportation Branch
सिककिं द्राबाद/Secunderabad.
ििंख्य./No. टी.T. 157/AM/AS/04 ददनािंक/Date: 05.02.2018.

DRMs/SC, BZA, GTL, HYB, GNT & NED

विषय/Sub: Amendment Slip no.04 to Accident Manual – 2012 of SCR


***

Rule no.803.1 of Chapter VIII “Scale of Compensation” (in page no. 95) is
AS No.04 dtd
05.02.2018

amended as follows:

803.1 Scale of compensation: The amount of compensation in case of death and


permanent disability is 8.00 lakhs. In case of Injuries, the minimum amount is
64, 000/- and the maximum is 7.20 lakhs.

The following should be cut and pasted in the Assurance Register by SMs for
information and acknowledgement by the Operating Staff.

Rule
Existing Rule Amended Rule
No.
AS No.04 dtd

803.1 803.1 Scale of compensation: 803.1 Scale of compensation:


05.02.2018

(at The amount of compensation in The amount of compensation in


page case of death and permanent case of death and permanent
no.95) disability is 4.00 lakhs. In case disability is 8.00 lakhs. In case
of Injuries, the minimum amount is of Injuries, the minimum amount is
32, 000/- and the maximum is 64, 000/- and the maximum is
3.60 lakhs. 7.20 lakhs.

Please note and notify to all concerned.

Sd/-
प्रमुख मुख्य ऩररचाऱन प्रबंधक/
Principal Chief Operations Manager
SOUTH CENTRAL RAILWAY

प्रधान कायााऱय/Headquarters Office,


ऩररिाहन शाखा/Transportation Branch
सिककिं द्राबाद/Secunderabad.
ििंख्य./No. टी.T. 157/AM/AS/05 ददनािंक/Date: 05.02.2018.

DRMs/SC, BZA, GTL, HYB, GNT & NED

विषय/Sub: Amendment Slip no.05 to Accident Manual – 2012 of SCR


***

Rule 803.3 of Chapter VIII - The Amount of Compensations in “Compensation


payable for Death and Injuries-Amount of Compensation” in “The Gazette of
India: Extraordinary Schedule of Chapter VIII (page nos. 97&98) are amended
as following:

THE GAZETTE OF INDIA: SCHEDULE


(See Rule-3)
Amount of Compensation Payable in respect of Death and Injuries
S. Amount
Death/Nature of Injury
No. (in rupees)
PART - I
1. Death. 8, 00, 000/-
AS No.05 dated 05.02.2018 (Rule no. 803.3)

PART - II
1. For loss of both hands or amputation at higher sites. 8, 00, 000/-
2. For loss of hand and a foot. 8, 00, 000/-
3. For double amputation through leg or thigh or amputation 8, 00, 000/-
through leg or thigh on one side and loss of other foot.
4. For loss of sight to such an extent as to render the claimant 8, 00, 000/-
unable to perform any work for which eye sight is essential.
5. For very severe facial disfigurement. 8, 00, 000/-
6. For absolute deafness. 8, 00, 000/-
PART – III
1. For amputation through shoulder joint. 7, 20, 000/-
2. For amputation below shoulder with stump less than 8” from 6, 40, 000/-
tip of acromion.
3. For amputation from 8” from tip of acromion to less than 4 5, 60, 000/-
½” below tip of olecranon.
4. For loss of a hand or the thumb and four fingers of one hand 4, 80, 000/-
or amputation from 4½” below space tip of olecranon.
5. For loss of thumb. 2, 40, 000/-
6. For loss of thumb and its metacarpal bone. 3, 20, 000/-
7. For loss of four fingers of one hand. 4, 00,000/-
8. For loss of three fingers of one hand. 2, 40,000/-

Contd.....2.
-2-

S. Amount
Death/Nature of Injury
No. (in rupees)
PART – III (contd.)
9. For loss of two fingers of one hand. 1, 60, 000/-
10. For loss of terminal phalanx of thumb 1, 60, 000/-
11. For amputation of both feet resulting in end bearing Stump. 7, 20, 000/-
12. For amputation through both feet proximal to the metatarso- 6, 40, 000/-
phalangeal joint.
13. For loss of all toes of both feet through the 2 metatarso- 3, 20, 000/-
phalangeal joint.
14. For loss of all toes of both feet proximal to the proximal inter- 2, 40, 000/-
phalangeal joint.
15. For loss of all toes of both feet distal to the proximal inter- 1, 60, 000/-
AS No.05 dated 05.02.2018 (Rule no. 803.3)

phalangeal joint.
16. For amputation at hip. 7, 20, 000/-
17. For amputation below hip with stump not exceeding 5” in 6, 40, 000/-
length measured from tip of great trenchanter but not beyond
middle thigh.
18. For amputation below hip with stump exceeding 5” in length 5, 60, 000/-
measured from tip to great trenchanter but not beyond
middle thigh.
19. For amputation below middle thigh to 3 ½” below Knee 4, 80, 000/-
20. For amputation below knee with stump exceeding 3 ½” but 4, 00 ,000/-
not exceeding 5”.
21. Fracture of spine with paraplegia. 4, 00, 000/-
22. For Amputation below knee with stump with exceeding 5”. 3, 20, 000/-
23. For loss of one eye without complications the other being 3, 20, 000/-
normal.
24. For amputation of one foot resulting in end bearing. 2, 40, 000/-
25. For amputation through one foot proximal to the metatarso- 2, 40, 000/-
phalangeal joint.
26. Fracture of spine without paraplegia. 2, 40, 000/-
27. For loss of vision of one eye without complications of 2, 40, 000/-
disfigurement of eyeball the other being normal.
28. For loss of all toes of one foot through metatarso-phalangeal 1, 60, 000/-
joint.
29. Fracture of hip joint. 1, 60, 000/-
30. Fracture of major bone femur tibia both limbs. 1, 60, 000/-
31. Fracture of major bone humerus radius both limbs. 1, 20, 000/-
32. Fracture of Pelvis not involving joint. 80, 000/-
33. Fracture of major bone femur tibia one limb. 80, 000/-
34. Fracture of major bone humerus radius ulna one Limb. 64, 000/-

The existing and amended rule is enclosed as Annexure and the same should be
pasted in the Assurance Register by SMs for information and acknowledgement by
the Operating staff.

Please note and notify to all concerned.


Sd/-
प्रमख
ु मख्
ु य ऩररचाऱन प्रबंधक/
Principal Chief Operations Manager