Module 5
Downloaded from Ktunotes.in
• Electrical installations of high-rise buildings: Distribution systems – rising main,
 cable system - Installation of lifts, standby generators, fire pumps - electric schematic
 drawing.
• Selection of standby Diesel Generator set (DG set) –power rating - Continuous, Prime
 and Standby power ratings- installation and essential protections-Introduction to
 Automatic Mains failure (AMF) systems.
• Energy Conservation Techniques in electrical power distribution - Automatic Power
 Factor Correction (APFC) panel – Principle of operation and advantages.
• Introduction to Solar PV Systems, off-grid and on-grid systems, Solar panel
 efficiencies design of a PV system for domestic application-Selection of battery for
 off-grid domestic systems.
                                  Downloaded from Ktunotes.in
Advantages of APFC
• Consistently high power factor under fluctuating loads.
• Eliminate power factor penalty
• Lower energy consumption by reducing losses
• Continuously sense and monitor load
• Automatically switch on/off relevant capacitor steps for consistent power supply
                                   Downloaded from Ktunotes.in
HIGH RISE BUILDINGS
  • Special features applicable for high-rise apartment buildings
   High rise residential apartments are those buildings having a height above
    ground level of more than 15 m.
   Lift machine rooms or the water tanks will not be taken into account in
    fixing the height of the building.
   These buildings come under the section 54 of the Electricity Act
    2003 and rule 50(A) of the Indian Electricity Rules 1956.
   The electric power supply arrangement in the high rise apartment
    buildings are normally provided through a transformer sub station
    which receives power at 11kV on the high voltage side.
                                Downloaded from Ktunotes.in
• S U B STATIONS
 Normally, out door type transformer sub stations are                   not
    permitted at the premises of high rise apartments.
 However, out door transformers with cable end boxes on both HT
    and MV sides can be permitted with special emphasis on safety
    measures.
 Only dry type transformers will be permitted to be installed in
    the basement floor or above the ground floors.
 If the total connected load of the apartment is 50 kVA                 and
    above, separate transformer shall be installed by the promoter /
    owner at his cost.
 If the common and essential loads exceed 100 kVA, it is advisable to
    install a separate transformer for this purpose by the promoter / owner.
                            Downloaded from Ktunotes.in
   Fire pump capacity is not to be included in assessing the total connected load.
    For    calculating   the connected load, a minimum of 1.2 kW for single phase
    connection     and    5   kW   for   three     phase connection shall be used if exact
    information is not available. Otherwise, a uniform rate of 50 W/m2 shall be used
    for working out the total connected load.
   A diversity factor not exceeding 2 is included in deciding the maximum demand
    for the apartment.
   Emergency supply disconnection facility using push button shall be provided at a
    conspicuous place in the ground floor, preferably at a height of 2.75m from the
    floor level.
                                    Downloaded from Ktunotes.in
• P RIMARY AND S E C ON D A RY PROTECTION
   If there is only one transformer, an H T load break switch fuse unit or a
    vacuum circuit breaker may be used as the primary controlling unit.
   H T load break switch is adequate for capacities below 1000 kVA.                   For higher
    ratings, vacuum circuit breakers are to be used.
   If there are more than one transformer in the same premise, the H T switch
    board shall have an H T load break isolator of adequate capacity on the incomer
    side   as   a   group   controller   and    HT S F U         or   VCB   as   out    going   for
    controlling individual transformers.
   The H T metering arrangement shall be arranged on the primary control unit.
   Only tamper proof digital TO D              (Time of Day) meters shall be provided for
    metering the energy consumption.
                                   Downloaded from Ktunotes.in
   The metering current transformer shall be of single ratio; single core type and no
    extra tapping points are permitted on this CT.
   Tappings        from       the     metering         Potential Transformer    (PT)    can   be
    permitted through separate fuses for connection to the indicating lamps, volt meters,
    power factor meter and watt hour meter.
   A circuit breaker of adequate capacity shall be provided              on    the     secondary
    side   of    the transformer.
   Oil filled circuit breakers or oil filled switch fuse units shall not to be used in high rise
    buildings.
   Low set earth fault protection using neutral CT need not be insisted for transformers
    feeding high rise buildings where, Low tension metering is provided for individual
    consumers.
   How ever E L C B (Earth leakage circuit breakers) shall be provided on all consumer
    distribution boards and other motor loads excepting the fire pump motors.
                                     Downloaded from Ktunotes.in
M E T E R I N G PA N E L
   For high rise apartment buildings, the metering panel shall be located at the ground
    floor level.
   The maximum number of outlets from a metering panel will be limited to eight
    in the case of three phase supply and twelve in the case of single phase system.
   The energy meters for the individual consumers are to be provided by the promoter of
    the building and these meters have to be certified by the competent authority before being
    installed in the metering panel.
   Fuse/ M C B     protection shall be provided for every energy meter. Locking and
    sealing facility shall also be provided on all metering panels, main switch boards,
    HT switch board etc to prevent theft of energy or to prevent crime.
   Unmetered spare outlets are not permitted in MSB, SSB’s and in the metering panels.
                                       Downloaded from Ktunotes.in
• CABLING
   Cables from the metering panel to various floors shall be routed through cable ducts only.
   There shall be access to these cable ducts from all floors.
   Fire barriers shall be provided in the cable ducts at all floor levels inside the ducts.
    This is to prevent the spread of fire to upper floors in the event of a fire breaking out in
    a lower floor.
   The grid power cables and the generator cables shall be segregated inside the duct.
   Other service cables like telephone, net work, C C T V cable etc shall not be provided in
    the cable ducts for power.
   Aluminium armoured cables are preferred up to the distribution               boards    of      the
    individual consumers. Beyond the distribution board copper wires are preferred
    for reasons of convenience and reliability.
                                      Downloaded from Ktunotes.in
• D ISTRIBUTION        BOARDS
   Factory assembled distribution boards with IP42 protection (Double door) is
    the best choice for apartments.
   The incomer device for these distribution boards shall       be      an     RCBO      or
    E L C B + M C B (30 mA sensitivity) of appropriate rating depending on the
    connected load.
   The out going MC Bs shall be of B-characteristics for        light        and   resistive
    loads   and   of    C- characteristics for highly inductive loads.
   The maximum         number of ways permitted for three phase distribution
    board is only 8.
                                   Downloaded from Ktunotes.in
• EMERGENCY         P O W E R S U P P LY
   A stand by generator of adequate capacity is to be provided for every apartment building to meet the
    emergency needs and essential loads in case of a power failure.
   The capacity of the generator shall be a minimum of 20 % of the connected load of the apartment.
   When     generator    supply    is     extended   to   individual consumers, it shall be carried out
    through a separate emergency distribution board.
   The generators shall conform to the requirements of the Pollution Control Board and shall be
    housed in an acoustic enclosure to limit the sound level below 70 dB.
   The exhaust pipe of the diesel generator set shall also be extended to the top of the building.
   If the generator is to be installed on any floor above the ground level, structural fitness of the building
    will have to be ascertained to check whether the building will be able to carry the static and
    vibratory loading of the generator.
   A separate room shall be provided with proper oil drainage facility. An emergency engine stopping
    arrangement also is to be provided out side the generator room.
                                               Downloaded from Ktunotes.in
   All    electrical    rooms     accommodating             the transformer, switch boards,
    metering panels, generator etc shall be located with easy access and proper
    ventilation.
   Adequate clearances are also to be guaranteed for easy maintenance work.
   The details of electrical installations of a High rise apartment building with
    twelve floors (G+11) which includes forty residential apartments and three
    penthouses     are   shown     below.     The ground floor is set apart for common
    facilities and each upper floor has four flats up to tenth floor and the eleventh
    floor has three pent houses.
                                    Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
   The details of the common service panel are shown in figure .
   This panel caters to the lighting requirements of common areas like entrance
    lobby, stair ways, car parks, equipment rooms, external lights etc.
   Supply to the lifts, domestic pumps, fire pumps and other building services
    are also provided from this panel.
   The total energy consumption from this panel is separately metered and the
    total cost is shared by the owners of the residential flats as part of the monthly
    maintenance charges .
                                 Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
                   Emergency and standby generation
• Intended to provide an alternate source of power if the normal source of power
  fails
• Classified as follows
    – Emergency power systems
    – Standby power systems
                             Downloaded from Ktunotes.in
• Emergency power system: An independent reserve source of electric energy that, upon
 failure or outage of the normal source, automatically provides reliable electric power
 within specified time to critical devices and equipment whose failure to operate
 satisfactorily affect the health and safety of personnel or result in damage to property.
• Standby power system: An independent reserve source of energy that, upon failure or
 outage of the normal source provides electrical power of acceptable quality so that the
 user’s facilities may continue in satisfactory operation.
                                  Downloaded from Ktunotes.in
                             General considerations
• Engine driven AC generator sets are used for industrial and commercial buildings as
 a source of power.
• Main prime movers used in engine driven type generators are diesel engines, gas
 turbines and steam turbines.
• Gas turbine generators are lighter in weight than diesel engine sets, run more quietly
 and require less cooling and combustion air leading to lower installation costs
                                 Downloaded from Ktunotes.in
• Gas turbine generator sets are more expensive than diesel engine generator sets,
 require more starting time
• Another factor is fuel supply,If fuel is stored in tanks, it should be stored away
 from the generators
                                Downloaded from Ktunotes.in
Ratings of standby generator sets
• When selecting the right generator for any application, one key place to
 start is with the generator’s ratings.
• Ratings will provide insight into how much power the generator is
 capable of producing.
• They also define how and what types of applications it can be used for.
• These ratings helps to buy a generator capable of providing proper
 coverage for the needs within the constraints of budget and efficiency.
• There are three basic rating types – prime, continuous, and standby.
                            Downloaded from Ktunotes.in
Prime Generator
• A prime generator is one that serves as the primary source of power for the
  operation.
• It is designed to work long term.
• The prime generator is designed to offer a variable power load that is drawn over
  time.
• The most common use for a prime generator is for establishing a location that is
  away from other sources of power, such as a remote building site or hard-to-access
  area.
• They are used for power lighting, sound systems, and facilities at various events
  and locations that may frequently change, such as for staging or ceremonies.
                                 Downloaded from Ktunotes.in
Continuous Generator
• A continuous generator is one that is used much like the primary power source.
• It is generally designed to work on a consistent basis as the primary source of
 power for the facility or function.
• The difference between a continuous and a prime generator is that the continuous
 form does not offer a variable amount of power. Instead, it is designed to provide a
 steady power load over the entire time frame it is used.
• They are often used in mining, military, and agriculture.
                                  Downloaded from Ktunotes.in
Standby Generators
• A standby generator is a backup generator, one used for emergency use
 only.
• It generally has the ability to run for a short amount of time as the main
 power supply.
• It is meant to run just long enough to get the other prime power back
 online.
• Standby generators can be usable in many situations, including residential,
 commercial, and industrial areas. The amount of time they can run varies
 significantly.
                              Downloaded from Ktunotes.in
                 Arrangement of standby generating system
• Normal operating conditions- load
  supplied from utility supply
• Upon loss of this supply Q3 is tripped,
  the generator set is started and load is
  supplied by the standby generator set by
  closing the CB Q2
• Critical loads are supplied from UPS
• UPS is equipped with static switch
  which will bypass the rectifier/inverter
  module in case of an internal fault in the
  UPS and ensure continuous supply of
  electric power to the critical loads
                                 Downloaded from Ktunotes.in
Emergency/standby power supply arrangement
                   Downloaded from Ktunotes.in
              Installation requirements of standby generators
• Minimum 1m clearance shall be provided on three sides of the generator set, minimum
  2m clearance shall be provided between them.
• Fuel tank of DG sets shall be installed outside the generator room.
• Exhaust pipe of DG sets shall maintain a minimum height of 1.8m clearance from the
  floor level
• Voltmeters and frequency meters shall be connected before the circuit breaker in the
  generator control panel.
• Watt hour meter and ammeters in each phase shall be provided.
• For generators of 500kVA and above, kVA/kW meter and pf meter shall also be
  provided
• Changeover switches of approved makes is permitted for capacities up to and including
  800A .
                                 Downloaded from Ktunotes.in
• Provide thermal O/L relay in the generator circuit.
• Generator room shall be made of non inflammable materials.
• Standard size of earthing cables and conductors for generators shall be provided.
• Proper protection schemes should also be provided for generators.
                                Downloaded from Ktunotes.in
Automatic Mains Failure(AMF)
• Automatic mains failure (AMF) panels – also referred to as automatic transfer switch
 (ATS) panels – make the power, switch to emergency standby generators in the event
 of a significant loss of mains power or total blackout.
• There are three main types of AMF units
Using Microcontroller in the unit itself
Using PLC (Programmable Logic Control) for control action
With the help of Relay Mechanism
 A relay based system is described for control action. Elements which are used are
 voltage monitoring relay/phase failure detector (PFD), Overload Relay and Air Circuit
 Breaker.                         Downloaded from Ktunotes.in
• The system continuously monitors the voltage level from the mains.
• If the voltage is dropped below the allowed level, this system will switch the Load
 to Generator (auxiliary supply) and switch back to the mains when the voltage is
 back to nominal required normal level.
• Continuity of supply to load is achieved with the help of AMF unit.
                                 Downloaded from Ktunotes.in
Block diagram of AMF
                       Downloaded from Ktunotes.in
• Power from mains supply is continuously monitored by PFD with the help of relay unit.
• It gives signal to the ACB for its operation / protection.
• When fault occurs in the mains supply PFD detects the fault and disconnect the mains
  supply form the load side by tripping the ACB.
• Generator will start automatically
• When generator runs at rated RPM & frequency then the ACB will operate & supply is
  given to the load form the generator.
• Phase Failure Detector: It is an electro mechanical device used in power system
  engineering to protect a load from damage due to failure in any of the phases supplying
  power to the load. It automatically cuts off the load from supply if one of the individual
  phase becomes faulty. It automatically cuts off the load from supply.
                                   Downloaded from Ktunotes.in
• Phase Failure Detector will operate in following conditions;
i) Unbalanced Voltage
ii) Single Phase or Phase loss
iii) Overload Condition
iv) Power Outage
v) Phase Reversal
• It monitor both Generator as well as Mains side parameter. Any above mentioned
 condition will cause PFD to operate & give signal to ACB as well as control signal
 is generated .
                                 Downloaded from Ktunotes.in
Energy conservation techniques in lighting
• Electric lighting is a major energy consumer.
• Enormous energy savings are possible using energy efficient equipment, effective
 controls, and careful design
• Electric lighting design also affects visual performance and visual comfort by
 maintaining adequate and appropriate illumination while controlling reflection and
 glare.
                                Downloaded from Ktunotes.in
                            Techniques implemented
• Installation of CFL in place of incandescent lamps.
   –   CFLs use about 2/3 less energy than standard incandescent bulbs, give the same
       amount of light, and can last 6 to 10 times longer
• Installation of energy-efficient fluorescent lamps in place of “conventional”
 fluorescent lamps
   –   There are a few styles worth noting; these models are simply labeled as “T-12”, “T-
       8”, or “T-5”
   –   The names come from the size of their diameter per eighth inch. For example, a T-12
       lamp is 12/8 inch in diameter (or 1 1/2 inch); a T-8 lamp is 8/8 inch in diameter (or 1
       inch); a T-5 lamp is 5/8 inch in diameter.
                                     Downloaded from Ktunotes.in
• The recommended style of fluorescent lighting is a T-8
• T-8 lights are the most cost effective
• More efficient than standard T-12 fluorescent lamps, which have poor color
 rendition and cause eye strain
• T-8 lamps provide more illumination, better color, and don't flicker
• T-5 lamps are the most energy efficient and also tend to transmit the best color;
 however, they are expensive.
                                Downloaded from Ktunotes.in
Installation of occupancy/motion sensors to turn lights on and off where
appropriate
• Lighting can be controlled by occupancy sensors to allow operation whenever
 someone is within the area being scanned.
• When motion can no longer be detected, the lights shut off.
                                  Downloaded from Ktunotes.in
Use an automated device, such as a key tag system, to regulate the electric
power in a room
• The key tag system uses a master switch at the entrance of each guest room,
 requiring the use of a room key-card to activate them
• Using this technique, only occupied rooms consume energy because most
 electrical appliances are switched off when the keycard is removed (when the
 guest leaves the room)
• Along with lighting, the heating, air-conditioning, radio and television may also be
 connected to the master switch
                                Downloaded from Ktunotes.in
Replace all exit signs with light emitting diode (LED) exit signs
• Multiple LEDs, properly configured, produce equivalent lighting and consume
 95% less electricity than incandescent bulbs and 75% less than energy-efficient
 compact fluorescent lamps
• 20 year life cycle and eliminates maintenance
• LED exit signs are the expensive, but are also the most efficient exit signs
 available.
                               Downloaded from Ktunotes.in
Use high efficiency exterior lighting
• Include mercury vapor, metal halide and high pressure sodium
• HID lighting is mostly utilized in floodlight, canopy, area fixtures outdoors etc
• The best type for any application depends on the area being lighted and mounting
 options.
Add lighting controls such as photo sensors or time clocks
• Photo sensor controls monitor daylight conditions and allow fixtures to operate
  only when needed
• Photo sensors detect the quantity of light and send a signal to a main controller to
  adjust the lighting
• Time controls save energy by reducing lighting time of use through
  preprogrammed scheduling.
                                 Downloaded from Ktunotes.in
Star certification
• Earning the ENERGY STAR certification means the product meets strict
  energy efficiency guidelines set by the US Environmental Protection Agency
• Lighting products that have earned the ENERGY STAR label deliver
  exceptional features, while using less energy.
• Saving energy helps you save money on utility bills and protects the
  environment by reducing greenhouse gas emissions.
ENERGY STAR Certified Light Bulbs:
• Use about 70-90% less energy than traditional incandescent bulbs
• Last at least 15 times longer and saves electricity costs over its lifetime
• Meet strict quality and efficiency standards that are tested by accredited labs
  and certified by a third party.
• Produce about 70-90% less heat, so it’s safer to operate and can cut energy
  costs associated with home cooling.
                             Downloaded from Ktunotes.in
• ENERGY STAR certified ceiling fan/light combination units:
   – Are 40% more efficient than conventional fan/light units
   – Use improved motors and blade designs
   – Provide quality, cutting edge design, and the latest in efficient technology.
                                  Downloaded from Ktunotes.in
                       Energy conservation in power
• ENERGY STAR certified room air conditioners come with better materials
• Offer additional convenience, comfort and energy-savings, including the ability to:
   – turn off the unit remotely using your phone or computer;
   – schedule changes to temperature settings based on your needs
   – receive feedback on the energy use of the product
   – use 10 percent less energy and saves electricity cost.
   • An ENERGY STAR certified solar water heating system can cut your
     annual hot water costs in half
   Life expectancy of certified solar water heating systems is 20 years
                                Downloaded from Ktunotes.in
                       Energy conservation in motors
• Motors and drives constitute two third of the energy consumed by manufacturing
  industry.
• The efficiency of conversion of this electrical energy , is of the order of 85%
• There are three important losses in motor, the largest being the resistive loss of
  windings(I2R loss)
• The next loss is that of magnetic circuit(known as iron loss) which varies with
  both voltage and frequency
• Third is windage and friction loss which varies with motor speed
                                  Downloaded from Ktunotes.in
                   Energy efficiency-Induction motors
• Induction motors have long been the workhorses of industry for fixed speed
  applications
• They are applied to variable speed duties through the use of variable frequency
  inverters.
• This electronic equipment allow the voltage and frequency supplied to the motor
  to be accurately controlled and hence very effective variable speed performance
  can be achieved over a wide operating range.
• The efficiency of standard induction motors can be significantly improved by
  using more materials in the motor.
                               Downloaded from Ktunotes.in
• Energy efficient motors are
   –   more expensive than standard motors
   –   lower noise and vibration
   –   lower operating temperature
   –   greater ability to accelerate high inertia loads
   –   Less affected by voltage variations
• An alternative method of reducing losses in the motor would be to use low
 magnetic loss materials such as silicon iron, which have losses of about one-fifth
 of those in conventional material.
                                   Downloaded from Ktunotes.in
Improvements to increase efficiency of motors include
• use of lower loss steel, longer core, thicker wire, thinner laminations smaller air
 gap between stator and rotor , copper instead of aluminum bars in the rotor,
 superior bearings and a smaller fan.
• Energy efficient motors now available in India, have 3-4% of higher efficiency
 than standard motors.
• B.I.S stipulates that energy efficient motors are to operate without loss of
 efficiency at loads between 75% and 100% of rated capacity
• The power factor is to be the same or higher than standard motors.
                               Downloaded from Ktunotes.in
Automatic Power Factor Correction (APFC)
• An APFC panel is an electrical panel that is used to improve the power factor of electrical
 systems.
• The power factor is a measure of how efficiently electrical power is being used, and it is
 calculated by dividing the real power (measured in watts) by the apparent power (measured
 in volt-amperes).
• A low power factor means that electrical energy is being wasted, which can result in
 increased electricity bills and reduced efficiency.
• APFC panels are used to correct the power factor by automatically adjusting the amount of
 reactive power (measured in VARs) that is being used in the electrical system.
                                    Downloaded from Ktunotes.in
• An APFC panel typically consists of a microprocessor-based controller, a capacitor
 bank, and a contactor.
• The controller monitors the power factor and activates the contactor to switch the
 capacitor bank on or off as needed to maintain a desired power factor.
• The capacitor bank consists of a series of capacitors that are connected in parallel with
 the load to supply reactive power to the system.
• APFC panels are commonly used in industries and commercial buildings where the
 power factor is low due to the use of inductive loads such as motors and transformers.
• By improving the power factor, APFC panels can help to reduce electricity bills and
 improve the efficiency of electrical systems.
                                  Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
                      Solar Photo Voltaic Systems
• PV systems generate electricity directly from sunlight.
• Electricity can be used directly or can be stored in batteries/fed to grid
• Most suitable for homes with a flat roof or with slanting roof facing
 south
                     Types of PV electrical systems
There are two general types of design for PV power systems are
• Grid connected or utility interactive systems
• Stand-alone or off grid PV systems
                             Downloaded from Ktunotes.in
Grid connected system
• Designed to operate in parallel with and
 interconnected with the utility grid.
• Primary component is the inverter or power
 conditioning unit (PCU).
• Inverter converts DC power produced by
 the PV array into AC power consistent with
 the voltage and power quality required by
 the utility grid.
• Bidirectional interface is made between PV
 system AC output circuits and the electric
 utility network.                  Downloaded from Ktunotes.in
• When the PV output is greater than the on site load demand ,PV system feed the
 grid .
• When electrical demand is greater than the PV system output, the balance of
 power required is drawn from the electric utility.
• Main Safety issue is PV system should not feed to utility grid when grid is down
 for service or repair.
                                 Downloaded from Ktunotes.in
Stand-alone system
• It is designed to operate independent
 of the electric utility grid.
• Supply DC/AC loads.
• Most suited for remote locations
 where there is no utility supply.
• Drawbacks are 1)batteries wont last
 forever 2) wastage of surplus energy.
• Need replacement every 5-6 years
                                 Downloaded from Ktunotes.in
                       PV system components
Basic components are
1)    Solar PV modules
2)    Array mounting racks
3)    Grounding system
4)    Junction box
5)    Surge protection
6)    Inverter
7)    Meters
8)    Disconnector
9)    Battery bank
10)   Charge controller
11)   Battery disconnect
                         Downloaded from Ktunotes.in
1) Solar PV modules
• Solar cell is the basic building block of a PV module.
• Many cells wired together form PV module (10W-300W) and many
  modules form PV array.
• Rating of a module is the maximum power the module can produce under
  standard test conditions with 1kW of sunlight per sq.meter at a temperature
  of 25° C in air
Types of solar modules
• Mono crystalline- high performance solar cells (efficiency 15-19%)
• Poly-crystalline- standard solar cells (efficiency 11-15%)
• Amorphous – thin film solar cells( efficiency 5-8%)
• Hybrid solar modules (combines two technologies for manufacture)
                             Downloaded from Ktunotes.in
2) Array mounting racks
• Orientation of PV array affects its performance.
• Best location of PV system is flat roof and south facing roof.
• On roof mounted systems, PV array is mounted on fixed racks parallel to the roof
  and lifted off few centimeters above the roof surface to allow airflow that will
  keep the surface cool.
• Solar modules can also be placed on the ground either on a fixed pole or a tracking
  mount.
• Mounting racks are adjustable such that angles can be set for PV modules to
  follow the sun.
• Tracked PV arrays can increase system’s daily energy output by 25%-40%.
• Tracking systems are not recommended for home solar applications
                                  Downloaded from Ktunotes.in
3) Grounding system
• Provides low resistance path from PV system to ground to protect the system from
  current surges, lightning strikes or equipment malfunctions.
• Provides protection from shock caused by ground fault.
• All system components and any exposed metal including equipment boxes, frames and
 PV mounting equipment should be properly grounded.
4) Junction box
• Output wires from individual PV modules are run to the junction box
• Junction box includes safety fuse or circuit breaker for each string and also includes a
  surge protector
5) Surge protection
• Protect the system from power surges due to lightning.
• Lightning surge is a sudden increase in voltage above the design voltage
                                 Downloaded from Ktunotes.in
6) Inverter
• Converts DC power of PV to AC power to feed domestic loads
• Also takes function of power conditioning
    – Reduce voltage fluctuations
    – Ensuring pure sinusoidal wave for grid connected systems
    – Ensuring 50 Hz frequency of electricity
Criteria for selecting a grid connected inverter: The following factors should be considered
  for selection
    – DC voltage of PV module
    – Quality of inverter such as efficiency, voltage regulation and good frequency
    – Manufacturer warranty
    – MPPT capability
   7) Metering
• Provides easy access to various parameters of the system and allows us to check whether
 the system is operating properly or not
                                  Downloaded from Ktunotes.in
8) Disconnector
• Automatic and manual type
• Ensure proper shut down of system for repair and maintenance
9) Battery bank
• Store DC power of PV system during daytime for later use
• Different types of batteries used in solar system are
   – Lead acid batteries
   – Alkaline batteries- high cost, used for extremely cold temperatures
                               Downloaded from Ktunotes.in
10) Charge controller
• Necessary for systems with battery back up
• Prevents overcharging and over discharging of batteries
• Selection based on
    – PV array voltage – The controller’s DC voltage input must match the nominal
      voltage of the solar array
    – PV array current – The controller must be sized to handle maximum current
      produced by the PV array
The charge controller must be selected such that it does not interfere with the proper
  operation of the inverter
                                Downloaded from Ktunotes.in
                   Typical design for home application
Design steps
Step 1) Determine the load to be served in watt-hours/day
Step 2) Determine the average solar energy available on at least a month by
month basis
Step 3) Calculate the size of solar panel that is required to meet the load
demand under the worst month conditions
Step 4) Calculate the size and type of battery that is needed to provide the
required reliability of power
Step 5) Determine the type of charge controller
Step 6) Determine the inverter capacity
                           Downloaded from Ktunotes.in
1) Determining load to be served in watt-hours per day
• Determine the power rating in watts of each of the appliances to be used in the
  household.
• Estimate the number of hours per day that each appliance will be used.
• For each appliance multiply the power rating in watts by the hours of use to get
  watt-hour/day.
• Calculate the total watt hour per day for all appliances taken together.
                               Downloaded from Ktunotes.in
2) Determining average solar energy available on at least a month
by month basis
                          Downloaded from Ktunotes.in
3) Size of solar panel required to meet the load
• Solar panels should produce 30% more energy that is required by the user.
• Watt – hour /day to be generated by the solar panel is about 130% of the watt
  hour needed by the equipment in the household.
• Panel generation factor (PGF) is an important component used in deciding solar
  panel size
• There are several factors that influence performance of the solar panels and we
  need to apply corrections for the same.
• Corrections include
   – 15% for ambient temperature above 25ᵒC (85% derating)
   – 5% loss due to sunlight not striking straight on the panel (95%)
   – 10% for loss due if there is a no MPPT charge controller 90% derating
   – 5% allowance for dirt collected on the solar panel (95% derating)
   – 10% allowance for the panel being below specification and for ageing (90%)
                             Downloaded from Ktunotes.in
• Therefore panel generation factor is obtained by multiplying the lowest Wh/day by
  the derating factor
• Number of PV modules required is calculated
• Number = (Panel size required/rated Wp of the PV module)
                                Downloaded from Ktunotes.in
4) Battery sizing
• Deep cycle battery is preferred for PV systems
• Batteries shall be large enough to operate the appliances at night and cloudy
  days
• Depth of discharge of the battery should not be large to have good life of
  battery
• The following assumptions are made for selecting the capacity of the
  battery bank
       Battery efficiency is assumed to be 85%
       Depth of discharge is assumed to be 50%
       Cloudy days are assumed to be 2
• Battery voltage levels are chosen based on the wattage capacity of the plant
   – 12V for up to 500W capacity
   – 24V for up to 1000W capacity
   – 48V for up to 2000W capacity
                              Downloaded from Ktunotes.in
5) Selection of charge controller
• Basic functions include
   –   Block reverse flow of current
   –   Prevent battery over charging
   –   Prevent battery over discharging
   –   Protect battery from overload
   –   Display battery status and flow of power
The charge controller is specified in terms of current and voltage.
It is selected to match the voltage of the PV array and batteries.
Should operate at 30% more than the short circuit current of the array.
                                Downloaded from Ktunotes.in
6) Selection of inverters
• Basic qualities of inverter for PV applications are
   –   Power quality- “Utility Interactive”
   –   Voltage input- inverter’s DC input should match the PV array
   –   AC power output
   –   Surge capacity
   –   Frequency and voltage variation
   –   Efficiency
   –   Integral safety disconnects
   –   MPPT
   –   Automatic load shedding
   –   Warranty
                                 Downloaded from Ktunotes.in
Downloaded from Ktunotes.in
                          SOLAR PV SYSTEM SIZING
1. Determine power consumption demands
The first step in designing a solar PV system is to find out the total power and energy
consumption of all loads that need to be supplied by the solar PV system as follows:
  1.1 Calculate total Watt-hours per day for each appliance used. Add the Watt-hours
  needed for all appliances together to get the total Watt-hours per day which must be
  delivered to the appliances.
   1.2 Calculate total Watt-hours per day needed from the PV modules. Solar panels
  should produce 30% more energy that is required by the user. Watt – hour /day to be
  generated by the solar panel is about 130% of the watt hour needed by the equipment in
  the household Multiply the total appliances Watt-hours per day times 1.3 (the energy lost
  in the system) to get the total Watt-hours per day which must be provided by the panels.
  Example: A house has the following electrical appliance usage:
  • One 18 Watt fluorescent lamp with electronic ballast used 4 hours per day.
  • One 60 Watt fan used for 2 hours per day.
   • One 75 Watt refrigerator that runs 24 hours per day with compressor run 12 hours and
  off 12 hours.
  The system will be powered by 12 Vdc, 110 Wp PV module.
  Solution
  Determine power consumption demands
  Total appliance use = (18 W x 4 hours) + (60 W x 2 hours) + (75 W x 24 x 0.5 hours)
  = 1,092 Wh/day
  Total PV panels energy needed = 1,092 x 1.3 = 1,419.6 Wh/day.
                       Downloaded from Ktunotes.in
2. Size the PV modules
 Different size of PV modules will produce different amount of power. The peak watt (Wp)
 produced depends on size of the PV module and climate of site location.
  We have to consider panel generation factor which is different in each site location. The
 panel generation factor is 3.43 kWh/m2/day. To determine the sizing of PV modules, calculate
 as follows:
    2.1 Calculate the total Watt-peak rating needed for PV modules
    Divide the total Watt-hours per day needed from the PV modules (from item 1.2) by panel
    generation factor (3.43) to get the total Watt-peak rating needed for the PV panels needed
    to operate the appliances.
    Total Wp of PV panel capacity needed = 1,419.6 / 3.4 = 413.9 Wp
    2.2 Calculate the number of PV panels for the system
    Divide the answer obtained in item 2.1 by the rated output Watt-peak of the PV modules
    available to you. Increase any fractional part of result to the next highest full number and
    that will be the number of PV modules required.
    Result of the calculation is the minimum number of PV panels. If more PV modules are
    installed, the system will perform better and battery life will be improved. If fewer PV
    modules are used, the system may not work at all during cloudy periods and battery life
    will be shortened.
    Number of PV panels needed = 413.9 / 110 = 3.76 modules
    Actual requirement = 4 modules
    So this system should be powered by at least 4 modules of 110 Wp PV module.
3.Inverter sizing
       An inverter is used in the system where AC power output is needed. The input rating
       of the inverter should never be lower than the total watt of appliances. The inverter
       must have the same nominal voltage as your battery.
       For stand-alone systems, the inverter must be large enough to handle the total amount
       of Watts you will be using at one time. The inverter size should be 25-30% bigger than
       total Watts of appliances.
                         Downloaded from Ktunotes.in
       In case of appliance type is motor or compressor then inverter size should be minimum
      3 times the capacity of those appliances and must be added to the inverter capacity to
      handle surge current during starting.
       For grid tie systems or grid connected systems, the input rating of the inverter should
      be same as PV array rating to allow for safe and efficient operation.
   Total Watt of all appliances = 18 + 60 + 75 = 153 W
   For safety, the inverter should be considered 25-30% bigger size.
   The inverter size should be about 190 W or greater.
4. Battery sizing
      The battery type recommended for using in solar PV system is deep cycle battery.
      Deep cycle battery is specifically designed for to be discharged to low energy level
      and rapid recharged or cycle charged and discharged day after day for years. The
      battery should be large enough to store sufficient energy to operate the appliances at
      night and cloudy days. To find out the size of battery, calculate as follows:
     4.1 Calculate total Watt-hours per day used by appliances.
     4.2 Divide the total Watt-hours per day used by 0.85 for battery loss.
     4.3 Divide the answer obtained in item 4.2 by 0.6 for depth of discharge.
     4.4 Divide the answer obtained in item 4.3 by the nominal battery voltage.
     4.5 Multiply the answer obtained in item 4.4 with days of autonomy (the number of days
         that you need the system to operate when there is no power produced by PV panels)
         to get the required Ampere-hour capacity of deep-cycle battery.
     Battery Capacity (Ah) = (Total Watt-hours per day used by appliances x Days of
     autonomy) / (0.85 x 0.6 x nominal battery voltage)
     Total appliances use = (18 W x 4 hours) + (60 W x 2 hours) + (75 W x 12 hours)
     Nominal battery voltage = 12 V
     Days of autonomy = 3 days
     Battery capacity = [(18 W x 4 hours) + (60 W x 2 hours) + (75 W x 12 hours)] x 3
     (0.85 x 0.6 x 12)
                         Downloaded from Ktunotes.in
      Total Ampere-hours required 535.29 Ah
      So the battery should be rated 12 V 600 Ah for 3 day autonomy.
5. Solar charge controller sizing
The solar charge controller is typically rated against Amperage and Voltage capacities. Select
the solar charge controller to match the voltage of PV array and batteries and then identify
which type of solar charge controller is right for your application. Make sure that solar charge
controller has enough capacity to handle the current from PV array.
For the series charge controller type, the sizing of controller depends on the total PV input
current which is delivered to the controller and also depends on PV panel configuration (series
or parallel configuration).
According to standard practice, the sizing of solar charge controller is to take the short circuit
current (Isc) of the PV array, and multiply it by 1.3
Solar charge controller rating = Total short circuit current of PV array x 1.3
PV module specification
Pm = 110 Wp
Vm = 16.7 Vdc
Im = 6.6 A
Voc = 20.7 V
Isc = 7.5 A
Solar charge controller rating = (4 strings x 7.5 A) x 1.3 = 39 A
So the solar charge controller should be rated 40 A at 12 V or great er
                         Downloaded from Ktunotes.in