Contractor's Manpower (Including Subcontractors) Plant/Equipment

The document outlines the construction progress of the King Fahad Complex - Girls in Riyadh, managed by Al Bawani Co. and AECOM, with a report dated May 14, 2017. It includes details on manpower, equipment, completed and ongoing activities, and various construction tasks with their respective completion percentages. The project has seen significant progress in excavation, structural work, and electrical installations, with various tasks at different stages of completion.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views2 pages

Contractor's Manpower (Including Subcontractors) Plant/Equipment

The document outlines the construction progress of the King Fahad Complex - Girls in Riyadh, managed by Al Bawani Co. and AECOM, with a report dated May 14, 2017. It includes details on manpower, equipment, completed and ongoing activities, and various construction tasks with their respective completion percentages. The project has seen significant progress in excavation, structural work, and electrical installations, with various tasks at different stages of completion.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Project name EDUCATIONAL BUILDINGS CONSTRUCTION IN RIYADH Project no.

RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name AECOM Data Date 14-May-17
To the Engineer Report no. C52/728
School Name KING FAHAD COMPLEX - GIRLS School Code C52
Temperature Max : 34°C Min : 20°C Site Hand-Over Day 17-Jan-15
Weather Sunny Cloudy Rainy Humidity High Medium Low

Contractor's Manpower (including Subcontractors)* Plant/Equipment*

Status (Idle
Staff No. Direct Labor No Type Qty. Location
or Repair)
Projt. MGR. 1 Supervisor/Foreman 2 Excavator/ Poclain/ Excavator 0
Tech. Team 1 Precast Man 18 Shovel/ Loader/ Grader 0
Contract MGR. 1 Equipment Optr. 0 BOBCAT 1
Precast Manager 1 Carpenter 0 Dump Truck 0
Const. Manager 1 Welder 1 Roller/ Compactor 0
Project Control Team 1 Steelfixer 0 Portable Generator 0
QA/QC 1 E/M 7 Mobile Crane 1
Tech. Support 1 Mason 2 Tower Crane 0
Purch & Procurement 1 Painter Loabor 0 Pick up 0
Set. Manager 1 Plastering man 1 Water Tanker 0
Site Engineer 1 labor 26 Welding Machine 0
General Fork Lift
Safety/ HSE 1 0
Contractor JCB
Timekeeper 1 0
Electro Mechanical Engrs 1 Water Pump 0
Surveyor & Survayor Assistant 1 Bulldozer 0
Guard 0 Levelling Machine 0
Total station 0
Container 0
Water Tank 1
Portacabin 2
Temporary Genset 0

Sub Total/Main 15 57 2

Sub-contractors

Sub Total/Subcon 0 0 0

Grand Total 15 57 2

Activities and Tasks*


COMPLETED ACTIVITIES ON-GOING ACTIVITIES
Percentage
Type of Work Building Name Start Date Finish Date Type of Work Building Name Activity name Start Date Finish Date
Complete
Excavation Main Building (A) - GF 2-May-15 20-May-15 Excavation Boundary Wall (A) Excavation Work For Boundary Wall 80.00% 10-Oct-16
Electric Room (A) 16-Aug-16 27-Aug-16 Collective Tank (B) Excavation Work For Collective Tank 15.00% 18-Apr-17
Canteen (A) 16-Aug-16 27-Aug-16 Septic Tank (B) Excavation Work For Septic Tank 15.00% 18-Apr-17
Electric Room (B) 16-Aug-16 27-Aug-16 Boundary Wall (B) Excavation Work For Boundary Wall 80.00% 12-Oct-16
Canteen (B) 18-Aug-16 28-Aug-16 Sub Structure Boundary Wall (A) R.C Concrete Grade Beams for Boundary Wall 40.00% 18-Dec-16
Guard House (A) 22-Aug-16 27-Aug-16 P.C Concrete for Boundary Wall 40.00% 6-Nov-16
Guard House (B) 22-Aug-16 27-Aug-16 Collective Tank Bituminous Sheet Waterproofing for Collective Tank 90.00% 13-Nov-16
Site layout (A) 12-Apr-15 23-Apr-15 Septic Tank Bituminous Sheet Waterproofing for Septic Tank 90.00% 13-Nov-16
Collective Tank 19-Sep-16 22-Sep-16 Water Tank Sheet Membrane Waterproofing 80.00% 16-Apr-17
Septic Tank 19-Sep-16 22-Sep-16 Bituminous Sheet Waterproofing for Water Tank 90.00% 13-Nov-16
Water Tank 16-Aug-16 22-Sep-16 Boundary Wall (B) R.C Concrete Column Neck for Boundary Wall 20.00% 19-Nov-16
Site layout (B) 12-Apr-15 23-Apr-15 P.C Concrete for Boundary Wall 50.00% 12-Nov-16
Water Tank (B) 18-Apr-17 26-Apr-17 Backfilling Boundary Wall (A) Backfilling Work for Boundary Wall 50.00% 28-Nov-16
Earth Works Site layout (A) 12-Apr-15 23-Apr-15 Boundary Wall (B) Backfilling Work for Boundary Wall 25.00% 2-Mar-17
Site layout (B) 12-Apr-15 23-Apr-15 Precast Main Building (B) - RF Install Pre-Cast Concrete Hollow Core Slabs 75.00% 23-Apr-17
Sub Structure Main Building (A) - GF 30-Jun-15 30-Mar-16 Block Work Main Building (A) - SF Block Work 90.00% 5-Feb-17
Electric Room (A) 22-Aug-16 7-Feb-17 Main Building (B) - GF Block Work 50.00% 22-Nov-16
Electric Room (B) 22-Aug-16 7-Feb-17 Main Building (B) - SF Block Work 90.00% 6-Mar-17
Guard House (A) 2-Oct-16 23-Jan-17 Plaster Main Building (A) - GF Cement Internal Plastering 80.00% 14-Nov-16
Guard House (B) 5-Oct-16 23-Jan-17 Main Building (A) - FF Cement Internal Plastering 90.00% 18-Dec-16
Backfilling Main Building (A) - GF 19-Sep-15 8-Mar-16 Main Building (A) - SF Cement Internal Plastering 85.00% 11-Mar-17
Electric Room (A) 20-Dec-16 25-Feb-17 Main Building (B) - GF Cement Internal Plastering 50.00% 24-Dec-16
Electric Room (B) 20-Dec-16 24-Feb-17 Main Building (B) - FF Cement Internal Plastering 90.00% 24-Jan-17
Guard House (A) 19-Oct-16 4-Feb-17 Main Building (B) - SF Cement Internal Plastering 13.00% 29-Apr-17
Guard House (B) 23-Oct-16 4-Feb-17 Mechanical Main Building (A) - GF Drainage Pipes for Toilets & Testing 80.00% 20-Mar-17
Slab On Grade Main Building (A) - GF 13-Jan-16 7-Apr-16 Floor Drain & Clean Out & Testing 80.00% 22-Mar-17
Electric Room (A) 21-Feb-17 25-Feb-17 Pipe Fitting & Testing 80.00% 23-Mar-17
Electric Room (B) 21-Feb-17 25-Feb-17 HVAC Duct & Testing 60.00% 14-Mar-17
Precast Main Building (A) - GF 1-Feb-16 2-Nov-16 Main Building (A) - FF Drainage Pipes for Toilets & Testing 20.00% 7-May-17
Main Building (A) - FF 19-Mar-16 31-Dec-16 HVAC Duct & Testing 60.00% 20-Mar-17
Main Building (A) - SF 13-Mar-16 1-Apr-17 Floor Drain & Clean Out & Testing 20.00% 5-May-17
Main Building (A) - RF 7-Mar-17 26-Apr-17 Pipe Fitting & Testing 20.00% 3-May-17
Main Building (B) - GF 16-Apr-16 3-Dec-16 Main Building (A) - SF Drainage Pipes for Toilets & Testing 50.00% 11-Mar-17
Main Building (B) - FF 24-Apr-16 31-Jan-17 HVAC Duct & Testing 23.00% 13-Mar-17
Main Building (B) - SF 13-Jul-16 2-Apr-17 Main Building (A) - RF Roof Drain & Testing 40.00% 18-Mar-17
Electric Room (A) 26-Feb-17 7-May-17 Main Building (B) - GF Water Supply Pipes ( Cold & Hot ) & Testing 5.00% 27-Nov-16
Electric Room (B) 26-Feb-17 7-May-17 Drainage Pipes for Toilets & Testing 50.00% 27-Nov-16
Concrete Works Collective Tank 18-Sep-16 15-Feb-17 Floor Drain & Clean Out & Testing 50.00% 27-Nov-16
Septic Tank 18-Sep-16 15-Feb-17 Pipe Fitting & Testing 70.00% 23-Feb-17
Block Work Main Building (A) - GF 12-Apr-16 22-Mar-17 HVAC Duct & Testing 50.00% 21-Mar-17
Main Building (A) - FF 1-Dec-16 28-Mar-17 Main Building (B) - FF Water Supply Pipes ( Cold & Hot ) & Testing 5.00% 14-Jan-17
Main Building (B) - FF 24-Dec-16 1-Apr-17 Drainage Pipes for Toilets & Testing 70.00% 27-Nov-16
HVAC Duct & Testing 60.00% 21-Mar-17
Floor Drain & Clean Out & Testing 5.00% 27-Nov-16
Main Building (B) - SF HVAC Duct & Testing 60.00% 22-Mar-17
Main Building (B) - RF Roof Drain & Testing 13.00% 21-Mar-17
Guard House (A) Water Supply Pipes ( Cold & Hot ) 80.00% 9-Apr-17
Drainage Pipes for Toilets 80.00% 18-Mar-17

Page 1 of 2
Floor Drain 80.00% 1-Apr-17
Guard House (B) Water Supply Pipes ( Cold & Hot ) 80.00% 9-Apr-17
Drainage Pipes for Toilets 80.00% 18-Mar-17
Floor Drain 80.00% 4-Apr-17
Electrical Main Building (A) - GF Lighting System Second Fix (Wires ) 90.00% 18-Dec-16
Wiring Devices First Fix (Pipes ) 90.00% 13-Apr-16
Wiring Devices Second Fix (Wires ) 60.00% 18-Feb-17
Fire Alarm First Fix (Pipes ) 90.00% 19-Feb-17
Fire Alarm Second Fix (Wires ) 80.00% 18-Feb-17
IP Telephone System First Fix (Pipes ) 90.00% 13-Apr-16
Main Building (A) - FF Wiring Devices Second Fix (Wires ) 60.00% 22-Apr-17
Fire Alarm First Fix (Pipes ) 80.00% 18-Feb-17
Fire Alarm Second Fix (Wires ) 80.00% 19-Feb-17
Data Communications System First Fix (Pipes ) 90.00% 18-Jan-17
Data Communications System Third Fix (Fixtures ) 45.00% 7-Dec-16
IP Telephone System First Fix (Pipes ) 80.00% 19-Jan-17
Lighting System First Fix (Pipes ) 90.00% 14-Dec-16
Lighting System Second Fix (Wires ) 80.00% 19-Jan-17
Wiring Devices First Fix (Pipes ) 80.00% 19-Jan-17
Main Building (A) - SF Fire Alarm Second Fix (Wires ) 80.00% 22-Feb-17
Data Communications System First Fix (Pipes ) 80.00% 19-Jan-17
Lighting System First Fix (Pipes ) 80.00% 23-Feb-17
Lighting System Second Fix (Wires ) 70.00% 23-Feb-17
Wiring Devices First Fix (Pipes ) 80.00% 19-Jan-17
Wiring Devices Second Fix (Wires ) 60.00% 8-Mar-17
Fire Alarm First Fix (Pipes ) 90.00% 17-Feb-17
IP Telephone System First Fix (Pipes ) 80.00% 22-Feb-17
Main Building (B) - GF Wiring Devices First Fix (Pipes ) 60.00% 27-Nov-16
Fire Alarm First Fix (Pipes ) 20.00% 23-Jan-17
Data Communications System First Fix (Pipes ) 40.00% 22-Jan-17
Lighting System First Fix (Pipes ) 50.00% 27-Nov-16
IP Telephone System First Fix (Pipes ) 40.00% 22-Feb-17
Main Building (B) - FF Lighting System First Fix (Pipes ) 40.00% 21-Feb-17
Wiring Devices First Fix (Pipes ) 90.00% 7-Dec-16
Data Communications System First Fix (Pipes ) 90.00% 7-Dec-16
IP Telephone System First Fix (Pipes ) 90.00% 7-Dec-16
Main Building (B) - SF Data Communications System First Fix (Pipes ) 70.00% 20-Feb-17
Lighting System First Fix (Pipes ) 35.00% 19-Feb-17
Wiring Devices First Fix (Pipes ) 70.00% 22-Feb-17
IP Telephone System First Fix (Pipes ) 70.00% 23-Feb-17
Electric Room (A) Wiring Devices First Fix (Pipes ) 50.00% 3-May-17
Electric Room (B) Wiring Devices First Fix (Pipes ) 50.00% 2-May-17
Guard House (A) Wiring Devices First Fix (Pipes ) 20.00% 5-May-17
Guard House (B) Wiring Devices First Fix (Pipes ) 20.00% 27-Apr-17
Doors Main Building (A) - GF Hollow Metal Frames 30.00% 12-Apr-17
Main Building (A) - FF Hollow Metal Frames 30.00% 12-Apr-17
Main Building (A) - SF Hollow Metal Frames 30.00% 12-Apr-17
Tiling Main Building (A) - GF Porcelain Tiles 20.00% 7-Mar-17
Ceramic Tiles for wall 13.00% 6-Mar-17
Main Building (A) - FF Porcelain Tiles 45.00% 14-Mar-17
Main Building (B) - GF Porcelain Tiles 13.00% 9-Apr-17
Main Building (B) - FF Porcelain Tiles 40.00% 9-Apr-17
Ceiling Main Building (A) - FF Solid Gypsum Ceiling 10.00% 5-Mar-17
Main Building (B) - GF Solid Gypsum Ceiling 12.00% 11-Mar-17
Main Building (B) - FF Solid Gypsum Ceiling 8.00% 8-Mar-17

Materials delivered to Site*


Item Unit Qty. Approved submittal reference

Contractor's authorized signatory Engineer's authorized signatory


Name: Ghassan Omar Name:
Signature: Signature:
Date: 14-May-17 Date: 14-May-17

* This form is to be used by the General Contractor to capture the above required information on a daily basis to report to the
Construction Supervisor (Engineer).

Page 2 of 2