Project name EDUCATIONAL BUILDINGS CONSTRUCTION IN RIYADH Project no.
RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name AECOM Data Date 14-May-17
To the Engineer Report no. C52/728
School Name KING FAHAD COMPLEX - GIRLS School Code C52
Temperature Max : 34°C Min : 20°C Site Hand-Over Day 17-Jan-15
Weather Sunny Cloudy Rainy Humidity High Medium Low
Contractor's Manpower (including Subcontractors)* Plant/Equipment*
Status (Idle
Staff No. Direct Labor No Type Qty. Location
or Repair)
Projt. MGR. 1 Supervisor/Foreman 2 Excavator/ Poclain/ Excavator 0
Tech. Team 1 Precast Man 18 Shovel/ Loader/ Grader 0
Contract MGR. 1 Equipment Optr. 0 BOBCAT 1
Precast Manager 1 Carpenter 0 Dump Truck 0
Const. Manager 1 Welder 1 Roller/ Compactor 0
Project Control Team 1 Steelfixer 0 Portable Generator 0
QA/QC 1 E/M 7 Mobile Crane 1
Tech. Support 1 Mason 2 Tower Crane 0
Purch & Procurement 1 Painter Loabor 0 Pick up 0
Set. Manager 1 Plastering man 1 Water Tanker 0
Site Engineer 1 labor 26 Welding Machine 0
General Fork Lift
Safety/ HSE 1 0
Contractor JCB
Timekeeper 1 0
Electro Mechanical Engrs 1 Water Pump 0
Surveyor & Survayor Assistant 1 Bulldozer 0
Guard 0 Levelling Machine 0
Total station 0
Container 0
Water Tank 1
Portacabin 2
Temporary Genset 0
Sub Total/Main 15 57 2
Sub-contractors
Sub Total/Subcon 0 0 0
Grand Total 15 57 2
Activities and Tasks*
COMPLETED ACTIVITIES ON-GOING ACTIVITIES
Percentage
Type of Work Building Name Start Date Finish Date Type of Work Building Name Activity name Start Date Finish Date
Complete
Excavation Main Building (A) - GF 2-May-15 20-May-15 Excavation Boundary Wall (A) Excavation Work For Boundary Wall 80.00% 10-Oct-16
Electric Room (A) 16-Aug-16 27-Aug-16 Collective Tank (B) Excavation Work For Collective Tank 15.00% 18-Apr-17
Canteen (A) 16-Aug-16 27-Aug-16 Septic Tank (B) Excavation Work For Septic Tank 15.00% 18-Apr-17
Electric Room (B) 16-Aug-16 27-Aug-16 Boundary Wall (B) Excavation Work For Boundary Wall 80.00% 12-Oct-16
Canteen (B) 18-Aug-16 28-Aug-16 Sub Structure Boundary Wall (A) R.C Concrete Grade Beams for Boundary Wall 40.00% 18-Dec-16
Guard House (A) 22-Aug-16 27-Aug-16 P.C Concrete for Boundary Wall 40.00% 6-Nov-16
Guard House (B) 22-Aug-16 27-Aug-16 Collective Tank Bituminous Sheet Waterproofing for Collective Tank 90.00% 13-Nov-16
Site layout (A) 12-Apr-15 23-Apr-15 Septic Tank Bituminous Sheet Waterproofing for Septic Tank 90.00% 13-Nov-16
Collective Tank 19-Sep-16 22-Sep-16 Water Tank Sheet Membrane Waterproofing 80.00% 16-Apr-17
Septic Tank 19-Sep-16 22-Sep-16 Bituminous Sheet Waterproofing for Water Tank 90.00% 13-Nov-16
Water Tank 16-Aug-16 22-Sep-16 Boundary Wall (B) R.C Concrete Column Neck for Boundary Wall 20.00% 19-Nov-16
Site layout (B) 12-Apr-15 23-Apr-15 P.C Concrete for Boundary Wall 50.00% 12-Nov-16
Water Tank (B) 18-Apr-17 26-Apr-17 Backfilling Boundary Wall (A) Backfilling Work for Boundary Wall 50.00% 28-Nov-16
Earth Works Site layout (A) 12-Apr-15 23-Apr-15 Boundary Wall (B) Backfilling Work for Boundary Wall 25.00% 2-Mar-17
Site layout (B) 12-Apr-15 23-Apr-15 Precast Main Building (B) - RF Install Pre-Cast Concrete Hollow Core Slabs 75.00% 23-Apr-17
Sub Structure Main Building (A) - GF 30-Jun-15 30-Mar-16 Block Work Main Building (A) - SF Block Work 90.00% 5-Feb-17
Electric Room (A) 22-Aug-16 7-Feb-17 Main Building (B) - GF Block Work 50.00% 22-Nov-16
Electric Room (B) 22-Aug-16 7-Feb-17 Main Building (B) - SF Block Work 90.00% 6-Mar-17
Guard House (A) 2-Oct-16 23-Jan-17 Plaster Main Building (A) - GF Cement Internal Plastering 80.00% 14-Nov-16
Guard House (B) 5-Oct-16 23-Jan-17 Main Building (A) - FF Cement Internal Plastering 90.00% 18-Dec-16
Backfilling Main Building (A) - GF 19-Sep-15 8-Mar-16 Main Building (A) - SF Cement Internal Plastering 85.00% 11-Mar-17
Electric Room (A) 20-Dec-16 25-Feb-17 Main Building (B) - GF Cement Internal Plastering 50.00% 24-Dec-16
Electric Room (B) 20-Dec-16 24-Feb-17 Main Building (B) - FF Cement Internal Plastering 90.00% 24-Jan-17
Guard House (A) 19-Oct-16 4-Feb-17 Main Building (B) - SF Cement Internal Plastering 13.00% 29-Apr-17
Guard House (B) 23-Oct-16 4-Feb-17 Mechanical Main Building (A) - GF Drainage Pipes for Toilets & Testing 80.00% 20-Mar-17
Slab On Grade Main Building (A) - GF 13-Jan-16 7-Apr-16 Floor Drain & Clean Out & Testing 80.00% 22-Mar-17
Electric Room (A) 21-Feb-17 25-Feb-17 Pipe Fitting & Testing 80.00% 23-Mar-17
Electric Room (B) 21-Feb-17 25-Feb-17 HVAC Duct & Testing 60.00% 14-Mar-17
Precast Main Building (A) - GF 1-Feb-16 2-Nov-16 Main Building (A) - FF Drainage Pipes for Toilets & Testing 20.00% 7-May-17
Main Building (A) - FF 19-Mar-16 31-Dec-16 HVAC Duct & Testing 60.00% 20-Mar-17
Main Building (A) - SF 13-Mar-16 1-Apr-17 Floor Drain & Clean Out & Testing 20.00% 5-May-17
Main Building (A) - RF 7-Mar-17 26-Apr-17 Pipe Fitting & Testing 20.00% 3-May-17
Main Building (B) - GF 16-Apr-16 3-Dec-16 Main Building (A) - SF Drainage Pipes for Toilets & Testing 50.00% 11-Mar-17
Main Building (B) - FF 24-Apr-16 31-Jan-17 HVAC Duct & Testing 23.00% 13-Mar-17
Main Building (B) - SF 13-Jul-16 2-Apr-17 Main Building (A) - RF Roof Drain & Testing 40.00% 18-Mar-17
Electric Room (A) 26-Feb-17 7-May-17 Main Building (B) - GF Water Supply Pipes ( Cold & Hot ) & Testing 5.00% 27-Nov-16
Electric Room (B) 26-Feb-17 7-May-17 Drainage Pipes for Toilets & Testing 50.00% 27-Nov-16
Concrete Works Collective Tank 18-Sep-16 15-Feb-17 Floor Drain & Clean Out & Testing 50.00% 27-Nov-16
Septic Tank 18-Sep-16 15-Feb-17 Pipe Fitting & Testing 70.00% 23-Feb-17
Block Work Main Building (A) - GF 12-Apr-16 22-Mar-17 HVAC Duct & Testing 50.00% 21-Mar-17
Main Building (A) - FF 1-Dec-16 28-Mar-17 Main Building (B) - FF Water Supply Pipes ( Cold & Hot ) & Testing 5.00% 14-Jan-17
Main Building (B) - FF 24-Dec-16 1-Apr-17 Drainage Pipes for Toilets & Testing 70.00% 27-Nov-16
HVAC Duct & Testing 60.00% 21-Mar-17
Floor Drain & Clean Out & Testing 5.00% 27-Nov-16
Main Building (B) - SF HVAC Duct & Testing 60.00% 22-Mar-17
Main Building (B) - RF Roof Drain & Testing 13.00% 21-Mar-17
Guard House (A) Water Supply Pipes ( Cold & Hot ) 80.00% 9-Apr-17
Drainage Pipes for Toilets 80.00% 18-Mar-17
Page 1 of 2
Floor Drain 80.00% 1-Apr-17
Guard House (B) Water Supply Pipes ( Cold & Hot ) 80.00% 9-Apr-17
Drainage Pipes for Toilets 80.00% 18-Mar-17
Floor Drain 80.00% 4-Apr-17
Electrical Main Building (A) - GF Lighting System Second Fix (Wires ) 90.00% 18-Dec-16
Wiring Devices First Fix (Pipes ) 90.00% 13-Apr-16
Wiring Devices Second Fix (Wires ) 60.00% 18-Feb-17
Fire Alarm First Fix (Pipes ) 90.00% 19-Feb-17
Fire Alarm Second Fix (Wires ) 80.00% 18-Feb-17
IP Telephone System First Fix (Pipes ) 90.00% 13-Apr-16
Main Building (A) - FF Wiring Devices Second Fix (Wires ) 60.00% 22-Apr-17
Fire Alarm First Fix (Pipes ) 80.00% 18-Feb-17
Fire Alarm Second Fix (Wires ) 80.00% 19-Feb-17
Data Communications System First Fix (Pipes ) 90.00% 18-Jan-17
Data Communications System Third Fix (Fixtures ) 45.00% 7-Dec-16
IP Telephone System First Fix (Pipes ) 80.00% 19-Jan-17
Lighting System First Fix (Pipes ) 90.00% 14-Dec-16
Lighting System Second Fix (Wires ) 80.00% 19-Jan-17
Wiring Devices First Fix (Pipes ) 80.00% 19-Jan-17
Main Building (A) - SF Fire Alarm Second Fix (Wires ) 80.00% 22-Feb-17
Data Communications System First Fix (Pipes ) 80.00% 19-Jan-17
Lighting System First Fix (Pipes ) 80.00% 23-Feb-17
Lighting System Second Fix (Wires ) 70.00% 23-Feb-17
Wiring Devices First Fix (Pipes ) 80.00% 19-Jan-17
Wiring Devices Second Fix (Wires ) 60.00% 8-Mar-17
Fire Alarm First Fix (Pipes ) 90.00% 17-Feb-17
IP Telephone System First Fix (Pipes ) 80.00% 22-Feb-17
Main Building (B) - GF Wiring Devices First Fix (Pipes ) 60.00% 27-Nov-16
Fire Alarm First Fix (Pipes ) 20.00% 23-Jan-17
Data Communications System First Fix (Pipes ) 40.00% 22-Jan-17
Lighting System First Fix (Pipes ) 50.00% 27-Nov-16
IP Telephone System First Fix (Pipes ) 40.00% 22-Feb-17
Main Building (B) - FF Lighting System First Fix (Pipes ) 40.00% 21-Feb-17
Wiring Devices First Fix (Pipes ) 90.00% 7-Dec-16
Data Communications System First Fix (Pipes ) 90.00% 7-Dec-16
IP Telephone System First Fix (Pipes ) 90.00% 7-Dec-16
Main Building (B) - SF Data Communications System First Fix (Pipes ) 70.00% 20-Feb-17
Lighting System First Fix (Pipes ) 35.00% 19-Feb-17
Wiring Devices First Fix (Pipes ) 70.00% 22-Feb-17
IP Telephone System First Fix (Pipes ) 70.00% 23-Feb-17
Electric Room (A) Wiring Devices First Fix (Pipes ) 50.00% 3-May-17
Electric Room (B) Wiring Devices First Fix (Pipes ) 50.00% 2-May-17
Guard House (A) Wiring Devices First Fix (Pipes ) 20.00% 5-May-17
Guard House (B) Wiring Devices First Fix (Pipes ) 20.00% 27-Apr-17
Doors Main Building (A) - GF Hollow Metal Frames 30.00% 12-Apr-17
Main Building (A) - FF Hollow Metal Frames 30.00% 12-Apr-17
Main Building (A) - SF Hollow Metal Frames 30.00% 12-Apr-17
Tiling Main Building (A) - GF Porcelain Tiles 20.00% 7-Mar-17
Ceramic Tiles for wall 13.00% 6-Mar-17
Main Building (A) - FF Porcelain Tiles 45.00% 14-Mar-17
Main Building (B) - GF Porcelain Tiles 13.00% 9-Apr-17
Main Building (B) - FF Porcelain Tiles 40.00% 9-Apr-17
Ceiling Main Building (A) - FF Solid Gypsum Ceiling 10.00% 5-Mar-17
Main Building (B) - GF Solid Gypsum Ceiling 12.00% 11-Mar-17
Main Building (B) - FF Solid Gypsum Ceiling 8.00% 8-Mar-17
Materials delivered to Site*
Item Unit Qty. Approved submittal reference
Contractor's authorized signatory Engineer's authorized signatory
Name: Ghassan Omar Name:
Signature: Signature:
Date: 14-May-17 Date: 14-May-17
* This form is to be used by the General Contractor to capture the above required information on a daily basis to report to the
Construction Supervisor (Engineer).
Page 2 of 2